Source Selection 101 Susan Smith 21CONS Col Tom Walker AFSPC/CX
Purpose Insight in how and why the RFP is developed Insight on how the Gov’t evaluates proposals “Demystify” the source selection process: Encourage more participation, especially small businesses Improve offeror’s potential for awards Objective is for the Gov’t to get better proposals
Topics RFP Development Process Evaluation Factors/Subfactors Overall Assessment Summary
RFP Development Process
RFP Development Process ,[object Object]
 Identify program risks associated with the requirements
 Analyze risks to determine priority and risk handling approach
 Develop a mitigation strategy for the highest risks
 Use RFP discriminators to mitigate program risks,[object Object]
Commercial Contract Format Standard Form (SF) 1449; Any contract documents, exhibits or attachments Solicitation provisions --  52.212-1, Instructions to Offerors -- Commercial Items and any addendum  52.212-2, Evaluation -- Commercial Items, or other description of evaluation factors for award 52.212-3, Offeror Representations and Certifications -- Commercial Items Contract clauses -- 52.212-4, Contract Terms and Conditions and any addendum 52.212-5, Contract Terms and Conditions Required to Implement Statutes and Executive orders
RFP Development Process Sec L  or 52.212-1 (What information offeror must submit to be evaluated against Sec M criteria): Sec L and Sec M should track closely  Requests only minimum data needed to evaluate proposals Sec M  or 52.212-2 (Evaluation Criteria): Most important  Represents about 95% of entire acquisition strategy  Rules of selection; forms compact with offerors:
Evaluation Factors  & Subfactors
Source Selection Types ,[object Object]
Lowest Price/Technically Acceptable (LPTA) -  2 Step
 1: Min. Technically Acceptable (Pass/Fail)
 2: Lowest Price among Technically Acceptable
Performance/Price Tradeoff (PPT) -  2 Step
 1: Min. Technically Acceptable (Pass/Fail)
 2: Trade-off between Past Performance & Price   Full Trade-Off (FTO) -  1 Step ,[object Object],      	    Mission Capability/                   Past                    Proposal PriceTech. AcceptabilityPerformanceRisk Low Price	 LPTA		             +/- PPT			             +/- 		       	 FTO            		             	      	             
Evaluation Factors ,[object Object]
This evaluation provides for two distinct but related assessments:  the Mission Capability Technical Rating and the Mission Capability Risk Rating
 Evaluation of offeror’s proposal against the Gov.’s minimum performance or capability requirements
Proposal risk assessment  - weaknesses associated with offeror’s proposed approach
Past Performance
 Assessment of the degree of confidence the USAF has in an offeror to provide products or services that meet the users’ needs (including cost and schedule) based on demonstrated record of performance
Price

Contenu connexe

Tendances

Anti-Red Tape Authority 2019-2020 Accomplishment Report
Anti-Red Tape Authority 2019-2020 Accomplishment ReportAnti-Red Tape Authority 2019-2020 Accomplishment Report
Anti-Red Tape Authority 2019-2020 Accomplishment ReportBerean Guide
 
Do-It-Yourself Logic Models: Examples, Templates, and Checklists
Do-It-Yourself Logic Models: Examples, Templates, and ChecklistsDo-It-Yourself Logic Models: Examples, Templates, and Checklists
Do-It-Yourself Logic Models: Examples, Templates, and ChecklistsInnovation Network
 
Principles of teaching 1
Principles of teaching 1Principles of teaching 1
Principles of teaching 1Leicel Doble
 
Essentials for Grant Management_
Essentials for Grant Management_Essentials for Grant Management_
Essentials for Grant Management_Mellish
 
Monitoring & evaluation presentation[1]
Monitoring & evaluation presentation[1]Monitoring & evaluation presentation[1]
Monitoring & evaluation presentation[1]skzarif
 
