Design of a Rigid pavement
                                                                                                      
 
 
 
 
 
 
 
Team :
1) Ahsan ullah Hussaini Syed
2) Ahmed Towfeequllah Siddiqui
 
 
Introduction
The project involved designing of two different types of Rigid pavements using the
AASHTOWare Pavement ME software.
1) JPCP (Jointed Plain Concrete Pavement) : It was designed as a three layered structure,
the layer distribution being as follows:
Layer 1 – PCC – 16 inch
Layer 2 – NonStabilized (Crushed gravel) – 8 inch
Layer 3 – Subgrade (A-1a) – Semi Infinite
Jointed plain concrete pavement uses contraction joints to control cracking and uses
reinforcing steel in form of dowel bars.
Transverse joint spacing is selected such that temperature and moisture stresses do not
produce intermediate cracking between joints.
This typically results in a spacing no longer than about 6.1 m (20 ft.).
2) CRCP (CONTINUOUSLY REINFORCED CONCRETE PAVEMENTS) : It was
designed as a 4 layered structure, the layer distribution being as follows:
Layer 1 – PCC – 11.3 inch
Layer 2 – Stabilized – 4 inch
Layer 3 – NonStabilized – 8 inch
Layer 4 – Subgrade – Semi infinite
CRCP is concrete pavement reinforced with continuous steel bars throughout its length.
Its design eliminates the need for transverse joints (other than at bridges and other
structures) and keeps cracks tight, resulting in a continuous, smooth-riding surface.
 
 
AASHTOWARE PAVEMENT ME
DESIGN USER INPUTS
The Pavement ME Design program
utilizes the user-defined inputs to
conduct a CRCP and JPCP mechanistic
analysis to predict the expected
incremental distress levels based on a
national calibration. As the Pavement
ME Design program represents a
fundamental change in design
philosophies in CRCP and JPCP design, it requires much greater knowledge of design parameters
affecting design including layer materials, climate, and traffic characterization. For users new to the
program, the following section outlines a basic overview of the program’s format and design
parameters. The Figure shows the main input screen of the Pavement ME Design program. General
input categories are viewed in the left of the screen while specific input parameters are viewed and
entered in the middle of the screen.
 
Figure 2 : Layer Structure & material properties – CRCP
Figure 1: Design user inputs for CRCP & JPCP –
AASHTOWare ME.
 
 
 
Figure 3 Layer structure & material properties - JPCP
Traffic
To characterize the volume, the total amount of truck traffic is input as average annual daily truck
traffic (AADTT), including the expected lane and directional distribution factor for the facility.
 
Figure 4: Quarterly ADT distribution for Naples, Fl.
Ref : https://www.colliergov.net/modules/showdocument.aspx?documentid=58143
The AADT of Naples, FL was used to design the JPC pavement (With Dowel Bars), likewise
the AADT of Chicago, IL was used in the designing of the CRCP (Ref: 
https://goo.gl/3OtCIY)
 
 
CLIMATE
A key improvement to the CRCP design process is accounting for site-specific climate. The
Pavement ME Design program models account for daily and seasonal fluctuations in
temperature and moisture profiles in the CRCP and soil layer, respectively, through site-
specific factors such as percent sunshine, air temperature, precipitation, wind, and water table
depth. There are several hundred weather stations across North America from which the user
can select the nearest one to the project site, or the user can create a “virtual weather station”
by allowing the program to interpolate nearby weather data to the user’s specific project site.
 
Figure 5 : Ideal station can be picked to input Climate information
The pavement is then analyzed for :
a) IRI and Punchout in case of CRCP
b) Cracking, faulting & IRI in case of JPCP.
Post analysis, thickness is determined (Trial & error) for both the pavements.
Figure 6-7: Climate data for both the pavements.
 
 
Result for JPCP
As far as terminal IRI is considered, Distress reliability of 122.56 was predicted from the
analysis against the targeted 172 which was well below the threshold. Similarly Joint Faulting
and Transverse cracking reliability criterion were satisfied.
The graphs above illustrate the achieved data for Cracking, Faulting and IRI and prediction
for a period of 30 years ahead.
By trial & error the thickness of the slab was found to be 16 inches.
 
