Senior/Graduate
                                      HMA Course


               Compaction of HMA Mixes

                      Background




Construction            Compaction                     1
What you will learn

 • Objective of Compaction
 • Engineering properties related to compaction
 • Factors affecting compaction




 Construction        Compaction                   2
Safety

•   Watch your back!
•   Keep visual contact with roller operators!
•   Keep an eye on traffic!
•   Wear your safety vest!




Construction           Compaction                3
Typical Compaction Process

Paving Machine     Vibratory Roller              Pneumatic     Steel wheeled
                                                   Roller          Roller




 Temperature        300° - 240°F                240° - 190°F    170 - 150°F
   Zones

  Construction                     Compaction                             4
Definitions

    •   Density
    •   Compaction
    •   Pass
    •   Coverage
    •   Time available for compaction (TAC)




 Construction           Compaction            5
Pass & Coverage Defined


                                                       Pass1
Width of mat




                                                       Pass 2
                                             Make up    Pass 5
                                                       Pass 3
                                                       Pass 4


                 This is a 5 pass pattern that
                 provides 2 complete coverages.
         Construction           Compaction                 6
Time Available for Compaction


                (TAC)


Construction     Compaction          7
Importance of Compaction

• Improve Mechanical Stability
• Improve Resistance to Permanent
  Deformation
• Reduce Moisture Penetration
• Improve Fatigue Resistance
• Reduce Low-Temperature Cracking Potential




Construction       Compaction                 8
Factors Affecting Compaction

• Properties of the Materials
• Environmental Variables
• Laydown Site Conditions




Construction         Compaction   9
Properties of the Materials

• Aggregate
• Asphalt Binder
• Mix Properties




Construction       Compaction       10
Construction   Compaction   11
Construction   Compaction   12
Construction   Compaction   13
Construction   Compaction   14
Construction   Compaction   15
Compact effort increases due to

•   Crushed content
•   Nominal maximum size
•   Hardness of the aggregate
•   Angularity of aggregate
•   Less natural sand
•   High dust content mixes
•   Note: Typically, HMA mixes will be harder to
    compact.

Construction          Compaction                   16
Construction   Compaction   17
Hot Mix Compaction

 • Asphalt binder holds particles together
    – Provides lubrication at high temperatures
    – Provides cohesion at in-service
      temperatures
 • Limits air and water intrusion into HMA mat




 Construction         Compaction                  18
Construction   Compaction   19
Environmental Variables

 •   Layer thickness
 •   Air and base temperature
 •   HMA mix laydown temperature
 •   Wind velocity
 •   Solar flux




 Construction        Compaction    20
o t a Mr o e mT
 t        f  i




                                                 0
                                                     10
                                                          20
                                                               30
                                                                     40
                                                                                50




                                             0



  Construction
                                             1
                                             2
                                                               F esa B x M
                                                                °      i




                                             3
                                                                    05 , 003
                                                                    23 , 003


                                             4
                                                                    41 , 003




  Compaction
                                             5                      05 , 052
                                                                     23 , 052
                                                                    41 , 052
                                             6

                 HMA Mat Thickness, inches
                                             7
                                             8



  21
Major Factors Affecting
                                  allows   allows
  Rolling Time
                                  MORE     LESS
                                   time     time

  Mat Thickness                   THICK    THIN


  Mix Temperature                 HIGH     LOW


  Base Temperature                HIGH     LOW

Construction         Compaction                     22
Construction   Compaction   23
Construction   Compaction   24
Construction   Compaction   25
Compaction Temperature Range




                 185 °F                  300 °F
                 (85 °C)                (150 °C)




Construction               Compaction              26
Laydown Site Conditions

 • Lift thickness versus aggregate size
 • Lift thickness uniformity
 • Base Conditions




 Construction         Compaction          27
Questions?




