SlideShare a Scribd company logo
1 of 2
Download to read offline
ID Task Name Duration Start Finish
1 Submit tender 1 d 14/01/13 14/01/13
2 Design finalization & construction dwg issue 7 d 14/01/13 23/01/13
3 Tender assessment 6 d 15/01/13 22/01/13
4 Building permit 10 d 16/01/13 31/01/13
5 Tender award 1 d 22/01/13 22/01/13
6 Finalize key trades 17 d 23/01/13 19/02/13
7 PIC issued 1 d 13/03/13 14/03/13
8 Off-site works 61 d 1/02/13 14/05/13
9 Structural steel - shop dwg preparation 21 d 1/02/13 5/03/13
12 DB - shop dwg preparation 19 d 26/02/13 26/03/13
10 Structural steel - shop dwg approval 5 d 6/03/13 14/03/13
11 Structural steel - manufacture 22 d 15/03/13 23/04/13
13 DB - shop dwg approval 4 d 27/03/13 9/04/13
14 DB - manufacture 23 d 10/04/13 14/05/13
15 Site Activities 140 d 20/02/13 2/10/13
16 Establishment 5 d 20/02/13 27/02/13
17 Tree / site clearing 5 d 21/02/13 28/02/13
18 Site Survey & setout 2 d 22/02/13 26/02/13
19 Building construction 136 d 27/02/13 2/10/13
20 Earthworks prep. to building footprint 9 d 27/02/13 13/03/13
21 Services rough in - below slab 7 d 14/03/13 22/03/13
22 Slab 1 (East slab) 14 d 19/03/13 15/04/13
23 Detailed excavation 5 d 19/03/13 25/03/13
25 Lift pit base - prep, tank & pour 4 d 21/03/13 26/03/13
24 Blinding 1 d 26/03/13 26/03/13
26 Lift pit sides - prep & pour 4 d 27/03/13 9/04/13
28 Prepare / form (not lift) 7 d 27/03/13 12/04/13
27 Lift pit walls - tank & backfill 2 d 10/04/13 11/04/13
29 Concrete pour 1 d 15/04/13 15/04/13
30 Slab 2 (Central slab) 15 d 28/03/13 26/04/13
31 Detailed excavation 5 d 28/03/13 12/04/13
32 Blinding 1 d 12/04/13 15/04/13
33 Prepare / form 7 d 16/04/13 24/04/13
34 Concrete pour 1 d 26/04/13 26/04/13
40 Structural steel - install east slab columns 4 d 18/04/13 23/04/13
35 Slab 3 (West slab) 9 d 22/04/13 3/05/13
36 Detailed excavation 2 d 22/04/13 24/04/13
37 Blinding 1 d 24/04/13 26/04/13
38 Prepare / form 4 d 29/04/13 2/05/13
39 Concrete pour 1 d 3/05/13 3/05/13
43 Framing - east slab walls 13 d 24/04/13 14/05/13
41 Structural steel - install Central slab zone 8 d 29/04/13 9/05/13
42 Blockwork - structural blade wall 3 d 7/05/13 9/05/13
44 Roof purlins - upper level 4 d 10/05/13 15/05/13
46 Framing - west slab walls 7 d 10/05/13 20/05/13
47 Timber roof trusses / LVL's (east slab) 5 d 15/05/13 21/05/13
48 Timber roof trusses / LVL's (west slab) 3 d 21/05/13 23/05/13
60 Roller shutter / doors - site measure agreed 1 d 21/05/13 21/05/13
45 Roofing - line / sheet roofs 11 d 22/05/13 6/06/13
52 Services rough in (walls / ceiling space) 17 d 22/05/13 18/06/13
49 Window / door frames install 9 d 23/05/13 5/06/13
50 Wall linings - external (Brickwork) 9 d 29/05/13 12/06/13
77 Lift pit infill floor 4 d 30/05/13 4/06/13
51 Wall linings - external (metal cladding) 13 d 6/06/13 27/06/13
53 Services - mech duct / pipe rough-in 8 d 17/06/13 27/06/13
55 Wall linings - internal (PB/villaboard) 16 d 19/06/13 12/07/13
61 Roller shutters - install 5 d 28/06/13 4/07/13
62 Roller doors - install 5 d 28/06/13 4/07/13
78 Wall linings - external (render) 4 d 28/06/13 3/07/13
64 Services - elec DB install 6 d 2/07/13 10/07/13
56 Ceilings - frame & line 15 d 15/07/13 6/08/13
57 2nd. Fix (doors / skirtings) 12 d 15/07/13 31/07/13
59 Paint - interior 25 d 31/07/13 5/09/13
67 Floor finishes - screeds & tanking 4 d 2/08/13 8/08/13
63 Services - mech fit off 9 d 8/08/13 21/08/13
Submit tender
Design finalization & construction dwg issue
Tender assessment
Building permit
Tender award
Finalize key trades
PIC issued
Off-site works
Structural steel - shop dwg preparation
