SlideShare a Scribd company logo
1 of 58
UTILITY RELOCATION
ASSOCIATED WITH THE
I-69 PROJECT
Eastern
Heights
Utilities
www.wesslerengineering.com
Office located in
Bloomfield at
316 N.
Washington
Street
EASTERN
HEIGHTS
UTILITIES
www.wesslerengineering.com
Greene County
and portions of
Martin
Lawrence
Monroe
Owen
Daviess
7000 service
connections
EHU
SERVICE
AREA
Greene County
Morgan County
www.wesslerengineering.com
Connecting
Evansville
and
Indianapolis
Section 4
of the
Project
in Greene
County
I – 69
PROJECT
www.wesslerengineering.com
Section 4
shown in blue
Southwest of
Bloomington
Northeast of
Crane Naval
Base
I-69
PROJECT
MAP
www.wesslerengineering.com
OVERVIEW OF WESSLER INVOLVEMENT
 Coordination with INDOT for the I-69 project
 Water mains sizes: 2-inch to 12-inch diameter.
 19 utility conflicts were identified
 Study and planning phase
 Design phase
 Construction survey, observation, and administration
 Permitting
WATER MAIN RELOCATION PROJECTS
www.wesslerengineering.com
UTILITY RELOCATION
19 PROJECTS
www.wesslerengineering.com
SR 231, CR 200 E, CR 215 E, CR 600 S,
CR 440 E & CR 600 E
www.wesslerengineering.com
CR 360 S, PINE RD, CR 920 E, SR 45, CR 1250 E,
SR 54, CR 190 S, CARMICHAEL, CROSS COUNTRY,
SR 445, CARTER RD, CR 150 N & BREEDEN RD
www.wesslerengineering.com
Pipe
installation
WATER MAIN
RELOCATION
PROJECTS
www.wesslerengineering.com
Pipe
installation
WATER MAIN
RELOCATION
PROJECTS
www.wesslerengineering.com
Deep
Excavations
WATER MAIN
RELOCATION
PROJECTS
www.wesslerengineering.com
Deep trenching
and hilly
topography
WATER MAIN
RELOCATION
PROJECTS
www.wesslerengineering.com
Stream
Crossing
WATER MAIN
RELOCATION
PROJECTS
www.wesslerengineering.com
Trench boxes
required for
deep
excavations
WATER MAIN
RELOCATION
PROJECTS
www.wesslerengineering.com
Jack and Bore
WATER MAIN
RELOCATION
PROJECTS
www.wesslerengineering.com
Trenching
Machine
WATER MAIN
RELOCATION
PROJECTS
www.wesslerengineering.com
WATER MAIN
RELOCATION
PROJECTS
I-69
CORRIDOR
www.wesslerengineering.com
 Study and planning phase (March 2011)
 Design phase (May 2011 – April 2013)
 Permit planning (March 2011)
 First permit in hand (December 13, 2011)
 Rule 5 permit for tree clearing project
 Inspection (December 2011 – June or July 2014)
 Length of project 3 years and 3 months
PROJECT TIMELINE
www.wesslerengineering.com
PLANNING, DESIGN AND
CONSTRUCTION
www.wesslerengineering.com
 21 separate sets of construction documents,
 47,000 linear feet of water main,
 65 private utility easements,
 52 regulatory permits,
 3,700 emails filed,
 40 Wessler employees involved,
 Total Construction Cost = $14.2 M
PROJECT BY THE NUMBERS
www.wesslerengineering.com
 UTILITY (EASTERN HEIGHTS)
 Engineer - Wessler Engineering
 Contractor - Infrastructure Systems, Inc.
 INDOT
 Utility coordinator
 Designers and consultants
 Inspectors
 Contractor (Crider & Crider, Gohmann, Milestone, Fred Weber)
 OTHERS
 Utilities (Smithville, UDWI REMC, others)
 Regulators (IDEM, ACoE, DNR, County SWDC)
 Land owners
 Utility customers
PROJECT TEAM
www.wesslerengineering.com
 Develop relocation alignment
 Identify easements
 Project costs
 Replacement in kind
 Betterment
 Utility Agreement
WORK PLAN / UTILITY AGREEMENT
www.wesslerengineering.com
 Construction plans
 Survey information
 Topographic
 Boundary
 Soil borings
 Environmental reports
 Wetland delineations
 Flood modeling
 Mitigation sites
 Karst areas
INFORMATION FROM INDOT
www.wesslerengineering.com
 CONSIDERATIONS
 Pipe material (DI, HDPE,
PVC)
 Depth of excavations
 CHALLENGES
 Drastic elevation changes
 Presence of rock
 Scheduling
DESIGN
www.wesslerengineering.com
www.wesslerengineering.com
CONSTRUCTION
 CHALLENGES
Tree clearing
Multiple INDOT contractors
Trench conditions
 Deep cuts
 Rock
Grade determination
www.wesslerengineering.com
Casing Trench
CR 190S
WATER MAIN
RELOCATION
PROJECTS
www.wesslerengineering.com
Casing
Installation
SR 45/445
WATER MAIN
RELOCATION
PROJECTS
www.wesslerengineering.com
Water Main
Installation
SR 45
WATER MAIN
RELOCATION
PROJECTS
www.wesslerengineering.com
ENVIRONMENTAL
CONSIDERATIONS