Construction    Compaction   28

Contenu connexe

Tendances

Rippers, loaders, trucks & hauling equipment
Rippers, loaders, trucks & hauling equipmentRippers, loaders, trucks & hauling equipment
Rippers, loaders, trucks & hauling equipmentshalomjudit3
 
Aggregate Crushing Equipment
Aggregate Crushing EquipmentAggregate Crushing Equipment
Aggregate Crushing EquipmentArpit Shrivastava
 
construction equipment and agreegate production equipment
construction equipment and agreegate production equipmentconstruction equipment and agreegate production equipment
construction equipment and agreegate production equipmentkonagallasrivardhan
 
Drag line excavator
Drag line excavatorDrag line excavator
Drag line excavatorParth Desani
 
Modern Construction equipments (dozers & power shovels)
Modern Construction equipments (dozers & power shovels)Modern Construction equipments (dozers & power shovels)
Modern Construction equipments (dozers & power shovels)Dipak Kadam
 
TOOLS AND MACHINERY USE FOR THE CONCRETE PRODUCTION AND SUPPLY
TOOLS AND MACHINERY USE FOR THE CONCRETE PRODUCTION AND SUPPLYTOOLS AND MACHINERY USE FOR THE CONCRETE PRODUCTION AND SUPPLY
TOOLS AND MACHINERY USE FOR THE CONCRETE PRODUCTION AND SUPPLYVj NiroSh
 
Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity SSudhaVelan
 
Construction equipment (earth work)
Construction equipment (earth work)Construction equipment (earth work)
Construction equipment (earth work)Suhaa Chine
 
Types Of Roller Used For Construction
Types Of Roller Used For Construction Types Of Roller Used For Construction
Types Of Roller Used For Construction Er Vivek Sampat
 
Equipments for erection and compaction
Equipments for erection and compactionEquipments for erection and compaction
Equipments for erection and compactionPrasanthi Nelloor
 
Excavating equipments_Advanced Construction Technology (Semester-6), Civil En...
Excavating equipments_Advanced Construction Technology (Semester-6), Civil En...Excavating equipments_Advanced Construction Technology (Semester-6), Civil En...
Excavating equipments_Advanced Construction Technology (Semester-6), Civil En...A Makwana
 
Transportation: Construction Equipments
Transportation: Construction EquipmentsTransportation: Construction Equipments
Transportation: Construction EquipmentsSanjana Gupta
 
Engineering fundamentals_Advanced Construction Technology (Semester-6), Civil...
Engineering fundamentals_Advanced Construction Technology (Semester-6), Civil...Engineering fundamentals_Advanced Construction Technology (Semester-6), Civil...
Engineering fundamentals_Advanced Construction Technology (Semester-6), Civil...A Makwana
 

Tendances (20)

compaction equipment
compaction equipmentcompaction equipment
compaction equipment
 
Draglines (fabil & venkatesh)
Draglines (fabil & venkatesh)Draglines (fabil & venkatesh)
Draglines (fabil & venkatesh)
 
Working of dragline
Working of draglineWorking of dragline
Working of dragline
 
Rippers, loaders, trucks & hauling equipment
Rippers, loaders, trucks & hauling equipmentRippers, loaders, trucks & hauling equipment
Rippers, loaders, trucks & hauling equipment
 
Aggregate Crushing Equipment
Aggregate Crushing EquipmentAggregate Crushing Equipment
Aggregate Crushing Equipment
 
construction equipment and agreegate production equipment
construction equipment and agreegate production equipmentconstruction equipment and agreegate production equipment
construction equipment and agreegate production equipment
 
Drag line excavator
Drag line excavatorDrag line excavator
Drag line excavator
 
CLAM SHELL BUCKETS
CLAM SHELL BUCKETSCLAM SHELL BUCKETS
CLAM SHELL BUCKETS
 
Modern Construction equipments (dozers & power shovels)
Modern Construction equipments (dozers & power shovels)Modern Construction equipments (dozers & power shovels)
Modern Construction equipments (dozers & power shovels)
 
TOOLS AND MACHINERY USE FOR THE CONCRETE PRODUCTION AND SUPPLY
TOOLS AND MACHINERY USE FOR THE CONCRETE PRODUCTION AND SUPPLYTOOLS AND MACHINERY USE FOR THE CONCRETE PRODUCTION AND SUPPLY
TOOLS AND MACHINERY USE FOR THE CONCRETE PRODUCTION AND SUPPLY
 
