PSP & Guidelines MOP.pptx

PUMPED STORAGE HYDROPOWER
Guidelines issued by Ministry of Power, Government of India
Abhishek Mallick
Executive Engineer (E&M)
POWER PROJECTS DIVISION, SCCL
● PSH acts as an energy store, If there is a surplus of power in the grid,
the pumped storage power station switches to pumping mode – an
electric motor drives the pump turbines, which pumps water from a
lower reservoir to a higher storage basin.
● If the demand for electricity in the grid rises, water is released from
the upper basin via a pressure pipeline to the bottom. The water causes
the pump turbines to rotate, now operating in turbine mode and used to
drive the generators. Within seconds, electricity is generated and fed
into the grid.
ABOUT PSP TECHNOLOGY:
PSP & Guidelines MOP.pptx
● ON-STREAM: Both reservoirs are located on any river
/stream
● OFF-STREAM OPEN LOOP - Only one of the reservoirs is
located on any river/ stream.
● OFF-STREAM CLOSED LOOP - None of the reservoirs is
located on any river/ stream
4
TYPES OF PSP:
OPEN-LOOP & CLOSED-LOOP PSH
● Pumped storage
Hydropower + Solar
Power/ Wind Power
● Once the solar power is
more than the needed,
excess is used to pump
water from lower
reservoir to upper
reservoir.
● If there is no solar power
generation, the water
flows from upper basin
to the lower and drives a
turbine to produce
power.
HYBRID PSP CONCEPT:
HIGHLIGHTS OF PSP
 PSP are also known as ‘Water Battery/ Green Battery’
 Long service life of 40-50 years
 Offers critical back up during peak hours (Flexible/Reliable)
 No residual environment impacts
 High economical value: Pumped storage plants works at an efficiency level
upto 82 percent
 PSP are designed for 06 hours of operations
 CEA estimate Potential: 103 GW- ON River, OFF River- Being estimated
 As per report by CEA 26.7 GW PSP are required by 2032
PRO CONS
Flexible and Reliable Long Planning and construction time
Long Service Life Specific geographical condition for
upper reservoir and lower reservoir
Relatively high efficiency upto 85% Large amount of initial investment
Most viable option Long Pay back period
Reduces energy wastage
PRO & CONS:
9
GUIDELINES ISSUED BY M.O.P
Dt. 10.04.2023
ENABLERS FOR PSP
 Environmental Clearances- PSP on existing reservoirs and on off-the-river
sites may be treated as a separate category for processing of applications
(Appraised under B2 category of MOEF &CC for grant of EC) . As per MOEF&CC
draft notification dated 11.10.22 the following criteria will be treated as B2 for
grant of EC:
1. Projects which do not attract Forest Clearance/ Wildlife Clearance
2. Projects where no new reservoirs are created
3. Projects where existing reservoirs are not expanded or structurally
modified
 Cost of Pumping Power- Three factors:
1. Cost of Input Power (Viability depends on availability of affordable input
power)
2. Conversion Losses
3. Cost of Storage
Value of Peak Power- PSP is capable of offering several services such as:
•Spinning Reserves- Generation capacity that is on-line but unloaded and
that can respond within 10 minutes to compensate for generation or
transmission outages, Reactive Support
•Reactive Support- used to provide the voltage levels necessary for active
power to do useful work
•Black start- the ability of generation to restart parts of the power system
to recover from a blackout
•Frequency response, faster start up’s and shutdowns which are essential
for grid stability
MEASURES TAKEN BY GOI FOR PROMOTION OF PSP
• States to allot PSP to PSU (Annex-I)
• Energy Storage Obligation (Annex-II)
• Waiver of ISTS Charges for PSP (Annex-III)- (Extendable to PSP where
construction work is awarded by 30.06.2025
• Budgetary Support (Annex-IV)
• Timelines for formulation and concurrence of DPR’s for PSP reduced from
900 days to 720 days and CEA shall further reduce timeline for Off-stream