AND PERMITTING
www.wesslerengineering.com
 Endangered and Threatened Species
 Waterways
 Wetlands
 Floodways and Floodplains
 Erosion Control Planning
 Wellhead Protection Areas
 Underground Karst Features
ENVIRONMENTAL CONSIDERATIONS
www.wesslerengineering.com
 GOALS and PRIORITIES
 Identify potential environmental impacts
 Avoid impacts
 Alternate layout for water main placement
 Directional drilling when possible (bedrock)
 General permits and exempted activities vs individual permits
 Minimize limits of disturbance
 Minimize adverse impacts to environmental resources
 Obtain permits for unavoidable impacts
 Mitigation planning
AVOID, MINIMIZE, MITIGATE
www.wesslerengineering.com
Bald Eagle Indiana Bat
ENDANGERED AND THREATENED SPECIES
www.wesslerengineering.com
Early coordination with the
DNR Division of Nature
Preserves (coordination
needed for IDEM 401)
Review of INDOT EIS
(Environmental Impact
Statement)
INDOT training video
Tree cutting restrictions
Indiana Bat roosting and
hibernating range
ENDANGERED
SPECIES
www.wesslerengineering.com
ETR NOTICE
www.wesslerengineering.com
TREE CLEARING
www.wesslerengineering.com
Allowable tree cutting period
3 inches DBH or greater
No cutting (April 1 – Nov. 15)
EHU prepared a separate
contract for Tree Clearing
Rule 5
No waterway impacts
Temporary soil stabilization
with wood chips
TREE
CLEARING
www.wesslerengineering.com
TREE
CLEARING
www.wesslerengineering.com
WATERWAYS
www.wesslerengineering.com
WATERWAYS
www.wesslerengineering.com
Permitted
waterway
crossing
WATERWAY
PROTECTION
www.wesslerengineering.com
35 – 40 potential waterway
crossings identified
IDEM Section 401 Water
Quality Certification (State
jurisdiction)
US Army Corps of Engineers
Section 404 of the Clean
Water Act (Federal
jurisdiction)
WATERWAY
PERMITS
www.wesslerengineering.com
WATERS OF
THE US
www.wesslerengineering.com
WETLAND AVOIDANCE
www.wesslerengineering.com
1 wetland impact
All other wetlands avoided
IDEM 401 individual permit
Army Corps 404 general
permit
WETLAND
PERMITS
www.wesslerengineering.com
SEDGE MEADOW WETLAND
www.wesslerengineering.com
FLOODWAYS AND FLOODPLAINS
www.wesslerengineering.com
Indiana Department of
Natural Resources (DNR)
Construction in a floodway
Flood Control Act IC 14-28-1
Exemption from licensing
for qualified utility line
crossings
FLOODWAYS
AND
FLOODPLAINS
www.wesslerengineering.com
EROSION CONTROL PLANNING
www.wesslerengineering.com
Rule 5 (327 IAC 15-5)
Coordination with IDEM
One permit or separate
permits
Site inspections for all
projects
Projects less than one acre
Greene County SWCD and
IDEM plan review
2 projects in Monroe County
EROSION
CONTROL
PLANNING
www.wesslerengineering.com
WELLHEAD PROTECTION
www.wesslerengineering.com
Wellhead Protection
Protection of underground
aquifers for public drinking
water supplies
EHU has 3 well fields
I-69 project is not located
within WHP 10-year times
of travel
Discussed project with WHP
Local Planning Team
WELLHEAD
PROTECTION
www.wesslerengineering.com
UNDERGROUND KARST FEATURES
www.wesslerengineering.com
INDOT Environmental
Impact Statement reviewed
for known karst features
Local knowledge from
Utility employees
None identified initially but
one area was found during
construction.
Incorporated BMPs for karst
area protection if
encountered
UNDERGROUND
KARST
FEATURES
www.wesslerengineering.com
UNDERGROUND
KARST
FEATURES
www.wesslerengineering.com
 Early planning prior to design
 Environmental Services Group on the Wessler project
team
 Identification of permitted activities early
 Separate contract for tree removal
 Knowledge of INDOT project schedule for utility relocates
 Keeping tight project schedule in mind
 EDUCATION TO CONTRACTOR
 Daily inspections of construction work (Wessler RPR)
 Bi-weekly inspections (Wessler Environmental Scientist)
SUCCESSES
www.wesslerengineering.com
www.wesslerengineering.com
Have a utility project coming up?
Let us help make it a great success!
Contact Us:
Mary Atkins, P.E.
MaryA@wesslerengineering.com
317-788-4551
Dylan Lambermont, P.E.
DylanL@wesslerengineering.com
317-788-4551