Excavating equipments (ACE)
Excavating equipments (ACE)Excavating equipments (ACE)
Excavating equipments (ACE)
 
Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity
 
Construction equipment (earth work)
Construction equipment (earth work)Construction equipment (earth work)
Construction equipment (earth work)
 
Types Of Roller Used For Construction
Types Of Roller Used For Construction Types Of Roller Used For Construction
Types Of Roller Used For Construction
 
Equipments for erection and compaction
Equipments for erection and compactionEquipments for erection and compaction
Equipments for erection and compaction
 
Types of excavating tools and machine
Types of excavating tools and machineTypes of excavating tools and machine
Types of excavating tools and machine
 
How clamshell bucket works
How clamshell bucket worksHow clamshell bucket works
How clamshell bucket works
 
Excavating equipments_Advanced Construction Technology (Semester-6), Civil En...
Excavating equipments_Advanced Construction Technology (Semester-6), Civil En...Excavating equipments_Advanced Construction Technology (Semester-6), Civil En...
Excavating equipments_Advanced Construction Technology (Semester-6), Civil En...
 
Transportation: Construction Equipments
Transportation: Construction EquipmentsTransportation: Construction Equipments
Transportation: Construction Equipments
 
Engineering fundamentals_Advanced Construction Technology (Semester-6), Civil...
Engineering fundamentals_Advanced Construction Technology (Semester-6), Civil...Engineering fundamentals_Advanced Construction Technology (Semester-6), Civil...
Engineering fundamentals_Advanced Construction Technology (Semester-6), Civil...
 

En vedette

En vedette (6)

Block 18 Placement 13
Block 18   Placement 13Block 18   Placement 13
Block 18 Placement 13
 
Block 15 Batch Plants 13
Block 15   Batch Plants 13Block 15   Batch Plants 13
Block 15 Batch Plants 13
 
Block 16 Drum Plants 13
Block 16   Drum Plants 13Block 16   Drum Plants 13
Block 16 Drum Plants 13
 
Block 17 Delivery aka Trucking 13
Block 17   Delivery aka Trucking 13Block 17   Delivery aka Trucking 13
Block 17 Delivery aka Trucking 13
 
Block 4 SP 14
Block 4 SP 14Block 4 SP 14
Block 4 SP 14
 
Superpave orientation local agencies
Superpave orientation local agenciesSuperpave orientation local agencies
Superpave orientation local agencies
 

Similaire à Block 19 Compacitons Background 13

Cc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumarCc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumarAkshay kumar
 
Bm wengl ceeng Lost Foam
Bm wengl ceeng Lost Foam Bm wengl ceeng Lost Foam
Bm wengl ceeng Lost Foam mossss
 
MANUFACTURING SCIENCE S5ME -NITC-2016
MANUFACTURING SCIENCE S5ME -NITC-2016MANUFACTURING SCIENCE S5ME -NITC-2016
MANUFACTURING SCIENCE S5ME -NITC-2016Jagadeesha Thimmaiah
 
IRJET- An Experimental Study of Ductile Behavior of Ferrocement Slab
IRJET- An Experimental Study of Ductile Behavior of Ferrocement SlabIRJET- An Experimental Study of Ductile Behavior of Ferrocement Slab
IRJET- An Experimental Study of Ductile Behavior of Ferrocement SlabIRJET Journal
 
Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)IJERD Editor
 
Ntpc summer training 2017
Ntpc summer training 2017Ntpc summer training 2017
Ntpc summer training 2017ktx500
 
SUMMER INTERN AT RICO
SUMMER INTERN AT RICOSUMMER INTERN AT RICO
SUMMER INTERN AT RICOMOHIT_SPONEN
 
Formwork failures and remedial measures
Formwork failures and remedial measuresFormwork failures and remedial measures
Formwork failures and remedial measuressabnisajit
 