closed loop PSP and PSP on existing hydro projects (Where one reservoir is
available)
• Since No tariff/ financial evaluation by CEA for tariff based Competitive
bidding, concurrence reduced from 150 days to 75 days. For other mode of
award concurrence reduced from 150 days to 125 days.
• Central Government will notify a benchmark tariff of storage for investment
decisions
BENEFITS TO BE EXTENDED BY STATE
• No upfront fee shall be charged by state government
• State Government shall consider reimbursement of SGST on PSP project
components.
• States may exempt Stamp duty and Registration fee for land to be
acquired by off-the-river PSP
• Government land may be provided at a concessional rate to the developers
on annual lease rent basis.
• To avoid double taxation, Electricity Duty and Cross subsidy charges shall
not be applicable for Pumping power and may be levied on final
consumption of electricity
• No requirement of Local Area Development fund
ALLOTMENT OF PSP PROJECTS
State Government may allot project sites to developers in the following
manner:
1. On Nomination Basis to CPSU/SPSU:
-States may award projects directly to PSU on nomination basis
- Award of EPC shall be through Competitive Bidding
2. Allotment through Competitive Bidding:
- May be allotted to Private developers by two stage competitive bidding
Stage 1: Pre-qualification based on financial strength, experience, turnover,
ability to meet performance guarantees
Stage 2: Bids to be called on quantifiable parameters such as concession period
of project or any other parameter as specified by Central/State Govt.
For above two modes:
• Home state shall have right of first refusal upto 80% of Project Capacity and
developer is free to sell power in any mode
• Tariff shall be fixed by appropriate commission u/s 62 of elec act 2003,
3. Allotment through Tariff Based Competitive Bidding:
May be awarded to a developer in TBCB mode:
 Survey & Investigation and Prep of DPR may be given to SPV under State/Central PSU
 SPV responsible for Pre-construction activities such as Project Report, Land
Acquisition, Environment & Forest Clearance etc.
 DPR may be subsequently bid out for construction and SPV transferred to the
successful bidder on the basis of :
 COMPOSITE TARIFF (including Cost of Input Power)- Input power arranged by
developer
 TARIFF FOR STORAGE ON MWh BASIS: Input Power Arranged by the procurer of the
storage Capacity
 Appropriate commission shall adopt the tariff u/s 63 of Electricity Act, 2003
4. Self Identified Off-Stream Pumped Storage Projects:
 Developers may also identify potential off stream sites where PSP can be constructed
 Allotment from state government not required
 All statutory clearances need to be obtained from central/state agencies before
construction
 All concessions would be provided
MARKET REFORMS/ CONSIDERATIONS:
 Timeline: Start of Construction within 02 years from the date of allotment,
relaxation of 01 year where delay is due to FC & EC.
 Appropriate commission shall ensure monetization of services offered by PSP
such as Spinning reserves, ramping support, black start etc
 Appropriate commission shall notify Peak and Off-Peak tariffs for generation
to provide appropriate pricing signal to peak and base load generating plants
 PSP allowed to participate in all market segments of Power exchange including
High price segment of Day Ahead Market (HP-DAM)
 During monsoon- 80% Power to home state at secondary tariff fixed by
CERC. Remaining 20 % can be sold
 In case contracted capacity is not fully utilized by agency, developer is free
to transfer usage of capacity to other interested consumers. Gains to be
shared with original beneficiary in ratio of 50:50
 Financial institutions like PFC, REC and IREDA shall treat PSP at par with