DB - shop dwg preparation
Structural steel - shop dwg approval
Structural steel - manufacture
DB - shop dwg approval
DB - manufacture
Site Activities
Establishment
Tree / site clearing
Site Survey & setout
Building construction
Earthworks prep. to building footprint
Services rough in - below slab
Detailed excavation
Lift pit base - prep, tank & pour
Blinding
Lift pit sides - prep & pour
Prepare / form (not lift)
Lift pit walls - tank & backfill
Concrete pour
Detailed excavation
Blinding
Prepare / form
Concrete pour
Structural steel - install east slab columns
Detailed excavation
Blinding
Prepare / form
Concrete pour
Framing - east slab walls
Structural steel - install Central slab zone
Blockwork - structural blade wall
Roof purlins - upper level
Framing - west slab walls
Timber roof trusses / LVL's (east slab)
Timber roof trusses / LVL's (west slab)
Roller shutter / doors - site measure agreed
Roofing - line / sheet roofs
Services rough in (walls / ceiling space)
Window / door frames install
Wall linings - external (Brickwork)
Lift pit infill floor
Wall linings - external (metal cladding)
Services - mech duct / pipe rough-in
Wall linings - internal (PB/villaboard)
Roller shutters - install
Roller doors - install
Wall linings - external (render)
Services - elec DB install
Ceilings - frame & line
2nd. Fix (doors / skirtings)
Paint - interior
Floor finishes - screeds & tanking
Services - mech fit off
7/1 4/1 1/1 7/01 4/0 1/0 8/0 4/02 1/0 8/0 5/0 4/03 1/0 8/0 5/0 1/04 8/04 5/0 2/0 9/0 6/05 3/0 0/0 7/0 3/06 0/0 7/0 4/0 1/07 8/07 5/0 2/0 9/0 5/08 2/0 9/0 6/0 2/09 9/09 6/0 3/0 0/0 7/10 4/1 1/1 8/1 4/11 1/1 8
Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Jul '13 Aug '13 Sep '13 Oct '13 Nov '13
Sample Construction Programme Issue: A
Print date: 10/01/13 Project: sample
Construction Programme
Page 1 of 2
ID Task Name Duration Start Finish
65 Services - elec / comms fit off 15 d 8/08/13 29/08/13
72 Joinery install - wet areas 5 d 9/08/13 15/08/13
54 Wall linings - internal (feature) 9 d 14/08/13 28/08/13
58 Paint - exterior elements 19 d 16/08/13 13/09/13
68 Floor finishes - vinyl 8 d 16/08/13 28/08/13
70 Floor finishes - epoxy 8 d 28/08/13 6/09/13
71 Wall vinyl 12 d 29/08/13 16/09/13
69 Floor finishes - carpet 6 d 11/09/13 18/09/13
66 Services - hyd fit off 8 d 12/09/13 23/09/13
73 Joinery install - balance areas 7 d 19/09/13 27/09/13
74 Toilet / shower partitions 3 d 20/09/13 24/09/13
75 Services - commission 6 d 24/09/13 2/10/13
76 Accessories 5 d 25/09/13 2/10/13
79 Clean & hand over 3 d 27/09/13 2/10/13
80 External civil works 119 d 25/03/13 1/10/13
83 Sewer - site reticulation works 6 d 25/03/13 9/04/13
84 Sewer - rising main works 13 d 10/04/13 29/04/13
85 Sewer - pump station installation 6 d 30/04/13 8/05/13
87 Water / fire service - street tapping 9 d 1/05/13 15/05/13
82 Stormwater - site reticulation works 19 d 7/05/13 3/06/13
86 Water / fire service - site reticulation works 9 d 15/05/13 28/05/13
89 Elec / comms - site reticulation works 14 d 22/05/13 13/06/13
88 Non-potable water service - site reticulation works 6 d 29/05/13 5/06/13
81 Civil earthworks 8 d 14/06/13 26/06/13
97 Retaining walls 9 d 19/06/13 2/07/13
90 Concrete pavement - prep subgrade 13 d 27/06/13 16/07/13
96 Shed slab - prep & install 18 d 27/06/13 24/07/13
91 Concrete pavement - kerb & channel 7 d 16/07/13 25/07/13
92 Concrete pavement - prep & place concrete 12 d 25/07/13 12/08/13
93 Cross-over works 6 d 13/08/13 21/08/13
95 Perimeter fencing & gates 20 d 13/08/13 11/09/13
98 Water tanks - install & commission 6 d 13/08/13 21/08/13