Studies on Graded Cemented Carbides
Studies on Graded Cemented CarbidesStudies on Graded Cemented Carbides
Studies on Graded Cemented CarbidesRahul Mitra
 
Development_Hstrength_rebar.pptx
Development_Hstrength_rebar.pptxDevelopment_Hstrength_rebar.pptx
Development_Hstrength_rebar.pptxMiguelZacarias9
 
AN EXPERIMENTAL STUDY ON THE EFFECT OF NANO SILICA AND THE BEHAVIOUR OF OPC A...
AN EXPERIMENTAL STUDY ON THE EFFECT OF NANO SILICA AND THE BEHAVIOUR OF OPC A...AN EXPERIMENTAL STUDY ON THE EFFECT OF NANO SILICA AND THE BEHAVIOUR OF OPC A...
AN EXPERIMENTAL STUDY ON THE EFFECT OF NANO SILICA AND THE BEHAVIOUR OF OPC A...IRJET Journal
 
EVALUATION OF NOVEL SURFACTANT-BASED POLYMER-FREE FRICTION REDUCER
EVALUATION OF NOVEL SURFACTANT-BASED POLYMER-FREE FRICTION REDUCEREVALUATION OF NOVEL SURFACTANT-BASED POLYMER-FREE FRICTION REDUCER
EVALUATION OF NOVEL SURFACTANT-BASED POLYMER-FREE FRICTION REDUCERiQHub
 
IRJET- Experimental Study on Mesh Confined Concrete Subjected to High Tempera...
IRJET- Experimental Study on Mesh Confined Concrete Subjected to High Tempera...IRJET- Experimental Study on Mesh Confined Concrete Subjected to High Tempera...
IRJET- Experimental Study on Mesh Confined Concrete Subjected to High Tempera...IRJET Journal
 

Similaire à Block 19 Compacitons Background 13 (20)

Watershell Catalogue Specto Ct August 2009
Watershell Catalogue Specto Ct August 2009Watershell Catalogue Specto Ct August 2009
Watershell Catalogue Specto Ct August 2009
 
Cc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumarCc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumar
 
Bm wengl ceeng Lost Foam
Bm wengl ceeng Lost Foam Bm wengl ceeng Lost Foam
Bm wengl ceeng Lost Foam
 
MANUFACTURING SCIENCE S5ME -NITC-2016
MANUFACTURING SCIENCE S5ME -NITC-2016MANUFACTURING SCIENCE S5ME -NITC-2016
MANUFACTURING SCIENCE S5ME -NITC-2016
 
Smartdeck
Smartdeck Smartdeck
Smartdeck
 
IRJET- An Experimental Study of Ductile Behavior of Ferrocement Slab
IRJET- An Experimental Study of Ductile Behavior of Ferrocement SlabIRJET- An Experimental Study of Ductile Behavior of Ferrocement Slab
IRJET- An Experimental Study of Ductile Behavior of Ferrocement Slab
 
Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)Welcome to International Journal of Engineering Research and Development (IJERD)
Welcome to International Journal of Engineering Research and Development (IJERD)
 
Ntpc summer training 2017
Ntpc summer training 2017Ntpc summer training 2017
Ntpc summer training 2017
 
SUMMER INTERN AT RICO
SUMMER INTERN AT RICOSUMMER INTERN AT RICO
SUMMER INTERN AT RICO
 
Formwork failures and remedial measures
Formwork failures and remedial measuresFormwork failures and remedial measures
Formwork failures and remedial measures
 
Studies on Graded Cemented Carbides
Studies on Graded Cemented CarbidesStudies on Graded Cemented Carbides
Studies on Graded Cemented Carbides
 
ppt.pptx
ppt.pptxppt.pptx
ppt.pptx
 
Development_Hstrength_rebar.pptx
Development_Hstrength_rebar.pptxDevelopment_Hstrength_rebar.pptx
Development_Hstrength_rebar.pptx
 
