Ce diaporama a bien été signalé.
Le téléchargement de votre SlideShare est en cours. ×

Feasibility of Solar Project with Open Access in Maharashtra

Publicité
Publicité
Publicité
Publicité
Publicité
Publicité
Publicité
Publicité
Publicité
Publicité
Publicité
Publicité

Consultez-les par la suite

1 sur 15 Publicité

Feasibility of Solar Project with Open Access in Maharashtra

Télécharger pour lire hors ligne

The presentation throws light on the commercial aspects of developing a solar project in Maharashtra with a view to supply power to a third party through open access.

Specifically, it probes into the spectrum of open access charges that are applicable while the generated power traverses through the state transmission and local distribution grid, starting from the plant end to the consumer end.

The presentation throws light on the commercial aspects of developing a solar project in Maharashtra with a view to supply power to a third party through open access.

Specifically, it probes into the spectrum of open access charges that are applicable while the generated power traverses through the state transmission and local distribution grid, starting from the plant end to the consumer end.

Publicité
Publicité

Plus De Contenu Connexe

Diaporamas pour vous (20)

Similaire à Feasibility of Solar Project with Open Access in Maharashtra (20)

Publicité

Plus par Gensol Engineering Limited (20)

Plus récents (20)

Publicité

Feasibility of Solar Project with Open Access in Maharashtra

  1. 1. Solar Power Purchase Services Gensol Engineering Pvt Ltd
  2. 2. The Document Feasibility of a Solar PV Project for Third Party Sale in Maharashtra
  3. 3. Open Access in Maharashtra
  4. 4. Enabling Policy in Maharashtra Maharashtra Electricity Regulatory Commission (Distribution Open Access) Regulations, 2014. 3.1 Subject to the provisions of these Regulations, a consumer having contract demand of 1 MW and above and where the minimum power to be made available for Open Access at any time is 1 MW and above, shall be eligible for seeking Open Access to the distribution system of such Distribution Licensee for obtaining supply of electricity from a Generating Company or Captive Power Plant or from a Licensee other than such Distribution Licensee or through the Power Exchange : Provided that the necessary conditionality mentioned in Regulation 3.1 about minimum power to be made available for Open Access at any time is 1 MW and above, for being eligible for seeking Open Access shall not be applicable for Open Access getting supply from a Renewable Energy generating plant identified as ‘Non firm power’ under MERC (Terms and conditions for determination of RE Tariff) Regulations, 2010, as amended from time to time
  5. 5. Consumer Categories and Tariffs Consumer Category Tariff (Rs./kWh ) Source HT II - Commercial Express Feeder 11.40 ANNEXURE II Revenue from revised Tariffs effective from 1 April, 2017 http://www.mercindia.org.in/pdf/Order%2058%2042/Order- 48%20of%202016-03112016.pdf HT II - Commercial Non-express Feeder 11.40 HT I - (Industrial Express Feeder) 7.07 HT I - (Industrial Non-express Feeder) 7.07
  6. 6. Calculation of Open Access Charges: HT II - Commercial Non-Express Feeder Units Notations Charges/losses kWh Price @ Generator Bus Rs/kWh A 5.00 Consumer category HT II - Commercial Non-Express Feeder Select Voltage Level kV 33 Group Captive/third party Thiry party Energy injected into transmission system kWh B 1,600,000 Transmission Charge Rs/kWh C 0.71 Transmission Losses % D 3.89% 62240 Energy injected into distribution system kWh E 1,537,760 Wheeling charges Rs/kWh F 0.09 Wheeling losses % G 6% 92266 Cross subsidy surcharge Rs/kWh CSS 0.68 Additional surcharge Rs/kWh AS 1.11 Units Injected at Buyer's Bus kWh H 1,445,494 Open access charges Rs / kWh 3.85
  7. 7. Calculation of Open Access Charges: HT II - Commercial Express Feeder Units Notations Charges/losses kWh Price @ Generator Bus Rs/kWh A 5.00 Consumer category HT II - Commercial Express Feeder Select Voltage Level kV 33 Group Captive/third party Thiry party Energy injected into transmission system kWh B 1,600,000 Transmission Charge Rs/kWh C 0.71 Transmission Losses % D 3.89% 62240 Energy injected into distribution system kWh E 1,537,760 Wheeling charges Rs/kWh F 0.09 Wheeling losses % G 6% 92266 Cross subsidy surcharge Rs/kWh CSS 0.71 Additional surcharge Rs/kWh AS 1.11 Units Injected at Buyer's Bus kWh H 1,445,494 Open access charges Rs / kWh 3.88
