SlideShare a Scribd company logo
1 of 18
Download to read offline
Int. J. Oil, Gas and Coal Technology, Vol. 5, No. 1, 2012                                     29


An analysis of inaccuracy in pipeline construction
cost estimation

         Zhenhua Rui*, Paul A. Metz and Gang Chen
         Department of Mining and Geological Engineering,
         University of Alaska Fairbanks,
         Duckering Building 418, P.O. Box 750708,
         Fairbanks, Alaska, 99775, USA
         Fax: +1-907-474-6635
         E-mail: zhenhuarui@gmail.com
         E-mail: pametz@alaska.edu
         E-mail: gchen@alaska.edu
         *Corresponding author

         Abstract: The aim of this paper is to investigate cost overrun of pipeline
         projects. A total of 412 pipeline projects between 1992 and 2008 have been
         collected, including material cost, labour cost, miscellaneous cost, right of way
         (ROW) cost, total cost, pipeline diameter, pipeline length, pipeline’s location,
         and year of completion. Statistical methods are used to identify the distribution
         of the cost overrun and the causes for overruns. The overall average cost
         overrun rates of pipeline material, labour, miscellaneous, ROW and total costs
         are 4.9%, 22.4%, –0.9%, 9.1% and 6.5% respectively. The cost estimation of
         pipeline cost components are biased except for total cost. In addition, the cost
         error of underestimated pipeline construction components is generally larger
         than that of overestimated pipeline construction components except total cost.
         Results of analysis show that pipeline size, capacity, diameter, length, location,
         and year of completion have different impacts on cost overrun of construction
         cost components. [Received: May 26, 2011; Accepted: June 28, 2011]

         Keywords: pipeline cost; cost overrun; cost estimation.

         Reference to this paper should be made as follows: Rui, Z., Metz, P.A. and
         Chen, G. (2012) ‘An analysis of inaccuracy in pipeline construction cost
         estimation’, Int. J. Oil, Gas and Coal Technology, Vol. 5, No. 1, pp.29–46.

         Biographical notes: Zhenhua Rui is a PhD candidate in Energy Engineering
         Management and MBA student at the University of Alaska Fairbanks. He also
         received his Master’s degree in Petroleum Engineering from the same
         university, in addition to his Master’s degree in Geophysics from China
         University of Petroleum, Beijing. His current research is the Engineering
         Economics of the Alaska In-state Natural Gas Pipeline.

         Paul A. Metz is a Professor of Department of Mining and Geological
         Engineering at the University of Alaska Fairbanks. He received his PhD from
         Imperial College of Science Technology and Medicine. He also received his
         MS in Economic Geology and MBA from the University of Alaska. His
         research interest include: market and transportation analysis of mineral
         resources; analysis of transport systems; engineering geological mapping and
         site investigation; mineral and energy resource evaluation.




Copyright © 2012 Inderscience Enterprises Ltd.
30       Z. Rui et al.

        Gang Chen is a Professor of Department of Mining and Geological Engineering
        at the University of Alaska Fairbanks. He received PhD in Mining Engineering
        from Virginia Polytechnic Institute and State University. He also received his
        MS in Mining Engineering from the Colorado School of Mines. His research
        interest include: rock mechanics in mining and civil engineering; mine ground
        engineering; frozen ground engineering and GIS application in mining industry.




1    Introduction

Cost error is the tendency for actual costs to deviate from estimated cost. Bias is the
tendency for that error to have a non-zero mean (Bertisen and Davis, 2008). Cost error or
bias is common and a global phenomenon in cost estimating (Flyvbjerg et al., 2003). Cost
estimating error and bias in other types of projects were mentioned and studied in many
papers. Pohl and Mihaljek (1992) reviewed 1,015 World Bank projects from 1947
to 1987 with 22% average cost overrun and 50% time overrun. Merrow (1998) found
that 47 of 52 megaprojects have an average overrun of 88%, and large projects and
megaprojects appear to have more cost growth than smaller projects. Flyvbjerg et al.
(2003) examined 258 transport infrastructure projects (rail, bridge and road) with average
28% cost overrun. Bertisen and Davis (2008) reviewed 63 international mining projects
with an average of 14% higher than estimated cost in the feasibility study. The literature
reviewed also shows that cost overrun exists over time. Overall cost overrun rates of all
Indiana departments of transportation projects was 4.5%, and 55% of all projects
experienced cost overruns (Bordat et al., 2004). Jacoby (2001) found that 74 projects with
a minimum cost of $10 million had 25% cost overruns. Many researchers also try to
explain the project cost overrun phenomenon. Some researchers proposed that optimism
and deception are major reasons for causing cost overrun (Flyvbjerg et al., 2003).
Some researchers believe that engineers and managers have incentive to underestimate
cost (Bertisen and Davis, 2008). Flyvbjerg (2007) suggested that cost underestimation
and overestimation of transport infrastructure appear to be intentional by project
promoters. Information asymmetries were also suggested as a reason for cost overrun
(Pindyck and Rubinfeld, 1995). Rowland (1981) mentioned that large projects increase
the likelihood of a high number of change orders. Jahren and Ashe (1990) suggested that
large projects have large cost overruns due to complexity, but also mentioned that
managers of large projects try to keep cost overrun rates from growing excessively large.
Large projects can lead to savings in unit cost, but it will limit the number of companies
who are able to carry out projects. Therefore, there is a trade-off between economies of
scale and competitive bidding practices (Bordat et al., 2004). Odeck (2004) indicated that
large projects have better management than small projects. Soil, drainage, climate and
weather conditions have an impact on design standard and cost of materials for road and
rail projects, and location influences construction and material cost due to varying
distance from supplies (RGL Forensics, 2009). An Australian study shows that public-
private partnership projects perform better than traditionally procured projects, While a
European study shows public-private partnerships exhibit higher costs than traditionally
procured infrastructure (Infrastructure Partnerships Australia, 2008; RGL Forensics,
2009). Flyvbjerg (2007) suggested that more research on the role of ownership in causing
An analysis of inaccuracy in pipeline construction cost estimation              31

efficiency difference between projects needs to be conducted. He also used technical,
psychological and political-economic factors to explain cost overruns.
    Although many studies have been conducted on projects’ cost overrun, there are
limited available references about pipeline project cost overrun. With available pipeline
data, this paper will focus on the cost estimation error of pipeline construction
components, and will investigate and identify the frequency of occurrence of cost
overruns as well as the magnitude of the differences between estimated cost and actual
cost in pipeline projects. In addition, cost overrun in terms of pipeline project size,
pipeline capacity, diameter, length, location, and year of completion are also investigated.


2   Data source

In this study, the pipelines are selected on the basis of data availability. The Oil and Gas
Journal pipeline cost data are collected from Federal Energy Regulatory Commission
filings from gas transmission companies, which are published by the Oil and Gas Journal
annual data book (Penn Well Corp, 1992–2009). Due to limited offshore pipeline data,
the pipeline data set in this paper contains only onshore pipeline data, and the pipeline
cost in this paper does not include compressor station cost.
     The pipeline data set provides location and year, pipeline diameter and length.
Pipelines in the data set were distributed in all states in the USA except Alaska and
Hawaii. It also contains the cost information of 15 Canadian pipelines. The pipelines
were completed between 1992 and 2008. Unfortunately, the data does not show the
construction period of the pipelines. Therefore, cost is defined as real, accounted costs
determined at the time of completion. The entire data set has 412 onshore pipelines. The
data include estimated and actual cost of five cost components. The estimated costs are
defined as budget, or forecast, costs at the time of decision to build the pipeline. The
actual costs are defined as real accounted costs determined at the time of completing
pipelines (Flyvbjerg et al., 2003). The five cost components are material, labour,
miscellaneous, right of way (ROW) and total costs. Material cost covers cost of line pipe,
pipeline coating and cathodic protection. Labour costs consist of the cost of pipeline
construction labour. Miscellaneous cost is a composite of the costs of surveying,
engineering, supervision, contingencies, telecommunications equipment, freight, taxes,
allowances for funds used during construction, administration and overheads, and
regulatory filing fees. ROW cost contains the cost of ROW and allowance for damages.
The total cost is the sum of material cost, labour cost, miscellaneous cost and ROW cost
(Penn Well Corp, 1992–2009).
     The location information for U.S pipelines was provided in a state format. A total of
48 states were referred to, except for Alaska and Hawaii. The US Energy Information
Administration (EIA) breaks down the US Natural Gas pipelines network into six
regions: Northeast, Southeast, Midwest, Southwest, Central and Western. The state
grouping is defined based on 10 federal regions of the US Bureau of Labour Statistics
(EIA, 2010). The map of regional definitions is shown in Figure 1. These regional
definitions are used to analyse geographic difference. In this paper, the USA pipeline data
are divided in to six regions according to the EIA definition. In addition, there are 15
Canadian pipelines, but reports did not show a specific province in Canada.
32         Z. Rui et al.

Figure 1    US natural gas pipeline region map (EIA) (see online version for colours)




Note: Alaska and Hawaii are not included in the US Natural pipeline network map.
In order to take a comparative analysis, all costs are adjusted by the Chemical
Engineering Plant Cost Index to 2008 dollars. The Chemical Engineering Plant Cost
Index is widely applied on process plants for adjusting construction cost. The Chemical
Engineering Plant Cost Index has 11 sub-indexes and a composite index, which is the
weight average of the 11 sub-indexes (Chemical Engineering, 2011). Pipeline index and
construction labour index is used to adjust pipeline material and labour cost. The
Chemical Engineering Plant Index is applied to pipeline miscellaneous and ROW cost.


3    Performance of individual pipeline construction component cost
     estimation

This section will evaluate performance of pipeline construction component cost
estimation. Several methods may be used to study the difference between the estimated
cost and the actual cost. In this study, the estimated cost and the actual cost are used to
calculate cost overrun rate as a measurement of cost overrun. The formula for cost
overrun rate is:
      Cost overrun rate = (actual cost - estimated cost) / estimated cost

If the cost overrun rate is positive, the cost is underestimated, otherwise it is
overestimated. In this paper, all cost overrun rates are calculated with the above formula.
    The histogram of the cost overrun rate for pipeline construction components are
shown in Figure 2 to Figure 6. If the cost error is small, the histogram would be narrowly
concentrated around zero. If underestimated cost is as common as overestimated cost, the
histogram would be symmetrically distributed around zero. It appears that five figures
exhibited non-symmetric distributions, and none of them satisfied the above mentioned
An analysis of inaccuracy in pipeline construction cost estimation        33

assumption. For material cost, 172 (42.0% of total) pipelines were underestimated, and
238 (58.0% of total) were overestimated. For labour cost, 273 (66.7% of total) pipelines
were underestimated, and 136 (33.3% of total) were overestimated. For miscellaneous
cost, 166 (40.8% of total) pipelines were underestimated, and 241 (59.2% of total) were
overestimated. For ROW cost, 174 (45.7% of total) pipelines were underestimated, and
207 (54.3% of total) were overestimated. For total cost, 222 (54.0% of total) pipelines
were underestimated, and 189 (46.0% of total) were overestimated.

Figure 2    Cost overrun rates of material cost (see online version for colours)




Figure 3    Cost overrun rates of labour cost (see online version for colours)
34         Z. Rui et al.

Figure 4    Cost overrun rates of miscellaneous cost (see online version for colours)




Figure 5    Cost overrun rates of ROW cost (see online version for colours)




In summary, more pipelines were overestimated for material, miscellaneous and ROW
costs, while more pipelines were underestimated for labour and total cost. In general, the
percentage of overestimated pipelines implies that there are still a fairly good number of
pipelines being completed with costs less than the estimated cost. In addition, the
majority of pipelines (87.1% for material cost, 72.3% for labour cost, 67.3% for
miscellaneous cost, and 89% for total cost) have cost overrun rates between –0.4 and 0.4.
However, only 49.0% of the pipelines for ROW cost have cost overrun rates between
An analysis of inaccuracy in pipeline construction cost estimation                35

–0.4 and 0.4. It demonstrates that ROW cost overrun is more severe than cost
components, which is also indicated by its standard deviation (SD) (Table 1).