METAL CASTING PROCESSES
METAL CASTING PROCESSESMETAL CASTING PROCESSES
METAL CASTING PROCESSES
 
AN EXPERIMENTAL STUDY ON THE EFFECT OF NANO SILICA AND THE BEHAVIOUR OF OPC A...
AN EXPERIMENTAL STUDY ON THE EFFECT OF NANO SILICA AND THE BEHAVIOUR OF OPC A...AN EXPERIMENTAL STUDY ON THE EFFECT OF NANO SILICA AND THE BEHAVIOUR OF OPC A...
AN EXPERIMENTAL STUDY ON THE EFFECT OF NANO SILICA AND THE BEHAVIOUR OF OPC A...
 
casting.pdf .
casting.pdf                                     .casting.pdf                                     .
casting.pdf .
 
8. bitumens
8. bitumens8. bitumens
8. bitumens
 
Unit i
Unit   iUnit   i
Unit i
 
EVALUATION OF NOVEL SURFACTANT-BASED POLYMER-FREE FRICTION REDUCER
EVALUATION OF NOVEL SURFACTANT-BASED POLYMER-FREE FRICTION REDUCEREVALUATION OF NOVEL SURFACTANT-BASED POLYMER-FREE FRICTION REDUCER
EVALUATION OF NOVEL SURFACTANT-BASED POLYMER-FREE FRICTION REDUCER
 
IRJET- Experimental Study on Mesh Confined Concrete Subjected to High Tempera...
IRJET- Experimental Study on Mesh Confined Concrete Subjected to High Tempera...IRJET- Experimental Study on Mesh Confined Concrete Subjected to High Tempera...
IRJET- Experimental Study on Mesh Confined Concrete Subjected to High Tempera...
 

Plus de Chris Yarnell

Plus de Chris Yarnell (20)

Block 3 SP 14
Block 3 SP 14Block 3 SP 14
Block 3 SP 14
 
Block 5 SP 14
Block 5 SP 14Block 5 SP 14
Block 5 SP 14
 
Block 2 SP 14
Block 2 SP 14Block 2 SP 14
Block 2 SP 14
 
Block 1 SP 14
Block 1 SP 14Block 1 SP 14
Block 1 SP 14
 
Block 6 SP 14
Block 6 SP 14Block 6 SP 14
Block 6 SP 14
 
Block 33 HMA Overlays c SP 13
Block 33   HMA Overlays c SP 13Block 33   HMA Overlays c SP 13
Block 33 HMA Overlays c SP 13
 
Block 33b SP 13
Block 33b SP 13Block 33b SP 13
Block 33b SP 13
 
Block 33a SP 13
Block 33a SP 13Block 33a SP 13
Block 33a SP 13
 
Block 32 SP 13
Block 32  SP 13Block 32  SP 13
Block 32 SP 13
 
Block 31 SP 13
Block 31   SP 13Block 31   SP 13
Block 31 SP 13
 
Block 30 SP 13
Block 30   SP 13Block 30   SP 13
Block 30 SP 13
 
Block 29 SP 13
Block 29   SP 13Block 29   SP 13
Block 29 SP 13
 
Block 28 Sp 13
Block 28   Sp 13Block 28   Sp 13
Block 28 Sp 13
 
Block 27 sp 13
Block 27 sp 13Block 27 sp 13
Block 27 sp 13
 
Block 25 Control Charts 13
Block 25   Control Charts 13Block 25   Control Charts 13
Block 25 Control Charts 13
 
Block 24 Obtaining Samples 13
Block 24   Obtaining Samples 13Block 24   Obtaining Samples 13
Block 24 Obtaining Samples 13
 
Block 23 Sampling - Theory 13
Block 23   Sampling - Theory 13Block 23   Sampling - Theory 13
Block 23 Sampling - Theory 13
 
Block 22 basic concepts
Block 22   basic conceptsBlock 22   basic concepts
Block 22 basic concepts
 
Block 21 Background 13
Block 21   Background 13Block 21   Background 13
Block 21 Background 13
 
Block 26 Acceptance 13
Block 26   Acceptance 13Block 26   Acceptance 13
Block 26 Acceptance 13
 

