SlideShare a Scribd company logo
1 of 29
PRESENTED BY
AJAY SHAHU
(20100872)
Industrial Training Report on
Residential building(G+3)
(2012-13)
Content
1. Introduction
2. Centre line plan
3. Foundation of Structure
4. Preparation prior casting of slab
5. Equipment
6. Volume of concrete
7. Activities carried out after casting of slab
8. Conclusion
9. References
1.Introduction
• It is a residential building having a proposal of 7-2bhk flat.
• Site location:- Goddhni, Nagpur
• Plot area:-3600sft
• Plinth area:-1100sft
• Slab area:-1559sft
• Number of flats:-7 flats
• Builder name:- Kishore Dhawas
• Name of firm:-City developers, Nagpur
• Architect: - Samir Deshmukh
• Structural designer: - Prasanna Kulkarni
• Site engineer: - Ajay D. Shahu
• Work duration:-7june to 7july
2.Centreline Plan
CENTRE LINE PLAN.
3.Foundation of the Structure
A. Single Spread Slope Footing
• The base of the column is enlarged or spread to provide individual
support for the load.
• A spread slope footing is a type or shallow foundation used to transmit
the load of an isolated column to the subsoil.
• Numbers of footing provided=19 no.
• Size of footing
 F1= (1500×1600),
 F2= (1500×1400)
B. Sectional detail
F1= (1500×1600), F2= (1500×1400)
F1= (1500×1600),
•It is a cress section of footing, showing
the reinforcement at the bottom of footing
and in the column.
C. Foundation Plan
4. PREPARATION PRIOR TO CASTING OF SLAB:-
A. Level fixing
 To maintain the slab at same an accurate level, i.e.
all the four corners of inner face the slab are must
be at same height from the floor level. Thus, to
maintain the slab at same height, levelling is
carried out by using
 level pipe,
 thread and
 Tape.
B. Formwork: - The formwork is built on site out of
timber, plywood and particleboard.
Use and application of centring can be made in
following manner:-
Fixing Column caps
Fixing beam bottom(wooden plank having width of
beam)
Providing support-Lumbers or props to rafters or
span
Laying steel plates or plywood for slab
Column caps, beam bottoms
With beam sides and proving
Support.
Laying steel plates over
Rafter or span
C. Checking of mould formed by formwork
 After completing all shuttering work, the next step is to check that
the available dimension over formwork (dimension of mould) is
same as required for beam, column, duct and slab.
 Checking the length, width and depth of beam, slab area over each
room is same as specified dimension.
 If any dimension of mould is found incorrect, then it is corrected at
the same time.
D. Line and Levelling:-
 Levelling is done in order to obtain flat and horizontal slab.
E. Oiling surface of formwork
 A thin single layer of burned engine oil is applied
manually over the surface of formwork. Advantage:-
a. To prevent the corrosion.
b. To prevent the absorption of slurry.
c. To fill the fine gaps, voids and various joints.
d. To prevent the spilling of concrete slurry.
e. To loosen the bond between roofing material of
formwork and the roof of slab, thus removing the
formwork easily.
f. To increase the life of both steel, wood and ply
formwork .
F. Reinforcement cutting and binding
 The diameter, length and number of the bar required can be
obtained from the structural drawing and bar bending schedule of
the slab.
 Cutting
 Bending
 Centre-to- centre distance is marked over formwork surface
 This marking referred as the point to lay longitudinal and transverse
bars.
 In case of beams, the centre-to-centre distance between two ties is
marked on the longitudinal bars of that beam.
 Then the ties are placed and tied with binding wire at that point.
 After bar-binding work is over, engineer checks the reinforcement of
the slab before casting and thus get corrected.
BAR BENDER BINDING TIES
G. Providing Cover: -
 Cover is the distance between the centre of the road and the
periphery of the structural member. Minimum cover for slab is
15mm.
H. Working out the quantity of concrete: -
By referring structural drawing, total quantity of concrete can worked
out.
Advantages of working out the quantity are as under:-
a. To know the volume of coarse aggregate, fine aggregate, number of
cement bags requires.
b. To know the nearest variation in the volume of concrete which may
occur during casting due to few irregularities, such as
c. Adding Less aggregate during batching
d. Unequal depth of slab
 To prevent wastage of concrete
 To know the nearest expenditure required to cast the slab
 To employ the contractor to cast slab
 In piece work basis or
 On rate basis.
 Since concrete of grade M20 is used for casting slab, the ratio is