 
Result for CRCP:
Distress Type
Distress @
Specified
Reliability (%) Criterio
n
SatisfiedTarget Predicted Target Achieved
Terminal IRI (in./mile) 172.00 143.15 90.00 99.29 Pass
CRCP punchouts (1/mile) 10.00 3.99 90.00 99.95 Pass
As far as terminal IRI is considered, Distress reliability of 143.15 was predicted from the
analysis against the targeted 172 which was well below the threshold. Similarly punchouts
achieved a satisfactory 99.95% reliability.
The graphs above illustrate the achieved data for IRI & Punchout and prediction for a period
of 30 years ahead.
By trial & error the thickness of the slab was found to be 11.3 inches.
 
 
KENPAVE
An analysis was carried out both the pavement types for Maximum stress using Kenpave.
CRCP
Slab thickness: 11.3 in ;
Dimensions: 12 x 12 ;
Reinforcement: 0.7%
Nodes : X : 0, 7, 14, 26, 50, 85, 120
Y : 0, 12, 36, 54, 78, 120
MAXIMUM STRESS (SMAX) IN LAYER 1 IS -95.112 ( NODE 2 )
MAXIMUM STRESS IN X DIRECTION = 0.0 ( NODE 0 )
MINIMUM STRESS IN X DIRECTION = 34.4 ( NODE 22 )
MAXIMUM STRESS IN Y DIRECTION = -95.1 ( NODE 2 )
MINIMUM STRESS IN Y DIRECTION = 13.4 ( NODE 5)
JCPC
Slab thickness: 16 in ;
Dimensions: 12 x 12 ;
Dowel bar: Dia: 1.25 in; Joint Spacing: 17ft
Nodes : X : 0, 7, 14, 26, 50, 85, 120
Y : 0, 12, 36, 54, 78, 120
MAXIMUM STRESS (SMAX) IN LAYER 1 IS -67.833 ( NODE 2 )
MAXIMUM STRESS IN X DIRECTION = 0.0 ( NODE 0 )
MINIMUM STRESS IN X DIRECTION = 24.2 ( NODE 43 )
MAXIMUM STRESS IN Y DIRECTION = -67.8 ( NODE 2 )
MINIMUM STRESS IN Y DIRECTION = 5.6 ( NODE 6 )
 
 
Conclusion
JPCP
For a period of 30 years cracking is shown to be constant and gives a possibility of the
pavement life extending through 40-50 years as far as cracking is concerned. The
faulting rose from 0.02 during construction to 0.09 over a period of 30 years and may
only breach the threshold value after 40-45 years which again is well beyond the design
life. The IRI curve shows a linear relation for 25 years and the curve begins to flatten
out hence indicating an extended life than what it was being designed for.
CRCP
The IRI at the 30 year threshold is 143.15 (172 Max) and it keeps ascending and will
breach the target value round about the 45-50 year mark which is well ahead of our
target design life. The punchout starts at 2.2 and the curve ascends to about 3.99 till 15
years and henceforth remains constant till the target design life of 30 years and may
breach the limit well beyond the 50 year mark.

More Related Content

What's hot

2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...VATSAL PATEL
 
construction of flexible pavement
construction of flexible pavementconstruction of flexible pavement
construction of flexible pavementRafi Khan
 
Rigid Pavements Design Part - I
Rigid Pavements Design Part - IRigid Pavements Design Part - I
Rigid Pavements Design Part - ISachin Kulkarni
 
Rigid Pavement Design Part II
Rigid Pavement Design Part IIRigid Pavement Design Part II
Rigid Pavement Design Part IISachin Kulkarni
 
First 20 year road plan /nagpur road plan
First  20 year road plan /nagpur road planFirst  20 year road plan /nagpur road plan
First 20 year road plan /nagpur road planAbhishekKadve
 
Bituminous road construction
Bituminous road constructionBituminous road construction
Bituminous road constructionAnitha Jacob
 
BITUMEN MIXES FOR ROAD
BITUMEN MIXES FOR ROADBITUMEN MIXES FOR ROAD
BITUMEN MIXES FOR ROADkumawat123
 
Study of design of the flexible pavements
Study of design of the flexible pavementsStudy of design of the flexible pavements
Study of design of the flexible pavementsShaik Asif Ahmed
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavementsHARITSEHRAWAT
 
highway development in india
highway development in indiahighway development in india
highway development in indiaPrathi Baa
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training pptSumit Singh
 
Dowel bars, tie bars and their design
Dowel bars, tie bars and their designDowel bars, tie bars and their design
Dowel bars, tie bars and their designBhavya Jaiswal
 
Subgrade Stabilization: Materials & Methods
Subgrade Stabilization: Materials & MethodsSubgrade Stabilization: Materials & Methods
Subgrade Stabilization: Materials & MethodsJill Reeves
 