Role of stakeholders in getting all children enrolled
Role of stakeholders in getting all children enrolledRole of stakeholders in getting all children enrolled
Role of stakeholders in getting all children enrolledNazia Goraya
 

Tendances (8)

Anti-Red Tape Authority 2019-2020 Accomplishment Report
Anti-Red Tape Authority 2019-2020 Accomplishment ReportAnti-Red Tape Authority 2019-2020 Accomplishment Report
Anti-Red Tape Authority 2019-2020 Accomplishment Report
 
Do-It-Yourself Logic Models: Examples, Templates, and Checklists
Do-It-Yourself Logic Models: Examples, Templates, and ChecklistsDo-It-Yourself Logic Models: Examples, Templates, and Checklists
Do-It-Yourself Logic Models: Examples, Templates, and Checklists
 
Principles of teaching 1
Principles of teaching 1Principles of teaching 1
Principles of teaching 1
 
curriculum
curriculumcurriculum
curriculum
 
Project Monitoring and Evaluation
Project Monitoring and Evaluation Project Monitoring and Evaluation
Project Monitoring and Evaluation
 
Essentials for Grant Management_
Essentials for Grant Management_Essentials for Grant Management_
Essentials for Grant Management_
 
Monitoring & evaluation presentation[1]
Monitoring & evaluation presentation[1]Monitoring & evaluation presentation[1]
Monitoring & evaluation presentation[1]
 
Role of stakeholders in getting all children enrolled
Role of stakeholders in getting all children enrolledRole of stakeholders in getting all children enrolled
Role of stakeholders in getting all children enrolled
 

En vedette

Build vs Buy Strategy
Build vs Buy StrategyBuild vs Buy Strategy
Build vs Buy StrategyChris Halton
 
Selection and acquisitions
Selection and acquisitionsSelection and acquisitions
Selection and acquisitionsJohan Koren
 
Make or buy, insourcingoutsourcing
Make or buy, insourcingoutsourcingMake or buy, insourcingoutsourcing
Make or buy, insourcingoutsourcingAnkit
 
Supplier evaluation & selection
Supplier evaluation & selectionSupplier evaluation & selection
Supplier evaluation & selectionAnkit
 
Supplier evaluation criteria
Supplier evaluation criteriaSupplier evaluation criteria
Supplier evaluation criteriaArt Acosta
 
Recruitment And Selection
Recruitment And SelectionRecruitment And Selection
Recruitment And Selectionharshalsk
 
SUPPLIER SELECTION AND EVALUATION
SUPPLIER SELECTION AND EVALUATIONSUPPLIER SELECTION AND EVALUATION
SUPPLIER SELECTION AND EVALUATIONZamri Yahya
 
How to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksHow to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksSlideShare
 
Getting Started With SlideShare
Getting Started With SlideShareGetting Started With SlideShare
Getting Started With SlideShareSlideShare
 

En vedette (9)

Build vs Buy Strategy
Build vs Buy StrategyBuild vs Buy Strategy
Build vs Buy Strategy
 
Selection and acquisitions
Selection and acquisitionsSelection and acquisitions
Selection and acquisitions
 
Make or buy, insourcingoutsourcing
Make or buy, insourcingoutsourcingMake or buy, insourcingoutsourcing
Make or buy, insourcingoutsourcing
 
Supplier evaluation & selection
Supplier evaluation & selectionSupplier evaluation & selection
Supplier evaluation & selection
 
Supplier evaluation criteria
Supplier evaluation criteriaSupplier evaluation criteria
Supplier evaluation criteria
 
Recruitment And Selection
Recruitment And SelectionRecruitment And Selection
Recruitment And Selection
 
SUPPLIER SELECTION AND EVALUATION
SUPPLIER SELECTION AND EVALUATIONSUPPLIER SELECTION AND EVALUATION
SUPPLIER SELECTION AND EVALUATION
 
How to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksHow to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & Tricks
 
Getting Started With SlideShare
Getting Started With SlideShareGetting Started With SlideShare
Getting Started With SlideShare
 