1:1.5:3.
 This prepared concrete is discharged in a pan of tower hoist, thus
concrete is transported vertically up to the second floor from ground
floor and then it is discharge.
 Manual transportation of material.
 Vibration-needle vibrator.
 If depth of slab is maintained.
 Finishing.
 Curing of concrete by ponding for minimum 15 days.
I. Casting of slab
Slab surface after 12 hours
5. Equipment:-Major equipment required during and before
casting of slab are as under:-
 Cubical gauge box
(Farma):- Volume of gauge
box is 0.035m3
. It is use to
volume batching of fine
aggregate and coarse aggregate
 Bar bending keys-use to
bend bars.
 Transit mixture-use to make
concrete by thoroughly mixing
sand, aggregate, cement and
water in proportionate amount
 Vertical hoist-use to lift the
concrete vertically from ground
floor to higher floors.
 Niddle vibrator-use to
penetrate into deep beam and
results in better compaction.
 Hook-use to bind
reinforcement with binding
wire.
6. WORKING OUT THE VOLUME OF CONCRETE: - Volume of concrete calculated by
using structural drawing, floor plan and bar bend schedule of slab, beam and column.
 Total volume of concrete
 Thus the total volume of concrete required for slab is 25.956m3
.
 Therefore, adding 52% to get dry volume=1.52×25.956=39.453m3
.
 For M20 grade, volume of cement is=39.453/ (1+1.5+3) =7.173m3.
 Therefore, no. of .cement bags=7.173÷.034=205bags
 Volume of fine aggregate=7.173×1.5=10.759m3
.
 Volume of coarse aggregate=7.173×3=21.519m3
total volume
SR.NO. MEMBERS VOLUME UNIT
1 BEAMS-R 4.9868 CUB.MT.
2 BEAMS-H 8.6064 CUB.MT.
3 SLAB 9.2566 CUB.MT.
4 BALCONY 1.1878 CUB.MT.
5 COLUMN 1.9184 CUB.MT.
TOTAL 25.956 CUB.MT.
total volume
SR.NO. MEMBERS VOLUME UNIT
1 BEAMS-R 4.9868 CUB.MT.
2 BEAMS-H 8.6064 CUB.MT.
3 SLAB 9.2566 CUB.MT.
4 BALCONY 1.1878 CUB.MT.
5 COLUMN 1.9184 CUB.MT.
TOTAL 25.956 CUB.MT.
7. Activities to be carried out after casting of slab:-
A. Removing some part of formwork or centring:-
 16-24 hours is the minimum period before striking vertical
formwork of columns, walls and beams.
B. Inspection: -
 A simple inspection is carried out to see the quality of concreting
and appearance of finishing surface when formwork is removed. If
any defect is detected such as :-
 Honey combing,
 Rough surface due to segregation of concrete, etc. appear on the
surface on beam sides after hardening
then it is repaired by applying
 Cement paste on that surface or
 Grouting.
C. Marking of centreline
 It is done by taking the reference of column position at plinth level
and transferring the point on the surface of slab at all four corners, so
that position of column above the slab must be located exactly over
the column below the slab.
 The centre-to-centre distance between upcoming columns over slab
must be marked as per centre line drawing.
 Using centre line marking, dimension of column (B×D) can be
located.
 Diagonal check can also be obtained and can also be corrected, if
found incorrect.
D. Ponding and Curing
small ponds of rectangular shape prepared on the
hardened surface of slab throughout the surface
area by using mortar prepared in a ratio of 1:8 to
1:10.
This rectangular pond after hardening is filled with
water, thus curing the concrete.
This poor quality of mortar is so prepared so that it
can be easily removed from the slab surface after
curing.
E. Casting the starter before casting of column:-
 Starters are the portion of column of depth 75-100mm
approximately.
 Wooden mould is of the size of column which is used to cast the
starter and is placed over the located position of column by referring
centreline.
 Then the mould is filled with concrete of grade M20.
 After hardening concrete, mould is removed……………contd.
8. Conclusion
 Industrial training has helped to understand the theoretical concepts
of the various subjects such as
 Foundation Engineering,
 Estimation and Costing,
 Concrete Technology,
 Building Construction and their relation with practical means.
 It has also helped me to understand the managerial part of planning
with respect to proper and timely execution of work, material
management, etc. Industrial training develops a skill of observation,
and a skill to understand the various problems faced at site and the
way to overcome with this problems.
 Since my training report in on the residential building, it has given
me the opportunity to calculate the volume of concerte required to
cast the slab which is a sure means of practical knowledge. It has also
given me the idea about the importance of stepwise execution of
work.
Thank you