  8. 8. Calculation of Open Access Charges: HT II - Industrial Non Express Feeder Units Notations Charges/losses kWh Price @ Generator Bus Rs/kWh A 5.00 Consumer category HT II - Industrial Non Express Feeder Select Voltage Level kV 33 Group Captive/third party Thiry party Energy injected into transmission system kWh B 1,600,000 Transmission Charge Rs/kWh C 0.71 Transmission Losses % D 3.89% 62240 Energy injected into distribution system kWh E 1,537,760 Wheeling charges Rs/kWh F 0.09 Wheeling losses % G 6% 92266 Cross subsidy surcharge Rs/kWh CSS 0.44 Additional surcharge Rs/kWh AS 1.11 Units Injected at Buyer's Bus kWh H 1,445,494 Open access charges Rs / kWh 3.60
  9. 9. Calculation of Open Access Charges: HT II - Industrial Express Feeder Units Notations Charges/losses kWh Price @ Generator Bus Rs/kWh A 5.00 Consumer category HT II - Industrial Express Feeder Select Voltage Level kV 33 Group Captive/third party Thiry party Energy injected into transmission system kWh B 1,600,000 Transmission Charge Rs/kWh C 0.71 Transmission Losses % D 3.89% 62240 Energy injected into distribution system kWh E 1,537,760 Wheeling charges Rs/kWh F 0.09 Wheeling losses % G 6% 92266 Cross subsidy surcharge Rs/kWh CSS 0.48 Additional surcharge Rs/kWh AS 1.11 Units Injected at Buyer's Bus kWh H 1,445,494 Open access charges Rs / kWh 3.64
  10. 10. Financial Feasibility of Solar PV Projects
  11. 11. Project Economics of a 10 MW Project DASHBOARD AD Benefet Availed NO Project Execution Mode PMC Area required per MW (acres) 4.5 Land cost per acre 0.045 Land Cost (Rs in Cr) 2.025 Permitting and commissioning costs (Rs in Cr) 0.02 EPC Cost per MWp (Rs in Cr) 3.8 EPC Cost (Rs in Cr) 38.20 USD/INR 66 AC Capacity (MW) 10 DC Overloading 20.0% DC Capacity (MW) 12.00 Generation (MWh) 21000 Total transmission losses 0.10% Generation net of transmission losses (MWh) 20979 PLF 23.97% Interest rate 11.25% Refinancing after 1 year of COD No Debt 70% Equity 30% Tariff 4.5000 Equity IRR 18.05% PIRR 13.28%
  12. 12. Possible Solar Tariffs for Consumer Categories Consumer Category Grid Tariff (Rs./kWh) Open Access Charges (Rs./kWh) Ceiling of Possible Solar Tariff (Rs./kWh) HT II - Commercial Express Feeder 11.4 3.88 7.52 HT II - Commercial Non-express Feeder 11.4 3.85 7.55 HT I - (Industrial Express Feeder) 7.07 3.64 3.43 HT I - (Industrial Non-express Feeder) 7.07 3.60 3.47
  13. 13. Savings for Consumer Categories at Rs 4.5/kWh of Solar Tariff Consumer Category Final Landed Tariff (Rs./kWh) a = b + c Open Access Charges (Rs./kWh) b Solar Tariff (Rs./kWh) c Cumulative Savings for 25 years (Rs in Cr) NPV of Savings @10% discount rate (Rs in Cr) HT II - Commercial Express Feeder 8.38 3.88 4.5 459.93 119.13 HT II - Commercial Non- express Feeder 8.35 3.85 4.5 462.08 119.83 HT I - (Industrial Express Feeder) 8.14 3.64 4.5 N.A N.A HT I - (Industrial Non- express Feeder) 8.10 3.60 4.5 N.A N.A
  14. 14. Cross Subsidy Surcharges EHV Consumers HT Consumers HT Consumers (66kV & above) (33kV) (22/11 kV) Industry HT I - (Industrial Express Feeder) 1.9 1.9 1.9 HT I - (Industrial Non-express Feeder) 1.77 1.77 1.77 Commercial HT II - Commercial Express Feeder 2.85 2.85 2.85 HT II - Commercial Non-express Feeder 2.71 2.71 2.71 Table 8-36: http://www.mercindia.org.in/pdf/Order%2058%2042/Order-48%20of%202016-03112016.pdf
  15. 15. Sources Transmission Charge Table 8-35: http://www.mercindia.org.in/pdf/Order%2058%2042/Order- 48%20of%202016-03112016.pdf Transmission Losses Table 3-10: http://www.mercindia.org.in/pdf/Order%2058%2042/Order- 48%20of%202016-03112016.pdf Wheeling charges Table 8-27/8-14: http://www.mercindia.org.in/pdf/Order%2058%2042/Order- 48%20of%202016-03112016.pdfWheeling losses Cross subsidy surcharge CSS -->Table 8-36: http://www.mercindia.org.in/pdf/Order%2058%2042/Order- 48%20of%202016-03112016.pdf CSS for renewable energy is 25% of applicable to conventional sources: http://www.mercindia.org.in/pdf/Order%2058%2042/DOA%20Regul ations%202015%20-16092015.pdf Additional surcharge Table 8-45: http://www.mercindia.org.in/pdf/Order%2058%2042/Order- 48%20of%202016-03112016.pdf

×