Figure 6    Cost overrun rates of total cost (see online version for colours)




Table 1      Summaries of cost overrun of pipeline construction cost components

                                         Material    Labour      Miscellaneous   ROW     Total
Skewness                                    5.77       4.83          4.77        3.25    2.20
Kurtosis                                   49.22      44.88          42.06       15.77   12.29
Minimum                                    –0.95      –0.94          –0.94       –1.00   –0.94
Maximum                                     5.67      7.04           4.56        4.55    2.12
Range                                      6.61       7.98           5.50        5.55    3.06
Average                                    0.05       0.22           –0.01       0.09    0.07
Standard deviation                         0.55       0.62           0.56        0.81    0.34
Total number of pipelines                   410        409            407         381     411
Number of underestimated pipelines          172        273            166         174     222
Number of overestimated pipelines           238        136            241         207     189

Furthermore, statistical summaries of cost overrun of individual pipeline construction
components are shown in Table 1. Skewness is a quantitative way to measure symmetry
of the distribution. Symmetrical distribution has a skewness of 0. Positive skewness
means that the right tail is ‘heavier’ than the left tail. Negative skewness means that the
left tail dominates distribution. Kurtosis is a quantitative method to evaluate whether the
shape of the data distribution fits the normal distribution. A normal distribution has a
kurtosis of 0. Kurtosis of a flatter distribution is negative and that of a more peaked
distribution is positive (Hill et al., 2007). Values of skewness and kurtosis in Table 1
show that none of the cost overrun of five components is symmetrical normal
distribution, which matches the implication from the histogram graphs. Some
36       Z. Rui et al.

transformation techniques (such as natural log transformation) are applied to cost overrun
rate data for fitting them to normal distribution, but the data transformations are
unsuccessful. Therefore, the non-parametric statistical test is used in the below sections.
P-value will be produced by each test. In statistics, traditionally, p < 0.01 is considered
highly significant, p < 0.05 is significant. This criterion is also adopted in this paper.
    Table 1 shows that the minimum cost overrun rate for individual cost components are
between –94% (labour cost) and –100% (ROW cost). The maximum cost overrun rate for
individual cost components are between 212% and 704%. The value of minimum and
maximum indicates that cost performance for some pipelines is extremely bad. The
labour cost overrun has the largest maximum-minimum range of 798%, while total cost
overrun has the smallest range of 306%. The SD of individual cost components are fairly
significant, between 34% and 81% of the estimated cost. The large maximum-minimum
range and SD indicate that performance of pipeline construction cost estimating is very
unstable. It is noteworthy that labour cost has the largest maximum-minimum range
and second largest SD, and ROW cost has the largest SD. Therefore, it is difficult to
estimate labour cost and ROW cost accurately. Total cost overrun has the smallest
maximum-minimum range and SD due to its aggregation of other components.
    Average cost overrun is a key parameter to measure cost estimation performance of
individual pipeline construction cost components. The labour cost has the highest average
cost overrun of 22%, followed by ROW cost of 9%, total cost of 7%, material cost of 5%
and miscellaneous cost of –1%. The material, labour, ROW and total costs show positive
average cost overrun, while the miscellaneous cost has negative average cost overrun.
This result denotes that, in average, actual cost is larger than estimated cost for all
pipeline construction cost components except the miscellaneous cost.
    As mentioned before, there are more pipelines with overestimated material,
miscellaneous and ROW costs than those with underestimated pipelines, and there are
more pipelines with underestimated labour and total costs than those with overestimation
of these two cost components. However, it is an interesting finding that the average cost
overruns of material and ROW cost are still positive, even though there are more
pipelines with overestimated material cost, and ROW cost. It appears that cost estimation
of pipeline construction cost components is biased, and the underestimating error is
generally greater than the overestimating error for some pipeline construction cost
components. In this paper, two statistical tests are performed to investigate this inference.
    A binomial test is conducted to examine if the error of cost overestimating is as
common as the error of cost underestimating. As shown in Table 2, the p-value of the
binomial test rejects the null hypothesis that the overestimating error is as common as the
underestimating error for material, labour, miscellaneous, and ROW cost estimation
(p < 0.05, two sided test), but fails to reject that for total cost (p > 0.05, two sided test).
Therefore, the cost estimations of all pipeline construction cost components are biased
except total cost. Furthermore, the non-parametric Mann-Whitney test is employed
to test if the cost underestimating error is the same as the cost overestimating error. The
p-value shown in Table 2 shows that the error of underestimated pipelines’ cost overrun
are much larger than the error of overestimated pipelines’ cost overrun for material,
labour, miscellaneous and ROW cost (p < 5%, one sided test), but not for total cost (p >
5%, two sided test). Hence, the underestimating error is significantly more common and
larger than the overestimating error for all pipeline cost components, but not for total
cost.
An analysis of inaccuracy in pipeline construction cost estimation                            37

Table 2      Statistical tests of cost overrun of pipeline construction cost components

                                        Material    Labour        Miscellaneous       ROW         Total
Binomial test                            0.001         0               0                0        0.114
Mann-Whitney test                        0.047         0               0              0.039      0.082

After analysing overall cost overrun of pipeline projects, it is more important to identify
significant factors that influence pipeline projects’ cost overruns. The analyses of cost
overruns in terms of pipeline project size, pipeline capacity, diameter, length, location,
and completion time are carried out in the following sections.


4   Cost overrun in terms of pipeline project size

Here, the project size is measured by the pipeline’s actual total cost. The pipeline
total cost ranges from $33,576 to $1,933,839,076. According to the pipeline actual
total cost, the pipeline project size is classified into groups of small, medium and large.
185 pipelines with a total actual cost less than $10,000,000 are classified as small
projects, 192 pipelines with a total actual cost between $10,000,000 and $100,000,000
are classified as medium projects, and 33 pipelines with a total actual cost larger than
$100,000,000 are classified as large projects.
Table 3      Average cost overrun rate for different project size groups

Components           Project size      Average             SD              Skewness           Kurtosis
Material                Small             0.10             0.70              4.55              30.86
                       Medium             0.01             0.42              7.34              80.95
                        Large            0.04              0.13             1.22                4.19
Labour                  Small             0.16             0.47              1.31               6.95
                       Medium             0.28             0.76              5.19              40.15
                        Large            0.13              0.41             -0.50               4.03
Miscellaneous           Small             0.01             0.46              1.08               5.68
                       Medium             0.01             0.46              0.98               4.01
                        Large            -0.04             0.46              1.08               5.68
ROW                     Small             0.18             1.20              2.87              13.30
                       Medium             0.30             1.39              3.28              15.00
                        Large            0.23              0.54             1.60                7.12
Total                   Small             0.04             0.36              1.89              10.04
                       Medium             0.08             0.32              2.70              15.24
                        Large            0.12              0.24             2.50               11.58

Descriptive statistical analysis of cost overrun in terms of project size is shown in
Table 3. As seen in Table 3, for the material, labour, miscellaneous cost and ROW cost,
there is no linear relationship between average cost overrun rates and project sizes.
However, for total cost, the average cost overrun rate increases as the project’s size
increases. For the total cost, large projects have the highest cost overrun rates. A
plausible explanation is that a large pipeline project, normally bigger than 1 billion
dollars, can cause a huge demand that influences market price, such as steel price, and
38         Z. Rui et al.

further increases the cost of pipeline construction. Expectation of increased pipeline
construction costs induced an increase in the current unit construction cost (Rui et al.,
2011a). Suppliers would raise prices with expectation for more demand. In addition, a
large project limits the numbers of suppliers and contractors, reduces competition
and increases the cost (Bordat et al., 2004; RGL Forensics, 2009). However, for the
miscellaneous cost, large projects have the lowest cost overrun. It is possible that larger
projects have better management systems which coordinate different departments,
increase the efficiency of material utilisation and take advantage of economies of scale.
    In order to determine if there is a strong relationship between project sizes and
cost overrun for different pipeline construction components, the non-parametric
Kruskal-Wallis (KW) test is used to test the null hypothesis that the project size has no
effect on cost overrun of pipelines. The KW test is chosen because the value of skewness
and kurtosis shows that the cost overrun of each diameter group is not a normal
distribution. Therefore, the KW test will be used in this part and following parts when the
data does not produce normal distributions.
    For total cost, the result of the KW test shows that cost overrun for different project
size groups are significantly different (p < 0.05). However, such a significant difference
is not found for other cost components (p > 0.05). Therefore, it is concluded that the
project size significantly influences cost overrun for total cost, but not for other
individual cost components.
Table 4       Average cost overrun rate for different diameter groups

Components        Diameter groups     Average     SD      Skewness      Kurtosis   Num. of pipelines
Material            4–20 inches        0.13       0.68      3.70         21.37           124
                    22–30 inches       0.03       0.42      5.62         51.28           131
                    34–48 inches       0.00       0.52      8.56         92.67           155
Labour              4–20 inches        0.39       0.95      3.85         23.97           126
                    22–30 inches       0.21       0.42      1.14         5.79            131
                    34–48 inches       0.09       0.33      0.87         7.18            155
Miscellaneous       4–20 inches        0.17       0.99      4.11         24.64           123
                    22–30 inches       –0.16      0.35      0.93         4.39            131
                    34–48 inches       0.02       0.48      0.92         4.38            152
ROW                 4–20 inches        0.43       1.57      2.61         10.01           115
                    22–30 inches       0.24       1.38      3.31         15.53           122
                    34–48 inches       0.11       0.81      2.71         15.52           153
Total               4–20 inches        0.17       0.48      1.72         6.96            124
                    22–30 inches       0.03       0.24      0.65         6.55            131
                    34–48 inches       0.02       0.23      1.39         9.59            155



5    Cost overrun in terms of pipeline diameter

The range in pipeline diameter is between 4 and 48 inches. The pipeline projects are
categorised into three diameter groups: 4–20 inch, 22–30 inches and 34–48 inches.
Pipeline construction component cost overruns for three different pipeline diameter
groups are shown in Table 4.
An analysis of inaccuracy in pipeline construction cost estimation                  39

    For material, labour, ROW and total costs, 4–20 inch pipelines have the highest
average cost overrun rate, followed by 22–30 inches pipelines and 34–48 inches
pipelines. For miscellaneous cost, 4–20 inches pipelines have the highest average cost
overrun, but 22–30 inches pipelines have the lowest average cost overrun of –16%. 4–20
inches groups have the highest average cost overrun rate for all construction components
costs. It appears that small diameter pipelines are prone to cost overrun.
    Therefore, the non-parametric KW test is used to test the null hypothesis that type of
pipeline diameter has no effect on cost overrun of pipelines construction component cost.
For material, ROW and total cost, the result of the KW test shows the cost overrun is not
significantly different for different diameter groups (p > 0.5). For labour and
miscellaneous costs, the result of the KW test shows the cost overrun for types of
diameter groups is significantly different (p < 0.01). Therefore, it is concluded that types
of diameter groups influence cost overrun of pipelines for labour and miscellaneous cost,
and not for other components costs.


6   Cost overrun in terms of pipeline length

The cost overrun in terms of pipeline length is tested in this section. The range of pipeline
length is between 0.1 and 713 miles. The length group is divided into two groups:
0–20 miles and 20–713 miles. About 78% of pipelines are shorter than 20 miles, and the
rest of the pipelines are between 20 and 713 miles. Pipeline construction component cost
overruns for two different pipeline length groups are shown in Table 5.
Table 5      Average cost overrun rate for different length groups

Components         Length groups     Average      SD     Skewness    Kurtosis   Num. of pipelines
Material            0–20 miles         0.05      0.56      5.25       44.21           321
                   20–713 miles        0.04      0.51      8.14       73.36            89
Labour              0–20 miles         0.21      0.60      5.37       56.39           323
                   20–713 miles        0.26      0.70      3.46       20.41            89
Miscellaneous       0–20 miles         0.17      0.72      4.71       38.60           319
                   20–713 miles       –0.03      0.40      0.82       4.74             87
ROW                 0–20 miles         0.23      1.28      3.11       14.53           303
                   20–713 miles        0.30      1.18      3.89       21.62            87
Total               0–20 miles         0.06      0.35      2.12       11.85           321
                   20–713 miles        0.10      0.30      2.80       14.57            89

For material, miscellaneous and ROW costs, the 0–20 miles group has the highest
average cost overrun rate, followed by the 20–713 miles inches pipelines. For labour cost
and total cost, the 20–713 miles pipelines have incurred the highest average cost overrun,
followed by 0–20 miles pipelines. It appears that different construction component costs
have different cost overrun rate patterns.
    The KW test is used to test the null hypothesis that type of pipeline length has no
effect on cost overrun. For all construction cost components, the results of the KW tests
show the cost overrun rate difference between types of length groups are not significant
at the 5% significance level (p > 0.1). Therefore, cost overrun rates of all construction
cost components are not significantly influenced by types of pipeline length.
40          Z. Rui et al.

