SlideShare une entreprise Scribd logo
1  sur  29
BOILER COMMISSIONING.
OBJECTIVE:
It is a systematic procedure used after
completion of erection in making the Boiler
and its auxiliaries available for safe, smooth
and reliable Operation.
Major events in Boiler Commissioning
01.Air leakage test.
02.Hydro testing of boiler.
03.Readiness of Boiler auxiliaries.
04.Gas distribution test.
05.Boiler light up
06.Alkali boil-out and first stage passivation.
07.Acid cleaning and second stage passivation.
08.Steam blowing of critical piping.
09.Safety valve floating.
10.Coal firing.
AIR LEAK TEST.
Air leak test is an erection activity and is conducted
before conducting the Hydro test of boiler. The aim of
air leak test is to ensure that erection of pressure
parts is completed.
Air leak test is conducted by introducing air into the
boiler pressure parts at a pressure of approximately
8 ksc and the entire boiler pressure parts are
checked manually for any leakage.
BOILER HYDRO TEST.
Boiler hydro test is an erection activity and conducted
after ensuring zero leakage from air leak test. Boiler
hydro test is done at 1.5 times the design pressure of
drum for the first time. It is statutory requirement and
conducted every year. It is a major milestone activity
in power plant installation schedule.
Boiler hydro test is done by filling water from the
bottom most portion of the boiler. After ensuring full
flow of water through the vents the vents are closed
and pressurization is done by an external pump
installed near the drain header.
REFRACTORY DRYOUT.
After completion of refractory erection which is around
1400 tons per units it has to be dried out to remove
the moisture and to attain the physical and chemical
properties. Refractory dry out is carried out as per the
curve given by Refractory manufacturer.
READNESS OF BOILER AUXILARIES.
After erection completion of individual equipments and
their related systems, commissioning of each
system and sub system are done individually to
confirm the availability of each equipment.
1. ID Fans & Auxiliaries
2. PA Fans & Auxiliaries
3. SA Fans & Auxiliaries
4. Start-up burners and Bed Lances i.e Oil System
5. Blowers safety settings
GAS DISTRIBUTION TEST.
Gas distribution test is conducted in ESP to ensure
that the velocity of flue gas is ESP in uniform through
the entire cross sectional area of ESP.
GD test is done by operating all fans and blower at the
rated parameters and the velocity of flue gas is
measured between the collecting electrodes for the
entire width of ESP at various elevation and the values
are recorded based on the values correction are made
in GD screen hence ensuring uniform flow across ESP
cross section.
BOILER LIGHT UP.
The following activities are to be done in sequence for light
up of boiler.
1. All HT / LT supplies of boiler auxiliaries are to kept on .
2. Compressor to be started and air pressure to be
maintained at boiler end.
3. HFO to be kept in recirculation.
4. Electric heater to be taken into service.
5. Air heater to be charged.
6. Electric heat tracing of HFO lines to be kept on.
7. Lube Oil system of fans to be kept in operation.
8. Cooling water to be charged for all boiler auxiliaries.
9. Propane / LPG to be kept charged till boiler area.
10.Cold trial of igniter to be completed.
BOILER LIGHT UP.
10.CST to be filled with DM water and quality to be
confirmed.
11.Drum level to be maintained to the required level.
12.Position of all drains and vents to be confirmed.
13.Bed material filling inside combustor to be ensured.
14.Free flow of bed material from BM bunker to be
confirmed.
15.Complete box up of boiler to be confirmed.
16.Fans and blowers to be started as per sequence.
17.Boiler purge to be completed.
18.Air flow to be adjusted as required.
19.Combustor DP to be adjusted as required.
20.Boiler light up to be done.
CHEMICAL CLEANING OF BOILERS.
The primary reasons for chemical cleaning of boilers are to
prevent tube failures and improve unit availability. A
relatively smaller quantity of deposits creates difficulties in
high pressure boilers. Deposits originating both from
fabrication should be considered potential problem.
All pressure parts of a steam generator may be subjected
to heat treatment of some sort during fabrication or
erection – during forming operations, stress relief, welding
or bending. Whenever carbon low alloy steels are
subjected to high temperatures in the presence of air,
oxidation occurs, the oxides produced is known as mill
scale.
Chemical cleaning are done for removal of these foreign
materials and keeping the pressure part internals clean.
CHEMICAL CLEANING OF BOILERS STAGE - I.
Chemical cleaning of boilers adopt the following
procedure.
Water washing :
Before staring of alkali boil out, boiler is completely
flushed with DM water. Boiler is filled through
economizer till the drum is filled completely, care to be
taken to ensure that DM water does not enters the
super heater section. After filling boiler is drained in the
shortest possible time by opening all drain valves. This
process is repeated two or three times till the water
collected from the drains are clear.
CHEMICAL CLEANING OF BOILERS STAGE - I.
Alkali Boil Out :
The alkali boil out is performed by lighting up of boiler
and boiling out alkaline solution of 1000 ppm of TSP
and 500 ppm of DSP at 40 ksc drum pressure.
Required chemicals are prepared outside and directly
charged into the boiler drum through the drum
manhole doors. Before charging chemicals boiler shall
be filled to the bottom of drum and after addition of
chemical drum manhole doors to be boxed up and
drum level to be raised to normal working level.
CHEMICAL CLEANING OF BOILERS STAGE - I.
Boiler is lighted up and pressure is raised gradually to
40 ksc. After attaining this pressure, blow down is
given through individual blow down valves for one
minute each to remove substantial quantities of
impurities collected in water wall header.
Blow down are given at an interval of 4 hours and
samples are taken for analysis every 2 hours for PH,
Alkalinity, Phosphate and Oil. Boil out to be continued
for about 24 hours till oil ppm comes to less than 5
ppm. Care should be taken to maintain feeding rate to
keep the drum level normal. Care should be taken to
keep furnace flue gas outlet temperature at super
heater and re heater below 540 deg. C.
CHEMICAL CLEANING OF BOILERS STAGE - I.
After completion of boil out, boiler is boxed up and
pressure in the drum allowed to fall gradually. Drum
vents are opened at 3 ksc. Boiler to be drained when
drum metal temperature has dropped to 90 deg. C.
Rinsing :
Rinsing operation is carried out by filling and draining
method. Rinsing should be done till drain water is free
from alkali and PO4 content has reduced to less than
50 ppm. Drum is inspected and cleaned manually.
CHEMICAL CLEANING OF BOILERS STAGE - II.