other renewable energy projects while extending loans of 20-25 years . Debt
equity ratio can be upto 80:20
 Green Finance: PSP may be supported through concessional climate
finance. Sovereign green bonds issues for mobilizing resources for green
infrastructure as a part of the government’s overall market borrowings may
be deployed
Annexure-II
MOP Letter 22.07.2022
(RPO & ENERGY STORAGE OBLIGATION Trajectory 2029-30):
 Large Hydro Projects (LHP’s) including PSP>25 MW as a part of RE.
 LHP’s commissioned after 08.03.2019 will be considered for RPO through a
separate obligation i.e Hydro Power Purchase Obligation (HPO).
 RPO shall be calculated in energy terms as a percentage of total consumption
of electricity.
 Wind RPO shall be met only by energy produced from Wind Power Plants
commissioned after 31st Mar 2022.
 Renewable Energy Certificate mechanism corresponding to Hydro Power to
be developed by CERC to facilitate compliance of HPO would have a capping
price of Rs 5.50/Unit from 08.03.20190 to 31.03.2021 and with an annual
escalation @ 5% thereafter.
RENEWABLE PURCHASE OBLIGATION
TRAJECTORY 2029-30
YEAR WIND RPO HPO OTHER RPO TOTAL RPO
2022-23 0.81% 0.35% 23.44% 24.6%
2023-24 1.6% 0.66% 24.81% 27.07%
2024-25 2.46% 1.08% 26.37% 29.91%
2025-26 3.36% 1.48% 28.17% 33.01%
2026-27 4.29% 1.8% 29.86% 35.95%
2027-28 5.23% 2.16% 31.43% 38.82%
2028-29 6.16% 2.51% 32.69% 41.36%
2029-30 6.94% 2.82% 33.57% 43.33%
ENERGY STORAGE OBLIGATION
 Shall be calculated in energy terms as a
percentage of total consumption of
electricity- Subject to fulfillment of
condition that at least 85% of electricity
stored is procured from RE Source
 POSOCO will maintain data related to
compliance of RPO obligations
FY
Storage
(On Energy
basis)
2023-24 1%
2024-25 1.50%
2025-26 2%
2026-27 2.50%
2027-28 3%
2028-29 3.50%
2029-30 4%
Annexure-III
MOP Letter 23.11.2023 (WAIVER OF ISTS):
 For Solar, Wind, Hydro PSP and BESS Projects commissioned upto 30.06.2025, the
waiver of ISTS charges shall be applicable
• At least 51% of electricity requirement for pumping water at PSP/ Batter charging at
BESS is from Solar/Wind
• Electricity Generated/ Supplied by PSP & BESS
• For Green Hydrogen Plants commissioned upto 30.06.2025- Hydrogen produced using
electricity from SOLAR/WIND/PSP/ BESS
• ISTS (Inter state transmission system)
• Waiver shall be applicable for a period of 25 years for solar, wind and hydro PSP or for a
period of 12 Years for BESS
• Waiver is for ISTS charges and not for losses.
Projects Commissioned before 30.06.2025 No ISTS Charges Applicable
01.07.2025 30.06.2026 25 %
01.07.2026 30.06.2027 50 %
01.07.2027 30.06.2028 75 %
01.07.2028 Onwards 100 %
Annexure-IV
MOP letter 28.09.2021
Budgetary Support towards Cost of Enabling Infrastructure i/e Roads,
Bridges
 Shall be provided for project starting construction after 08.03.2019
 Budgetary support would be provided after appraisal/ approval of each
project by PIB/CCEA (Cabinet Committee on economic affairs) through
MOP
 Limit is 1.5 Cr/MW upto 200 MW and 1.0 Cr/MW for projects above 200 MW
 Will be provided as reimbursement after achieving milestones
 In-Principle approval of MOP is required for budgetary support
 Procedure- After DPR concurrence by State Govt/CEA (Annex-I) to be
submitted to CEA
Eligibility:
 Cap>25MW concurred either by CEA or State Government wherein
LOA is issued after 08.03.2019
 All roads and bridges required to connect major components like
DAM, Power House, Adits (Tunnel), Surge Shafts, Pressure shafts,
TRT (tunnel for return water to tank) etc of the project to state/
national highway including strengthening / widening shall be
considered for budgetary support
 For Construction of Road/Bridges (Land Acquisition Cost/ All
statutory taxes, levies, duties, cess shall be included in budgetary
support)
1 sur 23

