OPERATIONS MANAGEMENT (MGCR-472-061)
Productivity Practice Problems
1. The South Dakota Clay Pigeon Corporation showed the following results for last
year:
(A) What was the total factor productivity?
(B) What was the multi-factor productivity measure for total output to labor and
materials?
(C) What was the multi-factor productivity measure for finished output to labor
and materials?
(D) What was the partial productivity measure for total output to energy?
(E) What was the partial productivity ratio for finished units to energy?
2. Two types of cars (Deluxe and Limited) were produced by a car manufacturer in
2001. Quantities sold, price per unit and labor hours follow. What is the labor
productivity for each car? Explain the problem(s) associated with labor
productivity.
Quantity $ per unit
Deluxe Car 4,000 units sold $8,000 per car
Limited Car 6,000 units sold $9,500 per car
Labor Deluxe 20,000 hours $12 per hour
Labor Limited 30,000 hours $14 per hour
3. 10,000 units produced, sold for $10/unit, 500 labor hours, labor rate: $9/hr, cost of
raw material: $5,000, cost of purchased material: $25,000.
2
a. What is the labor productivity in units per hour and in unitless figure?
b. What will be the labor productivity if 12,000 units are produced using 500
labor hours (in units per hour and unitless figure)?
c. How much labor hour should we use in order to reach the productivity
level of part (b), if the product is 10,000 units.
d. What will be the multi-factor productivity (MFP), in unitless figure and in
terms of units/dollar, taking into account the labor and material costs?
e. Suppose we hire very efficient workers who can finish the job in 350
hours. What is now the MFP with labor rate of $9/hour?
f. However we have to pay higher wages for the more efficient workers.
How much extra can we pay without reducing productivity from the level
of part (d) in units/dollar?
Solution to Productivity Exercise Problems
1.
(A) What was the total factor productivity?
1,050,000/650,000 = 1.62
(B) What was the multi-factor productivity measure for total output to labor and
materials?
1,050,000/450,000 = 2.33
(C) What was the multi-factor productivity measure for finished output to labor
and materials?
1,000,000/450,000 = 2.22
(D) What was the partial productivity measure for total output to energy?
1,050,000/25,000 = 42
(E) What was the partial productivity ratio for finished units to energy?
1,000,000/25,000 = 40
3
2. Deluxe = (4,000 units*$8,000/car)/(20,000 labor hour*$12/hour) = 133.33 (unitless);
limited = (6,000 units *$9,500/car)/(30,000 labor hour*$14/hour) = 135.71 (unitless)
Deluxe = (4,000 units/car)/(20,000 labor hour) = 0.2 unit/hour;
limited = 6,000 units/30,000 labor hour = 0.2 unit/hour
Labor productivity in terms of units/hour does not take into account the quality of the
product (i.e., does not take into account the selling prices) and does not take into
account the skill level of the workers (i.e. does not take into account the labor rate).
Labor productivity in unitless terms might be difficult for department managers to
comprehend who has a better idea about what units/hour mean. Unitlesss is mostly
used by high-level managers while units/hour is used by departmental managers.
3. a. Labor productivity = 10,000 units/500 labor hour = 20 units/hour;
Labor productivity = (10,000 units*$10/unit)/(500 labor hour*$9/hour) = 22.22
(unitless)
b. Labor productivity = 12,000 units/500 labor hour = 24 units/hour;
Labor productivity = (12,000 units*$10/unit)/(500 labor hour*$9/hour) = 26.67
(unitless)
c. 24
000,10
=
X
units
units/hour 4177.416000,1024 ≈=⇒=⇒ XX hours
d. MFP = 10,000 units/$(500*9 + 5,000 + 25,000) = 0.29 units/dollar;
MFP = (10,000*$10/unit)/$(500*9 + 5,000 + 25,000) = 2.9
e. MFP = 10,000 units/$(350*9 + 5,000 + 25,000) = 0.3 units/dollar;
f. MFP = (10,000 unit)/$(350*X + 5,000 + 25,000) = 0.29
81.125.1018700000,10
)000,255000350(29.0000,1029.0
)000,25000,5350(
000,10
=⇒=−⇒
++=⇒=
++
XX
X
X
At maximum, we can pay $12.81/hour.)

