2. Q1:
Activity Predecessor Duration Rate
Z W,X,Y 10 4
W R 14 2
R - 8 4
X R 20 8
Y R 12 4
For the 65 units Construction Project using the one unit net work it
is required to:
1) Draw LOB Chart.
2) Check project situation at 46th week.
3) What’s your recommendation if at 60th week activity Z finished in
39 unit ?
16. 2) The project situation at 46th week.
Activities R, Y AND X has been finished
Activity W finished in 49 unit
Activity Z not finished yet in any unit