Recommandé

Applications of pulsed power par
Applications of pulsed powerApplications of pulsed power
Applications of pulsed powerSergey Korenev
1.9K vues10 diapositives
04-DESIGN AND LAYOUT OF WIND FARM.pdf par
04-DESIGN AND LAYOUT OF WIND FARM.pdf04-DESIGN AND LAYOUT OF WIND FARM.pdf
04-DESIGN AND LAYOUT OF WIND FARM.pdfPrakashBadal9
122 vues68 diapositives
Carbon Capture, Utilization and Storage (CCUS) par
Carbon Capture, Utilization and Storage (CCUS)Carbon Capture, Utilization and Storage (CCUS)
Carbon Capture, Utilization and Storage (CCUS)PetroTeach1
222 vues21 diapositives
Renewable energy in India: Present Status and Policy par
Renewable energy in India: Present Status and PolicyRenewable energy in India: Present Status and Policy
Renewable energy in India: Present Status and PolicyMalik Sameeullah
16.5K vues28 diapositives
CH 7 Energy From Biomass par
CH 7 Energy From BiomassCH 7 Energy From Biomass
CH 7 Energy From BiomassTadviDevarshi
422 vues65 diapositives

Contenu connexe

Tendances

indian energy sector overview par
indian energy sector overviewindian energy sector overview
indian energy sector overviewshivraj negi
2.5K vues27 diapositives
Work in abroad vs India par
Work in abroad vs India Work in abroad vs India
Work in abroad vs India naresh globalgateways
831 vues37 diapositives
Solar and wind power forecasting par
Solar and wind power forecastingSolar and wind power forecasting
Solar and wind power forecastingRCREEE
3.9K vues79 diapositives
Emerging Opportunities - Wind Solar Hybrid System par
Emerging Opportunities - Wind Solar Hybrid System Emerging Opportunities - Wind Solar Hybrid System
Emerging Opportunities - Wind Solar Hybrid System Gensol Engineering Limited
1.7K vues16 diapositives
Hybrid Solar-Wind Power System par
Hybrid Solar-Wind Power SystemHybrid Solar-Wind Power System
Hybrid Solar-Wind Power SystemSwapnil Nakate
50.1K vues22 diapositives
Carbon finance par
Carbon financeCarbon finance
Carbon financeAlban Dsouza
1.2K vues11 diapositives

Tendances(20)

indian energy sector overview par shivraj negi
indian energy sector overviewindian energy sector overview
indian energy sector overview
shivraj negi2.5K vues
Solar and wind power forecasting par RCREEE
Solar and wind power forecastingSolar and wind power forecasting
Solar and wind power forecasting
RCREEE3.9K vues
Hybrid Solar-Wind Power System par Swapnil Nakate
Hybrid Solar-Wind Power SystemHybrid Solar-Wind Power System
Hybrid Solar-Wind Power System
Swapnil Nakate50.1K vues
Renewable Energy Certificate Mechanism in India par sanjeev jain
Renewable Energy Certificate Mechanism in India Renewable Energy Certificate Mechanism in India
Renewable Energy Certificate Mechanism in India
sanjeev jain9K vues
The Opportunities and Challenges of Renewable Energy Integration With Low-Car... par OECD Environment
The Opportunities and Challenges of Renewable Energy Integration With Low-Car...The Opportunities and Challenges of Renewable Energy Integration With Low-Car...
The Opportunities and Challenges of Renewable Energy Integration With Low-Car...
OECD Environment145 vues
New and renewable energy policy and investment in thailand 05-jun-13 par Peerasak C.
New and renewable energy policy and investment in thailand 05-jun-13New and renewable energy policy and investment in thailand 05-jun-13
New and renewable energy policy and investment in thailand 05-jun-13
Peerasak C.4.7K vues
Renewable energy sources – policies of india par Angu Ramesh
Renewable energy sources – policies of indiaRenewable energy sources – policies of india
Renewable energy sources – policies of india
Angu Ramesh1.5K vues
Renewable Energy Sources in Tamilnadu by MATHANKUAMR par Mathankumar S
Renewable Energy Sources in Tamilnadu by MATHANKUAMRRenewable Energy Sources in Tamilnadu by MATHANKUAMR
Renewable Energy Sources in Tamilnadu by MATHANKUAMR
Mathankumar S4.5K vues
Introduction to the Renewable Energy Certificate (REC) Mechanism par Spark Network
Introduction to the Renewable Energy Certificate (REC) MechanismIntroduction to the Renewable Energy Certificate (REC) Mechanism
Introduction to the Renewable Energy Certificate (REC) Mechanism
Spark Network1.4K vues
Non conventional energy sources par Nirmal Kumar
Non conventional energy sourcesNon conventional energy sources
Non conventional energy sources
Nirmal Kumar23K vues
Power sector in India par Daya Kherwar
Power sector in IndiaPower sector in India
Power sector in India
Daya Kherwar40.8K vues
Renewable Energy Resourses par shalini2093
Renewable Energy ResoursesRenewable Energy Resourses
Renewable Energy Resourses
shalini209334.5K vues

Similaire à PSP & Guidelines MOP.pptx

Renewable Energy - Recent Initiatives par
Renewable Energy - Recent InitiativesRenewable Energy - Recent Initiatives
Renewable Energy - Recent InitiativesSaurabh Mehta
1.2K vues25 diapositives
HYDRO_POLICY_UK_2015 par
HYDRO_POLICY_UK_2015HYDRO_POLICY_UK_2015
HYDRO_POLICY_UK_2015Anil Khadka
432 vues12 diapositives
Manipur solar policy 2014 par
Manipur solar policy 2014Manipur solar policy 2014
Manipur solar policy 2014Headway Solar
757 vues8 diapositives
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018 par
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018Gensol Engineering Limited
1.9K vues8 diapositives
Small Power Generation Plant par
Small Power Generation PlantSmall Power Generation Plant
Small Power Generation PlantCraig Abednego Malone
333 vues17 diapositives
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019 par
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Gensol Engineering Limited
1.4K vues2 diapositives