100 Landscape - soft landscaping works 19 d 28/08/13 24/09/13
99 Landscape accessories 7 d 18/09/13 26/09/13
94 Carpark - line marking 4 d 25/09/13 1/10/13
101 De-establish site 5 d 25/09/13 2/10/13
102 Project Hand Over 1 d 2/10/13 2/10/13
Services - elec / comms fit off
Joinery install - wet areas
Wall linings - internal (feature)
Paint - exterior elements
Floor finishes - vinyl
Floor finishes - epoxy
Wall vinyl
Floor finishes - carpet
Services - hyd fit off
Joinery install - balance areas
Toilet / shower partitions
Services - commission
Accessories
Clean & hand over
External civil works
Sewer - site reticulation works
Sewer - rising main works
Sewer - pump station installation
Water / fire service - street tapping
Stormwater - site reticulation works
Water / fire service - site reticulation works
Elec / comms - site reticulation works
Non-potable water service - site reticulation works
Civil earthworks
Retaining walls
Concrete pavement - prep subgrade
Shed slab - prep & install
Concrete pavement - kerb & channel
Concrete pavement - prep & place concrete
Cross-over works
Perimeter fencing & gates
Water tanks - install & commission
Landscape - soft landscaping works
Landscape accessories
Carpark - line marking
De-establish site
Project Hand Over
7/1 4/1 1/1 7/01 4/0 1/0 8/0 4/02 1/0 8/0 5/0 4/03 1/0 8/0 5/0 1/04 8/04 5/0 2/0 9/0 6/05 3/0 0/0 7/0 3/06 0/0 7/0 4/0 1/07 8/07 5/0 2/0 9/0 5/08 2/0 9/0 6/0 2/09 9/09 6/0 3/0 0/0 7/10 4/1 1/1 8/1 4/11 1/1 8
Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Jul '13 Aug '13 Sep '13 Oct '13 Nov '13
Sample Construction Programme Issue: A
Print date: 10/01/13 Project: sample
Construction Programme
Page 2 of 2

More Related Content

Similar to Sample-Construction-Programme.pdf

Spindrift-cinematique-traduit
Spindrift-cinematique-traduitSpindrift-cinematique-traduit
Spindrift-cinematique-traduitEmilie Guichard
ย 
Masters s
Masters sMasters s
Masters sMike Darwich
ย 
Microsoft Project Network Diagram
Microsoft Project Network DiagramMicrosoft Project Network Diagram
Microsoft Project Network DiagramMike Deskin
ย 
CONSTRUCTION PRESENTATION
CONSTRUCTION PRESENTATIONCONSTRUCTION PRESENTATION
CONSTRUCTION PRESENTATIONcyberyogi07
ย 
Document 1
Document 1Document 1
Document 1Chic Dickson
ย 
Shaft Construction
Shaft ConstructionShaft Construction
Shaft ConstructionJacob Groezinger
ย 
Shaft Construction
Shaft ConstructionShaft Construction
Shaft ConstructionJacob Groezinger
ย 
- ANDALUS HOUSE No 441
- ANDALUS HOUSE No 441- ANDALUS HOUSE No 441
- ANDALUS HOUSE No 441Mourad Iskandar
ย 
Royal Museum Alor Setar
Royal Museum Alor SetarRoyal Museum Alor Setar
Royal Museum Alor Setarshacjhow
ย 
Measured drawings
Measured drawingsMeasured drawings
Measured drawingsjiuaN59
ย 
ICI FINAL REPORT PDF
ICI FINAL REPORT PDFICI FINAL REPORT PDF
ICI FINAL REPORT PDFClement Seong
ย 
Building Technology 2
Building Technology 2Building Technology 2
Building Technology 2nadiacbass
ย 
FQUP PPT.pptx
FQUP PPT.pptxFQUP PPT.pptx
FQUP PPT.pptxSudiptaKolay2
ย 
=03 - Zakretanje Odlozne Trake.pdf
=03 - Zakretanje Odlozne Trake.pdf=03 - Zakretanje Odlozne Trake.pdf
=03 - Zakretanje Odlozne Trake.pdfssuser41d5bf
ย 
EMBASSY GARDENS FOH CONSTRUCTION PROGRAMME REV E
EMBASSY GARDENS FOH CONSTRUCTION PROGRAMME REV E EMBASSY GARDENS FOH CONSTRUCTION PROGRAMME REV E
EMBASSY GARDENS FOH CONSTRUCTION PROGRAMME REV E Dele Bankole
ย 
Bill ure cv 31 08-16
Bill ure cv 31 08-16Bill ure cv 31 08-16
Bill ure cv 31 08-16bill ure
ย 

Similar to Sample-Construction-Programme.pdf (20)

Spindrift-cinematique-traduit