After completion of rinsing subsequent system are
made ready for acid pickling after super heater is filled
and plugged. Drum internals are removed, orifice are
fixed in down comers and nitrogen blanketing
connection is made.
SH filling :
Hydrazine (200 ppm) and ammonia (to raise PH to 10)
are added to DM water in dissolving tank and slowly
pumped in super heaters. When PH of water raises to
10 at connecting tubes from super heaters in drum,
connecting pipes are plugged and super heater is kept
under pressure atleast 5.0 ksc above the drum
pressure through out the acid cleaning process.
CHEMICAL CLEANING OF BOILERS STAGE - II.
Acid Pickling :
System is filled with DM water and circulation is
established. Temperature of DM water is raised and
maintained at 65 deg. C by admitting heating system
to dissolving tank.
First inhibitor (Rodine 213) is charged fully (0.2%) and
after confirming inhibitor in return line, Hydrochloric
acid and ammonia biflouride are charged
simultaneously, addition of HCL is regulated to get an
ultimate concentration of 4% in return line preferably
within 90 minutes. Care to taken to confirm that the
concentration does not exceed beyond 6% during
charging.
CHEMICAL CLEANING OF BOILERS STAGE - II.
During acid cleaning concentration of Hcl and Fe
content in the system is checked every half an hour.
Concentration of Hcl decreases rapidly at first and
slowly afterwards and then steadies at a constant
value. Similarly, Iron value increases and attains a
steady value. Constant value of Hcl and iron content
marks the completion of acid pickling. System is
drained under nitrogen blanketing and the drained acid
is neutralized before disposal.
DM Rinse:
After draining of acid boiler is filled with DM water
circulated for one hour and the system is drained
under nitrogen blanketing.
CHEMICAL CLEANING OF BOILERS STAGE - II.
Citric acid rinse:
The system is again filled with water containing 0.2%
by weight of citric acid and PH maintained to 3.5 to 4
by adding ammonia. While filling the system with DM
water add proportionate quantity of citric acid so as to
get a uniform concentration of 0.2%. Ammonia is
added to increase the PH to 3.5 to 4.0. During this
process steam is admitted to raise the temperature to
55-60 Deg. C. After achieving uniform concentration
circulation is maintained for one hour. Samples are
collected for discharge and return lines and are
analysed for PH and iron. When value are stabilized
system is drained under nitrogen blanketing.
CHEMICAL CLEANING OF BOILERS STAGE - II.
DM rinse:
System is filled with DM water and circulated for one
hour, after one hour system is drained under nitrogen
blanketing. During rinsing operation drain samples are
checked for PH and iron contents. The same
procedure is repeated will iron content is les than 50
ppm.
After completion of rinsing boiler is boxed up and
allowed for natural cooling. At 3 ksc super heater and
drum vents are opened and at 90 deg. C boiler drum
metal temperature the system s drained and left
aerated by natural draft. After this second stage
passivation is completed which marks the completion
of chemical cleaning.
STEAM BLOWING.
Introduction :
The purpose of steam blowing is to remove scales,
loose material, iron cutting etc., which have been
entrapped in super heater, re heater and related piping
during manufacture, storage and erection. Failure to
remove these debris may result in damage to the
turbine blades, valves etc.
Technique adopted:
The steam blowing is carried out by puffing method.
This technique will give thermal shock to the contour
being purged to dislodge the scales etc., which will be
subsequently cleared by the expanding steam.
STEAM BLOWING.
Steam blowing is done in four stage a follows.
Stage I : Super heaters and Main steam lines upto HP
stop cum control valve.
Stage II : SH, MS lines and cold re heat lines, during
last few blows the HP by pass lines are included in
parallel. If necessary, HP by pass line are blown
separately.
Stage III : SH, MS lines, CRH lines, re heater, Hot re
heater lines an upstream of LP by pass valve.
Stage IV: Extraction lines & Misc. auxiliary steam lines.
STEAM BLOWING.
Procedure :
The boiler drum pressure is raised to 40ksc and the
line to be blown is warmed up. Then firing is stopped
and simultaneously both the temporary stop valves are
opened. It is preferred to have a single switch to
operate both the stop valves.
To prevent thermal stresses in the drum the saturation
temperature change in the drum is limited to 40 deg C
maximum i.e when the pressure in the drum comes
down to around 19 ksc, the temporary stop valves are
closed. The standard practice is to limit the number of
blows per day to 8/10 at an interval of 90 minutes with
overnight cooling usually from 2200 hrs. to 0600 hrs.
STEAM BLOWING.
Disturbance factor (DF) :
The ratio of force exerted by blowing steam on particular
matter to the force exerted by steam at MCR condition
during normal operation, is referred to as Disturbance
factor which is also known as Clean Force Ratio or
Cleanliness factor.
DF = (Drag under steam blowing) / (Drag under MCR flow).
= (Q2
SB x VSB) / (Q2
MCR x VMCR).
Where
QSB = Steam flow during steam blowing.
QMCR = Steam flow at MCR.
VSB = Specific volume of steam during steam blowing.
VMCR = Specific volume of steam at MCR.
British Electricity International, England recommend DF
of 1.3 to 1.6 while a per GE, it should be > 1.0.
STEAM BLOWING.
Acceptance :
The colour of the steam charged to atmosphere can be
used as an indication of the debris being removed from
the contour. In addition, the aberration on the polished
target plates fixed in the exhaust piping will be used to
indicate the effectiveness of blowing. Softer material like
aluminum, brass, copper etc. can also be used for target
plates. For evaluating the cleanliness and termination
point of steam blowing, target plates made of alloy steel
are to be used.
SAFETY VALVE FLOATING.
Safety valve floating is done to confirm the freeness
and automatic operation of the valve. Safety valve
are used to prevent the boiler pressure parts from
being pressurized more than the design value. It is
also a statutory requirement and is done yearly.
The sequence of floating at SLPP is
Drum (Right)
Drum (Left)
Main steam.
SAFETY VALVE FLOATING.
Set Pr. Re set Pr. % BD.Location.
Drum (Right)
Drum (Left)
Main steam
CRH
HRH (Right)
HRH (Left)
157.0 149.2 5.0
161.7 153.7 5.0
140.0 133.0 5.0
35.0 33.3 5.0
32.4 30.8 5.0
33.1 31.5 5.0
COAL FIRING.
After completion of safety valve floating coal firing is
done. After achieving required parameters coal
feeding is started by opening MFT, and starting
LRALF and lignite conveyor in sequence . Parallel
opening of manual isolation gates of lignite bunker
are done. After reaching rated parameters the
expansion readings of entire boiler is noted.
Boiler Commissioning Process Guide