More Related Content

Viewers also liked (11)

Life Orientation-Lifelong learning by Letty masombuka
Life Orientation-Lifelong learning by Letty masombukaLife Orientation-Lifelong learning by Letty masombuka
Life Orientation-Lifelong learning by Letty masombuka
 
AIM
AIMAIM
AIM
 
1. worksheet
1. worksheet1. worksheet
1. worksheet
 
Bricks (2)
Bricks (2)Bricks (2)
Bricks (2)
 
Boers migrate into the interior BY LETTY MASOMBUKA
Boers migrate into the interior BY LETTY MASOMBUKABoers migrate into the interior BY LETTY MASOMBUKA
Boers migrate into the interior BY LETTY MASOMBUKA
 
Chap16 cbm&cw
Chap16 cbm&cwChap16 cbm&cw
Chap16 cbm&cw
 
Science BY GAURAV BHATT 9
Science BY GAURAV BHATT 9Science BY GAURAV BHATT 9
Science BY GAURAV BHATT 9
 
1.building
1.building1.building
1.building
 
Brochure tank en
Brochure tank enBrochure tank en
Brochure tank en
 
5.plastering
5.plastering5.plastering
5.plastering
 
7.roofs
7.roofs7.roofs
7.roofs
 

Similar to Eman redha

Contoh Soal Perhitungan Kapasitas Manufaktur
Contoh Soal Perhitungan Kapasitas ManufakturContoh Soal Perhitungan Kapasitas Manufaktur
Contoh Soal Perhitungan Kapasitas Manufaktur
Mahros Darsin
 
Problem 6-2A manager wants to assign tasks to workstations as .docx
Problem 6-2A manager wants to assign tasks to workstations as .docxProblem 6-2A manager wants to assign tasks to workstations as .docx
Problem 6-2A manager wants to assign tasks to workstations as .docx
sleeperharwell
 
Bba ii cost and management accounting u 3.2 job and batch costing
Bba ii cost and management accounting u 3.2 job and batch costingBba ii cost and management accounting u 3.2 job and batch costing
Bba ii cost and management accounting u 3.2 job and batch costing
Rai University
 

Similar to Eman redha (20)

Contoh Soal Perhitungan Kapasitas Manufaktur
Contoh Soal Perhitungan Kapasitas ManufakturContoh Soal Perhitungan Kapasitas Manufaktur
Contoh Soal Perhitungan Kapasitas Manufaktur
 
Costs (3).pptx
Costs (3).pptxCosts (3).pptx
Costs (3).pptx
 
Problem 6-2A manager wants to assign tasks to workstations as .docx
Problem 6-2A manager wants to assign tasks to workstations as .docxProblem 6-2A manager wants to assign tasks to workstations as .docx
Problem 6-2A manager wants to assign tasks to workstations as .docx
 
Bengkel POM
Bengkel POMBengkel POM
Bengkel POM
 
ACCT 346 Effective Communication/tutorialrank.com
 ACCT 346 Effective Communication/tutorialrank.com ACCT 346 Effective Communication/tutorialrank.com
ACCT 346 Effective Communication/tutorialrank.com
 
Bba ii cost and management accounting u 3.2 job and batch costing
Bba ii cost and management accounting u 3.2 job and batch costingBba ii cost and management accounting u 3.2 job and batch costing
Bba ii cost and management accounting u 3.2 job and batch costing
 
Acct 434 week 4 midterm exam(uophelp)
Acct 434 week 4 midterm exam(uophelp)Acct 434 week 4 midterm exam(uophelp)
Acct 434 week 4 midterm exam(uophelp)
 
ACCT 346 Enhance teaching - tutorialrank.com
ACCT 346 Enhance teaching - tutorialrank.comACCT 346 Enhance teaching - tutorialrank.com
ACCT 346 Enhance teaching - tutorialrank.com
 
Examination paper of materials management
Examination paper of materials managementExamination paper of materials management
Examination paper of materials management
 