What's hot (20)

BITUMINOUS ROAD PPT
BITUMINOUS ROAD PPTBITUMINOUS ROAD PPT
BITUMINOUS ROAD PPT
 
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
 
construction of flexible pavement
construction of flexible pavementconstruction of flexible pavement
construction of flexible pavement
 
Rigid Pavements Design Part - I
Rigid Pavements Design Part - IRigid Pavements Design Part - I
Rigid Pavements Design Part - I
 
Rigid Pavement Design Part II
Rigid Pavement Design Part IIRigid Pavement Design Part II
Rigid Pavement Design Part II
 
CBR Test
CBR TestCBR Test
CBR Test
 
Burmister 2 layer
Burmister 2 layerBurmister 2 layer
Burmister 2 layer
 
Unit 1
Unit 1Unit 1
Unit 1
 
First 20 year road plan /nagpur road plan
First  20 year road plan /nagpur road planFirst  20 year road plan /nagpur road plan
First 20 year road plan /nagpur road plan
 
Pavements PPT
 Pavements PPT  Pavements PPT
Pavements PPT
 
Unit 4
Unit 4Unit 4
Unit 4
 
Design flexible and rigid pavements
Design flexible and rigid pavementsDesign flexible and rigid pavements
Design flexible and rigid pavements
 
Bituminous road construction
Bituminous road constructionBituminous road construction
Bituminous road construction
 
BITUMEN MIXES FOR ROAD
BITUMEN MIXES FOR ROADBITUMEN MIXES FOR ROAD
BITUMEN MIXES FOR ROAD
 
Study of design of the flexible pavements
Study of design of the flexible pavementsStudy of design of the flexible pavements
Study of design of the flexible pavements
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavements
 
highway development in india
highway development in indiahighway development in india
highway development in india
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training ppt
 
Dowel bars, tie bars and their design
Dowel bars, tie bars and their designDowel bars, tie bars and their design
Dowel bars, tie bars and their design
 
Subgrade Stabilization: Materials & Methods
Subgrade Stabilization: Materials & MethodsSubgrade Stabilization: Materials & Methods
Subgrade Stabilization: Materials & Methods
 

Viewers also liked

Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavementsMary John C
 
Design and construction of concrete roads
Design and construction of concrete roadsDesign and construction of concrete roads
Design and construction of concrete roadsOlukayode Alao
 
Rigid pavement distress
Rigid pavement distress Rigid pavement distress
Rigid pavement distress Ankit Sarkar
 
Road Construction
Road ConstructionRoad Construction
Road ConstructionDanish Mohd
 
Lect 6 pavement design
Lect 6 pavement designLect 6 pavement design
Lect 6 pavement designM Firdaus
 
PROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONPROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONGLA University
 
Operational Readiness Activation & Transit of Airport Construction
Operational Readiness Activation & Transit of Airport ConstructionOperational Readiness Activation & Transit of Airport Construction
Operational Readiness Activation & Transit of Airport ConstructionAhmed Towfeequllah Siddiqui
 
1 introduction ( Highway Engineering Dr. Sherif El-Badawy )
1 introduction ( Highway Engineering Dr. Sherif El-Badawy )1 introduction ( Highway Engineering Dr. Sherif El-Badawy )
1 introduction ( Highway Engineering Dr. Sherif El-Badawy )Hossam Shafiq I
 
Pavement materials and design in western australia by geoffrey cocks
Pavement materials and design in western australia by geoffrey cocksPavement materials and design in western australia by geoffrey cocks
Pavement materials and design in western australia by geoffrey cocksEngineers Australia
 
TO INVESTIGATE COMBINED INFLUENCE OF STEEL FIBER AND SILICAFUME ON HIGH STREN...
TO INVESTIGATE COMBINED INFLUENCE OF STEEL FIBER AND SILICAFUME ON HIGH STREN...TO INVESTIGATE COMBINED INFLUENCE OF STEEL FIBER AND SILICAFUME ON HIGH STREN...
TO INVESTIGATE COMBINED INFLUENCE OF STEEL FIBER AND SILICAFUME ON HIGH STREN...IAEME Publication
 
Fatigue Behaviour of Recycled Tyre Rubber-Filled Concrete and its implication...
Fatigue Behaviour of Recycled Tyre Rubber-Filled Concrete and its implication...Fatigue Behaviour of Recycled Tyre Rubber-Filled Concrete and its implication...
Fatigue Behaviour of Recycled Tyre Rubber-Filled Concrete and its implication...Mario Parra
 