More Related Content

What's hot

Maryland Environmental Site Design Presentation
Maryland Environmental Site Design PresentationMaryland Environmental Site Design Presentation
Maryland Environmental Site Design PresentationTheodore Scott
 
Kate Barnhart Resume
Kate Barnhart ResumeKate Barnhart Resume
Kate Barnhart Resumekatebarnhart
 
Dana Farber Yawkey Center for Cancer Care wins ACEC Silver
Dana Farber Yawkey Center for Cancer Care wins ACEC SilverDana Farber Yawkey Center for Cancer Care wins ACEC Silver
Dana Farber Yawkey Center for Cancer Care wins ACEC SilverWilliam Wieners
 
Geology 422 B
Geology 422 BGeology 422 B
Geology 422 BKenesei
 
2 site and temporary of works r0riginal (stu.ed)
2 site and temporary of works r0riginal (stu.ed)2 site and temporary of works r0riginal (stu.ed)
2 site and temporary of works r0riginal (stu.ed)Yohan Mudhoo
 
Ledgerwood_Dean, CEG, PG___
Ledgerwood_Dean, CEG, PG___Ledgerwood_Dean, CEG, PG___
Ledgerwood_Dean, CEG, PG___Dean Ledgerwood
 

What's hot (6)

Maryland Environmental Site Design Presentation
Maryland Environmental Site Design PresentationMaryland Environmental Site Design Presentation
Maryland Environmental Site Design Presentation
 
Kate Barnhart Resume
Kate Barnhart ResumeKate Barnhart Resume
Kate Barnhart Resume
 
Dana Farber Yawkey Center for Cancer Care wins ACEC Silver
Dana Farber Yawkey Center for Cancer Care wins ACEC SilverDana Farber Yawkey Center for Cancer Care wins ACEC Silver
Dana Farber Yawkey Center for Cancer Care wins ACEC Silver
 
Geology 422 B
Geology 422 BGeology 422 B
Geology 422 B
 
2 site and temporary of works r0riginal (stu.ed)
2 site and temporary of works r0riginal (stu.ed)2 site and temporary of works r0riginal (stu.ed)
2 site and temporary of works r0riginal (stu.ed)
 
Ledgerwood_Dean, CEG, PG___
Ledgerwood_Dean, CEG, PG___Ledgerwood_Dean, CEG, PG___
Ledgerwood_Dean, CEG, PG___
 

Similar to EHU I-69 Utility Project

IRJET- Predicting Piping Erosion Susceptibility by Statistical and Artificial...
IRJET- Predicting Piping Erosion Susceptibility by Statistical and Artificial...IRJET- Predicting Piping Erosion Susceptibility by Statistical and Artificial...
IRJET- Predicting Piping Erosion Susceptibility by Statistical and Artificial...IRJET Journal
 
ProjectExperience_BJU.pdf
ProjectExperience_BJU.pdfProjectExperience_BJU.pdf
ProjectExperience_BJU.pdfhumblelarry
 
2008 Engineering Excellence Awards
2008 Engineering Excellence Awards 2008 Engineering Excellence Awards
2008 Engineering Excellence Awards ACECSDES
 
Civil Engineering
Civil EngineeringCivil Engineering
Civil Engineeringkrishnamuj
 
Stormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationStormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationFairfax County
 
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...Fairfax County
 
Kansas CIty's Green Solutions Pilot Project - Technical Approaches, Emerging ...
Kansas CIty's Green Solutions Pilot Project - Technical Approaches, Emerging ...Kansas CIty's Green Solutions Pilot Project - Technical Approaches, Emerging ...
Kansas CIty's Green Solutions Pilot Project - Technical Approaches, Emerging ...Jessi Veach
 
Woodrock retrofit 11-13-14
Woodrock retrofit 11-13-14Woodrock retrofit 11-13-14
Woodrock retrofit 11-13-14MCDEP
 
Vesper St. Shared Use Path
Vesper St. Shared Use PathVesper St. Shared Use Path
Vesper St. Shared Use PathFairfax County
 
LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1Theodore McNeal
 
Hydrology and hydraulics for design design
Hydrology and hydraulics for design designHydrology and hydraulics for design design
Hydrology and hydraulics for design designavirup naskar
 
(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...
(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...
(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...Michal Krzeminski
 