Job costing slides
Job costing slidesJob costing slides
Job costing slides
 
Acct 326 week 4 midterm exam new 2016
Acct 326 week 4 midterm exam new 2016Acct 326 week 4 midterm exam new 2016
Acct 326 week 4 midterm exam new 2016
 
Acct303 chapter2
Acct303 chapter2Acct303 chapter2
Acct303 chapter2
 
Cost ch17 quis
Cost ch17 quisCost ch17 quis
Cost ch17 quis
 
Devry acct 346 week 4 midterm 1
Devry acct 346 week 4 midterm 1Devry acct 346 week 4 midterm 1
Devry acct 346 week 4 midterm 1
 
Operation management problems
Operation management problemsOperation management problems
Operation management problems
 
Ch04 m 06_09_10
Ch04 m 06_09_10Ch04 m 06_09_10
Ch04 m 06_09_10
 
ACCT 346 Education Specialist / snaptutorial.com
 ACCT 346 Education Specialist / snaptutorial.com ACCT 346 Education Specialist / snaptutorial.com
ACCT 346 Education Specialist / snaptutorial.com
 
Productivity,competitiveness,strategy
Productivity,competitiveness,strategyProductivity,competitiveness,strategy
Productivity,competitiveness,strategy
 
Acct 346 week 4 midterm 1
Acct 346 week 4 midterm 1Acct 346 week 4 midterm 1
Acct 346 week 4 midterm 1
 
Devry acct 346 week 4 midterm 2
Devry acct 346 week 4 midterm 2Devry acct 346 week 4 midterm 2
Devry acct 346 week 4 midterm 2
 

More from AYM1979 (20)

Polypipe
PolypipePolypipe
Polypipe
 
Mc alpine
Mc alpineMc alpine
Mc alpine
 
Maxirain1
Maxirain1Maxirain1
Maxirain1
 
Maxirain
MaxirainMaxirain
Maxirain
 
Hepworth2
Hepworth2Hepworth2
Hepworth2
 
Hepworth
HepworthHepworth
Hepworth
 
Cosmo plast2
Cosmo plast2Cosmo plast2
Cosmo plast2
 
Cosmo plast1
Cosmo plast1Cosmo plast1
Cosmo plast1
 
Cosmoplast
CosmoplastCosmoplast
Cosmoplast
 
Iso 4624 2002
Iso 4624 2002Iso 4624 2002
Iso 4624 2002
 
Bs iso 923 2000
Bs iso 923 2000Bs iso 923 2000
Bs iso 923 2000
 
Literature review r
Literature review rLiterature review r
Literature review r
 
Inventory control 1rev
Inventory control 1revInventory control 1rev
Inventory control 1rev
 
Mba8155 slides2
Mba8155 slides2Mba8155 slides2
Mba8155 slides2
 
Mba8155 slides1
Mba8155 slides1Mba8155 slides1
Mba8155 slides1
 
Strategic mangement
Strategic mangementStrategic mangement
Strategic mangement
 
Power point presentations 3
Power point presentations 3Power point presentations 3
Power point presentations 3
 
Asset doc loc_2521843_apc_raw
Asset doc loc_2521843_apc_rawAsset doc loc_2521843_apc_raw
Asset doc loc_2521843_apc_raw
 
Safety rules 2014
Safety rules 2014Safety rules 2014
Safety rules 2014
 
Current e manual
Current e manualCurrent e manual
Current e manual
 

Recently uploaded

Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
ZurliaSoop
 

Recently uploaded (20)

How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptxExploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
Exploring_the_Narrative_Style_of_Amitav_Ghoshs_Gun_Island.pptx
 
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptxCOMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
COMMUNICATING NEGATIVE NEWS - APPROACHES .pptx
 
Interdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxInterdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptx
 
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
Sensory_Experience_and_Emotional_Resonance_in_Gabriel_Okaras_The_Piano_and_Th...
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptx
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 