Logical assessment of hooked end steel fibre reinforced concrete in m 40 grad...
Logical assessment of hooked end steel fibre reinforced concrete in m 40 grad...Logical assessment of hooked end steel fibre reinforced concrete in m 40 grad...
Logical assessment of hooked end steel fibre reinforced concrete in m 40 grad...eSAT Journals
 
Andres salas batching effects on properties of recycled aggregate concretes...
Andres salas   batching effects on properties of recycled aggregate concretes...Andres salas   batching effects on properties of recycled aggregate concretes...
Andres salas batching effects on properties of recycled aggregate concretes...taqiayesha
 

Viewers also liked (20)

design of rigid
design of rigiddesign of rigid
design of rigid
 
Design of proposed highway
Design of proposed highwayDesign of proposed highway
Design of proposed highway
 
Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
 
Design and construction of concrete roads
Design and construction of concrete roadsDesign and construction of concrete roads
Design and construction of concrete roads
 
Rigid pavement distress
Rigid pavement distress Rigid pavement distress
Rigid pavement distress
 
Road Construction
Road ConstructionRoad Construction
Road Construction
 
Lect 6 pavement design
Lect 6 pavement designLect 6 pavement design
Lect 6 pavement design
 
PROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONPROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTION
 
Contract Management in BIM
Contract Management in BIMContract Management in BIM
Contract Management in BIM
 
Operational Readiness Activation & Transit of Airport Construction
Operational Readiness Activation & Transit of Airport ConstructionOperational Readiness Activation & Transit of Airport Construction
Operational Readiness Activation & Transit of Airport Construction
 
1 introduction ( Highway Engineering Dr. Sherif El-Badawy )
1 introduction ( Highway Engineering Dr. Sherif El-Badawy )1 introduction ( Highway Engineering Dr. Sherif El-Badawy )
1 introduction ( Highway Engineering Dr. Sherif El-Badawy )
 
Pavement materials and design in western australia by geoffrey cocks
Pavement materials and design in western australia by geoffrey cocksPavement materials and design in western australia by geoffrey cocks
Pavement materials and design in western australia by geoffrey cocks
 
Erik Updyke & Imelda Diaz: Bonded Wearing Course
Erik Updyke & Imelda Diaz: Bonded Wearing CourseErik Updyke & Imelda Diaz: Bonded Wearing Course
Erik Updyke & Imelda Diaz: Bonded Wearing Course
 
2. Evolution of roads
2. Evolution of roads2. Evolution of roads
2. Evolution of roads
 
TO INVESTIGATE COMBINED INFLUENCE OF STEEL FIBER AND SILICAFUME ON HIGH STREN...
TO INVESTIGATE COMBINED INFLUENCE OF STEEL FIBER AND SILICAFUME ON HIGH STREN...TO INVESTIGATE COMBINED INFLUENCE OF STEEL FIBER AND SILICAFUME ON HIGH STREN...
TO INVESTIGATE COMBINED INFLUENCE OF STEEL FIBER AND SILICAFUME ON HIGH STREN...
 
20320140505007
2032014050500720320140505007
20320140505007
 
Fatigue Behaviour of Recycled Tyre Rubber-Filled Concrete and its implication...
Fatigue Behaviour of Recycled Tyre Rubber-Filled Concrete and its implication...Fatigue Behaviour of Recycled Tyre Rubber-Filled Concrete and its implication...
Fatigue Behaviour of Recycled Tyre Rubber-Filled Concrete and its implication...
 
Logical assessment of hooked end steel fibre reinforced concrete in m 40 grad...
Logical assessment of hooked end steel fibre reinforced concrete in m 40 grad...Logical assessment of hooked end steel fibre reinforced concrete in m 40 grad...
Logical assessment of hooked end steel fibre reinforced concrete in m 40 grad...
 
Andres salas batching effects on properties of recycled aggregate concretes...
Andres salas   batching effects on properties of recycled aggregate concretes...Andres salas   batching effects on properties of recycled aggregate concretes...
Andres salas batching effects on properties of recycled aggregate concretes...
 