Similaire à 5. source selection_101

Best practices for a far 15 procurement part 1
Best practices for a far 15 procurement part 1Best practices for a far 15 procurement part 1
Best practices for a far 15 procurement part 1SacramentoNCMA Gold Rush
 
Request for-proposals-fundamentals4957
Request for-proposals-fundamentals4957Request for-proposals-fundamentals4957
Request for-proposals-fundamentals49570607ashley
 
Mar 2012 cdphe contractor performance monitoring trng
Mar 2012 cdphe contractor performance monitoring trngMar 2012 cdphe contractor performance monitoring trng
Mar 2012 cdphe contractor performance monitoring trngBrandon Williams
 
Source Selection Practicum: What You Need to Know About Source Selection Stra...
Source Selection Practicum: What You Need to Know About Source Selection Stra...Source Selection Practicum: What You Need to Know About Source Selection Stra...
Source Selection Practicum: What You Need to Know About Source Selection Stra...Government Contract Pricing Summit
 
CONSULTING SERVICES PROCUREMENT AND SELECTION AUGUST 2013 PRESENTATION
CONSULTING SERVICES PROCUREMENT AND SELECTION AUGUST 2013 PRESENTATIONCONSULTING SERVICES PROCUREMENT AND SELECTION AUGUST 2013 PRESENTATION
CONSULTING SERVICES PROCUREMENT AND SELECTION AUGUST 2013 PRESENTATIONChester, Ryan Bourne MSc., MBA, PMP
 
PowerPoint Presentation -Getachew M.pptx
PowerPoint Presentation -Getachew M.pptxPowerPoint Presentation -Getachew M.pptx
PowerPoint Presentation -Getachew M.pptxGetachewMekonnen22
 
James.taylor
James.taylorJames.taylor
James.taylorNASAPMC
 
How evaluators score proposals to select the right vendor.
How evaluators score proposals to select the right vendor.How evaluators score proposals to select the right vendor.
How evaluators score proposals to select the right vendor.Abhijit Majumdar CP.APMP
 
Acquisition Risk Analysis
Acquisition Risk AnalysisAcquisition Risk Analysis
Acquisition Risk AnalysisOmniaParatus
 
Supplier Relationship Management
Supplier Relationship ManagementSupplier Relationship Management
Supplier Relationship ManagementMichelle Lombard
 
7. past performance_seminar
7. past performance_seminar7. past performance_seminar
7. past performance_seminarColorado PTAC
 
Effective Specification Writing
Effective Specification WritingEffective Specification Writing
Effective Specification WritingDr Gordon Murray
 
How to Identify Accurate & Correct Cost Drivers to Capture the Best Pricing
How to Identify Accurate & Correct Cost Drivers to Capture the Best Pricing How to Identify Accurate & Correct Cost Drivers to Capture the Best Pricing
How to Identify Accurate & Correct Cost Drivers to Capture the Best Pricing Government Contract Pricing Summit
 
Rfp final
Rfp finalRfp final
Rfp finalsubu
 
Design Build Requirements In Washington State By Michael E Purdy
Design Build Requirements In Washington State   By Michael E PurdyDesign Build Requirements In Washington State   By Michael E Purdy
Design Build Requirements In Washington State By Michael E PurdyMike Purdy
 

Similaire à 5. source selection_101 (20)

Best practices for a far 15 procurement part 1
Best practices for a far 15 procurement part 1Best practices for a far 15 procurement part 1
Best practices for a far 15 procurement part 1
 
Request for-proposals-fundamentals4957
Request for-proposals-fundamentals4957Request for-proposals-fundamentals4957
Request for-proposals-fundamentals4957
 
Mar 2012 cdphe contractor performance monitoring trng
Mar 2012 cdphe contractor performance monitoring trngMar 2012 cdphe contractor performance monitoring trng
Mar 2012 cdphe contractor performance monitoring trng
 
Evaluation Training Guide
Evaluation Training GuideEvaluation Training Guide
Evaluation Training Guide
 
RFP Evaluation Training
RFP Evaluation TrainingRFP Evaluation Training
RFP Evaluation Training
 
Source Selection Practicum: What You Need to Know About Source Selection Stra...
Source Selection Practicum: What You Need to Know About Source Selection Stra...Source Selection Practicum: What You Need to Know About Source Selection Stra...
Source Selection Practicum: What You Need to Know About Source Selection Stra...
 