Contenu connexe

Tendances

Unit shutdown procedure operation
Unit shutdown procedure operationUnit shutdown procedure operation
Unit shutdown procedure operationNitin Patel
 
Boiler Drum And Its Internals
Boiler Drum And Its InternalsBoiler Drum And Its Internals
Boiler Drum And Its InternalsAshrant Dass
 
210 MW BHEL Turbine Cycle Heat Balance
210 MW BHEL Turbine Cycle Heat Balance210 MW BHEL Turbine Cycle Heat Balance
210 MW BHEL Turbine Cycle Heat BalanceManohar Tatwawadi
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownNitin Mahalle
 
Pulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedurePulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedureAshvani Shukla
 
INTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGINTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGSURAJ KUMAR
 
Factors Affecting Boiler Performance
Factors Affecting Boiler PerformanceFactors Affecting Boiler Performance
Factors Affecting Boiler PerformanceManohar Tatwawadi
 
Boiler Reheater protection
Boiler Reheater  protectionBoiler Reheater  protection
Boiler Reheater protectionanujkumarsingh79
 
Construction of 500 MW Steam Boiler
Construction of 500 MW Steam BoilerConstruction of 500 MW Steam Boiler
Construction of 500 MW Steam BoilerVaibhav Paydelwar
 
Energy adudit methodology for boiler
Energy adudit methodology for boilerEnergy adudit methodology for boiler
Energy adudit methodology for boilerKongkiert Tankayura
 
Boiler efficiency by loss Method
Boiler efficiency by loss MethodBoiler efficiency by loss Method
Boiler efficiency by loss MethodRajeev Saini
 
210 mw turbine cycle heat rate
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rateManohar Tatwawadi
 
BOILER OPERATION PPT.pptx
BOILER OPERATION PPT.pptxBOILER OPERATION PPT.pptx
BOILER OPERATION PPT.pptxSatwikSingh25
 
Cfbc boiler drive interlock
Cfbc boiler drive interlockCfbc boiler drive interlock
Cfbc boiler drive interlockAshvani Shukla
 

Tendances (20)

Unit shutdown procedure operation
Unit shutdown procedure operationUnit shutdown procedure operation
Unit shutdown procedure operation
 
Boiler Operation and Maintenance Experiences
Boiler Operation and Maintenance ExperiencesBoiler Operation and Maintenance Experiences
Boiler Operation and Maintenance Experiences
 
Boiler Drum And Its Internals
Boiler Drum And Its InternalsBoiler Drum And Its Internals
Boiler Drum And Its Internals
 
210 MW BHEL Turbine Cycle Heat Balance
210 MW BHEL Turbine Cycle Heat Balance210 MW BHEL Turbine Cycle Heat Balance
210 MW BHEL Turbine Cycle Heat Balance
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdown
 
Boiler -Emergency Handling
 Boiler -Emergency Handling Boiler -Emergency Handling
Boiler -Emergency Handling
 
Pulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedurePulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedure
 
INTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNINGINTRODUCTION TO GOVERNING
INTRODUCTION TO GOVERNING
 
Factors Affecting Boiler Performance
Factors Affecting Boiler PerformanceFactors Affecting Boiler Performance
Factors Affecting Boiler Performance
 
Boiler Reheater protection
Boiler Reheater  protectionBoiler Reheater  protection
Boiler Reheater protection
 
Construction of 500 MW Steam Boiler
Construction of 500 MW Steam BoilerConstruction of 500 MW Steam Boiler
Construction of 500 MW Steam Boiler
 
Condensate system
Condensate systemCondensate system
Condensate system
 
Energy adudit methodology for boiler
Energy adudit methodology for boilerEnergy adudit methodology for boiler
Energy adudit methodology for boiler
 
Boiler efficiency by loss Method
Boiler efficiency by loss MethodBoiler efficiency by loss Method
Boiler efficiency by loss Method
 
210 mw turbine cycle heat rate
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rate
 
Heat rate of coal fired power plant
Heat rate of coal fired power plantHeat rate of coal fired power plant
Heat rate of coal fired power plant
 
boiler turbine emergency
boiler turbine emergencyboiler turbine emergency
boiler turbine emergency
 
BOILER OPERATION PPT.pptx
BOILER OPERATION PPT.pptxBOILER OPERATION PPT.pptx
BOILER OPERATION PPT.pptx
 
Super critical boiler
Super critical boilerSuper critical boiler
Super critical boiler
 
Cfbc boiler drive interlock
Cfbc boiler drive interlockCfbc boiler drive interlock
Cfbc boiler drive interlock
 

En vedette

World Class Manufacturing:Plant Start Up and Commissioning Procedure
World  Class Manufacturing:Plant Start Up and Commissioning Procedure World  Class Manufacturing:Plant Start Up and Commissioning Procedure
World Class Manufacturing:Plant Start Up and Commissioning Procedure HIMADRI BANERJI
 
Cold hot working_annealing
Cold hot working_annealingCold hot working_annealing
Cold hot working_annealingPradeep I
 
Pre commissioning steam turbines load trial
Pre commissioning steam turbines load trialPre commissioning steam turbines load trial
Pre commissioning steam turbines load trialNagesh H
 
The commissioning process
The commissioning processThe commissioning process
The commissioning processtreshammedia
 
Precommissioning and Commissioning
Precommissioning and CommissioningPrecommissioning and Commissioning
Precommissioning and CommissioningWendy Soerachman
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process
 

En vedette (6)

World Class Manufacturing:Plant Start Up and Commissioning Procedure
World  Class Manufacturing:Plant Start Up and Commissioning Procedure World  Class Manufacturing:Plant Start Up and Commissioning Procedure
World Class Manufacturing:Plant Start Up and Commissioning Procedure
 