Similaire à PSP & Guidelines MOP.pptx(20)

Renewable Energy - Recent Initiatives par Saurabh Mehta
Renewable Energy - Recent InitiativesRenewable Energy - Recent Initiatives
Renewable Energy - Recent Initiatives
Saurabh Mehta1.2K vues
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh... par electricitygovernance
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
A Presentation on the Regulatory Regime for Renewable Energy Projects in Andh...
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O... par Resurgent India
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...
Affordable 24x7 Power To All @2019 - Key Strategies for Achieving Programme O...
Resurgent India282 vues
Renewables will shape Argentina’s new energy matrix par Doris Capurro
Renewables will shape Argentina’s new	energy matrixRenewables will shape Argentina’s new	energy matrix
Renewables will shape Argentina’s new energy matrix
Doris Capurro276 vues
Gujarat Wind Power Policy 2013 par Spark Network
Gujarat Wind Power Policy 2013Gujarat Wind Power Policy 2013
Gujarat Wind Power Policy 2013
Spark Network781 vues
Tariff policy of India: Salient Points par Amitava Nag
Tariff policy of India: Salient Points Tariff policy of India: Salient Points
Tariff policy of India: Salient Points
Amitava Nag2.8K vues
Analysis on Wind Solar Hybrid Tender.pptx par ssuser387308
Analysis on Wind Solar Hybrid Tender.pptxAnalysis on Wind Solar Hybrid Tender.pptx
Analysis on Wind Solar Hybrid Tender.pptx
ssuser3873085 vues
Andhra pradesh solar policy 2015 par Headway Solar
Andhra pradesh solar policy 2015Andhra pradesh solar policy 2015
Andhra pradesh solar policy 2015
Headway Solar538 vues

Dernier

GDSC Mikroskil Members Onboarding 2023.pdf par
GDSC Mikroskil Members Onboarding 2023.pdfGDSC Mikroskil Members Onboarding 2023.pdf
GDSC Mikroskil Members Onboarding 2023.pdfgdscmikroskil
63 vues62 diapositives
Renewal Projects in Seismic Construction par
Renewal Projects in Seismic ConstructionRenewal Projects in Seismic Construction
Renewal Projects in Seismic ConstructionEngineering & Seismic Construction
5 vues8 diapositives
_MAKRIADI-FOTEINI_diploma thesis.pptx par
_MAKRIADI-FOTEINI_diploma thesis.pptx_MAKRIADI-FOTEINI_diploma thesis.pptx
_MAKRIADI-FOTEINI_diploma thesis.pptxfotinimakriadi
12 vues32 diapositives
Global airborne satcom market report par
Global airborne satcom market reportGlobal airborne satcom market report
Global airborne satcom market reportdefencereport78
6 vues13 diapositives
MongoDB.pdf par
MongoDB.pdfMongoDB.pdf
MongoDB.pdfArthyR3
49 vues6 diapositives
Proposal Presentation.pptx par
Proposal Presentation.pptxProposal Presentation.pptx
Proposal Presentation.pptxkeytonallamon
67 vues36 diapositives

Dernier(20)