CONSULTING SERVICES PROCUREMENT AND SELECTION AUGUST 2013 PRESENTATION
CONSULTING SERVICES PROCUREMENT AND SELECTION AUGUST 2013 PRESENTATIONCONSULTING SERVICES PROCUREMENT AND SELECTION AUGUST 2013 PRESENTATION
CONSULTING SERVICES PROCUREMENT AND SELECTION AUGUST 2013 PRESENTATION
 
NCMA Performance-Based Acquisition Overview
NCMA Performance-Based Acquisition OverviewNCMA Performance-Based Acquisition Overview
NCMA Performance-Based Acquisition Overview
 
PowerPoint Presentation -Getachew M.pptx
PowerPoint Presentation -Getachew M.pptxPowerPoint Presentation -Getachew M.pptx
PowerPoint Presentation -Getachew M.pptx
 
James.taylor
James.taylorJames.taylor
James.taylor
 
How evaluators score proposals to select the right vendor.
How evaluators score proposals to select the right vendor.How evaluators score proposals to select the right vendor.
How evaluators score proposals to select the right vendor.
 
How To Respond To An RFP Training
How To Respond To An RFP TrainingHow To Respond To An RFP Training
How To Respond To An RFP Training
 
Acquisition Risk Analysis
Acquisition Risk AnalysisAcquisition Risk Analysis
Acquisition Risk Analysis
 
Submitting A Bid
Submitting A BidSubmitting A Bid
Submitting A Bid
 
Supplier Relationship Management
Supplier Relationship ManagementSupplier Relationship Management
Supplier Relationship Management
 
7. past performance_seminar
7. past performance_seminar7. past performance_seminar
7. past performance_seminar
 
Effective Specification Writing
Effective Specification WritingEffective Specification Writing
Effective Specification Writing
 
How to Identify Accurate & Correct Cost Drivers to Capture the Best Pricing
How to Identify Accurate & Correct Cost Drivers to Capture the Best Pricing How to Identify Accurate & Correct Cost Drivers to Capture the Best Pricing
How to Identify Accurate & Correct Cost Drivers to Capture the Best Pricing
 
Rfp final
Rfp finalRfp final
Rfp final
 
Design Build Requirements In Washington State By Michael E Purdy
Design Build Requirements In Washington State   By Michael E PurdyDesign Build Requirements In Washington State   By Michael E Purdy
Design Build Requirements In Washington State By Michael E Purdy
 

Plus de Colorado PTAC

Marketing to Large Prime Contractors
Marketing to Large Prime ContractorsMarketing to Large Prime Contractors
Marketing to Large Prime ContractorsColorado PTAC
 
successful small_busines_panel
successful small_busines_panelsuccessful small_busines_panel
successful small_busines_panelColorado PTAC
 
sca conformance_training
sca conformance_trainingsca conformance_training
sca conformance_trainingColorado PTAC
 
ptac state_&_local_info
ptac state_&_local_infoptac state_&_local_info
ptac state_&_local_infoColorado PTAC
 
the sba_lender's_advantage
the sba_lender's_advantagethe sba_lender's_advantage
the sba_lender's_advantageColorado PTAC
 
corp of_engineer_milcon_opportunities
corp of_engineer_milcon_opportunitiescorp of_engineer_milcon_opportunities
corp of_engineer_milcon_opportunitiesColorado PTAC
 
ptac -_you_won_a_contract...now_what
ptac -_you_won_a_contract...now_whatptac -_you_won_a_contract...now_what
ptac -_you_won_a_contract...now_whatColorado PTAC
 