More Related Content

What's hot

Civil-Report on industrial training at URCC
Civil-Report on industrial training at URCCCivil-Report on industrial training at URCC
Civil-Report on industrial training at URCCRakshita Raghunath
 
Report on Residential Construction
Report on Residential ConstructionReport on Residential Construction
Report on Residential ConstructionMayank Walecha
 
Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD Alok Mishra
 
Industrial report for civil engg. training
Industrial report for civil engg. trainingIndustrial report for civil engg. training
Industrial report for civil engg. trainingRam1239
 
Rail and Road Over Rail Bridge
Rail and Road Over Rail BridgeRail and Road Over Rail Bridge
Rail and Road Over Rail BridgeKorutla Harish
 
REPORTS ON BUILDING CONSTRUCTION
REPORTS ON BUILDING CONSTRUCTIONREPORTS ON BUILDING CONSTRUCTION
REPORTS ON BUILDING CONSTRUCTIONRising Sher
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavementpradip dangar
 
Industrial training report of construction of the residential building
Industrial training report of construction of the residential buildingIndustrial training report of construction of the residential building
Industrial training report of construction of the residential buildingsuraj jha
 
FOOTING CONSTRUCTION
FOOTING CONSTRUCTIONFOOTING CONSTRUCTION
FOOTING CONSTRUCTIONMd Shadab
 
Construction work of a multi storied residential building
Construction work of a multi storied residential buildingConstruction work of a multi storied residential building
Construction work of a multi storied residential buildingShariful Haque Robin
 
Civil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman KhokanCivil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman KhokanAnis Rahman Khokan
 
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION L&W BUILDING SOLUTIONS PVT. LMT.
 
Complete design of r.c.c over head tank & boq estimate
Complete design of r.c.c over head tank & boq estimateComplete design of r.c.c over head tank & boq estimate
Complete design of r.c.c over head tank & boq estimateHarish Mahavar
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction pptBeing Deepak
 
Non destructive test on concrete (ndt)
Non destructive test on concrete (ndt)Non destructive test on concrete (ndt)
Non destructive test on concrete (ndt)Abhishek Gupta
 
Building Construction
Building ConstructionBuilding Construction
Building ConstructionWilden How
 

What's hot (20)

Civil-Report on industrial training at URCC
Civil-Report on industrial training at URCCCivil-Report on industrial training at URCC
Civil-Report on industrial training at URCC
 
Report on Residential Construction
Report on Residential ConstructionReport on Residential Construction
Report on Residential Construction
 
ppt on training civil report on shuttering
ppt on training civil report on shutteringppt on training civil report on shuttering
ppt on training civil report on shuttering
 
Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD
 
Industrial report for civil engg. training
Industrial report for civil engg. trainingIndustrial report for civil engg. training
Industrial report for civil engg. training
 
Rail and Road Over Rail Bridge
Rail and Road Over Rail BridgeRail and Road Over Rail Bridge
Rail and Road Over Rail Bridge
 
REPORTS ON BUILDING CONSTRUCTION
REPORTS ON BUILDING CONSTRUCTIONREPORTS ON BUILDING CONSTRUCTION
REPORTS ON BUILDING CONSTRUCTION
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
 