7    Cost overrun in terms of pipeline capacity

In this paper, the pipeline volume (capacity) is calculated with formula (Zhao, 2000):
         V = S *L
                      2
               ⎛D⎞
where S = π ⎜ ⎟ , V is the pipeline volume (ft3), S is the pipeline cross-sectional area
               ⎝2⎠
(ft2), L is the pipeline length (ft), and D is the pipeline diameter (ft). In the data set for
this study, the smallest pipeline capacity is 92 ft3, and the largest is 36,220,080 ft3. In this
section, all pipelines are divided into three different groups of pipeline capacities to test
whether cost overrun rate is significantly different for different pipeline capacity.
135 pipelines with a capacity between less than 75,000 ft3 are classified as small projects,
136 pipelines with a capacity between 75, 000 ft3 and 284,768 ft3 are classified as
medium projects, and 139 pipelines with a capacity larger than 284,768 are classified as
large projects.
     Descriptive statistical analysis of cost overrun in terms of pipeline capacity is shown
in Table 6. A noticeable observation is that the small pipeline capacity group has the
highest average cost overrun rates for all construction cost components. Pipelines with
small capacity appear to be particularly prone to cost overrun. Projects with large
capacity may take more advantage of economies of scale.
Table 6        Average cost overrun rates for different capacity groups

 Components         Capacity groups    Average     SD      Skewness       Kurtosis   Num. of pipelines
 Material                  Small         0.19      0.80      3.81          22.63           135
                          Medium        –0.03      0.24      0.97           4.47           136
                           Large        –0.05      0.43      8.75          93.69           139
 Labour                    Small         0.24      0.57      1.54           7.35           135
                          Medium         0.25      0.84      5.37          38.99           137
                           Large         0.16      0.38      0.47           5.10           140
 Miscellaneous             Small         0.13      0.97      4.14          25.36           133
                          Medium        –0.08      0.43      1.11           4.25           135
                           Large        –0.03      0.43      0.94           4.79           138
 ROW                       Small         0.34      1.50      2.50           9.29           128
                          Medium         0.19      1.19      4.00          23.95           130
                           Large         0.20      1.05      3.54          19.34           132
 Total                     Small         0.12      0.46      1.72           7.77           135
                          Medium         0.03      0.29      2.45          13.17           136
                           Large         0.05      0.21      0.95           7.96           139

The KW test is used to verify that the pipeline capacity has no effect on cost overrun for
construction cost components. For material cost, the result of KW test rejects the null
hypothesis (p < 0.001), indicating that pipeline capacity influences material cost overrun,
and projects with small pipeline capacity have large positive cost overrun rates. Pipeline
projects with large capacity mean that more material is consumed. Therefore, projects
with a large capacity take advantage of economies of scale in purchasing materials,
resulting in lower costs for materials as pipeline capacity increases. It may be that the
An analysis of inaccuracy in pipeline construction cost estimation                 41

estimator of pipeline projects did not estimate unit price with capacity changing
accurately or did not consider economies of scale in material cost. This may result in
pipeline projects with small capacity that have large cost overrun. For labour,
miscellaneous, ROW and total costs, the results fail to reject the null hypothesis that
pipeline capacity has no effects on the cost overrun rates (p > 0.05). Therefore, the cost
overrun differences in the labour, miscellaneous, ROW and total costs are not statistically
significant for different types of pipeline capacities.
Table 7      Average cost overrun rates for different regions

Components         Region groups     Average      SD     Skewness   Kurtosis   Num. of pipelines
Material             Midwest          –0.02      0.29       0.03      4.81            55
                    Northeast         –0.02      0.56      7.33      72.15           156
                    Southwest          0.02      0.37       0.32      5.35            30
                     Canada           0.18       0.26      0.80       2.75            14
                     Central           0.06      0.28       1.58      8.24            52
                    Southeast          0.26      0.92       3.63     15.69            55
                     Western           0.09      0.50       3.22     16.22            48
Labour               Midwest           0.12      0.38       1.19      8.36            55
                    Northeast          0.12      0.34      0.87       5.91           157
                    Southwest          0.28      0.60       1.04      3.30            30
                     Canada           0.02       0.33      –1.04      3.95            15
                     Central           0.20      0.49       0.31      2.38            52
                    Southeast          0.33      0.85       3.01     14.70            55
                     Western           0.55      1.14       4.20     23.28            48
Miscellaneous        Midwest          –0.06      0.43       1.72      7.74            54
                    Northeast         –0.07      0.45      1.14       5.97           155
                    Southwest          0.05      0.52       0.62      2.62            30
                     Canada           1.32       2.25      1.56       4.03            14
                     Central          –0.02      0.37       0.84      3.97            51
                    Southeast          0.04      0.55       1.60      5.93            55
                     Western          –0.08      0.54       1.73      6.28            47
ROW                  Midwest           0.34      0.99       3.42     20.21            53
                    Northeast         –0.10      0.76      2.31      12.10           150
                    Southwest          0.12      1.14       3.66     17.27            27
                     Canada           1.59       2.18      0.76       2.01            14
                     Central           0.26      1.11       2.74     12.51            50
                    Southeast         –0.08      0.65       1.18      4.90            52
                     Western           1.01      2.35       1.84      5.14            44
Total                Midwest           0.01      0.24      –0.77      5.72            55
                    Northeast          0.00      0.26      1.72      10.97           155
                    Southwest          0.84      0.34       0.60      3.68            30
                     Canada           0.14       0.31      –0.86      4.11            15
                     Central           0.11      0.29       1.35      6.69            52
                    Southeast          0.13      0.45       1.93      6.80            55
                     Western           0.19      0.48       2.76     10.77            48
42       Z. Rui et al.

8    Cost overrun in terms of different regions

As we know, pipeline cost is significantly different for different regions (Rui et al.,
2011b). This section discusses whether cost overrun of pipeline construction cost
components is different for different regions.
    As seen from Table 7, it is noticeable that cost overrun rate of the pipelines in the
Northeast regions is the lowest in the USA as compared to the other regions, even though
the Northeast has a relatively high cost of living. In addition, the total cost overrun rate of
pipelines in the Northeast regions is a perfect 0. A possible explanation is that 155 out of
412 pipelines in the data set are located in the Northeast regions, which provides more
practical experience and historical information for new pipeline cost estimating in this
region. A few negative cost overrun rates also appear in some regions for different
construction component cost.
    The result of KW tests shows that the cost overruns of difference for different regions
are highly significant for all construction cost components (p < 0.001). Weather
condition, soil property, population density, cost of living, terrain condition, and distance
from supplies are variable for different regions and make pipeline project cost estimation
more difficult (Rui et al., 2011b; Zhao, 2000). More detailed information on pipeline
routes is needed to explain cost overrun difference among different regions.
    Therefore, it is concluded that the cost overrun rates of all cost components show
significant difference for different regions and the pipeline’s location matters to cost
overrun in all cost components.


9    Cost overrun over time

Forty-seven megaprojects between the mid 1960s and 1984 were reported with a cost
overrun rate of 88% (Merrow, 1998). Over 1,000 World Bank projects between 1947 and
1987 had cost estimated errors (Pohl and Mihaljek, 1992). 55% of all Indiana Department
of Transportation’s projects between 1996 and 2001 experienced cost overruns (Bordat
et al., 2004). Cost overrun is constant for more than a 70-year period between 1910 and
1998 for 208 transportation projects in 14 nations on five continents (Flyvbjerg et al.,
2003). All the literature show that the cost estimated error persists over time in many
different types of projects. But is there any improvement in pipeline compressor station
projects over time? This section tries to discover whether the cost estimating performance
has improved over time. Improved performance of cost estimating is normally expected.
The average cost overrun rate of compressor station construction components between
1992 and 2008 are displayed in Figure 7. The cost overrun rate of ROW cost fluctuates
widely with a declining trend. The cost overrun rate of labour cost shows a decrease
before 2004 and then a significant increase after 2004. But cost overrun rate of material,
miscellaneous and total costs change more gradually over time.
    The length of the construction phase influences cost overrun rate. Therefore, it is
better to use the year of planning to build as the time measurement (Flyvbjerg et al.,
2003), but the available data does not provide the year of building and construction
period. Therefore, the year of completion is used to as a measure of the time, which may
cause bias. The non-parametric Nptrend test is conducted to test whether there is a trend
of cost overrun rate over years. All results of the Nptrend test show only cost overrun
rate of ROW decreases over time (p < 0.05). Therefore, based on available data, it is
An analysis of inaccuracy in pipeline construction cost estimation                   43

concluded that cost estimating of ROW cost has improved over time, not for other
components.

Figure 7    Annual average cost overrun rate of pipeline construction cost components (see online
            version for colours)




10 Conclusions and future work

This paper statistically analyses the cost estimating performance of individual pipeline
construction cost components by using 412 pipeline projects. The trend and distribution
of all 412 pipelines construction cost components cost estimation over the 1992–2008
periods are analysed. Overall average cost overrun rates of the material cost, labour cost,
miscellaneous cost, ROW cost and total cost are 4.9% (SD = 54.8%), 22.4%
(SD = 61.8%), –0.9% (SD = 56.2%), 9.1% (SD = 80.9%) and 6.5% (SD = 33.5%)
respectively. The labour and ROW costs have the largest cost overrun compared to the
other cost components. The statistical test results show that cost estimating in all cost
components is biased except in the total cost. And the magnitude of cost underestimating
error is generally larger than the overestimating error except for total cost. Furthermore,
cost overrun rates of pipeline construction cost components are analysed in terms of
pipeline project size groups, capacity groups, diameter groups, length groups, location
groups, and the year of completion to investigate the relationship between cost overruns
and different groups. The cost overrun rate for the total cost shows a significant
difference for different project size groups, and the cost overrun rate increases with
project size. An expected large demand, limited supplies and contractors for large-size
projects cause big cost overruns (Bordat et al., 2004; RGL Forensics, 2009; Rui et al.,
2011a). The cost overrun rates of the labour and miscellaneous costs show significant
differences for diameter groups, and the small diameter group has the highest average
cost overrun rate. The cost overrun rates of all construction cost components are not
significantly influenced by pipeline length. The cost overrun rate of the material cost is
significant for different pipeline capacity groups, and projects with small pipeline
capacities appear to be particularly prone to cost overrun. Large capacity pipeline
projects may purchase material at low price due to large scale. The planners or estimator
44         Z. Rui et al.

may not estimate the material unit price changing with scale accurately or may even fail
to consider the economies of scale factors. The cost overruns of all construction cost
components are significantly different for different regions. The weather, soil, terrain,
terrain condition, population density and experience are suggested as causes for making it
difficult to estimate cost accurately. Cost estimating accuracy of pipeline projects have
not improved over the 1992–2008 time period.
    Based on the analysis of historical pipeline cost estimated errors, Table 8 provides
some proposed guidelines for project estimators conducting pipeline cost estimation. It is
considered that individual cost components should receive varying degree of attention
under different conditions in order to make cost estimation efficient and reliable. A four
level scale: maximum attention, moderate attention, less attention, and minimum
attention, is applied for the amount of attention and effort paid to individual cost
component cost analysis, depending on the project size, pipe diameter, pipeline length,
pipeline capacity, and region of construction, as given in Table 8.
Table 8        Proposed guidelines for pipeline cost estimators

Category            Sub-category      Material    Labour      Miscellaneous   ROW    Total
Project size            Small            C           B             D          B        D
                       Medium            D           A             D          A        C
                        Large            D           B             D          A        B
Diameter             4–20 inches         B           A             B          A        B
                    22–30 inches         D           A             B          A        D
                    34–48 inches         D           C             D          B        D
Length               0–20 miles          D           A             B          A        C
                    20–713 miles         D           A             D          A        C
Capacity                Small            B           A             B          A        B
                       Medium            D           A             C          B        D
                        Large            D           B             D          B        D
Region                 Midwest           D           B             C          A        D
                      Northeast          D           B             C          C        D
                      Southwest          D           A             D          B        A
                       Canada            B           D             A          A        B
                       Central           D           B             D          A        B
                      Southeast          D           A             D          C        B
                       Western           B           A             C          A        B
Notes: A = maximum attention; B = moderate attention;
       C = less attention; D = minimum attention
To the best of the authors’ knowledge, this paper is the first in-depth analysis of pipeline
construction component cost overruns. Suggested future work may include the following
list:
•    Different reasons for cost overrun for other types of projects are proposed by
     different researchers, and many of the proposed causes did not have hard data
     support. The same situation applies to pipeline projects; lack of good quality
     projects data is a major difficulty in investigating more in-depth causes of pipeline
     cost overrun. Therefore, collecting more accurate information on the pipeline
An analysis of inaccuracy in pipeline construction cost estimation                     45

    construction period, the ownership of projects, the material of pipeline, and the
    thickness of pipeline wall is a major part of future work. Furthermore, quantity
    analysis of collecting data should be conducted to investigate the causes of cost
    overrun.
•   More application with analysis results will be used in the future pipeline projects,
    such as pipeline cost overrun distribution and average cost overrun rate.
•   Develop a set of recommendations to help mangers and engineers to better estimate
    pipeline project costs and minimise the cost estimating errors.