10. gsa multiple_awards
10. gsa multiple_awards10. gsa multiple_awards
10. gsa multiple_awardsColorado PTAC
 
9. sba important_considerations_in_teaming_arrangement
9. sba important_considerations_in_teaming_arrangement9. sba important_considerations_in_teaming_arrangement
9. sba important_considerations_in_teaming_arrangementColorado PTAC
 
8. colorado ptac_business_development-_marketing-sales
8. colorado ptac_business_development-_marketing-sales8. colorado ptac_business_development-_marketing-sales
8. colorado ptac_business_development-_marketing-salesColorado PTAC
 
6. sba 8(a)-sdb-hubzone
6. sba 8(a)-sdb-hubzone6. sba 8(a)-sdb-hubzone
6. sba 8(a)-sdb-hubzoneColorado PTAC
 
4. contractor performance_assessment_reporting_system
4. contractor performance_assessment_reporting_system4. contractor performance_assessment_reporting_system
4. contractor performance_assessment_reporting_systemColorado PTAC
 
3. dcaa small_business_outreach
3. dcaa small_business_outreach3. dcaa small_business_outreach
3. dcaa small_business_outreachColorado PTAC
 
2. GSA Getting Started in Federal Contracting
2. GSA Getting Started in Federal Contracting2. GSA Getting Started in Federal Contracting
2. GSA Getting Started in Federal ContractingColorado PTAC
 

Plus de Colorado PTAC (14)

Marketing to Large Prime Contractors
Marketing to Large Prime ContractorsMarketing to Large Prime Contractors
Marketing to Large Prime Contractors
 
successful small_busines_panel
successful small_busines_panelsuccessful small_busines_panel
successful small_busines_panel
 
sca conformance_training
sca conformance_trainingsca conformance_training
sca conformance_training
 
ptac state_&_local_info
ptac state_&_local_infoptac state_&_local_info
ptac state_&_local_info
 
the sba_lender's_advantage
the sba_lender's_advantagethe sba_lender's_advantage
the sba_lender's_advantage
 
corp of_engineer_milcon_opportunities
corp of_engineer_milcon_opportunitiescorp of_engineer_milcon_opportunities
corp of_engineer_milcon_opportunities
 
ptac -_you_won_a_contract...now_what
ptac -_you_won_a_contract...now_whatptac -_you_won_a_contract...now_what
ptac -_you_won_a_contract...now_what
 
10. gsa multiple_awards
10. gsa multiple_awards10. gsa multiple_awards
10. gsa multiple_awards
 
9. sba important_considerations_in_teaming_arrangement
9. sba important_considerations_in_teaming_arrangement9. sba important_considerations_in_teaming_arrangement
9. sba important_considerations_in_teaming_arrangement
 
8. colorado ptac_business_development-_marketing-sales
8. colorado ptac_business_development-_marketing-sales8. colorado ptac_business_development-_marketing-sales
8. colorado ptac_business_development-_marketing-sales
 
6. sba 8(a)-sdb-hubzone
6. sba 8(a)-sdb-hubzone6. sba 8(a)-sdb-hubzone
6. sba 8(a)-sdb-hubzone
 
4. contractor performance_assessment_reporting_system
4. contractor performance_assessment_reporting_system4. contractor performance_assessment_reporting_system
4. contractor performance_assessment_reporting_system
 
3. dcaa small_business_outreach
3. dcaa small_business_outreach3. dcaa small_business_outreach
3. dcaa small_business_outreach
 
2. GSA Getting Started in Federal Contracting
2. GSA Getting Started in Federal Contracting2. GSA Getting Started in Federal Contracting
2. GSA Getting Started in Federal Contracting
 

Dernier

Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4JOYLYNSAMANIEGO
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxHumphrey A Beña
 