Cold hot working_annealing
Cold hot working_annealingCold hot working_annealing
Cold hot working_annealing
 
Pre commissioning steam turbines load trial
Pre commissioning steam turbines load trialPre commissioning steam turbines load trial
Pre commissioning steam turbines load trial
 
The commissioning process
The commissioning processThe commissioning process
The commissioning process
 
Precommissioning and Commissioning
Precommissioning and CommissioningPrecommissioning and Commissioning
Precommissioning and Commissioning
 
Tender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement GuideTender Process | A Complete Procurement Guide
Tender Process | A Complete Procurement Guide
 

Similaire à Boiler Commissioning Process Guide

Chemical Cleaning of Boiler in a Thermal Power Plant
Chemical Cleaning of Boiler in a Thermal Power PlantChemical Cleaning of Boiler in a Thermal Power Plant
Chemical Cleaning of Boiler in a Thermal Power PlantSUDHEER KUMAR KALYANAM
 
mech 2nd yr lab report.pdf
mech 2nd yr lab report.pdfmech 2nd yr lab report.pdf
mech 2nd yr lab report.pdfMOHDAHMED52
 
Training on OJT of Boiler Operation00.pdf
Training on OJT of Boiler Operation00.pdfTraining on OJT of Boiler Operation00.pdf
Training on OJT of Boiler Operation00.pdfMadan Karki
 
Boiler Operation and Maintenance - New.ppt
Boiler Operation and Maintenance - New.pptBoiler Operation and Maintenance - New.ppt
Boiler Operation and Maintenance - New.pptEsosa8
 
Final Presentation Mehedei ID-13207016.pptx
Final Presentation Mehedei ID-13207016.pptxFinal Presentation Mehedei ID-13207016.pptx
Final Presentation Mehedei ID-13207016.pptxmehede1
 
INDUCTION AT INDUSTRIAL SERVICE OF .pptx
INDUCTION AT INDUSTRIAL SERVICE OF .pptxINDUCTION AT INDUSTRIAL SERVICE OF .pptx
INDUCTION AT INDUSTRIAL SERVICE OF .pptxEmmanuelIsiayinekife
 
HYDROSTATIC TESTING
HYDROSTATIC TESTINGHYDROSTATIC TESTING
HYDROSTATIC TESTINGPaul Sumal
 
Boiler accessories
Boiler accessoriesBoiler accessories
Boiler accessoriesrudrik joshi
 
Sabardairy Training Report
Sabardairy Training ReportSabardairy Training Report
Sabardairy Training ReportNiravDesai66
 
Bio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERING
Bio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERINGBio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERING
Bio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERINGanirbanmaity1992
 
Boilers ppt (energy conversion)
Boilers ppt (energy conversion)Boilers ppt (energy conversion)
Boilers ppt (energy conversion)Dinesh Panchal
 

Similaire à Boiler Commissioning Process Guide (20)

Boiler operation (2)
Boiler operation (2)Boiler operation (2)
Boiler operation (2)
 
Presentation On Boiler Analysis
Presentation On Boiler AnalysisPresentation On Boiler Analysis
Presentation On Boiler Analysis
 
sugar mill ss.pptx
sugar mill ss.pptxsugar mill ss.pptx
sugar mill ss.pptx
 
Chemical Cleaning of Boiler in a Thermal Power Plant
Chemical Cleaning of Boiler in a Thermal Power PlantChemical Cleaning of Boiler in a Thermal Power Plant
Chemical Cleaning of Boiler in a Thermal Power Plant
 
mech 2nd yr lab report.pdf
mech 2nd yr lab report.pdfmech 2nd yr lab report.pdf
mech 2nd yr lab report.pdf
 
Steam and Steam Boiler
Steam and Steam BoilerSteam and Steam Boiler
Steam and Steam Boiler
 
Training on OJT of Boiler Operation00.pdf
Training on OJT of Boiler Operation00.pdfTraining on OJT of Boiler Operation00.pdf
Training on OJT of Boiler Operation00.pdf
 
Boiler Operation and Maintenance - New.ppt
Boiler Operation and Maintenance - New.pptBoiler Operation and Maintenance - New.ppt
Boiler Operation and Maintenance - New.ppt
 
Final Presentation Mehedei ID-13207016.pptx
Final Presentation Mehedei ID-13207016.pptxFinal Presentation Mehedei ID-13207016.pptx
Final Presentation Mehedei ID-13207016.pptx
 
INDUCTION AT INDUSTRIAL SERVICE OF .pptx
INDUCTION AT INDUSTRIAL SERVICE OF .pptxINDUCTION AT INDUSTRIAL SERVICE OF .pptx
INDUCTION AT INDUSTRIAL SERVICE OF .pptx
 
HYDROSTATIC TESTING
HYDROSTATIC TESTINGHYDROSTATIC TESTING
HYDROSTATIC TESTING
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
 
Boiler accessories
Boiler accessoriesBoiler accessories
Boiler accessories
 
Steam boilers
Steam boilersSteam boilers
Steam boilers
 
steam pow rplant
steam pow  rplantsteam pow  rplant
steam pow rplant
 
steam boilers.pptx
steam boilers.pptxsteam boilers.pptx
steam boilers.pptx
 
narendra VT SIT
narendra VT SITnarendra VT SIT
narendra VT SIT
 
Sabardairy Training Report
Sabardairy Training ReportSabardairy Training Report
Sabardairy Training Report
 
Bio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERING
Bio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERINGBio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERING
Bio medical incinerator by Anirban Maity, B.TECH, ELECTRICAL ENGINEERING
 
Boilers ppt (energy conversion)
Boilers ppt (energy conversion)Boilers ppt (energy conversion)
Boilers ppt (energy conversion)
 

Dernier

定制(UOIT学位证)加拿大安大略理工大学毕业证成绩单原版一比一
 定制(UOIT学位证)加拿大安大略理工大学毕业证成绩单原版一比一 定制(UOIT学位证)加拿大安大略理工大学毕业证成绩单原版一比一
定制(UOIT学位证)加拿大安大略理工大学毕业证成绩单原版一比一Fs sss
 