Block 19 Compacitons Background 13

  • 1. Senior/Graduate HMA Course Compaction of HMA Mixes Background Construction Compaction 1
  • 2. What you will learn • Objective of Compaction • Engineering properties related to compaction • Factors affecting compaction Construction Compaction 2
  • 3. Safety • Watch your back! • Keep visual contact with roller operators! • Keep an eye on traffic! • Wear your safety vest! Construction Compaction 3
  • 4. Typical Compaction Process Paving Machine Vibratory Roller Pneumatic Steel wheeled Roller Roller Temperature 300° - 240°F 240° - 190°F 170 - 150°F Zones Construction Compaction 4
  • 5. Definitions • Density • Compaction • Pass • Coverage • Time available for compaction (TAC) Construction Compaction 5
  • 6. Pass & Coverage Defined Pass1 Width of mat Pass 2 Make up Pass 5 Pass 3 Pass 4 This is a 5 pass pattern that provides 2 complete coverages. Construction Compaction 6
  • 7. Time Available for Compaction (TAC) Construction Compaction 7
  • 8. Importance of Compaction • Improve Mechanical Stability • Improve Resistance to Permanent Deformation • Reduce Moisture Penetration • Improve Fatigue Resistance • Reduce Low-Temperature Cracking Potential Construction Compaction 8
  • 9. Factors Affecting Compaction • Properties of the Materials • Environmental Variables • Laydown Site Conditions Construction Compaction 9
  • 10. Properties of the Materials • Aggregate • Asphalt Binder • Mix Properties Construction Compaction 10
  • 11. Construction Compaction 11
  • 12. Construction Compaction 12
  • 13. Construction Compaction 13
  • 14. Construction Compaction 14
  • 15. Construction Compaction 15
  • 16. Compact effort increases due to • Crushed content • Nominal maximum size • Hardness of the aggregate • Angularity of aggregate • Less natural sand • High dust content mixes • Note: Typically, HMA mixes will be harder to compact. Construction Compaction 16
  • 17. Construction Compaction 17
  • 18. Hot Mix Compaction • Asphalt binder holds particles together – Provides lubrication at high temperatures – Provides cohesion at in-service temperatures • Limits air and water intrusion into HMA mat Construction Compaction 18
  • 19. Construction Compaction 19
  • 20. Environmental Variables • Layer thickness • Air and base temperature • HMA mix laydown temperature • Wind velocity • Solar flux Construction Compaction 20
  • 21. o t a Mr o e mT t f i 0 10 20 30 40 50 0 Construction 1 2 F esa B x M ° i 3 05 , 003 23 , 003 4 41 , 003 Compaction 5 05 , 052 23 , 052 41 , 052 6 HMA Mat Thickness, inches 7 8 21
  • 22. Major Factors Affecting allows allows Rolling Time MORE LESS time time Mat Thickness THICK THIN Mix Temperature HIGH LOW Base Temperature HIGH LOW Construction Compaction 22
  • 23. Construction Compaction 23
  • 24. Construction Compaction 24
  • 25. Construction Compaction 25
  • 26. Compaction Temperature Range 185 °F 300 °F (85 °C) (150 °C) Construction Compaction 26
  • 27. Laydown Site Conditions • Lift thickness versus aggregate size • Lift thickness uniformity • Base Conditions Construction Compaction 27
  • 28. Questions? Construction Compaction 28