GDSC Mikroskil Members Onboarding 2023.pdf par gdscmikroskil
GDSC Mikroskil Members Onboarding 2023.pdfGDSC Mikroskil Members Onboarding 2023.pdf
GDSC Mikroskil Members Onboarding 2023.pdf
gdscmikroskil63 vues
_MAKRIADI-FOTEINI_diploma thesis.pptx par fotinimakriadi
_MAKRIADI-FOTEINI_diploma thesis.pptx_MAKRIADI-FOTEINI_diploma thesis.pptx
_MAKRIADI-FOTEINI_diploma thesis.pptx
fotinimakriadi12 vues
MongoDB.pdf par ArthyR3
MongoDB.pdfMongoDB.pdf
MongoDB.pdf
ArthyR349 vues
Créativité dans le design mécanique à l’aide de l’optimisation topologique par LIEGE CREATIVE
Créativité dans le design mécanique à l’aide de l’optimisation topologiqueCréativité dans le design mécanique à l’aide de l’optimisation topologique
Créativité dans le design mécanique à l’aide de l’optimisation topologique
2023Dec ASU Wang NETR Group Research Focus and Facility Overview.pptx par lwang78
2023Dec ASU Wang NETR Group Research Focus and Facility Overview.pptx2023Dec ASU Wang NETR Group Research Focus and Facility Overview.pptx
2023Dec ASU Wang NETR Group Research Focus and Facility Overview.pptx
lwang78180 vues
Ansari: Practical experiences with an LLM-based Islamic Assistant par M Waleed Kadous
Ansari: Practical experiences with an LLM-based Islamic AssistantAnsari: Practical experiences with an LLM-based Islamic Assistant
Ansari: Practical experiences with an LLM-based Islamic Assistant
SUMIT SQL PROJECT SUPERSTORE 1.pptx par Sumit Jadhav
SUMIT SQL PROJECT SUPERSTORE 1.pptxSUMIT SQL PROJECT SUPERSTORE 1.pptx
SUMIT SQL PROJECT SUPERSTORE 1.pptx
Sumit Jadhav 22 vues
Design of machine elements-UNIT 3.pptx par gopinathcreddy
Design of machine elements-UNIT 3.pptxDesign of machine elements-UNIT 3.pptx
Design of machine elements-UNIT 3.pptx
gopinathcreddy37 vues
Design_Discover_Develop_Campaign.pptx par ShivanshSeth6
Design_Discover_Develop_Campaign.pptxDesign_Discover_Develop_Campaign.pptx
Design_Discover_Develop_Campaign.pptx
ShivanshSeth649 vues