AI ppt introduction , advandtage pros and cons.pptx
AI ppt introduction , advandtage pros and cons.pptxAI ppt introduction , advandtage pros and cons.pptx
AI ppt introduction , advandtage pros and cons.pptxdeepakkrlkr2002
 
办理(Salford毕业证书)索尔福德大学毕业证成绩单原版一比一
办理(Salford毕业证书)索尔福德大学毕业证成绩单原版一比一办理(Salford毕业证书)索尔福德大学毕业证成绩单原版一比一
办理(Salford毕业证书)索尔福德大学毕业证成绩单原版一比一diploma 1
 
Back on Track: Navigating the Return to Work after Parental Leave
Back on Track: Navigating the Return to Work after Parental LeaveBack on Track: Navigating the Return to Work after Parental Leave
Back on Track: Navigating the Return to Work after Parental LeaveMarharyta Nedzelska
 
定制(SCU毕业证书)南十字星大学毕业证成绩单原版一比一
定制(SCU毕业证书)南十字星大学毕业证成绩单原版一比一定制(SCU毕业证书)南十字星大学毕业证成绩单原版一比一
定制(SCU毕业证书)南十字星大学毕业证成绩单原版一比一z xss
 
原版定制copy澳洲查尔斯达尔文大学毕业证CDU毕业证成绩单留信学历认证保障质量
原版定制copy澳洲查尔斯达尔文大学毕业证CDU毕业证成绩单留信学历认证保障质量原版定制copy澳洲查尔斯达尔文大学毕业证CDU毕业证成绩单留信学历认证保障质量
原版定制copy澳洲查尔斯达尔文大学毕业证CDU毕业证成绩单留信学历认证保障质量sehgh15heh
 
ME 205- Chapter 6 - Pure Bending of Beams.pdf
ME 205- Chapter 6 - Pure Bending of Beams.pdfME 205- Chapter 6 - Pure Bending of Beams.pdf
ME 205- Chapter 6 - Pure Bending of Beams.pdfaae4149584
 
Storytelling, Ethics and Workflow in Documentary Photography
Storytelling, Ethics and Workflow in Documentary PhotographyStorytelling, Ethics and Workflow in Documentary Photography
Storytelling, Ethics and Workflow in Documentary PhotographyOrtega Alikwe
 
办理哈珀亚当斯大学学院毕业证书文凭学位证书
办理哈珀亚当斯大学学院毕业证书文凭学位证书办理哈珀亚当斯大学学院毕业证书文凭学位证书
办理哈珀亚当斯大学学院毕业证书文凭学位证书saphesg8
 
Unlock Your Creative Potential: 7 Skills for Content Creator Evolution
Unlock Your Creative Potential: 7 Skills for Content Creator EvolutionUnlock Your Creative Potential: 7 Skills for Content Creator Evolution
Unlock Your Creative Potential: 7 Skills for Content Creator EvolutionRhazes Ghaisan
 
Ioannis Tzachristas Self-Presentation for MBA.pdf
Ioannis Tzachristas Self-Presentation for MBA.pdfIoannis Tzachristas Self-Presentation for MBA.pdf
Ioannis Tzachristas Self-Presentation for MBA.pdfjtzach
 
Escort Service Andheri WhatsApp:+91-9833363713
Escort Service Andheri WhatsApp:+91-9833363713Escort Service Andheri WhatsApp:+91-9833363713
Escort Service Andheri WhatsApp:+91-9833363713Riya Pathan
 
办理学位证(UoM证书)北安普顿大学毕业证成绩单原版一比一
办理学位证(UoM证书)北安普顿大学毕业证成绩单原版一比一办理学位证(UoM证书)北安普顿大学毕业证成绩单原版一比一
办理学位证(UoM证书)北安普顿大学毕业证成绩单原版一比一A SSS
 
8377877756 Full Enjoy @24/7 Call Girls in Pitampura Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Pitampura Delhi NCR8377877756 Full Enjoy @24/7 Call Girls in Pitampura Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Pitampura Delhi NCRdollysharma2066
 
定制英国克兰菲尔德大学毕业证成绩单原版一比一
定制英国克兰菲尔德大学毕业证成绩单原版一比一定制英国克兰菲尔德大学毕业证成绩单原版一比一
定制英国克兰菲尔德大学毕业证成绩单原版一比一z zzz
 
定制(Waikato毕业证书)新西兰怀卡托大学毕业证成绩单原版一比一
定制(Waikato毕业证书)新西兰怀卡托大学毕业证成绩单原版一比一定制(Waikato毕业证书)新西兰怀卡托大学毕业证成绩单原版一比一
定制(Waikato毕业证书)新西兰怀卡托大学毕业证成绩单原版一比一Fs
 
Protection of Children in context of IHL and Counter Terrorism
Protection of Children in context of IHL and  Counter TerrorismProtection of Children in context of IHL and  Counter Terrorism
Protection of Children in context of IHL and Counter TerrorismNilendra Kumar
 
Gurgaon Call Girls: Free Delivery 24x7 at Your Doorstep G.G.N = 8377087607
Gurgaon Call Girls: Free Delivery 24x7 at Your Doorstep G.G.N = 8377087607Gurgaon Call Girls: Free Delivery 24x7 at Your Doorstep G.G.N = 8377087607
Gurgaon Call Girls: Free Delivery 24x7 at Your Doorstep G.G.N = 8377087607dollysharma2066
 
Application deck- Cyril Caudroy-2024.pdf
Application deck- Cyril Caudroy-2024.pdfApplication deck- Cyril Caudroy-2024.pdf
Application deck- Cyril Caudroy-2024.pdfCyril CAUDROY
 
格里菲斯大学毕业证(Griffith毕业证)#文凭成绩单#真实留信学历认证永久存档
格里菲斯大学毕业证(Griffith毕业证)#文凭成绩单#真实留信学历认证永久存档格里菲斯大学毕业证(Griffith毕业证)#文凭成绩单#真实留信学历认证永久存档
格里菲斯大学毕业证(Griffith毕业证)#文凭成绩单#真实留信学历认证永久存档208367051
 

Dernier (20)

定制(UOIT学位证)加拿大安大略理工大学毕业证成绩单原版一比一
 定制(UOIT学位证)加拿大安大略理工大学毕业证成绩单原版一比一 定制(UOIT学位证)加拿大安大略理工大学毕业证成绩单原版一比一
定制(UOIT学位证)加拿大安大略理工大学毕业证成绩单原版一比一
 
