The presentation, made before a discussion group on 26.06.2020, discusses the possible ways forward for the Construction industry in India vis-a-vis resolution of construction disputes arising out of Covid19.
Senior Manager at Directorate General of Hydrocarbons/ Bharat Petroleum Corporation Limited
The presentation, made before a discussion group on 26.06.2020, discusses the possible ways forward for the Construction industry in India vis-a-vis resolution of construction disputes arising out of Covid19.
Indian Construction Contracts & Covid19 : Way Forward
1.
Indian Construction
Contracts & Covid19 : Way
Forward
SR. MANAGER (LEGAL), DIRECTORATE GENERAL OF HYDROCARBONS/ BHARAT
PETROLEUM CORPORATION LIMITED
WWW.PRACTICALACADEMIC.BLOGSPOT.IN
WWW.SSRN.COM/AUTHOR=665603
WWW.LINKEDIN.COM/PUB/BADRINATH-SRINIVASAN/13/604/916
LAWBADRI@GMAIL.COM
3.
Impact of Covid19 on Construction
Industry
Cash flow
Supply chain disruptions
Time overrun: need for extension of time
Cost overrun: need for increase in contract price
Contractors: Substantial Increase in Cost of Performance
Owners: Substantial decrease in Cost of Performance
Manpower Issues
Work resumption and other HSE issues
Views are personal
4.
Time Overrun: Some Issues
Time lost due to Covid-19 lockdown
Time lost due to Covid19 affecting/ impacting supplies/ services
even prior to lockdown
Time lost due to demobilisation and remobilisation
Extra time that would be required for carrying out works in a
restricted regime.
Views are personal
5.
Cost Overrun: Some Issues
Idling charges
Care of Facilities during Lockdown
Demobilisation/ Remobilisation Costs
Costs of paying labour wages during lockdown
Price increase in raw materials & goods post-lockdown
Mitigation plans in Project
Suppliers/ Contractors claims including demurrage
Other costs
Views are personal
6.
Government’s Role
Perusal of various Circulars
Proactive response from a policy angle.
Pandemic is considered as force majeure
But how force majeure will impact contract performance may depend
on case-to-case basis
Views are personal
7.
List of Government Notifications on
Covid19 as FM
Impact of COVID-19 on foreign supply chains recognized as force majeure in government supply
contracts: Department of Expenditure, Ministry of Finance's OM dt. 19.02.2020
DOE Notification dt. 13.05.2020 (time extensions)
Time extension in scheduled commissioning of Renewable Energy projects considering foreign supply
chain disruptions: Ministry of New & Renewable Energy, OM dt. 20.03.2020
MORTH Letter no. H-25016/01/2018-Toll dated 25th March 2020
Ministry of Shipping, Guidelines to Major Ports dt. 31.03.2020
Indian Railways (https://pib.gov.in/PressReleseDetail.aspx?PRID=1608603)
DGS Order No. 08 of 2020 dt. 31.03.2020
Ministry of Shipping order no. PD-13/33/2020-PPP/e-339106 dt. 20.03.2020
Other Circulars
Views are personal
8.
Some Questions
Whether force majeure or not?
Obligations affected by force majeure and manner?
Whether notice has been given in time?
Whether change in Law?
How should be the contract, especially terms relating to price and time, be re-
negotiated?
Time and Cost Overrun and escalation?
Non-applicability of LD/ claim for damages for delay.
Genuine dispute: How to resolve?
Prolonged force majeure and consequences
Views are personal
9.
Legal Issues & Problems
Inability of parties
to agree upon cost/ time overruns
Inability of a general Contractor to perform
The bleak prospect of disputes & the ability of the legal system to handle
it
Inability to get proper advice on financial and legal aspects
Government benefits: Awareness: Important role to be played by
construction associations, bodies like SCL and others.
How to Proceed?
Views are personal
11.
“Breathing Space”
How to deal with Construction Contracts Post-Covid19?
Amicably Sort out Issues with the objective of completing projects
ASAP
Provide for Amicable Dispute Resolution Solutions to make
construction contracts viable
To bring to an end contracts made unviable post-Covid19
Views are personal
12.
Ways Forward
Standard Operating Procedure for Construction Projects affected by Covid 19
Enablers
Way Forward: Formats & Checklists
Awareness of Government Measures
Dispute Resolution
SCL and other construction associations may take the lead
Views are personal
13.
SOP for Construction Projects affected by
Covid 19
SOP on the Way Forward
Invocation of Force Majeure/ Change in Law
Cost Overruns
Time Overruns
Other Issues
Discussions: in good faith & in interest of project completion
Cash Flow
Advance payments/ modification of contractual milestones
Escrow accounts
Views are personal
14.