Block 27 sp 13
Block 27 sp 13Block 27 sp 13
Block 27 sp 13
 

Similar to Design of a rigid pavement (jpcp & crcp)

Recent Advances in Pavement Deisgn of Flexoble Papenent by IRC:37.pdf
Recent Advances in Pavement Deisgn of Flexoble Papenent by IRC:37.pdfRecent Advances in Pavement Deisgn of Flexoble Papenent by IRC:37.pdf
Recent Advances in Pavement Deisgn of Flexoble Papenent by IRC:37.pdfRANGOJUSRINIVASAKUMA1
 
A CFD study of Wind Tunnel Wall Interference_Md Hasan
A CFD study of Wind Tunnel Wall Interference_Md HasanA CFD study of Wind Tunnel Wall Interference_Md Hasan
A CFD study of Wind Tunnel Wall Interference_Md HasanMd Rakibul Hasan
 
P07011_Gupta_et_al
P07011_Gupta_et_alP07011_Gupta_et_al
P07011_Gupta_et_alPankaj Gupta
 
CFD analysis of commercial vehicle
CFD analysis of commercial vehicleCFD analysis of commercial vehicle
CFD analysis of commercial vehicleShih Cheng Tung
 
IRJET- Parametric Study on Behaviour of RCC Box Culvert for Dynamic Loading
IRJET- Parametric Study on Behaviour of RCC Box Culvert for Dynamic LoadingIRJET- Parametric Study on Behaviour of RCC Box Culvert for Dynamic Loading
IRJET- Parametric Study on Behaviour of RCC Box Culvert for Dynamic LoadingIRJET Journal
 
Analysis of Flexible Pavement Using IIT PAVE software
Analysis of Flexible Pavement Using IIT PAVE softwareAnalysis of Flexible Pavement Using IIT PAVE software
Analysis of Flexible Pavement Using IIT PAVE softwareUnknownUser704294
 
Cdd mahesh dasar ijertv2 is120775
Cdd mahesh dasar ijertv2 is120775Cdd mahesh dasar ijertv2 is120775
Cdd mahesh dasar ijertv2 is120775Mahesh Dasar
 
Simulations Of Unsteady Flow Around A Generic Pickup Truck Using Reynolds Ave...
Simulations Of Unsteady Flow Around A Generic Pickup Truck Using Reynolds Ave...Simulations Of Unsteady Flow Around A Generic Pickup Truck Using Reynolds Ave...
Simulations Of Unsteady Flow Around A Generic Pickup Truck Using Reynolds Ave...Abhishek Jain
 
Pavement Design Methods 2 (Flexible and Rigid).pdf
Pavement Design Methods 2 (Flexible and Rigid).pdfPavement Design Methods 2 (Flexible and Rigid).pdf
Pavement Design Methods 2 (Flexible and Rigid).pdfMohammadKabirHossain4
 
Rehabilitation Study of NH34 Kabrai to Maudaha through the 35.00 Km Section L...
Rehabilitation Study of NH34 Kabrai to Maudaha through the 35.00 Km Section L...Rehabilitation Study of NH34 Kabrai to Maudaha through the 35.00 Km Section L...
Rehabilitation Study of NH34 Kabrai to Maudaha through the 35.00 Km Section L...IRJET Journal
 
Graduation Project (DESIGN AND ANALYSIS OF MULTI-TOWER STRUCTURE USING ETABS).
Graduation Project (DESIGN AND ANALYSIS OF MULTI-TOWER STRUCTURE USING ETABS).Graduation Project (DESIGN AND ANALYSIS OF MULTI-TOWER STRUCTURE USING ETABS).
Graduation Project (DESIGN AND ANALYSIS OF MULTI-TOWER STRUCTURE USING ETABS).khaledalshami93
 
07-Structural Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
07-Structural Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )07-Structural Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
07-Structural Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )Hossam Shafiq I
 
11-Structural Design ( Highway Engineering Dr. Sherif El-Badawy )
11-Structural Design ( Highway Engineering Dr. Sherif El-Badawy )11-Structural Design ( Highway Engineering Dr. Sherif El-Badawy )
11-Structural Design ( Highway Engineering Dr. Sherif El-Badawy )Hossam Shafiq I
 
Final year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement DesignFinal year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement DesignRiaz Zalil
 
Evaluation and strengthening of reconstructed roads excavated for utilities u...
Evaluation and strengthening of reconstructed roads excavated for utilities u...Evaluation and strengthening of reconstructed roads excavated for utilities u...
Evaluation and strengthening of reconstructed roads excavated for utilities u...IAEME Publication
 