AI ppt introduction , advandtage pros and cons.pptx
AI ppt introduction , advandtage pros and cons.pptxAI ppt introduction , advandtage pros and cons.pptx
AI ppt introduction , advandtage pros and cons.pptx
 
办理(Salford毕业证书)索尔福德大学毕业证成绩单原版一比一
办理(Salford毕业证书)索尔福德大学毕业证成绩单原版一比一办理(Salford毕业证书)索尔福德大学毕业证成绩单原版一比一
办理(Salford毕业证书)索尔福德大学毕业证成绩单原版一比一
 
Back on Track: Navigating the Return to Work after Parental Leave
Back on Track: Navigating the Return to Work after Parental LeaveBack on Track: Navigating the Return to Work after Parental Leave
Back on Track: Navigating the Return to Work after Parental Leave
 
定制(SCU毕业证书)南十字星大学毕业证成绩单原版一比一
定制(SCU毕业证书)南十字星大学毕业证成绩单原版一比一定制(SCU毕业证书)南十字星大学毕业证成绩单原版一比一
定制(SCU毕业证书)南十字星大学毕业证成绩单原版一比一
 
原版定制copy澳洲查尔斯达尔文大学毕业证CDU毕业证成绩单留信学历认证保障质量
原版定制copy澳洲查尔斯达尔文大学毕业证CDU毕业证成绩单留信学历认证保障质量原版定制copy澳洲查尔斯达尔文大学毕业证CDU毕业证成绩单留信学历认证保障质量
原版定制copy澳洲查尔斯达尔文大学毕业证CDU毕业证成绩单留信学历认证保障质量
 
ME 205- Chapter 6 - Pure Bending of Beams.pdf
ME 205- Chapter 6 - Pure Bending of Beams.pdfME 205- Chapter 6 - Pure Bending of Beams.pdf
ME 205- Chapter 6 - Pure Bending of Beams.pdf
 
Storytelling, Ethics and Workflow in Documentary Photography
Storytelling, Ethics and Workflow in Documentary PhotographyStorytelling, Ethics and Workflow in Documentary Photography
Storytelling, Ethics and Workflow in Documentary Photography
 
办理哈珀亚当斯大学学院毕业证书文凭学位证书
办理哈珀亚当斯大学学院毕业证书文凭学位证书办理哈珀亚当斯大学学院毕业证书文凭学位证书
办理哈珀亚当斯大学学院毕业证书文凭学位证书
 
Unlock Your Creative Potential: 7 Skills for Content Creator Evolution
Unlock Your Creative Potential: 7 Skills for Content Creator EvolutionUnlock Your Creative Potential: 7 Skills for Content Creator Evolution
Unlock Your Creative Potential: 7 Skills for Content Creator Evolution
 
Ioannis Tzachristas Self-Presentation for MBA.pdf
Ioannis Tzachristas Self-Presentation for MBA.pdfIoannis Tzachristas Self-Presentation for MBA.pdf
Ioannis Tzachristas Self-Presentation for MBA.pdf
 
Escort Service Andheri WhatsApp:+91-9833363713
Escort Service Andheri WhatsApp:+91-9833363713Escort Service Andheri WhatsApp:+91-9833363713
Escort Service Andheri WhatsApp:+91-9833363713
 
办理学位证(UoM证书)北安普顿大学毕业证成绩单原版一比一
办理学位证(UoM证书)北安普顿大学毕业证成绩单原版一比一办理学位证(UoM证书)北安普顿大学毕业证成绩单原版一比一
办理学位证(UoM证书)北安普顿大学毕业证成绩单原版一比一
 
8377877756 Full Enjoy @24/7 Call Girls in Pitampura Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Pitampura Delhi NCR8377877756 Full Enjoy @24/7 Call Girls in Pitampura Delhi NCR
8377877756 Full Enjoy @24/7 Call Girls in Pitampura Delhi NCR
 
定制英国克兰菲尔德大学毕业证成绩单原版一比一
定制英国克兰菲尔德大学毕业证成绩单原版一比一定制英国克兰菲尔德大学毕业证成绩单原版一比一
定制英国克兰菲尔德大学毕业证成绩单原版一比一
 
定制(Waikato毕业证书)新西兰怀卡托大学毕业证成绩单原版一比一
定制(Waikato毕业证书)新西兰怀卡托大学毕业证成绩单原版一比一定制(Waikato毕业证书)新西兰怀卡托大学毕业证成绩单原版一比一
定制(Waikato毕业证书)新西兰怀卡托大学毕业证成绩单原版一比一
 
Protection of Children in context of IHL and Counter Terrorism
Protection of Children in context of IHL and  Counter TerrorismProtection of Children in context of IHL and  Counter Terrorism
Protection of Children in context of IHL and Counter Terrorism
 
Gurgaon Call Girls: Free Delivery 24x7 at Your Doorstep G.G.N = 8377087607
Gurgaon Call Girls: Free Delivery 24x7 at Your Doorstep G.G.N = 8377087607Gurgaon Call Girls: Free Delivery 24x7 at Your Doorstep G.G.N = 8377087607
Gurgaon Call Girls: Free Delivery 24x7 at Your Doorstep G.G.N = 8377087607
 
Application deck- Cyril Caudroy-2024.pdf
Application deck- Cyril Caudroy-2024.pdfApplication deck- Cyril Caudroy-2024.pdf
Application deck- Cyril Caudroy-2024.pdf
 
格里菲斯大学毕业证(Griffith毕业证)#文凭成绩单#真实留信学历认证永久存档
格里菲斯大学毕业证(Griffith毕业证)#文凭成绩单#真实留信学历认证永久存档格里菲斯大学毕业证(Griffith毕业证)#文凭成绩单#真实留信学历认证永久存档
格里菲斯大学毕业证(Griffith毕业证)#文凭成绩单#真实留信学历认证永久存档
 

