Project Completion Review of Food Security Livelihood Improvement and Climate Change Adaptation Program
1. On
Project Completion Review of the Program โPRRO
(FSCCA) and RCIW Programsโ
Presented By:
Bijaya Upadhya
Project Coordinator
VDSEF, Kalikot - Nepal
Welcome
3. 1. Funding Organization: UN-WFP, GoN (VDC-KEP and
PAF)
2. Technical support: Save the Children
3. Implementation: Village Development and Save the
Environment Forum (VDSEF)- Kalikot/Nepal
Food Security Livelihood Improvement and Climate
Change Adaptation Program.
Project Duration: Sept 2012 โ
June 2013
5. General Objectives
โข Improve short term food security by providing safety nets for the most
vulnerable community.
โข Foster community resilience through creation of productive assets and
agriculture livelihood training.
Specific objectives
โขTo secure the short term food requirement of project area.
โขTo provide short term employment.
โขTo control seasonal migration of project area.
โขTo increase income of beneficiaries for food security.
โขTo make aware about mitigating/adapting technique of effect of climate
change.
Objectives of the Program
6. โขBased on need and demand.
โขStrengthen related line agencies (Community to
Gov)
โขCoordination.
โขCollaboration
โขMotivation & Mobilization
Working Approach
8. โข Non-Physical (Coordination and Collaboration)
โข Physical (Asset Creation)
โข Commodity Handling and distribution
Major Section of Program
9. Out of physical
โขInception Meeting โ District Level/Village level.
โข Orientation (Staff/Community).
โข Scheme Identification.
โข Household survey.
โข Feasibility Survey for construction.
โข User Committee Formation-15
Achievement
10. โขDistribution of Ration Card.
โข Endorsement of program on village council and DPMC.
โข Meetings ( Staff/DPMC/VDC secretary & UC).
โข Regular monitoring. (by site in charge/technical coordinator, M&E,
Members of executive committee, Staff from Save the Children,
United Nation, Governmental organization and Program
Coordinator of the Project.
โข Public Hearing.
โข Work completion review (District level)
โข Handover to maintenance committee
โข Collection of Collaboration Fund.
Cont..
17. 1. Orchard Management.
โข Apple Farming
2. Green Road
3. Water Resource Management
โข Drinking Water Supply System
โข Irrigation Canal
Physical Section
Interventions of the Project
18. Schemes Achievement
Table 1: Apple Farming
VDC Scheme Ward No. Household Farm area (ha)
Apple
Saplings
planted
(No.)
Length of
fencing
wall (m)
GoN-VDC
Contribution
(Rs)
Dhaulagau Dhaulagau Apple Farming
All except
4 1249 62.05 20938 11783 30,94,875
Thirpu
Phagauti-Gadwali Apple
Farming 1 & 8 219 3.64 3685 1785 7,03,668
Ramnakot
Banjkot Apple farming 1 to 4 380 25.10 6225 3222 10,66,212
Khardu Apple farming 5 to 9 413 24.97 6771 3421 11,85,373
Nanikot
Bolugau-tundikhet Apple
farming 1 &2 174 8.04 2408 1468.5 4,92,029
Nanikot Apple Farming 5 150 6.75 2705 1214 4,51,079
Gothichepprekhet Apple
Farming 7 55 3.50 983 461.75 1,62,637
Total 2640 134.05 43537 23355.2 71,55,873
20. Fig: 11. Fencing
wall of Khardu
Apple Farming,
Ramnakot
Fig: 10. Fencing
wall of
Bolugau-
Tundikhet Apple
Farming,
Nanikot
21. Fig: 12. Apple Sapling Plantation in Gothicheprekhet,
Nanikot-7
22. S.N Scheme Name VDC/Ward Canal
Length(m)
Command Area(ha) HH
1 Bhitta I.C Nanikot/6,7 1618 9.4 105
2 Mayakot I.C Nanikot-4 1670 10.3 184
3 Tikharti I.C Nanikot-9 1776 15 118
4 Kotila I.C Nanikot-8 2034 8.44 81
Tota
l
4 Scheme 1 VDC 6269 43.14 488
S.N Scheme VDC/Ward No. of tap stand Household
1 Nuwaghar DWSS Nanikot-2/3 12 out of 23 273
2 Dhaulagoha DWSS Dhaulagoha-4 3 165
3 2 scheme 2 VDC 26 438
Table 2: Drinking water supply System
Table 3: Irrigation Canal
23. Fig: 14. Drywall
Constructed in
Tikharti Irrigation
canal, Nanikot.