EMBODO Lesson Plan Grade 9 Law of Sines.docx
EMBODO Lesson Plan Grade 9 Law of Sines.docxEMBODO Lesson Plan Grade 9 Law of Sines.docx
EMBODO Lesson Plan Grade 9 Law of Sines.docxElton John Embodo
 
Integumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptIntegumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptshraddhaparab530
 
Textual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHSTextual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHSMae Pangan
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxAnupkumar Sharma
 
TEACHER REFLECTION FORM (NEW SET........).docx
TEACHER REFLECTION FORM (NEW SET........).docxTEACHER REFLECTION FORM (NEW SET........).docx
TEACHER REFLECTION FORM (NEW SET........).docxruthvilladarez
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4MiaBumagat1
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfVanessa Camilleri
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designMIPLM
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfJemuel Francisco
 
ClimART Action | eTwinning Project
ClimART Action    |    eTwinning ProjectClimART Action    |    eTwinning Project
ClimART Action | eTwinning Projectjordimapav
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management systemChristalin Nelson
 
Activity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationActivity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationRosabel UA
 
The Contemporary World: The Globalization of World Politics
The Contemporary World: The Globalization of World PoliticsThe Contemporary World: The Globalization of World Politics
The Contemporary World: The Globalization of World PoliticsRommel Regala
 
Presentation Activity 2. Unit 3 transv.pptx
Presentation Activity 2. Unit 3 transv.pptxPresentation Activity 2. Unit 3 transv.pptx
Presentation Activity 2. Unit 3 transv.pptxRosabel UA
 
Expanded definition: technical and operational
Expanded definition: technical and operationalExpanded definition: technical and operational
Expanded definition: technical and operationalssuser3e220a
 

Dernier (20)

Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4
 
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptxLEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
LEFT_ON_C'N_ PRELIMS_EL_DORADO_2024.pptx
 
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptxFINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
FINALS_OF_LEFT_ON_C'N_EL_DORADO_2024.pptx
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptxINTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
INTRODUCTION TO CATHOLIC CHRISTOLOGY.pptx
 
EMBODO Lesson Plan Grade 9 Law of Sines.docx
EMBODO Lesson Plan Grade 9 Law of Sines.docxEMBODO Lesson Plan Grade 9 Law of Sines.docx
EMBODO Lesson Plan Grade 9 Law of Sines.docx
 
Integumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.pptIntegumentary System SMP B. Pharm Sem I.ppt
Integumentary System SMP B. Pharm Sem I.ppt
 
Textual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHSTextual Evidence in Reading and Writing of SHS
Textual Evidence in Reading and Writing of SHS
 
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptxMULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
MULTIDISCIPLINRY NATURE OF THE ENVIRONMENTAL STUDIES.pptx
 
TEACHER REFLECTION FORM (NEW SET........).docx
TEACHER REFLECTION FORM (NEW SET........).docxTEACHER REFLECTION FORM (NEW SET........).docx
TEACHER REFLECTION FORM (NEW SET........).docx
 
ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4ANG SEKTOR NG agrikultura.pptx QUARTER 4
ANG SEKTOR NG agrikultura.pptx QUARTER 4
 
ICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdfICS2208 Lecture6 Notes for SL spaces.pdf
ICS2208 Lecture6 Notes for SL spaces.pdf
 
Keynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-designKeynote by Prof. Wurzer at Nordex about IP-design
Keynote by Prof. Wurzer at Nordex about IP-design
 
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdfGrade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
Grade 9 Quarter 4 Dll Grade 9 Quarter 4 DLL.pdf
 
ClimART Action | eTwinning Project
ClimART Action    |    eTwinning ProjectClimART Action    |    eTwinning Project
ClimART Action | eTwinning Project
 
Concurrency Control in Database Management system
Concurrency Control in Database Management systemConcurrency Control in Database Management system
Concurrency Control in Database Management system
 