References
Bertisen, J. and Davis, G.A. (2008) ‘Bias and error in mine project capital cost estimation’, The
      Engineering Economist, Vol. 53, No. 2, pp.118–139.
Bordat, C., McCullouch, B., Sinba, K. and Labi, S. (2004) An Analysis of Cost Overruns and Time
      Delays of INDOT Projects, Joint Transportation Research Program, Indiana Department of
      Transportation and Purdue University, West Lafayette, Indiana.
Chemical Engineering (2011) Chemical Engineering’s Plant Cost Index, available at
      http://www.che.com/pci (accessed on May 2011).
Energy Information Administration (EIA) (2010) U.S. Natural Gas Pipeline Regional Definitions
      Map, available at http://www.eia.doe.gov (accessed on July 2010).
Flyvbjerg, B. (2007) ‘Policy and planning for large infrastructure projects: problems, causes,
      cures’, Environment and Planning B: Planning and Design, Vol. 34, No. 4, pp.578–597.
Flyvbjerg, B., Skamris, M. and Buhl, S. (2003) ‘How common and how large are cost overrun in
      transport infrastructure projects?’, Transport Reviews, Vol. 23, No. 1, pp.71–88.
Hill, R.C., Griffiths, W.E. and Lim, G.C. (2007) Principle of Econometrics, 3rd ed., John Wiley
      and Sons, Inc., New York.
Infrastructure Partnerships Australia (2008) Available at http://www.infrastructure.org.au (accessed
      on May 2011).
Jacoby, C. (2001) Report on Supplemental Agreement Reasons, AASHTO-FHWA Project Cost
      Overrun Study, Federal Highway Administration, US Department of Transportation,
      Washington, D.C.
Jahren, C. and Ashe, A. (1990) ‘Predictors of cost-overrun rates’, ASCE Journal of Construction
      Engineering and Management, Vol. 116, No. 3, pp.548–551, American Society of Civil
      Engineers, Reston, VA.
Merrow, E.W. (1998) Understanding the Outcomes of Megaprojects: A Quantitative Analysis of
      Very Large Civilian Projects, R-3560-PSSP, Rand Corporation, CA.
Odeck, J. (2004) ‘Cost overruns in road construction-what are their sizes and determinants?’,
      Transport Policy, Vol. 11, No. 1, pp.43–53.
Penn Well Corporation (1992–2009) Oil & Gas Journal Databook, Tulsa, Oklahoma.
Pindyck, R.S. and Rubinfeld, D.L. (1995) Microeconomics, 3rd ed., Prentice-Hall, Englewood
      Cliffs, N.J.
Pohl, G. and Mihaljek, D. (1992) ‘Project evaluation and uncertainty in practice: a statistical
      analysis of rate-of-return divergences of 1015 world bank projects’, The World Bank
      Economic Review, Vol. 6, No. 2, pp.255–277.
RGL Forensics (2009) Ex Post Evaluation of Cohesion Policy Programmes 2000–2006, Work
      Package 10, European Commission, Brussels, BE.
Rowland, H. (1981) The Causes and Effects of Change Orders on the Construction Process, PhD
      Thesis, Georgia Institute of Technology, Atlanta, GA.
46        Z. Rui et al.

Rui, Z., Metz, P.A., Reynolds, D.B., Chen, G. and Zhou, X. (2011a) ‘Historical pipeline
     construction cost analysis’, International Journal of Oil, Gas and Coal Technology, Vol. 4,
     No. 3, pp.244–263.
Rui, Z., Metz, A.P., Reynolds, B.D., Chen, G. and Zhou, X. (2011b) ‘Regression models estimate
     pipeline construction costs’, Oil & Gas Journal, Vol. 109, No. 14, pp.120–127.
Zhao, J. (2000) ‘Diffusion, costs and learning in the development of international gas transmission
     lines’, Working paper IR-00-054, International Institute for Applied Systems Analysis,
     Austria.

More Related Content

What's hot

PATERAKI ABSTRACT 1(1)
PATERAKI ABSTRACT  1(1)PATERAKI ABSTRACT  1(1)
PATERAKI ABSTRACT 1(1)George Chousos
 
Application of Soft Computing Techniques for Analysis of Groundwater Table Fl...
Application of Soft Computing Techniques for Analysis of Groundwater Table Fl...Application of Soft Computing Techniques for Analysis of Groundwater Table Fl...
Application of Soft Computing Techniques for Analysis of Groundwater Table Fl...drboon
 
Prediction of scour depth at bridge abutments in cohesive bed using gene expr...
Prediction of scour depth at bridge abutments in cohesive bed using gene expr...Prediction of scour depth at bridge abutments in cohesive bed using gene expr...
Prediction of scour depth at bridge abutments in cohesive bed using gene expr...Mohd Danish
 
Investigating the implications of a new-build hybrid power system for RoRo ca...
Investigating the implications of a new-build hybrid power system for RoRo ca...Investigating the implications of a new-build hybrid power system for RoRo ca...
Investigating the implications of a new-build hybrid power system for RoRo ca...Janie Ling Chin
 
Karion uinta basin emissions
Karion uinta basin emissionsKarion uinta basin emissions
Karion uinta basin emissionsgdecock
 
Resource Assessment of Potentially Producible Natural Gas Volumes From the Ma...
Resource Assessment of Potentially Producible Natural Gas Volumes From the Ma...Resource Assessment of Potentially Producible Natural Gas Volumes From the Ma...
Resource Assessment of Potentially Producible Natural Gas Volumes From the Ma...Marcellus Drilling News
 
Mcmahon best practice in 3d seismic 1999
Mcmahon best practice in 3d seismic 1999Mcmahon best practice in 3d seismic 1999
Mcmahon best practice in 3d seismic 1999Fands-llc
 
J-Impacts of Different Funding Sources on Long-lead Items Procurement in Indo...
J-Impacts of Different Funding Sources on Long-lead Items Procurement in Indo...J-Impacts of Different Funding Sources on Long-lead Items Procurement in Indo...
J-Impacts of Different Funding Sources on Long-lead Items Procurement in Indo...AdrianSyaifullah2
 
Investigating a conventional and retrofit power plant on-board a Roll-on-Roll...
Investigating a conventional and retrofit power plant on-board a Roll-on-Roll...Investigating a conventional and retrofit power plant on-board a Roll-on-Roll...
Investigating a conventional and retrofit power plant on-board a Roll-on-Roll...Janie Ling Chin
 
GMA 8 Northern Trinity Woodbine GAM Update: Bill Mullican and Van Kelley
GMA 8 Northern Trinity Woodbine GAM Update: Bill Mullican and Van KelleyGMA 8 Northern Trinity Woodbine GAM Update: Bill Mullican and Van Kelley
GMA 8 Northern Trinity Woodbine GAM Update: Bill Mullican and Van KelleyTexas Alliance of Groundwater Districts
 
Scour prediction at bridge piers in cohesive bed using gene expression progra...
Scour prediction at bridge piers in cohesive bed using gene expression progra...Scour prediction at bridge piers in cohesive bed using gene expression progra...
Scour prediction at bridge piers in cohesive bed using gene expression progra...Mohd Danish
 

What's hot (13)

PATERAKI ABSTRACT 1(1)
PATERAKI ABSTRACT  1(1)PATERAKI ABSTRACT  1(1)
PATERAKI ABSTRACT 1(1)
 
Application of Soft Computing Techniques for Analysis of Groundwater Table Fl...
Application of Soft Computing Techniques for Analysis of Groundwater Table Fl...Application of Soft Computing Techniques for Analysis of Groundwater Table Fl...
Application of Soft Computing Techniques for Analysis of Groundwater Table Fl...
 
Prediction of scour depth at bridge abutments in cohesive bed using gene expr...
Prediction of scour depth at bridge abutments in cohesive bed using gene expr...Prediction of scour depth at bridge abutments in cohesive bed using gene expr...
Prediction of scour depth at bridge abutments in cohesive bed using gene expr...
 
Investigating the implications of a new-build hybrid power system for RoRo ca...
Investigating the implications of a new-build hybrid power system for RoRo ca...Investigating the implications of a new-build hybrid power system for RoRo ca...
Investigating the implications of a new-build hybrid power system for RoRo ca...
 
Karion uinta basin emissions
Karion uinta basin emissionsKarion uinta basin emissions
Karion uinta basin emissions
 
Resource Assessment of Potentially Producible Natural Gas Volumes From the Ma...
Resource Assessment of Potentially Producible Natural Gas Volumes From the Ma...Resource Assessment of Potentially Producible Natural Gas Volumes From the Ma...
Resource Assessment of Potentially Producible Natural Gas Volumes From the Ma...
 
bwr-tt102es
bwr-tt102esbwr-tt102es
bwr-tt102es
 
Mcmahon best practice in 3d seismic 1999
Mcmahon best practice in 3d seismic 1999Mcmahon best practice in 3d seismic 1999
Mcmahon best practice in 3d seismic 1999
 
J-Impacts of Different Funding Sources on Long-lead Items Procurement in Indo...
J-Impacts of Different Funding Sources on Long-lead Items Procurement in Indo...J-Impacts of Different Funding Sources on Long-lead Items Procurement in Indo...
J-Impacts of Different Funding Sources on Long-lead Items Procurement in Indo...
 
Investigating a conventional and retrofit power plant on-board a Roll-on-Roll...
Investigating a conventional and retrofit power plant on-board a Roll-on-Roll...Investigating a conventional and retrofit power plant on-board a Roll-on-Roll...
Investigating a conventional and retrofit power plant on-board a Roll-on-Roll...
 
GMA 8 Northern Trinity Woodbine GAM Update: Bill Mullican and Van Kelley
GMA 8 Northern Trinity Woodbine GAM Update: Bill Mullican and Van KelleyGMA 8 Northern Trinity Woodbine GAM Update: Bill Mullican and Van Kelley
GMA 8 Northern Trinity Woodbine GAM Update: Bill Mullican and Van Kelley
 
Scour prediction at bridge piers in cohesive bed using gene expression progra...
Scour prediction at bridge piers in cohesive bed using gene expression progra...Scour prediction at bridge piers in cohesive bed using gene expression progra...
Scour prediction at bridge piers in cohesive bed using gene expression progra...
 
LCA
LCALCA
LCA
 

Viewers also liked

Estimation and project costing training module
Estimation and project costing training moduleEstimation and project costing training module
Estimation and project costing training modulekhalid noman husainy
 
Cash flow estimation ppt @ bec doms on finance
Cash flow estimation ppt @ bec doms on financeCash flow estimation ppt @ bec doms on finance
Cash flow estimation ppt @ bec doms on financeBabasab Patil
 
1 project cash flow
1 project cash flow1 project cash flow
1 project cash flowBhumit Patel
 
50639312 roll-of-quantity-surveyor
50639312 roll-of-quantity-surveyor50639312 roll-of-quantity-surveyor
50639312 roll-of-quantity-surveyorhlksd
 
Ibe quantity surveyor 2013
Ibe quantity surveyor 2013Ibe quantity surveyor 2013
Ibe quantity surveyor 2013nurun2010
 
Software cost estimation
Software cost estimationSoftware cost estimation
Software cost estimationHaitham Ahmed
 
Software estimation techniques
Software estimation techniquesSoftware estimation techniques
Software estimation techniquesTan Tran
 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and materialALI HYDER GADHI
 
Software cost estimation
Software cost estimationSoftware cost estimation
Software cost estimationdjview
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveyingAwanish Shukla
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costingGanesh Murugan
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing bookThomas Britto
 
Software cost estimation project
Software  cost estimation projectSoftware  cost estimation project
Software cost estimation projectShashank Puppala
 

Viewers also liked (18)

Earthwork and excavation
Earthwork  and  excavationEarthwork  and  excavation
Earthwork and excavation
 
Non renewable sources of energy
Non renewable sources of energyNon renewable sources of energy
Non renewable sources of energy
 
Estimation and project costing training module
Estimation and project costing training moduleEstimation and project costing training module
Estimation and project costing training module
 
Cash flow estimation ppt @ bec doms on finance
Cash flow estimation ppt @ bec doms on financeCash flow estimation ppt @ bec doms on finance
Cash flow estimation ppt @ bec doms on finance
 
Project cash flow
Project cash flowProject cash flow
Project cash flow
 
1 project cash flow
1 project cash flow1 project cash flow
1 project cash flow
 
50639312 roll-of-quantity-surveyor
50639312 roll-of-quantity-surveyor50639312 roll-of-quantity-surveyor
50639312 roll-of-quantity-surveyor
 
Ibe quantity surveyor 2013
Ibe quantity surveyor 2013Ibe quantity surveyor 2013
Ibe quantity surveyor 2013
 
Software cost estimation
Software cost estimationSoftware cost estimation
Software cost estimation
 
Software cost estimation
Software cost estimationSoftware cost estimation
Software cost estimation
 