Fig: 13.
Beneficiaries
working for One
side canal lining
in Tikharti
irrigation canal,
Nanikot
25. Fig:16. Canal under-
construction at
Kotila Irrigation
Canal, Nanikot-8
Fig: 17. Skilled
labour working
for Canal lining in
Kotila Irrigation
canal
30. Fig:25. Gabion Wall
construction in
Thirpu Badki green
road at Thirpu VDC
Fig: 24. Dry
Wall of
Thirpu -
Badki Green
Road at
Thirpu VDC
31. Fig: 26. Road
Alignment of
Khina Road,
Khina
Fig:27.
Gabion wall
constructed in
Khina road,
Khina
32. โข Assessment of location for EDP.
โข Agreement with House owner to store food.
โข Establishment of EDP with arrangement of required tools
and equipments.(Visibility board, weighing machine,
pallets.)
Work from EDP
โข Food handling, storage and distribution.
EDP and Food Status
33. Contโฆ
Commodity Total Received(Mt) Total Distributed (Mt)
Rice 1200 1200
Pulse 150 150
Total 1350 1350
23%
16%
18%
28%
15%
Commodity Distributed According to VDCs
Nanikot Ramnakot Thirpu Dhaulagaun Kheena
44. Work-Done
Work out of Physical
โข Inception Meeting โ Village level.
โข Orientation of Staff and at Community level.
โข Scheme Identification.
โข HH survey.
โข Feasibility Survey for construction work.
โข Formation of User Committee-8
โข Distribution of Ration Card.
โข Endorsement of the program at village council and
DPMC.
โข Meetings at Staff/DPMC/VDC secretary & UC level.
โข Regular monitoring.
โข Conduction of Public Hearing.
โข Completion review (District level)
60. Financial Activity
Topics Total Allocated(Rs) Total Expenses(Rs)
Program Activities 7981250.0 7976791.0
Program Staff cost 1856203.5 1861646.2
Travel, Monitoring &Evaluation 189787.0 189905.0
Administration Cost 327004.0 323117.0
Total 354244.5 10351459.2
77%
18%
2% 3%
Total Expenses(Rs)
Program Activities Program Staffcost
Travel, Monitoring &Evaluation Administration Cost
61. โขPoor Communication.
โขBig volume of program VS Short term period (Time bound)
โขCongested fixed rate of transportation cost
โขDifficulties in collection of collaboration fund.
โขLarge volume of scheme in tough geography.
โขLow human resource.
โข Different level of knowledge/awareness at community level as well in
district.
โขDominance of few people over whole community
โขFrequent weather change.
Challenges observed during the
Program
62. โขEnough budgets, enough safety tools and equipments, safety
awareness trainings for workers are the mandatory things for big
volume of construction projects like road.
โขModified system should be adapted for cash transfer to ensure
security of cash.
โข Creation of good communication system for day to day updates of
commodity tracking, cash transfer status and construction updates.
โขConsideration on tough topography, community and challenge on
accomplishment of activity on time, there need to be good flow of
human resource in field level.
โข Large volume of scheme with collection of collaboration fund and
Constructive Feedbacks
63. โข11850 HH benefited from the program which includes male 32,497 and female
31,250
โขInfrastructure : four Irrigation Canal Scheme, two drinking water supply system
scheme, two green roads, seven apple farming,3 Foot Trail and 5 Rural Road.
โข Completion of scheme on the basis of need and demand of the community.
โข Effective and efficient mobilization of community for their own work has
empowered them for long term development.
โข Coordination and collaboration with different stakeholders.
โข Collection of collaboration fund Rs. 22982316.92 from stakeholders like VDC,
PAF.
โขEmployment to various age group who cannot go far to sustain their livelihood.
Key achievements