Activity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translationActivity 2-unit 2-update 2024. English translation
Activity 2-unit 2-update 2024. English translation
 
The Contemporary World: The Globalization of World Politics
The Contemporary World: The Globalization of World PoliticsThe Contemporary World: The Globalization of World Politics
The Contemporary World: The Globalization of World Politics
 
Presentation Activity 2. Unit 3 transv.pptx
Presentation Activity 2. Unit 3 transv.pptxPresentation Activity 2. Unit 3 transv.pptx
Presentation Activity 2. Unit 3 transv.pptx
 
Expanded definition: technical and operational
Expanded definition: technical and operationalExpanded definition: technical and operational
Expanded definition: technical and operational
 

5. source selection_101

  • 1. Source Selection 101 Susan Smith 21CONS Col Tom Walker AFSPC/CX
  • 2. Purpose Insight in how and why the RFP is developed Insight on how the Gov’t evaluates proposals “Demystify” the source selection process: Encourage more participation, especially small businesses Improve offeror’s potential for awards Objective is for the Gov’t to get better proposals
  • 3. Topics RFP Development Process Evaluation Factors/Subfactors Overall Assessment Summary
  • 5.
  • 6. Identify program risks associated with the requirements
  • 7. Analyze risks to determine priority and risk handling approach
  • 8. Develop a mitigation strategy for the highest risks
  • 9.
  • 10. Commercial Contract Format Standard Form (SF) 1449; Any contract documents, exhibits or attachments Solicitation provisions -- 52.212-1, Instructions to Offerors -- Commercial Items and any addendum 52.212-2, Evaluation -- Commercial Items, or other description of evaluation factors for award 52.212-3, Offeror Representations and Certifications -- Commercial Items Contract clauses -- 52.212-4, Contract Terms and Conditions and any addendum 52.212-5, Contract Terms and Conditions Required to Implement Statutes and Executive orders
  • 11. RFP Development Process Sec L or 52.212-1 (What information offeror must submit to be evaluated against Sec M criteria): Sec L and Sec M should track closely Requests only minimum data needed to evaluate proposals Sec M or 52.212-2 (Evaluation Criteria): Most important Represents about 95% of entire acquisition strategy Rules of selection; forms compact with offerors:
  • 12. Evaluation Factors & Subfactors
  • 13.
  • 15. 1: Min. Technically Acceptable (Pass/Fail)
  • 16. 2: Lowest Price among Technically Acceptable
  • 18. 1: Min. Technically Acceptable (Pass/Fail)
  • 19.
  • 20.
  • 21. This evaluation provides for two distinct but related assessments: the Mission Capability Technical Rating and the Mission Capability Risk Rating
  • 22. Evaluation of offeror’s proposal against the Gov.’s minimum performance or capability requirements
  • 23. Proposal risk assessment - weaknesses associated with offeror’s proposed approach
  • 25. Assessment of the degree of confidence the USAF has in an offeror to provide products or services that meet the users’ needs (including cost and schedule) based on demonstrated record of performance
  • 26. Price
  • 27.
  • 28. Mission Capability Risk Ratings High - Likely to cause significant disruption of schedule, increased cost or degradation of performance. Extraordinary contractor emphasis and rigorous government monitoring may be able to overcome difficulties. Moderate - Can potentially cause disruption of schedule, increased cost or degradation of performance. Special contractor emphasis and close government monitoring will likely be able to overcome difficulties.. Low - Has little potential to cause disruption of schedule, increased cost or degradation of performance. Normal contractor effort and normal government monitoring will likely be able to overcome any difficulties
  • 29. Technical Evaluation Process Evaluator’s Process: 1) What is the minimum performance or capability requirement in the Section M evaluation criteria? 2) Does the Offeror’s proposal meet, fail to meet, or exceed that min. requirement? 3) Explain how and where in the Offeror’s proposal it meets, fails to meet, or exceeds. 4) If it exceeds, does it meet the definition of a “strength”? 5) If a “strength,” explain how it is a strength. Listing salient features of proposals as strengths is not enough. Benefits of strengths must be clearly articulated.