SOP for Construction Projects affected by
Covid 19 (contd.)
Inability of the general Contractor to perform/ make payment-
direct payment between Client and Sub-Contractors & modalities
Preliminary/ Interim Orders aimed at completion of project & at
the same time maintaining Contractor cash flows
Dispute Resolution
Conciliation/ Mediation
Arbitration
Stress on inexpensive, swift, virtual and decisive resolution of disputes.
Views are personal
15.
Enablers
Templates/ Checklists/ Formats:
Force majeure & change in law invocation & response templates
Checklists on Impact
Checklists on negotiations on Cost/ Time overruns
Novation Agreement Formats
Arbitration, Conciliation & Mediation Agreements Formats
Settlement agreements Formats
Compilation of Government schemes and judicial decisions in
construction sector for general awareness
Views are personal
16.
Accelerated Dispute Resolution
Drastic Times call for Drastic Measures
Speed, Inexpensive and Effective dispute resolution
Fixed time ~ 3 months & Fixed costs ~5- 6 lakhs
Completely Virtual
Construction Dispute Specific
Neutral
Interim Measures: Extension of BGs & Preservation- Completion of
Project should be the objective
Three modes: Accelerated Conciliation, Mediation & Arbitration
Checklists/ Formats for use in Dispute resolution to be fixed
Views are personal
17.
Accelerated Construction Conciliation
Inability of the general contractor to perform/ make payment- direct payment between
Client and Sub-Contractors
A finance, technical and a legal expert in each Panel
Virtual & Time limit of three months
No external counsels
Specific disputes to be agreed between the parties and referred
Common statement of facts and points of disagreement
Proceedings to be confidential except as to costs
In case of rejection of Settlement Proposal, costs of conciliation & subsequent legal
proceedings to be on Indemnity basis, if unsuccessful.
Views are personal
18.
Accelerated Construction Mediation
Professional Mediator well-versed in Construction Disputes
Virtual & Time limit of three months
No external counsels
Specific disputes to be agreed between the parties and referred
Common statement of facts and points of disagreement
Proceedings to be confidential except as to costs
For party rejecting the last settlement offer, costs of mediation & subsequent legal
proceedings to be on Indemnity basis, if unsuccessful.
Views are personal
19.
Accelerated Construction Arbitration
Fixed Costs: Not more than Rs. 5- 6 lakhs net
A finance, technical and a legal expert in each Tribunal
Time limit of three months
Documents only/ Expedited (S. 29B ACA 1996)
Specific disputes to be agreed between the parties and referred
Common statement of facts and points of disagreement reg. facts/ law
Power to decide on the basis of commercial sense, equity, etc.
Strict implementation of Loser Pays principle for Costs
Views are personal
20.
Parting Thoughts
Construction bodies may discuss with
stakeholders about measures suggested
Multi-tier Dispute Resolution
May enter into deals with Arbitral
institutions
Need to Proceed quickly
Statute on construction contracts
THANK YOU
Views are personal
Il semblerait que vous ayez déjà ajouté cette diapositive à .
Créer un clipboard
Vous avez clippé votre première diapositive !
En clippant ainsi les diapos qui vous intéressent, vous pourrez les revoir plus tard. Personnalisez le nom d’un clipboard pour mettre de côté vos diapositives.
Créer un clipboard
Partager ce SlideShare
Vous avez les pubs en horreur?
Obtenez SlideShare sans publicité
Bénéficiez d'un accès à des millions de présentations, documents, e-books, de livres audio, de magazines et bien plus encore, sans la moindre publicité.
Offre spéciale pour les lecteurs de SlideShare
Juste pour vous: Essai GRATUIT de 60 jours dans la plus grande bibliothèque numérique du monde.
La famille SlideShare vient de s'agrandir. Profitez de l'accès à des millions de livres numériques, livres audio, magazines et bien plus encore sur Scribd.
Apparemment, vous utilisez un bloqueur de publicités qui est en cours d'exécution. En ajoutant SlideShare à la liste blanche de votre bloqueur de publicités, vous soutenez notre communauté de créateurs de contenu.
Vous détestez les publicités?
Nous avons mis à jour notre politique de confidentialité.
Nous avons mis à jour notre politique de confidentialité pour nous conformer à l'évolution des réglementations mondiales en matière de confidentialité et pour vous informer de la manière dont nous utilisons vos données de façon limitée.
Vous pouvez consulter les détails ci-dessous. En cliquant sur Accepter, vous acceptez la politique de confidentialité mise à jour.