Software estimation techniques
Software estimation techniquesSoftware estimation techniques
Software estimation techniques
 
Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and material
 
Software cost estimation
Software cost estimationSoftware cost estimation
Software cost estimation
 
Estimation and quantity surveying
Estimation and quantity surveyingEstimation and quantity surveying
Estimation and quantity surveying
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
 
Structural Steel Work
 Structural Steel  Work Structural Steel  Work
Structural Steel Work
 
Estimating and-costing book
Estimating and-costing bookEstimating and-costing book
Estimating and-costing book
 
Software cost estimation project
Software  cost estimation projectSoftware  cost estimation project
Software cost estimation project
 

Similar to Analysis of Inaccuracy in Pipeline Construction Cost Estimation

Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectIRJET Journal
 
Mastersresearch 06-02-16
Mastersresearch 06-02-16Mastersresearch 06-02-16
Mastersresearch 06-02-16Matthias Hess
 
A Review Article on "Environmental Impact Assessment" (Eia)
A Review Article on "Environmental Impact Assessment" (Eia)A Review Article on "Environmental Impact Assessment" (Eia)
A Review Article on "Environmental Impact Assessment" (Eia)IRJET Journal
 
Diagnose the causes of cost deviation in highway construction
Diagnose the causes of cost deviation in highway constructionDiagnose the causes of cost deviation in highway construction
Diagnose the causes of cost deviation in highway constructionFaiq M. S. Al-Zwainy
 
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...IOSR Journals
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET Journal
 
A comparison of the carbon footprint of pavement infrastructure and associate...
A comparison of the carbon footprint of pavement infrastructure and associate...A comparison of the carbon footprint of pavement infrastructure and associate...
A comparison of the carbon footprint of pavement infrastructure and associate...IJAAS Team
 
Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Charles Abraham Scheck
 
Causes of cracks and deterioration of pavement on highways in jordan from con...
Causes of cracks and deterioration of pavement on highways in jordan from con...Causes of cracks and deterioration of pavement on highways in jordan from con...
Causes of cracks and deterioration of pavement on highways in jordan from con...Alexander Decker
 
CSCM Causes of project delay
CSCM Causes of project delayCSCM Causes of project delay
CSCM Causes of project delayEst
 
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...Vamsi Kovalam
 
Assessment of risk on road projects in nigeria construction industry
Assessment of risk on road projects in nigeria construction industryAssessment of risk on road projects in nigeria construction industry
Assessment of risk on road projects in nigeria construction industryResearchWap
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis IOSR Journals
 
ENeilsenresume- Dec2015PE
ENeilsenresume- Dec2015PEENeilsenresume- Dec2015PE
ENeilsenresume- Dec2015PEErik NEILSEN
 
Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...
Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...
Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...IJERA Editor
 
Project Performance Analysis And Delivery Methods - Quantitative Analysis
Project Performance Analysis And Delivery Methods - Quantitative AnalysisProject Performance Analysis And Delivery Methods - Quantitative Analysis
Project Performance Analysis And Delivery Methods - Quantitative AnalysisSeta Ohanesian, PMP, LEED AP
 
Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...
Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...
Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...ijtsrd
 

Similar to Analysis of Inaccuracy in Pipeline Construction Cost Estimation (20)

Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road project
 
Mastersresearch 06-02-16
Mastersresearch 06-02-16Mastersresearch 06-02-16
Mastersresearch 06-02-16
 
Ijetr012001
Ijetr012001Ijetr012001
Ijetr012001
 
A Review Article on "Environmental Impact Assessment" (Eia)
A Review Article on "Environmental Impact Assessment" (Eia)A Review Article on "Environmental Impact Assessment" (Eia)
A Review Article on "Environmental Impact Assessment" (Eia)
 
Diagnose the causes of cost deviation in highway construction
Diagnose the causes of cost deviation in highway constructionDiagnose the causes of cost deviation in highway construction
Diagnose the causes of cost deviation in highway construction
 
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
 
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
IRJET-Factors influencing Time and Cost Overruns in Road Construction Project...
 
asdfds
asdfdsasdfds
asdfds
 
A comparison of the carbon footprint of pavement infrastructure and associate...
A comparison of the carbon footprint of pavement infrastructure and associate...A comparison of the carbon footprint of pavement infrastructure and associate...
A comparison of the carbon footprint of pavement infrastructure and associate...
 
Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...Causes of delay and cost overruns in construction of groundwater projects in ...
Causes of delay and cost overruns in construction of groundwater projects in ...
 
Causes of cracks and deterioration of pavement on highways in jordan from con...
Causes of cracks and deterioration of pavement on highways in jordan from con...Causes of cracks and deterioration of pavement on highways in jordan from con...
Causes of cracks and deterioration of pavement on highways in jordan from con...
 
CSCM Causes of project delay
CSCM Causes of project delayCSCM Causes of project delay
CSCM Causes of project delay
 
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
STUDY AND ANALYSIS OF CONCRETE STRENGTH PARAMETERS USING VETIVER GRASS ASH AS...
 
Assessment of risk on road projects in nigeria construction industry
Assessment of risk on road projects in nigeria construction industryAssessment of risk on road projects in nigeria construction industry
Assessment of risk on road projects in nigeria construction industry
 
road contruction.pptx
road contruction.pptxroad contruction.pptx
road contruction.pptx
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis
 
ENeilsenresume- Dec2015PE
ENeilsenresume- Dec2015PEENeilsenresume- Dec2015PE
ENeilsenresume- Dec2015PE
 
Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...
Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...
Conceptual Cost Estimate of Libyan Highway Projects Using Artificial Neural N...
 
Project Performance Analysis And Delivery Methods - Quantitative Analysis
Project Performance Analysis And Delivery Methods - Quantitative AnalysisProject Performance Analysis And Delivery Methods - Quantitative Analysis
Project Performance Analysis And Delivery Methods - Quantitative Analysis
 
Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...
Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...
Systematic Study of Factors Causing Cost Overrun and Delay in Pune Metro Line...
 

More from zhenhuarui

A study on multple time lapse seismic avo inversion
A study on multple time lapse seismic avo inversionA study on multple time lapse seismic avo inversion
A study on multple time lapse seismic avo inversionzhenhuarui
 
A study on multiple time lapse seismic avo inversion chinesepdf
A study on multiple time lapse seismic avo inversion chinesepdfA study on multiple time lapse seismic avo inversion chinesepdf
A study on multiple time lapse seismic avo inversion chinesepdfzhenhuarui
 
盖层各向异性对时移地震avo 的影响
盖层各向异性对时移地震avo 的影响盖层各向异性对时移地震avo 的影响
盖层各向异性对时移地震avo 的影响zhenhuarui
 
Study on multiple attenuation method based on match filter
Study on multiple attenuation method based on match filterStudy on multiple attenuation method based on match filter
Study on multiple attenuation method based on match filterzhenhuarui
 
Regressions allow development of compressor cost estimation models print th...
Regressions allow development of compressor cost estimation models   print th...Regressions allow development of compressor cost estimation models   print th...
Regressions allow development of compressor cost estimation models print th...zhenhuarui
 
Regression models estimate pipeline construction costs
Regression models estimate pipeline construction costsRegression models estimate pipeline construction costs
Regression models estimate pipeline construction costszhenhuarui
 

More from zhenhuarui (6)

A study on multple time lapse seismic avo inversion
A study on multple time lapse seismic avo inversionA study on multple time lapse seismic avo inversion
A study on multple time lapse seismic avo inversion
 
A study on multiple time lapse seismic avo inversion chinesepdf
A study on multiple time lapse seismic avo inversion chinesepdfA study on multiple time lapse seismic avo inversion chinesepdf
A study on multiple time lapse seismic avo inversion chinesepdf
 
盖层各向异性对时移地震avo 的影响
盖层各向异性对时移地震avo 的影响盖层各向异性对时移地震avo 的影响
盖层各向异性对时移地震avo 的影响
 
Study on multiple attenuation method based on match filter
Study on multiple attenuation method based on match filterStudy on multiple attenuation method based on match filter
Study on multiple attenuation method based on match filter
 
Regressions allow development of compressor cost estimation models print th...
Regressions allow development of compressor cost estimation models   print th...Regressions allow development of compressor cost estimation models   print th...
Regressions allow development of compressor cost estimation models print th...
 
Regression models estimate pipeline construction costs
Regression models estimate pipeline construction costsRegression models estimate pipeline construction costs
Regression models estimate pipeline construction costs
 

Recently uploaded

How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxLoriGlavin3
 
Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rick Flair
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .Alan Dix
 
Decarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a realityDecarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a realityIES VE
 
Scale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL RouterScale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL RouterMydbops
 
UiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to HeroUiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to HeroUiPathCommunity
 
Potential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsPotential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsRavi Sanghani
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxLoriGlavin3
 
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better StrongerModern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better Strongerpanagenda
 
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentEmixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentPim van der Noll
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...panagenda
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteDianaGray10
 
Sample pptx for embedding into website for demo
Sample pptx for embedding into website for demoSample pptx for embedding into website for demo
Sample pptx for embedding into website for demoHarshalMandlekar2
 
Data governance with Unity Catalog Presentation
Data governance with Unity Catalog PresentationData governance with Unity Catalog Presentation
Data governance with Unity Catalog PresentationKnoldus Inc.
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxLoriGlavin3
 
2024 April Patch Tuesday
2024 April Patch Tuesday2024 April Patch Tuesday
2024 April Patch TuesdayIvanti
 
A Framework for Development in the AI Age
A Framework for Development in the AI AgeA Framework for Development in the AI Age
A Framework for Development in the AI AgeCprime
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 

Recently uploaded (20)

How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
 
Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...Rise of the Machines: Known As Drones...
Rise of the Machines: Known As Drones...
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .
 
Decarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a realityDecarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a reality
 
Scale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL RouterScale your database traffic with Read & Write split using MySQL Router
Scale your database traffic with Read & Write split using MySQL Router
 
UiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to HeroUiPath Community: Communication Mining from Zero to Hero
UiPath Community: Communication Mining from Zero to Hero
 
Potential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsPotential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and Insights
 
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptxThe Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
The Role of FIDO in a Cyber Secure Netherlands: FIDO Paris Seminar.pptx
 
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better StrongerModern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
 
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentEmixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
Why device, WIFI, and ISP insights are crucial to supporting remote Microsoft...
 
Take control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test SuiteTake control of your SAP testing with UiPath Test Suite
Take control of your SAP testing with UiPath Test Suite
 
Sample pptx for embedding into website for demo
Sample pptx for embedding into website for demoSample pptx for embedding into website for demo
Sample pptx for embedding into website for demo
 
Data governance with Unity Catalog Presentation
Data governance with Unity Catalog PresentationData governance with Unity Catalog Presentation
Data governance with Unity Catalog Presentation
 
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptxUse of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
Use of FIDO in the Payments and Identity Landscape: FIDO Paris Seminar.pptx
 
2024 April Patch Tuesday
2024 April Patch Tuesday2024 April Patch Tuesday
2024 April Patch Tuesday
 
A Framework for Development in the AI Age
A Framework for Development in the AI AgeA Framework for Development in the AI Age
A Framework for Development in the AI Age
 