Contino Stephen Resume LinkedIn
Contino Stephen Resume LinkedInContino Stephen Resume LinkedIn
Contino Stephen Resume LinkedInStephen Contino
 
Section 404 Clean Water Act Overview Riparian Workshop
Section 404 Clean Water Act Overview Riparian WorkshopSection 404 Clean Water Act Overview Riparian Workshop
Section 404 Clean Water Act Overview Riparian Workshopddmddn
 
Resume JW ENG City 01-12
Resume JW ENG City 01-12Resume JW ENG City 01-12
Resume JW ENG City 01-12Jerry Williams
 
Question 4 (5 pts) Timber elements will be used as floor joist in the.pdf
Question 4 (5 pts) Timber elements will be used as floor joist in the.pdfQuestion 4 (5 pts) Timber elements will be used as floor joist in the.pdf
Question 4 (5 pts) Timber elements will be used as floor joist in the.pdfaroramobiles1
 

Similar to EHU I-69 Utility Project (20)

IRJET- Predicting Piping Erosion Susceptibility by Statistical and Artificial...
IRJET- Predicting Piping Erosion Susceptibility by Statistical and Artificial...IRJET- Predicting Piping Erosion Susceptibility by Statistical and Artificial...
IRJET- Predicting Piping Erosion Susceptibility by Statistical and Artificial...
 
ProjectExperience_BJU.pdf
ProjectExperience_BJU.pdfProjectExperience_BJU.pdf
ProjectExperience_BJU.pdf
 
CLARK PE RESUME
CLARK PE RESUMECLARK PE RESUME
CLARK PE RESUME
 
2008 Engineering Excellence Awards
2008 Engineering Excellence Awards 2008 Engineering Excellence Awards
2008 Engineering Excellence Awards
 
Civil Engineering
Civil EngineeringCivil Engineering
Civil Engineering
 
Stormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationStormwater Wastewater Consolidation
Stormwater Wastewater Consolidation
 
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
 
Kansas CIty's Green Solutions Pilot Project - Technical Approaches, Emerging ...
Kansas CIty's Green Solutions Pilot Project - Technical Approaches, Emerging ...Kansas CIty's Green Solutions Pilot Project - Technical Approaches, Emerging ...
Kansas CIty's Green Solutions Pilot Project - Technical Approaches, Emerging ...
 
Metz Lateral Conservation Project
Metz Lateral Conservation ProjectMetz Lateral Conservation Project
Metz Lateral Conservation Project
 
Woodrock retrofit 11-13-14
Woodrock retrofit 11-13-14Woodrock retrofit 11-13-14
Woodrock retrofit 11-13-14
 
RYAN STODDARD
RYAN STODDARDRYAN STODDARD
RYAN STODDARD
 
Vesper St. Shared Use Path
Vesper St. Shared Use PathVesper St. Shared Use Path
Vesper St. Shared Use Path
 
LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1LMPP Final Presentation_FINAL1
LMPP Final Presentation_FINAL1
 
Hydrology and hydraulics for design design
Hydrology and hydraulics for design designHydrology and hydraulics for design design
Hydrology and hydraulics for design design
 
(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...
(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...
(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...
 
Contino Stephen Resume LinkedIn
Contino Stephen Resume LinkedInContino Stephen Resume LinkedIn
Contino Stephen Resume LinkedIn
 
RESUME JULY 2016
RESUME JULY 2016RESUME JULY 2016
RESUME JULY 2016
 
Section 404 Clean Water Act Overview Riparian Workshop
Section 404 Clean Water Act Overview Riparian WorkshopSection 404 Clean Water Act Overview Riparian Workshop
Section 404 Clean Water Act Overview Riparian Workshop
 
Resume JW ENG City 01-12
Resume JW ENG City 01-12Resume JW ENG City 01-12
Resume JW ENG City 01-12
 
Question 4 (5 pts) Timber elements will be used as floor joist in the.pdf
Question 4 (5 pts) Timber elements will be used as floor joist in the.pdfQuestion 4 (5 pts) Timber elements will be used as floor joist in the.pdf
Question 4 (5 pts) Timber elements will be used as floor joist in the.pdf
 

Recently uploaded

Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayEpec Engineered Technologies
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxSCMS School of Architecture
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesMayuraD1
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiessarkmank1
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxmaisarahman1
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Servicemeghakumariji156
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersMairaAshraf6
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptxJIT KUMAR GUPTA
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsvanyagupta248
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdfAldoGarca30
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 

Recently uploaded (20)

Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptxHOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
HOA1&2 - Module 3 - PREHISTORCI ARCHITECTURE OF KERALA.pptx
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 

EHU I-69 Utility Project

Editor's Notes

  1. All of Greene county and then portions of the surrounding Counties (Martin, Lawrence, Monroe and Owen)