Eman redha

  • 1. 1 OPERATIONS MANAGEMENT (MGCR-472-061) Productivity Practice Problems 1. The South Dakota Clay Pigeon Corporation showed the following results for last year: (A) What was the total factor productivity? (B) What was the multi-factor productivity measure for total output to labor and materials? (C) What was the multi-factor productivity measure for finished output to labor and materials? (D) What was the partial productivity measure for total output to energy? (E) What was the partial productivity ratio for finished units to energy? 2. Two types of cars (Deluxe and Limited) were produced by a car manufacturer in 2001. Quantities sold, price per unit and labor hours follow. What is the labor productivity for each car? Explain the problem(s) associated with labor productivity. Quantity $ per unit Deluxe Car 4,000 units sold $8,000 per car Limited Car 6,000 units sold $9,500 per car Labor Deluxe 20,000 hours $12 per hour Labor Limited 30,000 hours $14 per hour 3. 10,000 units produced, sold for $10/unit, 500 labor hours, labor rate: $9/hr, cost of raw material: $5,000, cost of purchased material: $25,000.
  • 2. 2 a. What is the labor productivity in units per hour and in unitless figure? b. What will be the labor productivity if 12,000 units are produced using 500 labor hours (in units per hour and unitless figure)? c. How much labor hour should we use in order to reach the productivity level of part (b), if the product is 10,000 units. d. What will be the multi-factor productivity (MFP), in unitless figure and in terms of units/dollar, taking into account the labor and material costs? e. Suppose we hire very efficient workers who can finish the job in 350 hours. What is now the MFP with labor rate of $9/hour? f. However we have to pay higher wages for the more efficient workers. How much extra can we pay without reducing productivity from the level of part (d) in units/dollar? Solution to Productivity Exercise Problems 1. (A) What was the total factor productivity? 1,050,000/650,000 = 1.62 (B) What was the multi-factor productivity measure for total output to labor and materials? 1,050,000/450,000 = 2.33 (C) What was the multi-factor productivity measure for finished output to labor and materials? 1,000,000/450,000 = 2.22 (D) What was the partial productivity measure for total output to energy? 1,050,000/25,000 = 42 (E) What was the partial productivity ratio for finished units to energy? 1,000,000/25,000 = 40
  • 3. 3 2. Deluxe = (4,000 units*$8,000/car)/(20,000 labor hour*$12/hour) = 133.33 (unitless); limited = (6,000 units *$9,500/car)/(30,000 labor hour*$14/hour) = 135.71 (unitless) Deluxe = (4,000 units/car)/(20,000 labor hour) = 0.2 unit/hour; limited = 6,000 units/30,000 labor hour = 0.2 unit/hour Labor productivity in terms of units/hour does not take into account the quality of the product (i.e., does not take into account the selling prices) and does not take into account the skill level of the workers (i.e. does not take into account the labor rate). Labor productivity in unitless terms might be difficult for department managers to comprehend who has a better idea about what units/hour mean. Unitlesss is mostly used by high-level managers while units/hour is used by departmental managers. 3. a. Labor productivity = 10,000 units/500 labor hour = 20 units/hour; Labor productivity = (10,000 units*$10/unit)/(500 labor hour*$9/hour) = 22.22 (unitless) b. Labor productivity = 12,000 units/500 labor hour = 24 units/hour; Labor productivity = (12,000 units*$10/unit)/(500 labor hour*$9/hour) = 26.67 (unitless) c. 24 000,10 = X units units/hour 4177.416000,1024 ≈=⇒=⇒ XX hours d. MFP = 10,000 units/$(500*9 + 5,000 + 25,000) = 0.29 units/dollar; MFP = (10,000*$10/unit)/$(500*9 + 5,000 + 25,000) = 2.9 e. MFP = 10,000 units/$(350*9 + 5,000 + 25,000) = 0.3 units/dollar; f. MFP = (10,000 unit)/$(350*X + 5,000 + 25,000) = 0.29 81.125.1018700000,10 )000,255000350(29.0000,1029.0 )000,25000,5350( 000,10 =⇒=−⇒ ++=⇒= ++ XX X X At maximum, we can pay $12.81/hour.)