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 

Analysis of Inaccuracy in Pipeline Construction Cost Estimation

  • 1. Int. J. Oil, Gas and Coal Technology, Vol. 5, No. 1, 2012 29 An analysis of inaccuracy in pipeline construction cost estimation Zhenhua Rui*, Paul A. Metz and Gang Chen Department of Mining and Geological Engineering, University of Alaska Fairbanks, Duckering Building 418, P.O. Box 750708, Fairbanks, Alaska, 99775, USA Fax: +1-907-474-6635 E-mail: zhenhuarui@gmail.com E-mail: pametz@alaska.edu E-mail: gchen@alaska.edu *Corresponding author Abstract: The aim of this paper is to investigate cost overrun of pipeline projects. A total of 412 pipeline projects between 1992 and 2008 have been collected, including material cost, labour cost, miscellaneous cost, right of way (ROW) cost, total cost, pipeline diameter, pipeline length, pipeline’s location, and year of completion. Statistical methods are used to identify the distribution of the cost overrun and the causes for overruns. The overall average cost overrun rates of pipeline material, labour, miscellaneous, ROW and total costs are 4.9%, 22.4%, –0.9%, 9.1% and 6.5% respectively. The cost estimation of pipeline cost components are biased except for total cost. In addition, the cost error of underestimated pipeline construction components is generally larger than that of overestimated pipeline construction components except total cost. Results of analysis show that pipeline size, capacity, diameter, length, location, and year of completion have different impacts on cost overrun of construction cost components. [Received: May 26, 2011; Accepted: June 28, 2011] Keywords: pipeline cost; cost overrun; cost estimation. Reference to this paper should be made as follows: Rui, Z., Metz, P.A. and Chen, G. (2012) ‘An analysis of inaccuracy in pipeline construction cost estimation’, Int. J. Oil, Gas and Coal Technology, Vol. 5, No. 1, pp.29–46. Biographical notes: Zhenhua Rui is a PhD candidate in Energy Engineering Management and MBA student at the University of Alaska Fairbanks. He also received his Master’s degree in Petroleum Engineering from the same university, in addition to his Master’s degree in Geophysics from China University of Petroleum, Beijing. His current research is the Engineering Economics of the Alaska In-state Natural Gas Pipeline. Paul A. Metz is a Professor of Department of Mining and Geological Engineering at the University of Alaska Fairbanks. He received his PhD from Imperial College of Science Technology and Medicine. He also received his MS in Economic Geology and MBA from the University of Alaska. His research interest include: market and transportation analysis of mineral resources; analysis of transport systems; engineering geological mapping and site investigation; mineral and energy resource evaluation. Copyright © 2012 Inderscience Enterprises Ltd.
  • 2. 30 Z. Rui et al. Gang Chen is a Professor of Department of Mining and Geological Engineering at the University of Alaska Fairbanks. He received PhD in Mining Engineering from Virginia Polytechnic Institute and State University. He also received his MS in Mining Engineering from the Colorado School of Mines. His research interest include: rock mechanics in mining and civil engineering; mine ground engineering; frozen ground engineering and GIS application in mining industry. 1 Introduction Cost error is the tendency for actual costs to deviate from estimated cost. Bias is the tendency for that error to have a non-zero mean (Bertisen and Davis, 2008). Cost error or bias is common and a global phenomenon in cost estimating (Flyvbjerg et al., 2003). Cost estimating error and bias in other types of projects were mentioned and studied in many papers. Pohl and Mihaljek (1992) reviewed 1,015 World Bank projects from 1947 to 1987 with 22% average cost overrun and 50% time overrun. Merrow (1998) found that 47 of 52 megaprojects have an average overrun of 88%, and large projects and megaprojects appear to have more cost growth than smaller projects. Flyvbjerg et al. (2003) examined 258 transport infrastructure projects (rail, bridge and road) with average 28% cost overrun. Bertisen and Davis (2008) reviewed 63 international mining projects with an average of 14% higher than estimated cost in the feasibility study. The literature reviewed also shows that cost overrun exists over time. Overall cost overrun rates of all Indiana departments of transportation projects was 4.5%, and 55% of all projects experienced cost overruns (Bordat et al., 2004). Jacoby (2001) found that 74 projects with a minimum cost of $10 million had 25% cost overruns. Many researchers also try to explain the project cost overrun phenomenon. Some researchers proposed that optimism and deception are major reasons for causing cost overrun (Flyvbjerg et al., 2003). Some researchers believe that engineers and managers have incentive to underestimate cost (Bertisen and Davis, 2008). Flyvbjerg (2007) suggested that cost underestimation and overestimation of transport infrastructure appear to be intentional by project promoters. Information asymmetries were also suggested as a reason for cost overrun (Pindyck and Rubinfeld, 1995). Rowland (1981) mentioned that large projects increase the likelihood of a high number of change orders. Jahren and Ashe (1990) suggested that large projects have large cost overruns due to complexity, but also mentioned that managers of large projects try to keep cost overrun rates from growing excessively large. Large projects can lead to savings in unit cost, but it will limit the number of companies who are able to carry out projects. Therefore, there is a trade-off between economies of scale and competitive bidding practices (Bordat et al., 2004). Odeck (2004) indicated that large projects have better management than small projects. Soil, drainage, climate and weather conditions have an impact on design standard and cost of materials for road and rail projects, and location influences construction and material cost due to varying distance from supplies (RGL Forensics, 2009). An Australian study shows that public- private partnership projects perform better than traditionally procured projects, While a European study shows public-private partnerships exhibit higher costs than traditionally procured infrastructure (Infrastructure Partnerships Australia, 2008; RGL Forensics, 2009). Flyvbjerg (2007) suggested that more research on the role of ownership in causing
  • 3. An analysis of inaccuracy in pipeline construction cost estimation 31 efficiency difference between projects needs to be conducted. He also used technical, psychological and political-economic factors to explain cost overruns. Although many studies have been conducted on projects’ cost overrun, there are limited available references about pipeline project cost overrun. With available pipeline data, this paper will focus on the cost estimation error of pipeline construction components, and will investigate and identify the frequency of occurrence of cost overruns as well as the magnitude of the differences between estimated cost and actual cost in pipeline projects. In addition, cost overrun in terms of pipeline project size, pipeline capacity, diameter, length, location, and year of completion are also investigated. 2 Data source In this study, the pipelines are selected on the basis of data availability. The Oil and Gas Journal pipeline cost data are collected from Federal Energy Regulatory Commission filings from gas transmission companies, which are published by the Oil and Gas Journal annual data book (Penn Well Corp, 1992–2009). Due to limited offshore pipeline data, the pipeline data set in this paper contains only onshore pipeline data, and the pipeline cost in this paper does not include compressor station cost. The pipeline data set provides location and year, pipeline diameter and length. Pipelines in the data set were distributed in all states in the USA except Alaska and Hawaii. It also contains the cost information of 15 Canadian pipelines. The pipelines were completed between 1992 and 2008. Unfortunately, the data does not show the construction period of the pipelines. Therefore, cost is defined as real, accounted costs determined at the time of completion. The entire data set has 412 onshore pipelines. The data include estimated and actual cost of five cost components. The estimated costs are defined as budget, or forecast, costs at the time of decision to build the pipeline. The actual costs are defined as real accounted costs determined at the time of completing pipelines (Flyvbjerg et al., 2003). The five cost components are material, labour, miscellaneous, right of way (ROW) and total costs. Material cost covers cost of line pipe, pipeline coating and cathodic protection. Labour costs consist of the cost of pipeline construction labour. Miscellaneous cost is a composite of the costs of surveying, engineering, supervision, contingencies, telecommunications equipment, freight, taxes, allowances for funds used during construction, administration and overheads, and regulatory filing fees. ROW cost contains the cost of ROW and allowance for damages. The total cost is the sum of material cost, labour cost, miscellaneous cost and ROW cost (Penn Well Corp, 1992–2009). The location information for U.S pipelines was provided in a state format. A total of 48 states were referred to, except for Alaska and Hawaii. The US Energy Information Administration (EIA) breaks down the US Natural Gas pipelines network into six regions: Northeast, Southeast, Midwest, Southwest, Central and Western. The state grouping is defined based on 10 federal regions of the US Bureau of Labour Statistics (EIA, 2010). The map of regional definitions is shown in Figure 1. These regional definitions are used to analyse geographic difference. In this paper, the USA pipeline data are divided in to six regions according to the EIA definition. In addition, there are 15 Canadian pipelines, but reports did not show a specific province in Canada.
  • 4. 32 Z. Rui et al. Figure 1 US natural gas pipeline region map (EIA) (see online version for colours) Note: Alaska and Hawaii are not included in the US Natural pipeline network map. In order to take a comparative analysis, all costs are adjusted by the Chemical Engineering Plant Cost Index to 2008 dollars. The Chemical Engineering Plant Cost Index is widely applied on process plants for adjusting construction cost. The Chemical Engineering Plant Cost Index has 11 sub-indexes and a composite index, which is the weight average of the 11 sub-indexes (Chemical Engineering, 2011). Pipeline index and construction labour index is used to adjust pipeline material and labour cost. The Chemical Engineering Plant Index is applied to pipeline miscellaneous and ROW cost. 3 Performance of individual pipeline construction component cost estimation This section will evaluate performance of pipeline construction component cost estimation. Several methods may be used to study the difference between the estimated cost and the actual cost. In this study, the estimated cost and the actual cost are used to calculate cost overrun rate as a measurement of cost overrun. The formula for cost overrun rate is: Cost overrun rate = (actual cost - estimated cost) / estimated cost If the cost overrun rate is positive, the cost is underestimated, otherwise it is overestimated. In this paper, all cost overrun rates are calculated with the above formula. The histogram of the cost overrun rate for pipeline construction components are shown in Figure 2 to Figure 6. If the cost error is small, the histogram would be narrowly concentrated around zero. If underestimated cost is as common as overestimated cost, the histogram would be symmetrically distributed around zero. It appears that five figures exhibited non-symmetric distributions, and none of them satisfied the above mentioned
  • 5. An analysis of inaccuracy in pipeline construction cost estimation 33 assumption. For material cost, 172 (42.0% of total) pipelines were underestimated, and 238 (58.0% of total) were overestimated. For labour cost, 273 (66.7% of total) pipelines were underestimated, and 136 (33.3% of total) were overestimated. For miscellaneous cost, 166 (40.8% of total) pipelines were underestimated, and 241 (59.2% of total) were overestimated. For ROW cost, 174 (45.7% of total) pipelines were underestimated, and 207 (54.3% of total) were overestimated. For total cost, 222 (54.0% of total) pipelines were underestimated, and 189 (46.0% of total) were overestimated. Figure 2 Cost overrun rates of material cost (see online version for colours) Figure 3 Cost overrun rates of labour cost (see online version for colours)
  • 6. 34 Z. Rui et al. Figure 4 Cost overrun rates of miscellaneous cost (see online version for colours) Figure 5 Cost overrun rates of ROW cost (see online version for colours) In summary, more pipelines were overestimated for material, miscellaneous and ROW costs, while more pipelines were underestimated for labour and total cost. In general, the percentage of overestimated pipelines implies that there are still a fairly good number of pipelines being completed with costs less than the estimated cost. In addition, the majority of pipelines (87.1% for material cost, 72.3% for labour cost, 67.3% for miscellaneous cost, and 89% for total cost) have cost overrun rates between –0.4 and 0.4. However, only 49.0% of the pipelines for ROW cost have cost overrun rates between
  • 7. An analysis of inaccuracy in pipeline construction cost estimation 35 –0.4 and 0.4. It demonstrates that ROW cost overrun is more severe than cost components, which is also indicated by its standard deviation (SD) (Table 1). Figure 6 Cost overrun rates of total cost (see online version for colours) Table 1 Summaries of cost overrun of pipeline construction cost components Material Labour Miscellaneous ROW Total Skewness 5.77 4.83 4.77 3.25 2.20 Kurtosis 49.22 44.88 42.06 15.77 12.29 Minimum –0.95 –0.94 –0.94 –1.00 –0.94 Maximum 5.67 7.04 4.56 4.55 2.12 Range 6.61 7.98 5.50 5.55 3.06 Average 0.05 0.22 –0.01 0.09 0.07 Standard deviation 0.55 0.62 0.56 0.81 0.34 Total number of pipelines 410 409 407 381 411 Number of underestimated pipelines 172 273 166 174 222 Number of overestimated pipelines 238 136 241 207 189 Furthermore, statistical summaries of cost overrun of individual pipeline construction components are shown in Table 1. Skewness is a quantitative way to measure symmetry of the distribution. Symmetrical distribution has a skewness of 0. Positive skewness means that the right tail is ‘heavier’ than the left tail. Negative skewness means that the left tail dominates distribution. Kurtosis is a quantitative method to evaluate whether the shape of the data distribution fits the normal distribution. A normal distribution has a kurtosis of 0. Kurtosis of a flatter distribution is negative and that of a more peaked distribution is positive (Hill et al., 2007). Values of skewness and kurtosis in Table 1 show that none of the cost overrun of five components is symmetrical normal distribution, which matches the implication from the histogram graphs. Some