  • 30. Technical Evaluation Process Evaluator’s Process: 6) Describe the risk associated with the Offeror’s approach to meeting the Offeror’s proposed requirement (vs the RFP’s minimum requirement). 7) What is the schedule, performance, or cost impact of the risk? 8) Does the risk meet the definition of Weakness or Significant Weakness? How?
  • 31. Past Performance Data Sources Contractor Past Performance Volume Performance Data Other Service/Command/ Agency/Commercial/State or Local Government Questionnaires/ Interviews Past Performance Information Retrieval System (PPIRS)
  • 32. Past Performance Information Past performance information is one indicator of an offeror’s ability to perform the contract successfully Recency, relevancy of the information, and quality in contractor’s performance are considered Offeror’s information on problems encountered on contracts they identify, and the offeror’s corrective actions shall be considered when evaluating the offeror’s past performance
  • 33. Typical Past PerformanceEvaluation Process Offerors requested in solicitation to ID their most relevant contracts with in the past number of years (typically 3) PCAG gathers information on these and others (thru PPIRS, questionnaires, etc.) Contract performance for each is assessed Each are assigned relevancy rating Past Performance assessment is weighted with contract performance from most relevant, most recent contracts One final Past Performance confidence assessment is given for each Offeror
  • 35. Past Performance Relevancy Definitions VERY RELEVANT: Past/present performance programs involved essentially the same magnitude of effort and complexities this solicitation requires RELEVANT: Past/present performance programs involved much of the magnitude of effort and complexities this solicitation requires SOMEWHAT-RELEVANT: Past/present performance programs involved some of the magnitude of effort and complexities this solicitation requires NOT RELEVANT: Past/present performance programs did not involve any magnitude of effort and complexities this solicitation requires
  • 36. Past Performance Quality Definitions BLUE/EXCEPTIONAL - The contractor’s performance meets contractual requirements and exceeds many (requirements) to the Government’s benefit. The contractual performance was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective PURPLE/VERY GOOD- The contractor’s performance meets contractual requirements and exceeds some (requirements) to the Government’s benefit. The contractual performance was accomplished with some minor problems for which corrective actions taken by the contractor were effective GREEN/SATISFACTORY – The contractor’s performance meets contractual requirements. The contractual performance contained some minor problems for which corrective actions taken by the contractor appear or were satisfactory YELLOW/MARGINAL – Performance does not meet some contractual requirements. The contractual performance reflects a serious problem for which the contractor has not yet identified corrective actions or the contractor’s proposed actions appear only marginally effective or were not fully implemented RED/UNSATISFACTORY – Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective NOT APPLICABLE - Unable to provide a score.
  • 38. Factor/Subfactor Order of Importance RFP Section M, Evaluation Factors for Award, SHALL specify order of importance, including subfactors and elements, if used All evaluation factors (other than cost or price), when combined, are: Significantly more important than cost or price; Approximately equal to cost or price; or Significantly less important than cost or price Order of importance is needed when trade-offs are to be used
  • 39. Evaluation Principles Source selection is a process of discrimination: - All offerors come into the process with a clean slate - If source selection is properly structured and conducted: - - Offerors who are too expensive, too risky, don’t understand the requirements, will drop to the bottom - - Offerors who have superior ideas, excellent past performance, low costs will rise to the top - - Offerors who are OK or mediocre, will be in the middle
  • 41. Keys to Successful Source Selection - Gov’t evaluates proposals against the RFP, not against each other - Documents how minimum requirements were met, exceeded, or failed - Risks, weaknesses, strengths, inadequacies must be consistent with RFP requirements - Benefits of strengths and impacts of risks help support trade-off decisions - Gov’t evaluates all proposals consistently - Follow the RFP!