Industrial training report of construction of the residential building
Industrial training report of construction of the residential buildingIndustrial training report of construction of the residential building
Industrial training report of construction of the residential building
 
water tank
water tankwater tank
water tank
 
FOOTING CONSTRUCTION
FOOTING CONSTRUCTIONFOOTING CONSTRUCTION
FOOTING CONSTRUCTION
 
Vacuum dewatering
Vacuum dewateringVacuum dewatering
Vacuum dewatering
 
Construction work of a multi storied residential building
Construction work of a multi storied residential buildingConstruction work of a multi storied residential building
Construction work of a multi storied residential building
 
Civil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman KhokanCivil Engineering Internship Presentation-Anis Rahman Khokan
Civil Engineering Internship Presentation-Anis Rahman Khokan
 
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
 
Complete design of r.c.c over head tank & boq estimate
Complete design of r.c.c over head tank & boq estimateComplete design of r.c.c over head tank & boq estimate
Complete design of r.c.c over head tank & boq estimate
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction ppt
 
Design and analasys of a g+2 residential building
Design and analasys of a g+2 residential building Design and analasys of a g+2 residential building
Design and analasys of a g+2 residential building
 
Non destructive test on concrete (ndt)
Non destructive test on concrete (ndt)Non destructive test on concrete (ndt)
Non destructive test on concrete (ndt)
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
 

Similar to Industrial Training Report-(2012-13)

Re development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiRe development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiJaspreet singh
 
Summer training report
Summer training reportSummer training report
Summer training reportaki8872233
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIPMkh Nantu
 
Svp field training report final
Svp field training report finalSvp field training report final
Svp field training report finalShubham Parab
 
Slipform construction
Slipform constructionSlipform construction
Slipform constructionErankajKumar
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formworkKHUSHBU SHAH
 
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWRE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWJaspreet singh
 
Mat foundation
Mat foundationMat foundation
Mat foundationshuvo293
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxsfQyoom
 
NMRC Civil Construction
NMRC Civil Construction NMRC Civil Construction
NMRC Civil Construction ajinkyaraj
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptxHimanshumangal12
 
ppt on sub structure construction.pptx
ppt on sub structure construction.pptxppt on sub structure construction.pptx
ppt on sub structure construction.pptxRaviUraiya1
 
Upload a presentation to download Space frame
Upload a presentation to download Space frameUpload a presentation to download Space frame
Upload a presentation to download Space frameBurkaDinka
 

Similar to Industrial Training Report-(2012-13) (20)

Re development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New DelhiRe development works at east kidwai nagar, New Delhi
Re development works at east kidwai nagar, New Delhi
 
Summer training report
Summer training reportSummer training report
Summer training report
 
Ash creation report
Ash creation reportAsh creation report
Ash creation report
 
Ayush
AyushAyush
Ayush
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIP
 
Site report 1
Site report 1Site report 1
Site report 1
 
Svp field training report final
Svp field training report finalSvp field training report final
Svp field training report final
 
Work check list
Work check listWork check list
Work check list
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEWRE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
RE-DEVELOPMENT WORKS AT EAST KIDWAI NAGAR, NEW
 
Mat foundation
Mat foundationMat foundation
Mat foundation
 
training1 (1).pptx
training1 (1).pptxtraining1 (1).pptx
training1 (1).pptx
 
Form Work
Form Work Form Work
Form Work
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
Pavements PPT
 Pavements PPT  Pavements PPT
Pavements PPT
 
NMRC Civil Construction
NMRC Civil Construction NMRC Civil Construction
NMRC Civil Construction
 
Sample copy of IT PPT.pptx
Sample copy of IT PPT.pptxSample copy of IT PPT.pptx
Sample copy of IT PPT.pptx
 
ppt on sub structure construction.pptx
ppt on sub structure construction.pptxppt on sub structure construction.pptx
ppt on sub structure construction.pptx
 
Upload a presentation to download Space frame
Upload a presentation to download Space frameUpload a presentation to download Space frame
Upload a presentation to download Space frame
 

Industrial Training Report-(2012-13)