Spindrift-cinematique-traduitSpindrift-cinematique-traduit
Spindrift-cinematique-traduit
ย 
Masters s
Masters sMasters s
Masters s
ย 
Microsoft Project Network Diagram
Microsoft Project Network DiagramMicrosoft Project Network Diagram
Microsoft Project Network Diagram
ย 
CONSTRUCTION PRESENTATION
CONSTRUCTION PRESENTATIONCONSTRUCTION PRESENTATION
CONSTRUCTION PRESENTATION
ย 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
ย 
Document 1
Document 1Document 1
Document 1
ย 
Shaft Construction
Shaft ConstructionShaft Construction
Shaft Construction
ย 
Shaft Construction
Shaft ConstructionShaft Construction
Shaft Construction
ย 
- ANDALUS HOUSE No 441
- ANDALUS HOUSE No 441- ANDALUS HOUSE No 441
- ANDALUS HOUSE No 441
ย 
Royal Museum Alor Setar
Royal Museum Alor SetarRoyal Museum Alor Setar
Royal Museum Alor Setar
ย 
Measured drawings
Measured drawingsMeasured drawings
Measured drawings
ย 
ICI FINAL REPORT PDF
ICI FINAL REPORT PDFICI FINAL REPORT PDF
ICI FINAL REPORT PDF
ย 
Building Technology 2
Building Technology 2Building Technology 2
Building Technology 2
ย 
FQUP PPT.pptx
FQUP PPT.pptxFQUP PPT.pptx
FQUP PPT.pptx
ย 
=03 - Zakretanje Odlozne Trake.pdf
=03 - Zakretanje Odlozne Trake.pdf=03 - Zakretanje Odlozne Trake.pdf
=03 - Zakretanje Odlozne Trake.pdf
ย 
kuku.pptx
kuku.pptxkuku.pptx
kuku.pptx
ย 
Munger ganga bridge
Munger ganga bridgeMunger ganga bridge
Munger ganga bridge
ย 
EMBASSY GARDENS FOH CONSTRUCTION PROGRAMME REV E
EMBASSY GARDENS FOH CONSTRUCTION PROGRAMME REV E EMBASSY GARDENS FOH CONSTRUCTION PROGRAMME REV E
EMBASSY GARDENS FOH CONSTRUCTION PROGRAMME REV E
ย 
Bill ure cv 31 08-16
Bill ure cv 31 08-16Bill ure cv 31 08-16
Bill ure cv 31 08-16
ย 
SECTIONAL DIAGRAM
SECTIONAL DIAGRAMSECTIONAL DIAGRAM
SECTIONAL DIAGRAM
ย 

Recently uploaded

BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
ย 
Call Girls In Bangalore โ˜Ž 7737669865 ๐Ÿฅต Book Your One night Stand
Call Girls In Bangalore โ˜Ž 7737669865 ๐Ÿฅต Book Your One night StandCall Girls In Bangalore โ˜Ž 7737669865 ๐Ÿฅต Book Your One night Stand
Call Girls In Bangalore โ˜Ž 7737669865 ๐Ÿฅต Book Your One night Standamitlee9823
ย 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
ย 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
ย 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
ย 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
ย 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
ย 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
ย 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
ย 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
ย 
Top Rated Pune Call Girls Budhwar Peth โŸŸ 6297143586 โŸŸ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth โŸŸ 6297143586 โŸŸ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth โŸŸ 6297143586 โŸŸ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth โŸŸ 6297143586 โŸŸ Call Me For Genuine Se...Call Girls in Nagpur High Profile
ย 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
ย 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
ย 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
ย 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7Call Girls in Nagpur High Profile Call Girls
ย 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
ย 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
ย 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
ย 
Call Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
Call Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort ServiceCall Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