Notes de l'éditeur

  1. During this unit, we will look specifically at what compaction does for an HMA mix design and for a pavement. We will look at the variables and factors that affect the compaction process. We will look specifically at the types of rollers or compaction equipment available and how to pick the best roller for the job.
  2. The construction environment is dangerous. The need for safety on the job needs to be emphasized.
  3. This slide shows the typical compaction process. The paving machine will compact the HMA mix to about 85 % of G mm . Generally the first roller will be a vibratory roller – it will compact the HMA mat to about 91 % of G mm and then the pneumatic roller will compact it to about 94% of G mm . The last steel-wheeled roller is there to seal of the surface and iron out any marks that may have been left by the pneumatic roller.
  4. The density of a material is simply the weight of the material that occupies a certain volume of space. For example, an HMA mixture containing limestone aggregate might have a compacted density of 140 pounds per cubic foot; this density, or unit weight is an indication of the degree of compaction of the HMA. Compaction is the process through which the HMA is compressed and reduced in volume. A pass is defined as the entire roller moving over one point on the HMA mat one time. If you were standing on the side of the road counting the number of time the roller goes by in each direction, that total number would equal the number of passes. A coverage is defined as the roller moving over the entire width of the HMA mat one time. Since the roller is almost always less than the width of the HMA mat, it takes multiple passes to cover the mat. It is best illustrated in the next slide.
  5. This slide shows graphically the concept of pass and coverage.
  6. The time available for compaction is the time (in minutes) that a particular mix is at the right temperature range for efficient compaction. Ideally, there is a TAC for breakdown, intermediate, and finish rolling. Compaction must be accomplished before the HMA mat cools to a temperature below 175-185 °F (80-85 °C).
  7. Compaction is the single most important factor that affects the ultimate performance of a HMA pavement. Adequate compaction of the HMA mix increases the fatigue life, decreases permanent deformation (rutting), reduces oxidation or aging, decreases moisture damage, increases strength and stability, and decreases low-temperature cracking. An HMA that has all the desirable mix design characteristics will perform poorly under traffic if that HMA mix is not compacted to the proper density level.
  8. Properties of the materials include the surface texture, porosity and particle shape of the aggregate and the viscosity of the liquid asphalt binder. Environmental variables are temperature, wind, and solar flux. Letdown site conditions include the existing road surface texture, lift thickness and profile or the sub-base stability.
  9. Aggregates vary greatly across the nation from sedimentary to metamorphic and igneous. Aggregates may be natural deposits with little to no processing, processed aggregates such as limestone, dolomite, expanded shale, quartzite, and granite, and synthetic aggregates such as steel and blast furnace slags. Asphalt binder is graded by penetration, viscosity, or performance, and varies in hardness based on climate. HMA mixture properties vary based on type of HMA mixture specified. The type of HMA mixture specified varies directly with traffic loading. (Equivalent Single Axle Loadings, ESAL)
  10. Dense graded HMA mixtures are the most common types of HMA pavements specified worldwide. Dense graded mixtures are comprised of coarse, medium and fine aggregate particles. Today, Superpave, Stone Matrix Asphalt (SMA) and other specialty HMA mixtures tend to not be dense graded but more gap or open-graded. These HMA mixtures have a much larger proportion of coarse aggregate.
  11. Gap Graded or Porous Pavements, aggregate size will depend on the use / loading
  12. Stone Matrix Asphalt or SMA
  13. Aggregate is “the rock that carries the load.” Three properties of the coarse aggregate particles used in an asphalt mixture that can affect the ability to obtain the proper level of density are: particle shape of the aggregate, the number of fractured faces, and the surface texture. As the crushed content, nominal maximum size, and hardness of the aggregate increase, the compaction effort needed to obtain density also increases. Angular particles offer more compaction resistance than rounded particles, as do harsh mixtures versus dense graded HMA mixtures. In general, HMA mixes will be harder to compact. It is difficult to achieve density with high dust content mixes.
  14. As the crushed content, nominal maximum size, and hardness of the aggregate increase, the compaction effort needed to obtain density also increases. Angular particles offer more compaction resistance than rounded particles, as do harsh mixtures versus dense graded mixtures. In general, HMA mixes will be harder to compact. High dust content mixes are also difficult to densify.