  • 1. PRESENTED BY AJAY SHAHU (20100872) Industrial Training Report on Residential building(G+3) (2012-13)
  • 2. Content 1. Introduction 2. Centre line plan 3. Foundation of Structure 4. Preparation prior casting of slab 5. Equipment 6. Volume of concrete 7. Activities carried out after casting of slab 8. Conclusion 9. References
  • 3. 1.Introduction • It is a residential building having a proposal of 7-2bhk flat. • Site location:- Goddhni, Nagpur • Plot area:-3600sft • Plinth area:-1100sft • Slab area:-1559sft • Number of flats:-7 flats • Builder name:- Kishore Dhawas • Name of firm:-City developers, Nagpur • Architect: - Samir Deshmukh • Structural designer: - Prasanna Kulkarni • Site engineer: - Ajay D. Shahu • Work duration:-7june to 7july
  • 5. 3.Foundation of the Structure A. Single Spread Slope Footing • The base of the column is enlarged or spread to provide individual support for the load. • A spread slope footing is a type or shallow foundation used to transmit the load of an isolated column to the subsoil. • Numbers of footing provided=19 no. • Size of footing  F1= (1500×1600),  F2= (1500×1400)
  • 6. B. Sectional detail F1= (1500×1600), F2= (1500×1400) F1= (1500×1600), •It is a cress section of footing, showing the reinforcement at the bottom of footing and in the column.
  • 8. 4. PREPARATION PRIOR TO CASTING OF SLAB:- A. Level fixing  To maintain the slab at same an accurate level, i.e. all the four corners of inner face the slab are must be at same height from the floor level. Thus, to maintain the slab at same height, levelling is carried out by using  level pipe,  thread and  Tape.
  • 9. B. Formwork: - The formwork is built on site out of timber, plywood and particleboard. Use and application of centring can be made in following manner:- Fixing Column caps Fixing beam bottom(wooden plank having width of beam) Providing support-Lumbers or props to rafters or span Laying steel plates or plywood for slab
  • 10. Column caps, beam bottoms With beam sides and proving Support. Laying steel plates over Rafter or span
  • 11. C. Checking of mould formed by formwork  After completing all shuttering work, the next step is to check that the available dimension over formwork (dimension of mould) is same as required for beam, column, duct and slab.  Checking the length, width and depth of beam, slab area over each room is same as specified dimension.  If any dimension of mould is found incorrect, then it is corrected at the same time.
  • 12. D. Line and Levelling:-  Levelling is done in order to obtain flat and horizontal slab.
  • 13. E. Oiling surface of formwork  A thin single layer of burned engine oil is applied manually over the surface of formwork. Advantage:- a. To prevent the corrosion. b. To prevent the absorption of slurry. c. To fill the fine gaps, voids and various joints. d. To prevent the spilling of concrete slurry. e. To loosen the bond between roofing material of formwork and the roof of slab, thus removing the formwork easily. f. To increase the life of both steel, wood and ply formwork .
  • 14. F. Reinforcement cutting and binding  The diameter, length and number of the bar required can be obtained from the structural drawing and bar bending schedule of the slab.  Cutting  Bending  Centre-to- centre distance is marked over formwork surface  This marking referred as the point to lay longitudinal and transverse bars.  In case of beams, the centre-to-centre distance between two ties is marked on the longitudinal bars of that beam.  Then the ties are placed and tied with binding wire at that point.  After bar-binding work is over, engineer checks the reinforcement of the slab before casting and thus get corrected.
  • 16. G. Providing Cover: -  Cover is the distance between the centre of the road and the periphery of the structural member. Minimum cover for slab is 15mm.
  • 17. H. Working out the quantity of concrete: - By referring structural drawing, total quantity of concrete can worked out. Advantages of working out the quantity are as under:- a. To know the volume of coarse aggregate, fine aggregate, number of cement bags requires. b. To know the nearest variation in the volume of concrete which may occur during casting due to few irregularities, such as c. Adding Less aggregate during batching d. Unequal depth of slab  To prevent wastage of concrete  To know the nearest expenditure required to cast the slab  To employ the contractor to cast slab  In piece work basis or  On rate basis.