Boiler Commissioning Process Guide

  • 2. OBJECTIVE: It is a systematic procedure used after completion of erection in making the Boiler and its auxiliaries available for safe, smooth and reliable Operation.
  • 3. Major events in Boiler Commissioning 01.Air leakage test. 02.Hydro testing of boiler. 03.Readiness of Boiler auxiliaries. 04.Gas distribution test. 05.Boiler light up 06.Alkali boil-out and first stage passivation. 07.Acid cleaning and second stage passivation. 08.Steam blowing of critical piping. 09.Safety valve floating. 10.Coal firing.
  • 4. AIR LEAK TEST. Air leak test is an erection activity and is conducted before conducting the Hydro test of boiler. The aim of air leak test is to ensure that erection of pressure parts is completed. Air leak test is conducted by introducing air into the boiler pressure parts at a pressure of approximately 8 ksc and the entire boiler pressure parts are checked manually for any leakage.
  • 5. BOILER HYDRO TEST. Boiler hydro test is an erection activity and conducted after ensuring zero leakage from air leak test. Boiler hydro test is done at 1.5 times the design pressure of drum for the first time. It is statutory requirement and conducted every year. It is a major milestone activity in power plant installation schedule. Boiler hydro test is done by filling water from the bottom most portion of the boiler. After ensuring full flow of water through the vents the vents are closed and pressurization is done by an external pump installed near the drain header.
  • 6. REFRACTORY DRYOUT. After completion of refractory erection which is around 1400 tons per units it has to be dried out to remove the moisture and to attain the physical and chemical properties. Refractory dry out is carried out as per the curve given by Refractory manufacturer.
  • 7. READNESS OF BOILER AUXILARIES. After erection completion of individual equipments and their related systems, commissioning of each system and sub system are done individually to confirm the availability of each equipment. 1. ID Fans & Auxiliaries 2. PA Fans & Auxiliaries 3. SA Fans & Auxiliaries 4. Start-up burners and Bed Lances i.e Oil System 5. Blowers safety settings
  • 8. GAS DISTRIBUTION TEST. Gas distribution test is conducted in ESP to ensure that the velocity of flue gas is ESP in uniform through the entire cross sectional area of ESP. GD test is done by operating all fans and blower at the rated parameters and the velocity of flue gas is measured between the collecting electrodes for the entire width of ESP at various elevation and the values are recorded based on the values correction are made in GD screen hence ensuring uniform flow across ESP cross section.
  • 9. BOILER LIGHT UP. The following activities are to be done in sequence for light up of boiler. 1. All HT / LT supplies of boiler auxiliaries are to kept on . 2. Compressor to be started and air pressure to be maintained at boiler end. 3. HFO to be kept in recirculation. 4. Electric heater to be taken into service. 5. Air heater to be charged. 6. Electric heat tracing of HFO lines to be kept on. 7. Lube Oil system of fans to be kept in operation. 8. Cooling water to be charged for all boiler auxiliaries. 9. Propane / LPG to be kept charged till boiler area. 10.Cold trial of igniter to be completed.
  • 10. BOILER LIGHT UP. 10.CST to be filled with DM water and quality to be confirmed. 11.Drum level to be maintained to the required level. 12.Position of all drains and vents to be confirmed. 13.Bed material filling inside combustor to be ensured. 14.Free flow of bed material from BM bunker to be confirmed. 15.Complete box up of boiler to be confirmed. 16.Fans and blowers to be started as per sequence. 17.Boiler purge to be completed. 18.Air flow to be adjusted as required. 19.Combustor DP to be adjusted as required. 20.Boiler light up to be done.
  • 11. CHEMICAL CLEANING OF BOILERS. The primary reasons for chemical cleaning of boilers are to prevent tube failures and improve unit availability. A relatively smaller quantity of deposits creates difficulties in high pressure boilers. Deposits originating both from fabrication should be considered potential problem. All pressure parts of a steam generator may be subjected to heat treatment of some sort during fabrication or erection – during forming operations, stress relief, welding or bending. Whenever carbon low alloy steels are subjected to high temperatures in the presence of air, oxidation occurs, the oxides produced is known as mill scale. Chemical cleaning are done for removal of these foreign materials and keeping the pressure part internals clean.
  • 12. CHEMICAL CLEANING OF BOILERS STAGE - I. Chemical cleaning of boilers adopt the following procedure. Water washing : Before staring of alkali boil out, boiler is completely flushed with DM water. Boiler is filled through economizer till the drum is filled completely, care to be taken to ensure that DM water does not enters the super heater section. After filling boiler is drained in the shortest possible time by opening all drain valves. This process is repeated two or three times till the water collected from the drains are clear.
  • 13. CHEMICAL CLEANING OF BOILERS STAGE - I. Alkali Boil Out : The alkali boil out is performed by lighting up of boiler and boiling out alkaline solution of 1000 ppm of TSP and 500 ppm of DSP at 40 ksc drum pressure. Required chemicals are prepared outside and directly charged into the boiler drum through the drum manhole doors. Before charging chemicals boiler shall be filled to the bottom of drum and after addition of chemical drum manhole doors to be boxed up and drum level to be raised to normal working level.
  • 14. CHEMICAL CLEANING OF BOILERS STAGE - I. Boiler is lighted up and pressure is raised gradually to 40 ksc. After attaining this pressure, blow down is given through individual blow down valves for one minute each to remove substantial quantities of impurities collected in water wall header. Blow down are given at an interval of 4 hours and samples are taken for analysis every 2 hours for PH, Alkalinity, Phosphate and Oil. Boil out to be continued for about 24 hours till oil ppm comes to less than 5 ppm. Care should be taken to maintain feeding rate to keep the drum level normal. Care should be taken to keep furnace flue gas outlet temperature at super heater and re heater below 540 deg. C.
  • 15. CHEMICAL CLEANING OF BOILERS STAGE - I. After completion of boil out, boiler is boxed up and pressure in the drum allowed to fall gradually. Drum vents are opened at 3 ksc. Boiler to be drained when drum metal temperature has dropped to 90 deg. C. Rinsing : Rinsing operation is carried out by filling and draining method. Rinsing should be done till drain water is free from alkali and PO4 content has reduced to less than 50 ppm. Drum is inspected and cleaned manually.