EVALUATION AND STRENGTHENING OF RECONSTRUCTED ROADS EXCAVATED FOR UTILITIES U...
EVALUATION AND STRENGTHENING OF RECONSTRUCTED ROADS EXCAVATED FOR UTILITIES U...EVALUATION AND STRENGTHENING OF RECONSTRUCTED ROADS EXCAVATED FOR UTILITIES U...
EVALUATION AND STRENGTHENING OF RECONSTRUCTED ROADS EXCAVATED FOR UTILITIES U...IAEME Publication
 
Analysis of hpcc pavements using kenpave fea software
Analysis of hpcc pavements using kenpave fea softwareAnalysis of hpcc pavements using kenpave fea software
Analysis of hpcc pavements using kenpave fea softwareeSAT Publishing House
 

Similar to Design of a rigid pavement (jpcp & crcp) (20)

Recent Advances in Pavement Deisgn of Flexoble Papenent by IRC:37.pdf
Recent Advances in Pavement Deisgn of Flexoble Papenent by IRC:37.pdfRecent Advances in Pavement Deisgn of Flexoble Papenent by IRC:37.pdf
Recent Advances in Pavement Deisgn of Flexoble Papenent by IRC:37.pdf
 
A CFD study of Wind Tunnel Wall Interference_Md Hasan
A CFD study of Wind Tunnel Wall Interference_Md HasanA CFD study of Wind Tunnel Wall Interference_Md Hasan
A CFD study of Wind Tunnel Wall Interference_Md Hasan
 
P07011_Gupta_et_al
P07011_Gupta_et_alP07011_Gupta_et_al
P07011_Gupta_et_al
 
CFD analysis of commercial vehicle
CFD analysis of commercial vehicleCFD analysis of commercial vehicle
CFD analysis of commercial vehicle
 
IRJET- Parametric Study on Behaviour of RCC Box Culvert for Dynamic Loading
IRJET- Parametric Study on Behaviour of RCC Box Culvert for Dynamic LoadingIRJET- Parametric Study on Behaviour of RCC Box Culvert for Dynamic Loading
IRJET- Parametric Study on Behaviour of RCC Box Culvert for Dynamic Loading
 
PaveXpress: Designing Pavements for the Future
PaveXpress: Designing Pavements for the FuturePaveXpress: Designing Pavements for the Future
PaveXpress: Designing Pavements for the Future
 
Analysis of Flexible Pavement Using IIT PAVE software
Analysis of Flexible Pavement Using IIT PAVE softwareAnalysis of Flexible Pavement Using IIT PAVE software
Analysis of Flexible Pavement Using IIT PAVE software
 
Pavement eng re
Pavement eng rePavement eng re
Pavement eng re
 
Cdd mahesh dasar ijertv2 is120775
Cdd mahesh dasar ijertv2 is120775Cdd mahesh dasar ijertv2 is120775
Cdd mahesh dasar ijertv2 is120775
 
Simulations Of Unsteady Flow Around A Generic Pickup Truck Using Reynolds Ave...
Simulations Of Unsteady Flow Around A Generic Pickup Truck Using Reynolds Ave...Simulations Of Unsteady Flow Around A Generic Pickup Truck Using Reynolds Ave...
Simulations Of Unsteady Flow Around A Generic Pickup Truck Using Reynolds Ave...
 
Pavement Design Methods 2 (Flexible and Rigid).pdf
Pavement Design Methods 2 (Flexible and Rigid).pdfPavement Design Methods 2 (Flexible and Rigid).pdf
Pavement Design Methods 2 (Flexible and Rigid).pdf
 
Aashto design
Aashto designAashto design
Aashto design
 
Rehabilitation Study of NH34 Kabrai to Maudaha through the 35.00 Km Section L...
Rehabilitation Study of NH34 Kabrai to Maudaha through the 35.00 Km Section L...Rehabilitation Study of NH34 Kabrai to Maudaha through the 35.00 Km Section L...
Rehabilitation Study of NH34 Kabrai to Maudaha through the 35.00 Km Section L...
 
Graduation Project (DESIGN AND ANALYSIS OF MULTI-TOWER STRUCTURE USING ETABS).
Graduation Project (DESIGN AND ANALYSIS OF MULTI-TOWER STRUCTURE USING ETABS).Graduation Project (DESIGN AND ANALYSIS OF MULTI-TOWER STRUCTURE USING ETABS).
Graduation Project (DESIGN AND ANALYSIS OF MULTI-TOWER STRUCTURE USING ETABS).
 