Call Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service9953056974 Low Rate Call Girls In Saket, Delhi NCR
ย 

Recently uploaded (20)

BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
ย 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
ย 
Call Girls In Bangalore โ˜Ž 7737669865 ๐Ÿฅต Book Your One night Stand
Call Girls In Bangalore โ˜Ž 7737669865 ๐Ÿฅต Book Your One night StandCall Girls In Bangalore โ˜Ž 7737669865 ๐Ÿฅต Book Your One night Stand
Call Girls In Bangalore โ˜Ž 7737669865 ๐Ÿฅต Book Your One night Stand
ย 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
ย 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
ย 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
ย 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
ย 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
ย 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
ย 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
ย 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
ย 
Top Rated Pune Call Girls Budhwar Peth โŸŸ 6297143586 โŸŸ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth โŸŸ 6297143586 โŸŸ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth โŸŸ 6297143586 โŸŸ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth โŸŸ 6297143586 โŸŸ Call Me For Genuine Se...
ย 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
ย 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
ย 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
ย 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
ย 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
ย 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ย 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
ย 
Call Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
Call Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort ServiceCall Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
Call Girls in Ramesh Nagar Delhi ๐Ÿ’ฏ Call Us ๐Ÿ”9953056974 ๐Ÿ” Escort Service
ย 

Sample-Construction-Programme.pdf

  • 1. ID Task Name Duration Start Finish 1 Submit tender 1 d 14/01/13 14/01/13 2 Design finalization & construction dwg issue 7 d 14/01/13 23/01/13 3 Tender assessment 6 d 15/01/13 22/01/13 4 Building permit 10 d 16/01/13 31/01/13 5 Tender award 1 d 22/01/13 22/01/13 6 Finalize key trades 17 d 23/01/13 19/02/13 7 PIC issued 1 d 13/03/13 14/03/13 8 Off-site works 61 d 1/02/13 14/05/13 9 Structural steel - shop dwg preparation 21 d 1/02/13 5/03/13 12 DB - shop dwg preparation 19 d 26/02/13 26/03/13 10 Structural steel - shop dwg approval 5 d 6/03/13 14/03/13 11 Structural steel - manufacture 22 d 15/03/13 23/04/13 13 DB - shop dwg approval 4 d 27/03/13 9/04/13 14 DB - manufacture 23 d 10/04/13 14/05/13 15 Site Activities 140 d 20/02/13 2/10/13 16 Establishment 5 d 20/02/13 27/02/13 17 Tree / site clearing 5 d 21/02/13 28/02/13 18 Site Survey & setout 2 d 22/02/13 26/02/13 19 Building construction 136 d 27/02/13 2/10/13 20 Earthworks prep. to building footprint 9 d 27/02/13 13/03/13 21 Services rough in - below slab 7 d 14/03/13 22/03/13 22 Slab 1 (East slab) 14 d 19/03/13 15/04/13 23 Detailed excavation 5 d 19/03/13 25/03/13 25 Lift pit base - prep, tank & pour 4 d 21/03/13 26/03/13 24 Blinding 1 d 26/03/13 26/03/13 26 Lift pit sides - prep & pour 4 d 27/03/13 9/04/13 28 Prepare / form (not lift) 7 d 27/03/13 12/04/13 27 Lift pit walls - tank & backfill 2 d 10/04/13 11/04/13 29 Concrete pour 1 d 15/04/13 15/04/13 30 Slab 2 (Central slab) 15 d 28/03/13 26/04/13 31 Detailed excavation 5 d 28/03/13 12/04/13 32 Blinding 1 d 12/04/13 15/04/13 33 Prepare / form 7 d 16/04/13 24/04/13 34 Concrete pour 1 d 26/04/13 