  • 8. 36 Z. Rui et al. transformation techniques (such as natural log transformation) are applied to cost overrun rate data for fitting them to normal distribution, but the data transformations are unsuccessful. Therefore, the non-parametric statistical test is used in the below sections. P-value will be produced by each test. In statistics, traditionally, p < 0.01 is considered highly significant, p < 0.05 is significant. This criterion is also adopted in this paper. Table 1 shows that the minimum cost overrun rate for individual cost components are between –94% (labour cost) and –100% (ROW cost). The maximum cost overrun rate for individual cost components are between 212% and 704%. The value of minimum and maximum indicates that cost performance for some pipelines is extremely bad. The labour cost overrun has the largest maximum-minimum range of 798%, while total cost overrun has the smallest range of 306%. The SD of individual cost components are fairly significant, between 34% and 81% of the estimated cost. The large maximum-minimum range and SD indicate that performance of pipeline construction cost estimating is very unstable. It is noteworthy that labour cost has the largest maximum-minimum range and second largest SD, and ROW cost has the largest SD. Therefore, it is difficult to estimate labour cost and ROW cost accurately. Total cost overrun has the smallest maximum-minimum range and SD due to its aggregation of other components. Average cost overrun is a key parameter to measure cost estimation performance of individual pipeline construction cost components. The labour cost has the highest average cost overrun of 22%, followed by ROW cost of 9%, total cost of 7%, material cost of 5% and miscellaneous cost of –1%. The material, labour, ROW and total costs show positive average cost overrun, while the miscellaneous cost has negative average cost overrun. This result denotes that, in average, actual cost is larger than estimated cost for all pipeline construction cost components except the miscellaneous cost. As mentioned before, there are more pipelines with overestimated material, miscellaneous and ROW costs than those with underestimated pipelines, and there are more pipelines with underestimated labour and total costs than those with overestimation of these two cost components. However, it is an interesting finding that the average cost overruns of material and ROW cost are still positive, even though there are more pipelines with overestimated material cost, and ROW cost. It appears that cost estimation of pipeline construction cost components is biased, and the underestimating error is generally greater than the overestimating error for some pipeline construction cost components. In this paper, two statistical tests are performed to investigate this inference. A binomial test is conducted to examine if the error of cost overestimating is as common as the error of cost underestimating. As shown in Table 2, the p-value of the binomial test rejects the null hypothesis that the overestimating error is as common as the underestimating error for material, labour, miscellaneous, and ROW cost estimation (p < 0.05, two sided test), but fails to reject that for total cost (p > 0.05, two sided test). Therefore, the cost estimations of all pipeline construction cost components are biased except total cost. Furthermore, the non-parametric Mann-Whitney test is employed to test if the cost underestimating error is the same as the cost overestimating error. The p-value shown in Table 2 shows that the error of underestimated pipelines’ cost overrun are much larger than the error of overestimated pipelines’ cost overrun for material, labour, miscellaneous and ROW cost (p < 5%, one sided test), but not for total cost (p > 5%, two sided test). Hence, the underestimating error is significantly more common and larger than the overestimating error for all pipeline cost components, but not for total cost.
  • 9. An analysis of inaccuracy in pipeline construction cost estimation 37 Table 2 Statistical tests of cost overrun of pipeline construction cost components Material Labour Miscellaneous ROW Total Binomial test 0.001 0 0 0 0.114 Mann-Whitney test 0.047 0 0 0.039 0.082 After analysing overall cost overrun of pipeline projects, it is more important to identify significant factors that influence pipeline projects’ cost overruns. The analyses of cost overruns in terms of pipeline project size, pipeline capacity, diameter, length, location, and completion time are carried out in the following sections. 4 Cost overrun in terms of pipeline project size Here, the project size is measured by the pipeline’s actual total cost. The pipeline total cost ranges from $33,576 to $1,933,839,076. According to the pipeline actual total cost, the pipeline project size is classified into groups of small, medium and large. 185 pipelines with a total actual cost less than $10,000,000 are classified as small projects, 192 pipelines with a total actual cost between $10,000,000 and $100,000,000 are classified as medium projects, and 33 pipelines with a total actual cost larger than $100,000,000 are classified as large projects. Table 3 Average cost overrun rate for different project size groups Components Project size Average SD Skewness Kurtosis Material Small 0.10 0.70 4.55 30.86 Medium 0.01 0.42 7.34 80.95 Large 0.04 0.13 1.22 4.19 Labour Small 0.16 0.47 1.31 6.95 Medium 0.28 0.76 5.19 40.15 Large 0.13 0.41 -0.50 4.03 Miscellaneous Small 0.01 0.46 1.08 5.68 Medium 0.01 0.46 0.98 4.01 Large -0.04 0.46 1.08 5.68 ROW Small 0.18 1.20 2.87 13.30 Medium 0.30 1.39 3.28 15.00 Large 0.23 0.54 1.60 7.12 Total Small 0.04 0.36 1.89 10.04 Medium 0.08 0.32 2.70 15.24 Large 0.12 0.24 2.50 11.58 Descriptive statistical analysis of cost overrun in terms of project size is shown in Table 3. As seen in Table 3, for the material, labour, miscellaneous cost and ROW cost, there is no linear relationship between average cost overrun rates and project sizes. However, for total cost, the average cost overrun rate increases as the project’s size increases. For the total cost, large projects have the highest cost overrun rates. A plausible explanation is that a large pipeline project, normally bigger than 1 billion dollars, can cause a huge demand that influences market price, such as steel price, and
  • 10. 38 Z. Rui et al. further increases the cost of pipeline construction. Expectation of increased pipeline construction costs induced an increase in the current unit construction cost (Rui et al., 2011a). Suppliers would raise prices with expectation for more demand. In addition, a large project limits the numbers of suppliers and contractors, reduces competition and increases the cost (Bordat et al., 2004; RGL Forensics, 2009). However, for the miscellaneous cost, large projects have the lowest cost overrun. It is possible that larger projects have better management systems which coordinate different departments, increase the efficiency of material utilisation and take advantage of economies of scale. In order to determine if there is a strong relationship between project sizes and cost overrun for different pipeline construction components, the non-parametric Kruskal-Wallis (KW) test is used to test the null hypothesis that the project size has no effect on cost overrun of pipelines. The KW test is chosen because the value of skewness and kurtosis shows that the cost overrun of each diameter group is not a normal distribution. Therefore, the KW test will be used in this part and following parts when the data does not produce normal distributions. For total cost, the result of the KW test shows that cost overrun for different project size groups are significantly different (p < 0.05). However, such a significant difference is not found for other cost components (p > 0.05). Therefore, it is concluded that the project size significantly influences cost overrun for total cost, but not for other individual cost components. Table 4 Average cost overrun rate for different diameter groups Components Diameter groups Average SD Skewness Kurtosis Num. of pipelines Material 4–20 inches 0.13 0.68 3.70 21.37 124 22–30 inches 0.03 0.42 5.62 51.28 131 34–48 inches 0.00 0.52 8.56 92.67 155 Labour 4–20 inches 0.39 0.95 3.85 23.97 126 22–30 inches 0.21 0.42 1.14 5.79 131 34–48 inches 0.09 0.33 0.87 7.18 155 Miscellaneous 4–20 inches 0.17 0.99 4.11 24.64 123 22–30 inches –0.16 0.35 0.93 4.39 131 34–48 inches 0.02 0.48 0.92 4.38 152 ROW 4–20 inches 0.43 1.57 2.61 10.01 115 22–30 inches 0.24 1.38 3.31 15.53 122 34–48 inches 0.11 0.81 2.71 15.52 153 Total 4–20 inches 0.17 0.48 1.72 6.96 124 22–30 inches 0.03 0.24 0.65 6.55 131 34–48 inches 0.02 0.23 1.39 9.59 155 5 Cost overrun in terms of pipeline diameter The range in pipeline diameter is between 4 and 48 inches. The pipeline projects are categorised into three diameter groups: 4–20 inch, 22–30 inches and 34–48 inches. Pipeline construction component cost overruns for three different pipeline diameter groups are shown in Table 4.
  • 11. An analysis of inaccuracy in pipeline construction cost estimation 39 For material, labour, ROW and total costs, 4–20 inch pipelines have the highest average cost overrun rate, followed by 22–30 inches pipelines and 34–48 inches pipelines. For miscellaneous cost, 4–20 inches pipelines have the highest average cost overrun, but 22–30 inches pipelines have the lowest average cost overrun of –16%. 4–20 inches groups have the highest average cost overrun rate for all construction components costs. It appears that small diameter pipelines are prone to cost overrun. Therefore, the non-parametric KW test is used to test the null hypothesis that type of pipeline diameter has no effect on cost overrun of pipelines construction component cost. For material, ROW and total cost, the result of the KW test shows the cost overrun is not significantly different for different diameter groups (p > 0.5). For labour and miscellaneous costs, the result of the KW test shows the cost overrun for types of diameter groups is significantly different (p < 0.01). Therefore, it is concluded that types of diameter groups influence cost overrun of pipelines for labour and miscellaneous cost, and not for other components costs. 6 Cost overrun in terms of pipeline length The cost overrun in terms of pipeline length is tested in this section. The range of pipeline length is between 0.1 and 713 miles. The length group is divided into two groups: 0–20 miles and 20–713 miles. About 78% of pipelines are shorter than 20 miles, and the rest of the pipelines are between 20 and 713 miles. Pipeline construction component cost overruns for two different pipeline length groups are shown in Table 5. Table 5 Average cost overrun rate for different length groups Components Length groups Average SD Skewness Kurtosis Num. of pipelines Material 0–20 miles 0.05 0.56 5.25 44.21 321 20–713 miles 0.04 0.51 8.14 73.36 89 Labour 0–20 miles 0.21 0.60 5.37 56.39 323 20–713 miles 0.26 0.70 3.46 20.41 89 Miscellaneous 0–20 miles 0.17 0.72 4.71 38.60 319 20–713 miles –0.03 0.40 0.82 4.74 87 ROW 0–20 miles 0.23 1.28 3.11 14.53 303 20–713 miles 0.30 1.18 3.89 21.62 87 Total 0–20 miles 0.06 0.35 2.12 11.85 321 20–713 miles 0.10 0.30 2.80 14.57 89 For material, miscellaneous and ROW costs, the 0–20 miles group has the highest average cost overrun rate, followed by the 20–713 miles inches pipelines. For labour cost and total cost, the 20–713 miles pipelines have incurred the highest average cost overrun, followed by 0–20 miles pipelines. It appears that different construction component costs have different cost overrun rate patterns. The KW test is used to test the null hypothesis that type of pipeline length has no effect on cost overrun. For all construction cost components, the results of the KW tests show the cost overrun rate difference between types of length groups are not significant at the 5% significance level (p > 0.1). Therefore, cost overrun rates of all construction cost components are not significantly influenced by types of pipeline length.
  • 12. 40 Z. Rui et al. 7 Cost overrun in terms of pipeline capacity In this paper, the pipeline volume (capacity) is calculated with formula (Zhao, 2000): V = S *L 2 ⎛D⎞ where S = π ⎜ ⎟ , V is the pipeline volume (ft3), S is the pipeline cross-sectional area ⎝2⎠ (ft2), L is the pipeline length (ft), and D is the pipeline diameter (ft). In the data set for this study, the smallest pipeline capacity is 92 ft3, and the largest is 36,220,080 ft3. In this section, all pipelines are divided into three different groups of pipeline capacities to test whether cost overrun rate is significantly different for different pipeline capacity. 135 pipelines with a capacity between less than 75,000 ft3 are classified as small projects, 136 pipelines with a capacity between 75, 000 ft3 and 284,768 ft3 are classified as medium projects, and 139 pipelines with a capacity larger than 284,768 are classified as large projects. Descriptive statistical analysis of cost overrun in terms of pipeline capacity is shown in Table 6. A noticeable observation is that the small pipeline capacity group has the highest average cost overrun rates for all construction cost components. Pipelines with small capacity appear to be particularly prone to cost overrun. Projects with large capacity may take more advantage of economies of scale. Table 6 Average cost overrun rates for different capacity groups Components Capacity groups Average SD Skewness Kurtosis Num. of pipelines Material Small 0.19 0.80 3.81 22.63 135 Medium –0.03 0.24 0.97 4.47 136 Large –0.05 0.43 8.75 93.69 139 Labour Small 0.24 0.57 1.54 7.35 135 Medium 0.25 0.84 5.37 38.99 137 Large 0.16 0.38 0.47 5.10 140 Miscellaneous Small 0.13 0.97 4.14 25.36 133 Medium –0.08 0.43 1.11 4.25 135 Large –0.03 0.43 0.94 4.79 138 ROW Small 0.34 1.50 2.50 9.29 128 Medium 0.19 1.19 4.00 23.95 130 Large 0.20 1.05 3.54 19.34 132 Total Small 0.12 0.46 1.72 7.77 135 Medium 0.03 0.29 2.45 13.17 136 Large 0.05 0.21 0.95 7.96 139 The KW test is used to verify that the pipeline capacity has no effect on cost overrun for construction cost components. For material cost, the result of KW test rejects the null hypothesis (p < 0.001), indicating that pipeline capacity influences material cost overrun, and projects with small pipeline capacity have large positive cost overrun rates. Pipeline projects with large capacity mean that more material is consumed. Therefore, projects with a large capacity take advantage of economies of scale in purchasing materials, resulting in lower costs for materials as pipeline capacity increases. It may be that the