07-Structural Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
07-Structural Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )07-Structural Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
07-Structural Design ( Highway and Airport Engineering Dr. Sherif El-Badawy )
 
11-Structural Design ( Highway Engineering Dr. Sherif El-Badawy )
11-Structural Design ( Highway Engineering Dr. Sherif El-Badawy )11-Structural Design ( Highway Engineering Dr. Sherif El-Badawy )
11-Structural Design ( Highway Engineering Dr. Sherif El-Badawy )
 
Final year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement DesignFinal year project ppt - The Future of Pavement Design
Final year project ppt - The Future of Pavement Design
 
Evaluation and strengthening of reconstructed roads excavated for utilities u...
Evaluation and strengthening of reconstructed roads excavated for utilities u...Evaluation and strengthening of reconstructed roads excavated for utilities u...
Evaluation and strengthening of reconstructed roads excavated for utilities u...
 
EVALUATION AND STRENGTHENING OF RECONSTRUCTED ROADS EXCAVATED FOR UTILITIES U...
EVALUATION AND STRENGTHENING OF RECONSTRUCTED ROADS EXCAVATED FOR UTILITIES U...EVALUATION AND STRENGTHENING OF RECONSTRUCTED ROADS EXCAVATED FOR UTILITIES U...
EVALUATION AND STRENGTHENING OF RECONSTRUCTED ROADS EXCAVATED FOR UTILITIES U...
 
Analysis of hpcc pavements using kenpave fea software
Analysis of hpcc pavements using kenpave fea softwareAnalysis of hpcc pavements using kenpave fea software
Analysis of hpcc pavements using kenpave fea software
 

Recently uploaded

Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network DevicesChandrakantDivate1
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxchumtiyababu
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxNadaHaitham1
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwaitjaanualu31
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxMuhammadAsimMuhammad6
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadhamedmustafa094
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 

Recently uploaded (20)

Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptx
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
kiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal loadkiln thermal load.pptx kiln tgermal load
kiln thermal load.pptx kiln tgermal load
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 

Design of a rigid pavement (jpcp & crcp)