26/04/13 40 Structural steel - install east slab columns 4 d 18/04/13 23/04/13 35 Slab 3 (West slab) 9 d 22/04/13 3/05/13 36 Detailed excavation 2 d 22/04/13 24/04/13 37 Blinding 1 d 24/04/13 26/04/13 38 Prepare / form 4 d 29/04/13 2/05/13 39 Concrete pour 1 d 3/05/13 3/05/13 43 Framing - east slab walls 13 d 24/04/13 14/05/13 41 Structural steel - install Central slab zone 8 d 29/04/13 9/05/13 42 Blockwork - structural blade wall 3 d 7/05/13 9/05/13 44 Roof purlins - upper level 4 d 10/05/13 15/05/13 46 Framing - west slab walls 7 d 10/05/13 20/05/13 47 Timber roof trusses / LVL's (east slab) 5 d 15/05/13 21/05/13 48 Timber roof trusses / LVL's (west slab) 3 d 21/05/13 23/05/13 60 Roller shutter / doors - site measure agreed 1 d 21/05/13 21/05/13 45 Roofing - line / sheet roofs 11 d 22/05/13 6/06/13 52 Services rough in (walls / ceiling space) 17 d 22/05/13 18/06/13 49 Window / door frames install 9 d 23/05/13 5/06/13 50 Wall linings - external (Brickwork) 9 d 29/05/13 12/06/13 77 Lift pit infill floor 4 d 30/05/13 4/06/13 51 Wall linings - external (metal cladding) 13 d 6/06/13 27/06/13 53 Services - mech duct / pipe rough-in 8 d 17/06/13 27/06/13 55 Wall linings - internal (PB/villaboard) 16 d 19/06/13 12/07/13 61 Roller shutters - install 5 d 28/06/13 4/07/13 62 Roller doors - install 5 d 28/06/13 4/07/13 78 Wall linings - external (render) 4 d 28/06/13 3/07/13 64 Services - elec DB install 6 d 2/07/13 10/07/13 56 Ceilings - frame & line 15 d 15/07/13 6/08/13 57 2nd. Fix (doors / skirtings) 12 d 15/07/13 31/07/13 59 Paint - interior 25 d 31/07/13 5/09/13 67 Floor finishes - screeds & tanking 4 d 2/08/13 8/08/13 63 Services - mech fit off 9 d 8/08/13 21/08/13 Submit tender Design finalization & construction dwg issue Tender assessment Building permit Tender award Finalize key trades PIC issued Off-site works Structural steel - shop dwg preparation DB - shop dwg preparation Structural steel - shop dwg approval Structural steel - manufacture DB - shop dwg approval DB - manufacture Site Activities Establishment Tree / site clearing Site Survey & setout Building construction Earthworks prep. to building footprint Services rough in - below slab Detailed excavation Lift pit base - prep, tank & pour Blinding Lift pit sides - prep & pour Prepare / form (not lift) Lift pit walls - tank & backfill Concrete pour Detailed excavation Blinding Prepare / form Concrete pour Structural steel - install east slab columns Detailed excavation Blinding Prepare / form Concrete pour Framing - east slab walls Structural steel - install Central slab zone Blockwork - structural blade wall Roof purlins - upper level Framing - west slab walls Timber roof trusses / LVL's (east slab) Timber roof trusses / LVL's (west slab) Roller shutter / doors - site measure agreed Roofing - line / sheet roofs Services rough in (walls / ceiling space) Window / door frames install Wall linings - external (Brickwork) Lift pit infill floor Wall linings - external (metal cladding) Services - mech duct / pipe rough-in Wall linings - internal (PB/villaboard) Roller shutters - install Roller doors - install Wall linings - external (render) Services - elec DB install Ceilings - frame & line 2nd. Fix (doors / skirtings) Paint - interior Floor finishes - screeds & tanking Services - mech fit off 7/1 4/1 1/1 7/01 4/0 1/0 8/0 4/02 1/0 8/0 5/0 4/03 1/0 8/0 5/0 1/04 8/04 5/0 2/0 9/0 6/05 3/0 0/0 7/0 3/06 0/0 7/0 4/0 1/07 8/07 5/0 2/0 9/0 5/08 2/0 9/0 6/0 2/09 9/09 6/0 3/0 0/0 7/10 4/1 1/1 8/1 4/11 1/1 8 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Jul '13 Aug '13 Sep '13 Oct '13 Nov '13 Sample Construction Programme Issue: A Print date: 10/01/13 Project: sample Construction Programme Page 1 of 2