PSP & Guidelines MOP.pptx

  • 1. PUMPED STORAGE HYDROPOWER Guidelines issued by Ministry of Power, Government of India Abhishek Mallick Executive Engineer (E&M) POWER PROJECTS DIVISION, SCCL
  • 2. ● PSH acts as an energy store, If there is a surplus of power in the grid, the pumped storage power station switches to pumping mode – an electric motor drives the pump turbines, which pumps water from a lower reservoir to a higher storage basin. ● If the demand for electricity in the grid rises, water is released from the upper basin via a pressure pipeline to the bottom. The water causes the pump turbines to rotate, now operating in turbine mode and used to drive the generators. Within seconds, electricity is generated and fed into the grid. ABOUT PSP TECHNOLOGY:
  • 4. ● ON-STREAM: Both reservoirs are located on any river /stream ● OFF-STREAM OPEN LOOP - Only one of the reservoirs is located on any river/ stream. ● OFF-STREAM CLOSED LOOP - None of the reservoirs is located on any river/ stream 4 TYPES OF PSP:
  • 6. ● Pumped storage Hydropower + Solar Power/ Wind Power ● Once the solar power is more than the needed, excess is used to pump water from lower reservoir to upper reservoir. ● If there is no solar power generation, the water flows from upper basin to the lower and drives a turbine to produce power. HYBRID PSP CONCEPT:
  • 7. HIGHLIGHTS OF PSP  PSP are also known as ‘Water Battery/ Green Battery’  Long service life of 40-50 years  Offers critical back up during peak hours (Flexible/Reliable)  No residual environment impacts  High economical value: Pumped storage plants works at an efficiency level upto 82 percent  PSP are designed for 06 hours of operations  CEA estimate Potential: 103 GW- ON River, OFF River- Being estimated  As per report by CEA 26.7 GW PSP are required by 2032
  • 8. PRO CONS Flexible and Reliable Long Planning and construction time Long Service Life Specific geographical condition for upper reservoir and lower reservoir Relatively high efficiency upto 85% Large amount of initial investment Most viable option Long Pay back period Reduces energy wastage PRO & CONS:
  • 9. 9 GUIDELINES ISSUED BY M.O.P Dt. 10.04.2023
  • 10. ENABLERS FOR PSP  Environmental Clearances- PSP on existing reservoirs and on off-the-river sites may be treated as a separate category for processing of applications (Appraised under B2 category of MOEF &CC for grant of EC) . As per MOEF&CC draft notification dated 11.10.22 the following criteria will be treated as B2 for grant of EC: 1. Projects which do not attract Forest Clearance/ Wildlife Clearance 2. Projects where no new reservoirs are created 3. Projects where existing reservoirs are not expanded or structurally modified  Cost of Pumping Power- Three factors: 1. Cost of Input Power (Viability depends on availability of affordable input power) 2. Conversion Losses 3. Cost of Storage
  • 11. Value of Peak Power- PSP is capable of offering several services such as: •Spinning Reserves- Generation capacity that is on-line but unloaded and that can respond within 10 minutes to compensate for generation or transmission outages, Reactive Support •Reactive Support- used to provide the voltage levels necessary for active power to do useful work •Black start- the ability of generation to restart parts of the power system to recover from a blackout •Frequency response, faster start up’s and shutdowns which are essential for grid stability
  • 12. MEASURES TAKEN BY GOI FOR PROMOTION OF PSP • States to allot PSP to PSU (Annex-I) • Energy Storage Obligation (Annex-II) • Waiver of ISTS Charges for PSP (Annex-III)- (Extendable to PSP where construction work is awarded by 30.06.2025 • Budgetary Support (Annex-IV) • Timelines for formulation and concurrence of DPR’s for PSP reduced from 900 days to 720 days and CEA shall further reduce timeline for Off-stream closed loop PSP and PSP on existing hydro projects (Where one reservoir is available) • Since No tariff/ financial evaluation by CEA for tariff based Competitive bidding, concurrence reduced from 150 days to 75 days. For other mode of award concurrence reduced from 150 days to 125 days. • Central Government will notify a benchmark tariff of storage for investment decisions
  • 13. BENEFITS TO BE EXTENDED BY STATE • No upfront fee shall be charged by state government • State Government shall consider reimbursement of SGST on PSP project components. • States may exempt Stamp duty and Registration fee for land to be acquired by off-the-river PSP • Government land may be provided at a concessional rate to the developers on annual lease rent basis. • To avoid double taxation, Electricity Duty and Cross subsidy charges shall not be applicable for Pumping power and may be levied on final consumption of electricity • No requirement of Local Area Development fund
  • 14. ALLOTMENT OF PSP PROJECTS State Government may allot project sites to developers in the following manner: 1. On Nomination Basis to CPSU/SPSU: -States may award projects directly to PSU on nomination basis - Award of EPC shall be through Competitive Bidding 2. Allotment through Competitive Bidding: - May be allotted to Private developers by two stage competitive bidding Stage 1: Pre-qualification based on financial strength, experience, turnover, ability to meet performance guarantees Stage 2: Bids to be called on quantifiable parameters such as concession period of project or any other parameter as specified by Central/State Govt. For above two modes: • Home state shall have right of first refusal upto 80% of Project Capacity and developer is free to sell power in any mode • Tariff shall be fixed by appropriate commission u/s 62 of elec act 2003,