  • 16. CHEMICAL CLEANING OF BOILERS STAGE - II. After completion of rinsing subsequent system are made ready for acid pickling after super heater is filled and plugged. Drum internals are removed, orifice are fixed in down comers and nitrogen blanketing connection is made. SH filling : Hydrazine (200 ppm) and ammonia (to raise PH to 10) are added to DM water in dissolving tank and slowly pumped in super heaters. When PH of water raises to 10 at connecting tubes from super heaters in drum, connecting pipes are plugged and super heater is kept under pressure atleast 5.0 ksc above the drum pressure through out the acid cleaning process.
  • 17. CHEMICAL CLEANING OF BOILERS STAGE - II. Acid Pickling : System is filled with DM water and circulation is established. Temperature of DM water is raised and maintained at 65 deg. C by admitting heating system to dissolving tank. First inhibitor (Rodine 213) is charged fully (0.2%) and after confirming inhibitor in return line, Hydrochloric acid and ammonia biflouride are charged simultaneously, addition of HCL is regulated to get an ultimate concentration of 4% in return line preferably within 90 minutes. Care to taken to confirm that the concentration does not exceed beyond 6% during charging.
  • 18. CHEMICAL CLEANING OF BOILERS STAGE - II. During acid cleaning concentration of Hcl and Fe content in the system is checked every half an hour. Concentration of Hcl decreases rapidly at first and slowly afterwards and then steadies at a constant value. Similarly, Iron value increases and attains a steady value. Constant value of Hcl and iron content marks the completion of acid pickling. System is drained under nitrogen blanketing and the drained acid is neutralized before disposal. DM Rinse: After draining of acid boiler is filled with DM water circulated for one hour and the system is drained under nitrogen blanketing.
  • 19. CHEMICAL CLEANING OF BOILERS STAGE - II. Citric acid rinse: The system is again filled with water containing 0.2% by weight of citric acid and PH maintained to 3.5 to 4 by adding ammonia. While filling the system with DM water add proportionate quantity of citric acid so as to get a uniform concentration of 0.2%. Ammonia is added to increase the PH to 3.5 to 4.0. During this process steam is admitted to raise the temperature to 55-60 Deg. C. After achieving uniform concentration circulation is maintained for one hour. Samples are collected for discharge and return lines and are analysed for PH and iron. When value are stabilized system is drained under nitrogen blanketing.
  • 20. CHEMICAL CLEANING OF BOILERS STAGE - II. DM rinse: System is filled with DM water and circulated for one hour, after one hour system is drained under nitrogen blanketing. During rinsing operation drain samples are checked for PH and iron contents. The same procedure is repeated will iron content is les than 50 ppm. After completion of rinsing boiler is boxed up and allowed for natural cooling. At 3 ksc super heater and drum vents are opened and at 90 deg. C boiler drum metal temperature the system s drained and left aerated by natural draft. After this second stage passivation is completed which marks the completion of chemical cleaning.
  • 21. STEAM BLOWING. Introduction : The purpose of steam blowing is to remove scales, loose material, iron cutting etc., which have been entrapped in super heater, re heater and related piping during manufacture, storage and erection. Failure to remove these debris may result in damage to the turbine blades, valves etc. Technique adopted: The steam blowing is carried out by puffing method. This technique will give thermal shock to the contour being purged to dislodge the scales etc., which will be subsequently cleared by the expanding steam.
  • 22. STEAM BLOWING. Steam blowing is done in four stage a follows. Stage I : Super heaters and Main steam lines upto HP stop cum control valve. Stage II : SH, MS lines and cold re heat lines, during last few blows the HP by pass lines are included in parallel. If necessary, HP by pass line are blown separately. Stage III : SH, MS lines, CRH lines, re heater, Hot re heater lines an upstream of LP by pass valve. Stage IV: Extraction lines & Misc. auxiliary steam lines.
  • 23. STEAM BLOWING. Procedure : The boiler drum pressure is raised to 40ksc and the line to be blown is warmed up. Then firing is stopped and simultaneously both the temporary stop valves are opened. It is preferred to have a single switch to operate both the stop valves. To prevent thermal stresses in the drum the saturation temperature change in the drum is limited to 40 deg C maximum i.e when the pressure in the drum comes down to around 19 ksc, the temporary stop valves are closed. The standard practice is to limit the number of blows per day to 8/10 at an interval of 90 minutes with overnight cooling usually from 2200 hrs. to 0600 hrs.
  • 24. STEAM BLOWING. Disturbance factor (DF) : The ratio of force exerted by blowing steam on particular matter to the force exerted by steam at MCR condition during normal operation, is referred to as Disturbance factor which is also known as Clean Force Ratio or Cleanliness factor. DF = (Drag under steam blowing) / (Drag under MCR flow). = (Q2 SB x VSB) / (Q2 MCR x VMCR). Where QSB = Steam flow during steam blowing. QMCR = Steam flow at MCR. VSB = Specific volume of steam during steam blowing. VMCR = Specific volume of steam at MCR. British Electricity International, England recommend DF of 1.3 to 1.6 while a per GE, it should be > 1.0.
  • 25. STEAM BLOWING. Acceptance : The colour of the steam charged to atmosphere can be used as an indication of the debris being removed from the contour. In addition, the aberration on the polished target plates fixed in the exhaust piping will be used to indicate the effectiveness of blowing. Softer material like aluminum, brass, copper etc. can also be used for target plates. For evaluating the cleanliness and termination point of steam blowing, target plates made of alloy steel are to be used.
  • 26. SAFETY VALVE FLOATING. Safety valve floating is done to confirm the freeness and automatic operation of the valve. Safety valve are used to prevent the boiler pressure parts from being pressurized more than the design value. It is also a statutory requirement and is done yearly. The sequence of floating at SLPP is Drum (Right) Drum (Left) Main steam.
  • 27. SAFETY VALVE FLOATING. Set Pr. Re set Pr. % BD.Location. Drum (Right) Drum (Left) Main steam CRH HRH (Right) HRH (Left) 157.0 149.2 5.0 161.7 153.7 5.0 140.0 133.0 5.0 35.0 33.3 5.0 32.4 30.8 5.0 33.1 31.5 5.0
  • 28. COAL FIRING. After completion of safety valve floating coal firing is done. After achieving required parameters coal feeding is started by opening MFT, and starting LRALF and lignite conveyor in sequence . Parallel opening of manual isolation gates of lignite bunker are done. After reaching rated parameters the expansion readings of entire boiler is noted.