  • 2. ID Task Name Duration Start Finish 65 Services - elec / comms fit off 15 d 8/08/13 29/08/13 72 Joinery install - wet areas 5 d 9/08/13 15/08/13 54 Wall linings - internal (feature) 9 d 14/08/13 28/08/13 58 Paint - exterior elements 19 d 16/08/13 13/09/13 68 Floor finishes - vinyl 8 d 16/08/13 28/08/13 70 Floor finishes - epoxy 8 d 28/08/13 6/09/13 71 Wall vinyl 12 d 29/08/13 16/09/13 69 Floor finishes - carpet 6 d 11/09/13 18/09/13 66 Services - hyd fit off 8 d 12/09/13 23/09/13 73 Joinery install - balance areas 7 d 19/09/13 27/09/13 74 Toilet / shower partitions 3 d 20/09/13 24/09/13 75 Services - commission 6 d 24/09/13 2/10/13 76 Accessories 5 d 25/09/13 2/10/13 79 Clean & hand over 3 d 27/09/13 2/10/13 80 External civil works 119 d 25/03/13 1/10/13 83 Sewer - site reticulation works 6 d 25/03/13 9/04/13 84 Sewer - rising main works 13 d 10/04/13 29/04/13 85 Sewer - pump station installation 6 d 30/04/13 8/05/13 87 Water / fire service - street tapping 9 d 1/05/13 15/05/13 82 Stormwater - site reticulation works 19 d 7/05/13 3/06/13 86 Water / fire service - site reticulation works 9 d 15/05/13 28/05/13 89 Elec / comms - site reticulation works 14 d 22/05/13 13/06/13 88 Non-potable water service - site reticulation works 6 d 29/05/13 5/06/13 81 Civil earthworks 8 d 14/06/13 26/06/13 97 Retaining walls 9 d 19/06/13 2/07/13 90 Concrete pavement - prep subgrade 13 d 27/06/13 16/07/13 96 Shed slab - prep & install 18 d 27/06/13 24/07/13 91 Concrete pavement - kerb & channel 7 d 16/07/13 25/07/13 92 Concrete pavement - prep & place concrete 12 d 25/07/13 12/08/13 93 Cross-over works 6 d 13/08/13 21/08/13 95 Perimeter fencing & gates 20 d 13/08/13 11/09/13 98 Water tanks - install & commission 6 d 13/08/13 21/08/13 100 Landscape - soft landscaping works 19 d 28/08/13 24/09/13 99 Landscape accessories 7 d 18/09/13 26/09/13 94 Carpark - line marking 4 d 25/09/13 1/10/13 101 De-establish site 5 d 25/09/13 2/10/13 102 Project Hand Over 1 d 2/10/13 2/10/13 Services - elec / comms fit off Joinery install - wet areas Wall linings - internal (feature) Paint - exterior elements Floor finishes - vinyl Floor finishes - epoxy Wall vinyl Floor finishes - carpet Services - hyd fit off Joinery install - balance areas Toilet / shower partitions Services - commission Accessories Clean & hand over External civil works Sewer - site reticulation works Sewer - rising main works Sewer - pump station installation Water / fire service - street tapping Stormwater - site reticulation works Water / fire service - site reticulation works Elec / comms - site reticulation works Non-potable water service - site reticulation works Civil earthworks Retaining walls Concrete pavement - prep subgrade Shed slab - prep & install Concrete pavement - kerb & channel Concrete pavement - prep & place concrete Cross-over works Perimeter fencing & gates Water tanks - install & commission Landscape - soft landscaping works Landscape accessories Carpark - line marking De-establish site Project Hand Over 7/1 4/1 1/1 7/01 4/0 1/0 8/0 4/02 1/0 8/0 5/0 4/03 1/0 8/0 5/0 1/04 8/04 5/0 2/0 9/0 6/05 3/0 0/0 7/0 3/06 0/0 7/0 4/0 1/07 8/07 5/0 2/0 9/0 5/08 2/0 9/0 6/0 2/09 9/09 6/0 3/0 0/0 7/10 4/1 1/1 8/1 4/11 1/1 8 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13 Jul '13 Aug '13 Sep '13 Oct '13 Nov '13 Sample Construction Programme Issue: A Print date: 10/01/13 Project: sample Construction Programme Page 2 of 2