  • 15. 3. Allotment through Tariff Based Competitive Bidding: May be awarded to a developer in TBCB mode:  Survey & Investigation and Prep of DPR may be given to SPV under State/Central PSU  SPV responsible for Pre-construction activities such as Project Report, Land Acquisition, Environment & Forest Clearance etc.  DPR may be subsequently bid out for construction and SPV transferred to the successful bidder on the basis of :  COMPOSITE TARIFF (including Cost of Input Power)- Input power arranged by developer  TARIFF FOR STORAGE ON MWh BASIS: Input Power Arranged by the procurer of the storage Capacity  Appropriate commission shall adopt the tariff u/s 63 of Electricity Act, 2003 4. Self Identified Off-Stream Pumped Storage Projects:  Developers may also identify potential off stream sites where PSP can be constructed  Allotment from state government not required  All statutory clearances need to be obtained from central/state agencies before construction  All concessions would be provided
  • 16. MARKET REFORMS/ CONSIDERATIONS:  Timeline: Start of Construction within 02 years from the date of allotment, relaxation of 01 year where delay is due to FC & EC.  Appropriate commission shall ensure monetization of services offered by PSP such as Spinning reserves, ramping support, black start etc  Appropriate commission shall notify Peak and Off-Peak tariffs for generation to provide appropriate pricing signal to peak and base load generating plants  PSP allowed to participate in all market segments of Power exchange including High price segment of Day Ahead Market (HP-DAM)
  • 17.  During monsoon- 80% Power to home state at secondary tariff fixed by CERC. Remaining 20 % can be sold  In case contracted capacity is not fully utilized by agency, developer is free to transfer usage of capacity to other interested consumers. Gains to be shared with original beneficiary in ratio of 50:50  Financial institutions like PFC, REC and IREDA shall treat PSP at par with other renewable energy projects while extending loans of 20-25 years . Debt equity ratio can be upto 80:20  Green Finance: PSP may be supported through concessional climate finance. Sovereign green bonds issues for mobilizing resources for green infrastructure as a part of the government’s overall market borrowings may be deployed
  • 18. Annexure-II MOP Letter 22.07.2022 (RPO & ENERGY STORAGE OBLIGATION Trajectory 2029-30):  Large Hydro Projects (LHP’s) including PSP>25 MW as a part of RE.  LHP’s commissioned after 08.03.2019 will be considered for RPO through a separate obligation i.e Hydro Power Purchase Obligation (HPO).  RPO shall be calculated in energy terms as a percentage of total consumption of electricity.  Wind RPO shall be met only by energy produced from Wind Power Plants commissioned after 31st Mar 2022.  Renewable Energy Certificate mechanism corresponding to Hydro Power to be developed by CERC to facilitate compliance of HPO would have a capping price of Rs 5.50/Unit from 08.03.20190 to 31.03.2021 and with an annual escalation @ 5% thereafter.
  • 19. RENEWABLE PURCHASE OBLIGATION TRAJECTORY 2029-30 YEAR WIND RPO HPO OTHER RPO TOTAL RPO 2022-23 0.81% 0.35% 23.44% 24.6% 2023-24 1.6% 0.66% 24.81% 27.07% 2024-25 2.46% 1.08% 26.37% 29.91% 2025-26 3.36% 1.48% 28.17% 33.01% 2026-27 4.29% 1.8% 29.86% 35.95% 2027-28 5.23% 2.16% 31.43% 38.82% 2028-29 6.16% 2.51% 32.69% 41.36% 2029-30 6.94% 2.82% 33.57% 43.33%
  • 20. ENERGY STORAGE OBLIGATION  Shall be calculated in energy terms as a percentage of total consumption of electricity- Subject to fulfillment of condition that at least 85% of electricity stored is procured from RE Source  POSOCO will maintain data related to compliance of RPO obligations FY Storage (On Energy basis) 2023-24 1% 2024-25 1.50% 2025-26 2% 2026-27 2.50% 2027-28 3% 2028-29 3.50% 2029-30 4%
  • 21. Annexure-III MOP Letter 23.11.2023 (WAIVER OF ISTS):  For Solar, Wind, Hydro PSP and BESS Projects commissioned upto 30.06.2025, the waiver of ISTS charges shall be applicable • At least 51% of electricity requirement for pumping water at PSP/ Batter charging at BESS is from Solar/Wind • Electricity Generated/ Supplied by PSP & BESS • For Green Hydrogen Plants commissioned upto 30.06.2025- Hydrogen produced using electricity from SOLAR/WIND/PSP/ BESS • ISTS (Inter state transmission system) • Waiver shall be applicable for a period of 25 years for solar, wind and hydro PSP or for a period of 12 Years for BESS • Waiver is for ISTS charges and not for losses. Projects Commissioned before 30.06.2025 No ISTS Charges Applicable 01.07.2025 30.06.2026 25 % 01.07.2026 30.06.2027 50 % 01.07.2027 30.06.2028 75 % 01.07.2028 Onwards 100 %
  • 22. Annexure-IV MOP letter 28.09.2021 Budgetary Support towards Cost of Enabling Infrastructure i/e Roads, Bridges  Shall be provided for project starting construction after 08.03.2019  Budgetary support would be provided after appraisal/ approval of each project by PIB/CCEA (Cabinet Committee on economic affairs) through MOP  Limit is 1.5 Cr/MW upto 200 MW and 1.0 Cr/MW for projects above 200 MW  Will be provided as reimbursement after achieving milestones  In-Principle approval of MOP is required for budgetary support  Procedure- After DPR concurrence by State Govt/CEA (Annex-I) to be submitted to CEA
  • 23. Eligibility:  Cap>25MW concurred either by CEA or State Government wherein LOA is issued after 08.03.2019  All roads and bridges required to connect major components like DAM, Power House, Adits (Tunnel), Surge Shafts, Pressure shafts, TRT (tunnel for return water to tank) etc of the project to state/ national highway including strengthening / widening shall be considered for budgetary support  For Construction of Road/Bridges (Land Acquisition Cost/ All statutory taxes, levies, duties, cess shall be included in budgetary support)