  15. Asphalt binder is what “binds the rock together.” The grade and amount of Asphalt binder used in the mix affects the ability to densify the HMA. The degree of hardening that occurs in the asphalt binder during the manufacture of the HMA affects the compaction. Modifying the asphalt binder increases the compaction effort needed to obtain density. Asphalt binders can be similar to conventional asphalt binders. However, some PG grades will be modified. These will probably necessitate higher HMA mixture temperatures.
  16. Properly compacted and designed mixtures will ensure a durable mixture which performs long-term by limiting air and water to pass through it. In general, a mix with too little asphalt binder may be stiff and require an increase in compaction effort, whereas a mix with too much asphalt binder may shove under the rollers.
  17. A close-up view of a compacted HMA is shown in this slide. The slide shows aggregate, asphalt binder, and air voids. The densification behind the rollers typically takes us to 8% air voids so that a properly designed HMA mixture will consolidate to 4% air voids in the pavement, long term. A HMA mix that is placed at a higher temperature will be easier to compact than will a HMA mix that is lower in temperature when it is laid. The moisture content of the HMA mix should be less than 0.5 percent by weight of HMA mix, or 0.3 percent for high gravity mixtures.
  18. Research work and field experience show that once a pavement cools to about 170 F, the internal friction and cohesion of the mix increases to the point that little density gain is achievable. Six variables were found to have an effect on the rate of cooling a layer of asphalt binder placed on top of another existing layer of the same material. Layer thickness, air temperature, base temperature, HMA mix temperature, wind velocity, and solar flux are the variables.
  19. A series of “cooling curves” for HMA illustrate the amount of time available for compaction under different combinations of the variables. The figures shown assume air temperature to be equal to the surface temperature of the base. A constant wind velocity of 10 knots and a constant degree of solar radiation is also used to generate the graphs. The curves then provide the time in minutes, for the HMA mix to cool from the laydown temperature to a minimum compaction temperature for different compacted layer thicknesses.
  20. Layer thickness is the thickness of an HMA pavement layer, and it is the most important variable in the rate of cooling of HMA mixtures. It is very difficult to obtain the desired density on thin lifts of HMA in cool weather because of the rapid loss in temperature in the HMA mix. A portion of the heat in the HMA layer is lost to the air as well as the base as it is placed. Depending on the air and base temperature as well as moisture content, the loss of temperature could be large or small.
  21. HMA mixes are usually produced at temperatures between 280F and 330F, with higher temperatures being specified for modified asphalt binder mixtures. Depending on environmental conditions and the length of haul, the HMA mixture can lose between 10F and 30F from the plant to the paver. As the temperature of the HMA being placed is increased, the time available for compaction is greater.
  22. For a thickness of 2 inches (50 mm) and a base/air temperature of 40F(4 C), the time to cool to 175F ( 80C) increases from 9 min to 16 min as the placement temperature increases from 250 to 300F (120C to 150C). For a 4 inch (100 mm) layer and a base/air temperature of 60F (16C), a change in laydown temperature from 300F to 250F (150C to 120C) reduces the time available for compaction from 36 min to 21 min. The effect of HMA mat laydown temperature is more significant at lesser HMA mat thicknesses and lower base temperatures.
  23. A thin layer of HMA mix will cool more quickly in a strong wind than when there is little or no wind. Wind has a greater effect at the surface of the HMA mix than within the HMA mix, and can cause the surface to cool so rapidly that a crust will form and checking of the HMA may occur.
  24. The amount of radiant energy available from the sun is a function of many variables, including the position of the sun above the horizon, the distance above sea level of the project, the amount of turbidity in the air, and the degree of cloud cover. The amount of solar flux is more important in its effect on base temperature than HMA mix temperature. Summarizing, a HMA mixture placed too warm or too cold will lead to compaction problems in the field during placement. Modified asphalt binder producers typically supply end users with temperature-viscosity charts showing recommended compaction temperatures.
  25. Many factors–such as the relationship between lift thickness and nominal maximum aggregate size in the HMA mix (typically two or three times), or the uniformity of the lift thickness–at the laydown site directly affect the ability of the compaction equipment to gain the required level of pavement density. The suggested lift thickness is 3 to 4 times the nominal max size. It is much easier to obtain a required level of density in an HMA layer that has a constant thickness compared with a course that varies in depth. HMA leveling courses that, by their very nature and purpose, are nonuniform in thickness, are often difficult to densify to a given air void content uniformly, when placed over a rutted or wavy road.