  • 13. An analysis of inaccuracy in pipeline construction cost estimation 41 estimator of pipeline projects did not estimate unit price with capacity changing accurately or did not consider economies of scale in material cost. This may result in pipeline projects with small capacity that have large cost overrun. For labour, miscellaneous, ROW and total costs, the results fail to reject the null hypothesis that pipeline capacity has no effects on the cost overrun rates (p > 0.05). Therefore, the cost overrun differences in the labour, miscellaneous, ROW and total costs are not statistically significant for different types of pipeline capacities. Table 7 Average cost overrun rates for different regions Components Region groups Average SD Skewness Kurtosis Num. of pipelines Material Midwest –0.02 0.29 0.03 4.81 55 Northeast –0.02 0.56 7.33 72.15 156 Southwest 0.02 0.37 0.32 5.35 30 Canada 0.18 0.26 0.80 2.75 14 Central 0.06 0.28 1.58 8.24 52 Southeast 0.26 0.92 3.63 15.69 55 Western 0.09 0.50 3.22 16.22 48 Labour Midwest 0.12 0.38 1.19 8.36 55 Northeast 0.12 0.34 0.87 5.91 157 Southwest 0.28 0.60 1.04 3.30 30 Canada 0.02 0.33 –1.04 3.95 15 Central 0.20 0.49 0.31 2.38 52 Southeast 0.33 0.85 3.01 14.70 55 Western 0.55 1.14 4.20 23.28 48 Miscellaneous Midwest –0.06 0.43 1.72 7.74 54 Northeast –0.07 0.45 1.14 5.97 155 Southwest 0.05 0.52 0.62 2.62 30 Canada 1.32 2.25 1.56 4.03 14 Central –0.02 0.37 0.84 3.97 51 Southeast 0.04 0.55 1.60 5.93 55 Western –0.08 0.54 1.73 6.28 47 ROW Midwest 0.34 0.99 3.42 20.21 53 Northeast –0.10 0.76 2.31 12.10 150 Southwest 0.12 1.14 3.66 17.27 27 Canada 1.59 2.18 0.76 2.01 14 Central 0.26 1.11 2.74 12.51 50 Southeast –0.08 0.65 1.18 4.90 52 Western 1.01 2.35 1.84 5.14 44 Total Midwest 0.01 0.24 –0.77 5.72 55 Northeast 0.00 0.26 1.72 10.97 155 Southwest 0.84 0.34 0.60 3.68 30 Canada 0.14 0.31 –0.86 4.11 15 Central 0.11 0.29 1.35 6.69 52 Southeast 0.13 0.45 1.93 6.80 55 Western 0.19 0.48 2.76 10.77 48
  • 14. 42 Z. Rui et al. 8 Cost overrun in terms of different regions As we know, pipeline cost is significantly different for different regions (Rui et al., 2011b). This section discusses whether cost overrun of pipeline construction cost components is different for different regions. As seen from Table 7, it is noticeable that cost overrun rate of the pipelines in the Northeast regions is the lowest in the USA as compared to the other regions, even though the Northeast has a relatively high cost of living. In addition, the total cost overrun rate of pipelines in the Northeast regions is a perfect 0. A possible explanation is that 155 out of 412 pipelines in the data set are located in the Northeast regions, which provides more practical experience and historical information for new pipeline cost estimating in this region. A few negative cost overrun rates also appear in some regions for different construction component cost. The result of KW tests shows that the cost overruns of difference for different regions are highly significant for all construction cost components (p < 0.001). Weather condition, soil property, population density, cost of living, terrain condition, and distance from supplies are variable for different regions and make pipeline project cost estimation more difficult (Rui et al., 2011b; Zhao, 2000). More detailed information on pipeline routes is needed to explain cost overrun difference among different regions. Therefore, it is concluded that the cost overrun rates of all cost components show significant difference for different regions and the pipeline’s location matters to cost overrun in all cost components. 9 Cost overrun over time Forty-seven megaprojects between the mid 1960s and 1984 were reported with a cost overrun rate of 88% (Merrow, 1998). Over 1,000 World Bank projects between 1947 and 1987 had cost estimated errors (Pohl and Mihaljek, 1992). 55% of all Indiana Department of Transportation’s projects between 1996 and 2001 experienced cost overruns (Bordat et al., 2004). Cost overrun is constant for more than a 70-year period between 1910 and 1998 for 208 transportation projects in 14 nations on five continents (Flyvbjerg et al., 2003). All the literature show that the cost estimated error persists over time in many different types of projects. But is there any improvement in pipeline compressor station projects over time? This section tries to discover whether the cost estimating performance has improved over time. Improved performance of cost estimating is normally expected. The average cost overrun rate of compressor station construction components between 1992 and 2008 are displayed in Figure 7. The cost overrun rate of ROW cost fluctuates widely with a declining trend. The cost overrun rate of labour cost shows a decrease before 2004 and then a significant increase after 2004. But cost overrun rate of material, miscellaneous and total costs change more gradually over time. The length of the construction phase influences cost overrun rate. Therefore, it is better to use the year of planning to build as the time measurement (Flyvbjerg et al., 2003), but the available data does not provide the year of building and construction period. Therefore, the year of completion is used to as a measure of the time, which may cause bias. The non-parametric Nptrend test is conducted to test whether there is a trend of cost overrun rate over years. All results of the Nptrend test show only cost overrun rate of ROW decreases over time (p < 0.05). Therefore, based on available data, it is
  • 15. An analysis of inaccuracy in pipeline construction cost estimation 43 concluded that cost estimating of ROW cost has improved over time, not for other components. Figure 7 Annual average cost overrun rate of pipeline construction cost components (see online version for colours) 10 Conclusions and future work This paper statistically analyses the cost estimating performance of individual pipeline construction cost components by using 412 pipeline projects. The trend and distribution of all 412 pipelines construction cost components cost estimation over the 1992–2008 periods are analysed. Overall average cost overrun rates of the material cost, labour cost, miscellaneous cost, ROW cost and total cost are 4.9% (SD = 54.8%), 22.4% (SD = 61.8%), –0.9% (SD = 56.2%), 9.1% (SD = 80.9%) and 6.5% (SD = 33.5%) respectively. The labour and ROW costs have the largest cost overrun compared to the other cost components. The statistical test results show that cost estimating in all cost components is biased except in the total cost. And the magnitude of cost underestimating error is generally larger than the overestimating error except for total cost. Furthermore, cost overrun rates of pipeline construction cost components are analysed in terms of pipeline project size groups, capacity groups, diameter groups, length groups, location groups, and the year of completion to investigate the relationship between cost overruns and different groups. The cost overrun rate for the total cost shows a significant difference for different project size groups, and the cost overrun rate increases with project size. An expected large demand, limited supplies and contractors for large-size projects cause big cost overruns (Bordat et al., 2004; RGL Forensics, 2009; Rui et al., 2011a). The cost overrun rates of the labour and miscellaneous costs show significant differences for diameter groups, and the small diameter group has the highest average cost overrun rate. The cost overrun rates of all construction cost components are not significantly influenced by pipeline length. The cost overrun rate of the material cost is significant for different pipeline capacity groups, and projects with small pipeline capacities appear to be particularly prone to cost overrun. Large capacity pipeline projects may purchase material at low price due to large scale. The planners or estimator
  • 16. 44 Z. Rui et al. may not estimate the material unit price changing with scale accurately or may even fail to consider the economies of scale factors. The cost overruns of all construction cost components are significantly different for different regions. The weather, soil, terrain, terrain condition, population density and experience are suggested as causes for making it difficult to estimate cost accurately. Cost estimating accuracy of pipeline projects have not improved over the 1992–2008 time period. Based on the analysis of historical pipeline cost estimated errors, Table 8 provides some proposed guidelines for project estimators conducting pipeline cost estimation. It is considered that individual cost components should receive varying degree of attention under different conditions in order to make cost estimation efficient and reliable. A four level scale: maximum attention, moderate attention, less attention, and minimum attention, is applied for the amount of attention and effort paid to individual cost component cost analysis, depending on the project size, pipe diameter, pipeline length, pipeline capacity, and region of construction, as given in Table 8. Table 8 Proposed guidelines for pipeline cost estimators Category Sub-category Material Labour Miscellaneous ROW Total Project size Small C B D B D Medium D A D A C Large D B D A B Diameter 4–20 inches B A B A B 22–30 inches D A B A D 34–48 inches D C D B D Length 0–20 miles D A B A C 20–713 miles D A D A C Capacity Small B A B A B Medium D A C B D Large D B D B D Region Midwest D B C A D Northeast D B C C D Southwest D A D B A Canada B D A A B Central D B D A B Southeast D A D C B Western B A C A B Notes: A = maximum attention; B = moderate attention; C = less attention; D = minimum attention To the best of the authors’ knowledge, this paper is the first in-depth analysis of pipeline construction component cost overruns. Suggested future work may include the following list: • Different reasons for cost overrun for other types of projects are proposed by different researchers, and many of the proposed causes did not have hard data support. The same situation applies to pipeline projects; lack of good quality projects data is a major difficulty in investigating more in-depth causes of pipeline cost overrun. Therefore, collecting more accurate information on the pipeline
  • 17. An analysis of inaccuracy in pipeline construction cost estimation 45 construction period, the ownership of projects, the material of pipeline, and the thickness of pipeline wall is a major part of future work. Furthermore, quantity analysis of collecting data should be conducted to investigate the causes of cost overrun. • More application with analysis results will be used in the future pipeline projects, such as pipeline cost overrun distribution and average cost overrun rate. • Develop a set of recommendations to help mangers and engineers to better estimate pipeline project costs and minimise the cost estimating errors. References Bertisen, J. and Davis, G.A. (2008) ‘Bias and error in mine project capital cost estimation’, The Engineering Economist, Vol. 53, No. 2, pp.118–139. Bordat, C., McCullouch, B., Sinba, K. and Labi, S. (2004) An Analysis of Cost Overruns and Time Delays of INDOT Projects, Joint Transportation Research Program, Indiana Department of Transportation and Purdue University, West Lafayette, Indiana. Chemical Engineering (2011) Chemical Engineering’s Plant Cost Index, available at http://www.che.com/pci (accessed on May 2011). Energy Information Administration (EIA) (2010) U.S. Natural Gas Pipeline Regional Definitions Map, available at http://www.eia.doe.gov (accessed on July 2010). Flyvbjerg, B. (2007) ‘Policy and planning for large infrastructure projects: problems, causes, cures’, Environment and Planning B: Planning and Design, Vol. 34, No. 4, pp.578–597. Flyvbjerg, B., Skamris, M. and Buhl, S. (2003) ‘How common and how large are cost overrun in transport infrastructure projects?’, Transport Reviews, Vol. 23, No. 1, pp.71–88. Hill, R.C., Griffiths, W.E. and Lim, G.C. (2007) Principle of Econometrics, 3rd ed., John Wiley and Sons, Inc., New York. Infrastructure Partnerships Australia (2008) Available at http://www.infrastructure.org.au (accessed on May 2011). Jacoby, C. (2001) Report on Supplemental Agreement Reasons, AASHTO-FHWA Project Cost Overrun Study, Federal Highway Administration, US Department of Transportation, Washington, D.C. Jahren, C. and Ashe, A. (1990) ‘Predictors of cost-overrun rates’, ASCE Journal of Construction Engineering and Management, Vol. 116, No. 3, pp.548–551, American Society of Civil Engineers, Reston, VA. Merrow, E.W. (1998) Understanding the Outcomes of Megaprojects: A Quantitative Analysis of Very Large Civilian Projects, R-3560-PSSP, Rand Corporation, CA. Odeck, J. (2004) ‘Cost overruns in road construction-what are their sizes and determinants?’, Transport Policy, Vol. 11, No. 1, pp.43–53. Penn Well Corporation (1992–2009) Oil & Gas Journal Databook, Tulsa, Oklahoma. Pindyck, R.S. and Rubinfeld, D.L. (1995) Microeconomics, 3rd ed., Prentice-Hall, Englewood Cliffs, N.J. Pohl, G. and Mihaljek, D. (1992) ‘Project evaluation and uncertainty in practice: a statistical analysis of rate-of-return divergences of 1015 world bank projects’, The World Bank Economic Review, Vol. 6, No. 2, pp.255–277. RGL Forensics (2009) Ex Post Evaluation of Cohesion Policy Programmes 2000–2006, Work Package 10, European Commission, Brussels, BE. Rowland, H. (1981) The Causes and Effects of Change Orders on the Construction Process, PhD Thesis, Georgia Institute of Technology, Atlanta, GA.
  • 18. 46 Z. Rui et al. Rui, Z., Metz, P.A., Reynolds, D.B., Chen, G. and Zhou, X. (2011a) ‘Historical pipeline construction cost analysis’, International Journal of Oil, Gas and Coal Technology, Vol. 4, No. 3, pp.244–263. Rui, Z., Metz, A.P., Reynolds, B.D., Chen, G. and Zhou, X. (2011b) ‘Regression models estimate pipeline construction costs’, Oil & Gas Journal, Vol. 109, No. 14, pp.120–127. Zhao, J. (2000) ‘Diffusion, costs and learning in the development of international gas transmission lines’, Working paper IR-00-054, International Institute for Applied Systems Analysis, Austria.