  • 18.  Since concrete of grade M20 is used for casting slab, the ratio is 1:1.5:3.  This prepared concrete is discharged in a pan of tower hoist, thus concrete is transported vertically up to the second floor from ground floor and then it is discharge.  Manual transportation of material.  Vibration-needle vibrator.  If depth of slab is maintained.  Finishing.  Curing of concrete by ponding for minimum 15 days. I. Casting of slab
  • 19. Slab surface after 12 hours
  • 20. 5. Equipment:-Major equipment required during and before casting of slab are as under:-  Cubical gauge box (Farma):- Volume of gauge box is 0.035m3 . It is use to volume batching of fine aggregate and coarse aggregate  Bar bending keys-use to bend bars.
  • 21.  Transit mixture-use to make concrete by thoroughly mixing sand, aggregate, cement and water in proportionate amount  Vertical hoist-use to lift the concrete vertically from ground floor to higher floors.  Niddle vibrator-use to penetrate into deep beam and results in better compaction.  Hook-use to bind reinforcement with binding wire.
  • 22. 6. WORKING OUT THE VOLUME OF CONCRETE: - Volume of concrete calculated by using structural drawing, floor plan and bar bend schedule of slab, beam and column.  Total volume of concrete  Thus the total volume of concrete required for slab is 25.956m3 .  Therefore, adding 52% to get dry volume=1.52×25.956=39.453m3 .  For M20 grade, volume of cement is=39.453/ (1+1.5+3) =7.173m3.  Therefore, no. of .cement bags=7.173÷.034=205bags  Volume of fine aggregate=7.173×1.5=10.759m3 .  Volume of coarse aggregate=7.173×3=21.519m3 total volume SR.NO. MEMBERS VOLUME UNIT 1 BEAMS-R 4.9868 CUB.MT. 2 BEAMS-H 8.6064 CUB.MT. 3 SLAB 9.2566 CUB.MT. 4 BALCONY 1.1878 CUB.MT. 5 COLUMN 1.9184 CUB.MT. TOTAL 25.956 CUB.MT. total volume SR.NO. MEMBERS VOLUME UNIT 1 BEAMS-R 4.9868 CUB.MT. 2 BEAMS-H 8.6064 CUB.MT. 3 SLAB 9.2566 CUB.MT. 4 BALCONY 1.1878 CUB.MT. 5 COLUMN 1.9184 CUB.MT. TOTAL 25.956 CUB.MT.
  • 23. 7. Activities to be carried out after casting of slab:- A. Removing some part of formwork or centring:-  16-24 hours is the minimum period before striking vertical formwork of columns, walls and beams. B. Inspection: -  A simple inspection is carried out to see the quality of concreting and appearance of finishing surface when formwork is removed. If any defect is detected such as :-  Honey combing,  Rough surface due to segregation of concrete, etc. appear on the surface on beam sides after hardening then it is repaired by applying  Cement paste on that surface or  Grouting.
  • 24.
  • 25. C. Marking of centreline  It is done by taking the reference of column position at plinth level and transferring the point on the surface of slab at all four corners, so that position of column above the slab must be located exactly over the column below the slab.  The centre-to-centre distance between upcoming columns over slab must be marked as per centre line drawing.  Using centre line marking, dimension of column (B×D) can be located.  Diagonal check can also be obtained and can also be corrected, if found incorrect.
  • 26. D. Ponding and Curing small ponds of rectangular shape prepared on the hardened surface of slab throughout the surface area by using mortar prepared in a ratio of 1:8 to 1:10. This rectangular pond after hardening is filled with water, thus curing the concrete. This poor quality of mortar is so prepared so that it can be easily removed from the slab surface after curing.
  • 27. E. Casting the starter before casting of column:-  Starters are the portion of column of depth 75-100mm approximately.  Wooden mould is of the size of column which is used to cast the starter and is placed over the located position of column by referring centreline.  Then the mould is filled with concrete of grade M20.  After hardening concrete, mould is removed……………contd.
  • 28. 8. Conclusion  Industrial training has helped to understand the theoretical concepts of the various subjects such as  Foundation Engineering,  Estimation and Costing,  Concrete Technology,  Building Construction and their relation with practical means.  It has also helped me to understand the managerial part of planning with respect to proper and timely execution of work, material management, etc. Industrial training develops a skill of observation, and a skill to understand the various problems faced at site and the way to overcome with this problems.  Since my training report in on the residential building, it has given me the opportunity to calculate the volume of concerte required to cast the slab which is a sure means of practical knowledge. It has also given me the idea about the importance of stepwise execution of work.