  • 1.                  Design of a Rigid pavement                                                                                                                      Team : 1) Ahsan ullah Hussaini Syed 2) Ahmed Towfeequllah Siddiqui
  • 2.     Introduction The project involved designing of two different types of Rigid pavements using the AASHTOWare Pavement ME software. 1) JPCP (Jointed Plain Concrete Pavement) : It was designed as a three layered structure, the layer distribution being as follows: Layer 1 – PCC – 16 inch Layer 2 – NonStabilized (Crushed gravel) – 8 inch Layer 3 – Subgrade (A-1a) – Semi Infinite Jointed plain concrete pavement uses contraction joints to control cracking and uses reinforcing steel in form of dowel bars. Transverse joint spacing is selected such that temperature and moisture stresses do not produce intermediate cracking between joints. This typically results in a spacing no longer than about 6.1 m (20 ft.). 2) CRCP (CONTINUOUSLY REINFORCED CONCRETE PAVEMENTS) : It was designed as a 4 layered structure, the layer distribution being as follows: Layer 1 – PCC – 11.3 inch Layer 2 – Stabilized – 4 inch Layer 3 – NonStabilized – 8 inch Layer 4 – Subgrade – Semi infinite CRCP is concrete pavement reinforced with continuous steel bars throughout its length. Its design eliminates the need for transverse joints (other than at bridges and other structures) and keeps cracks tight, resulting in a continuous, smooth-riding surface.
  • 3.     AASHTOWARE PAVEMENT ME DESIGN USER INPUTS The Pavement ME Design program utilizes the user-defined inputs to conduct a CRCP and JPCP mechanistic analysis to predict the expected incremental distress levels based on a national calibration. As the Pavement ME Design program represents a fundamental change in design philosophies in CRCP and JPCP design, it requires much greater knowledge of design parameters affecting design including layer materials, climate, and traffic characterization. For users new to the program, the following section outlines a basic overview of the program’s format and design parameters. The Figure shows the main input screen of the Pavement ME Design program. General input categories are viewed in the left of the screen while specific input parameters are viewed and entered in the middle of the screen.   Figure 2 : Layer Structure & material properties – CRCP Figure 1: Design user inputs for CRCP & JPCP – AASHTOWare ME.
  • 4.       Figure 3 Layer structure & material properties - JPCP Traffic To characterize the volume, the total amount of truck traffic is input as average annual daily truck traffic (AADTT), including the expected lane and directional distribution factor for the facility.   Figure 4: Quarterly ADT distribution for Naples, Fl. Ref : https://www.colliergov.net/modules/showdocument.aspx?documentid=58143 The AADT of Naples, FL was used to design the JPC pavement (With Dowel Bars), likewise the AADT of Chicago, IL was used in the designing of the CRCP (Ref:  https://goo.gl/3OtCIY)
  • 5.     CLIMATE A key improvement to the CRCP design process is accounting for site-specific climate. The Pavement ME Design program models account for daily and seasonal fluctuations in temperature and moisture profiles in the CRCP and soil layer, respectively, through site- specific factors such as percent sunshine, air temperature, precipitation, wind, and water table depth. There are several hundred weather stations across North America from which the user can select the nearest one to the project site, or the user can create a “virtual weather station” by allowing the program to interpolate nearby weather data to the user’s specific project site.   Figure 5 : Ideal station can be picked to input Climate information The pavement is then analyzed for : a) IRI and Punchout in case of CRCP b) Cracking, faulting & IRI in case of JPCP. Post analysis, thickness is determined (Trial & error) for both the pavements. Figure 6-7: Climate data for both the pavements.
  • 6.     Result for JPCP As far as terminal IRI is considered, Distress reliability of 122.56 was predicted from the analysis against the targeted 172 which was well below the threshold. Similarly Joint Faulting and Transverse cracking reliability criterion were satisfied. The graphs above illustrate the achieved data for Cracking, Faulting and IRI and prediction for a period of 30 years ahead. By trial & error the thickness of the slab was found to be 16 inches.
  • 7.     Result for CRCP: Distress Type Distress @ Specified Reliability (%) Criterio n SatisfiedTarget Predicted Target Achieved Terminal IRI (in./mile) 172.00 143.15 90.00 99.29 Pass CRCP punchouts (1/mile) 10.00 3.99 90.00 99.95 Pass As far as terminal IRI is considered, Distress reliability of 143.15 was predicted from the analysis against the targeted 172 which was well below the threshold. Similarly punchouts achieved a satisfactory 99.95% reliability. The graphs above illustrate the achieved data for IRI & Punchout and prediction for a period of 30 years ahead. By trial & error the thickness of the slab was found to be 11.3 inches.
  • 8.     KENPAVE An analysis was carried out both the pavement types for Maximum stress using Kenpave. CRCP Slab thickness: 11.3 in ; Dimensions: 12 x 12 ; Reinforcement: 0.7% Nodes : X : 0, 7, 14, 26, 50, 85, 120 Y : 0, 12, 36, 54, 78, 120 MAXIMUM STRESS (SMAX) IN LAYER 1 IS -95.112 ( NODE 2 ) MAXIMUM STRESS IN X DIRECTION = 0.0 ( NODE 0 ) MINIMUM STRESS IN X DIRECTION = 34.4 ( NODE 22 ) MAXIMUM STRESS IN Y DIRECTION = -95.1 ( NODE 2 ) MINIMUM STRESS IN Y DIRECTION = 13.4 ( NODE 5) JCPC Slab thickness: 16 in ; Dimensions: 12 x 12 ; Dowel bar: Dia: 1.25 in; Joint Spacing: 17ft Nodes : X : 0, 7, 14, 26, 50, 85, 120 Y : 0, 12, 36, 54, 78, 120 MAXIMUM STRESS (SMAX) IN LAYER 1 IS -67.833 ( NODE 2 ) MAXIMUM STRESS IN X DIRECTION = 0.0 ( NODE 0 ) MINIMUM STRESS IN X DIRECTION = 24.2 ( NODE 43 ) MAXIMUM STRESS IN Y DIRECTION = -67.8 ( NODE 2 ) MINIMUM STRESS IN Y DIRECTION = 5.6 ( NODE 6 )
  • 9.     Conclusion JPCP For a period of 30 years cracking is shown to be constant and gives a possibility of the pavement life extending through 40-50 years as far as cracking is concerned. The faulting rose from 0.02 during construction to 0.09 over a period of 30 years and may only breach the threshold value after 40-45 years which again is well beyond the design life. The IRI curve shows a linear relation for 25 years and the curve begins to flatten out hence indicating an extended life than what it was being designed for. CRCP The IRI at the 30 year threshold is 143.15 (172 Max) and it keeps ascending and will breach the target value round about the 45-50 year mark which is well ahead of our target design life. The punchout starts at 2.2 and the curve ascends to about 3.99 till 15 years and henceforth remains constant till the target design life of 30 years and may breach the limit well beyond the 50 year mark.