SlideShare une entreprise Scribd logo
1  sur  18
Télécharger pour lire hors ligne
March 4, 2021
Eglinton Crosstown LRT
Construction Liaison Meeting
Brentcliffe Road to Victoria Park Avenue
Section One At-Grade:
Brentcliffe Portal to Sunnybrook Park Stop
SECTION ONE AT-GRADE UPDATE
3
Activity Location Approx. Date & Duration
Brentcliffe Retaining Wall
Construction
North side of Eglinton Ave, east of
Brentcliffe Rd
On hold
North curb concrete pour
Waterproofing
West Don River Bridge
Completed February
Ongoing through March
• Shelter finishing activities
• Platform ramps
• Platform walls
• Handrails
Sunnybrook Park Stop Ongoing through March
Track Works: Overnight OCS wiring
installation
Closures at Leslie Rd March 1 – April 2
Multi-use path construction: backfill
and compaction
Serena Gundy Park – West of Leslie St. Ongoing through Spring 2021
Pedestrian staircase installation
Backfill on Leslie Trail
Eglinton and Leslie St. – South side Ongoing through Spring 2021
Concrete and road works Don Mills Rd & Eglinton Ave E Ongoing through 2021
RETAINING WALL CONSTRUCTION
NORTH SIDE OF EGLINTON
EAST OF BRENTCLIFFE ROAD
4
• This retaining wall is required to hold the
embankment created from the widened Eglinton
Ave.
• Retaining wall construction was put on hold while
temporary slope stabilization work took place
• Slope stabilization work is now complete and
retaining wall construction will resume in March
2021
• Slope restoration design is in review by CTS and
the City of Toronto
TRACK WORK: OCS WIRING INSTALLATION
5
Overnight, March 1 – April 2
RAMP CONSTRUCTION, WEST OF LESLIE STREET
MULTI-USE PATH CONNECTING EGLINTON AVE E TO SERENA GUNDY PARK
6
• Construction activities for path construction include: Excavation, backfill and installation of topsoil
• Landscaping will take place this year as part of the final restoration plan
Mid-July 2020 through Spring 2021
PARKING LOT CLOSURE FOR NEW PEDESTRIAN STAIRCASE INSTALLATION
EGLINTON AVENUE EAST AT LESLIE STREET – SOUTH SIDE
7
• Crews will be installing structural steel to form the new pedestrian staircase. A crane is installed installed at the work zone
to lift materials into place.
• To accommodate these activities, a section of the E.T Seton Park north parking lot will be closed. Access for pedestrian,
cyclists and vehicles will be maintained.
• No changes to traffic on Eglinton Avenue East.
Ongoing until Spring 2021
CONSTRUCTION PROGRESS PHOTOS
8
BACKFILLING
LESLIE TRAIL
CURBS COMPLETE
EAST DON RIVER BRIDGE
Science Centre Station
SCIENCE CENTRE STATION UPDATE
10
Activity Location Approx. Date & Duration
Artwork tiling
Electrical equipment installation
Station box Completed February
Roofing installation Bus terminal Completed February
Wall tiling
Elevator installation
Main entrance Completed February
Ceiling grid & tile installation
Pedestrian tunnel
Bus terminal
Main entrance
Station box
Ongoing through Spring 2021
Wall & floor tiling
Second art wall installation
Mechanical and electrical installation
Station box Ongoing through Spring 2021
Drywall installation
Wall & floor tiling
Sliding door installation
Bus terminal Ongoing through Spring 2021
Electrical finishes
Floor tiling
Sliding door installation
Main entrance Ongoing through Spring 2021
SCIENCE CENTRE TRAFFIC CONFIGURATION
11
December 6, 2020 for approx. eight months
CONSTRUCTION PROGRESS PHOTOS
12
STAIR TILE AND RAILING
INSTALLATION
CONCOURSE LEVEL
ARCHITECTURAL FINISHES
PEDESTRIAN TUNNEL
CONSTRUCTION PROGRESS PHOTOS
13
GLASS RAILING INSTALLATION
MAIN ENTRANCE
LIGHT PORTAL INSTALLATION
BUS TERMINAL
Section Two At-Grade
Aga Khan Park & Museum Stop to O’Connor Stop
SECTION TWO AT-GRADE UPDATE
15
Activity Location Approx. Date & Duration
• Shelter finishing activities
• Platform curbs
Aga Khan Park & Museum Stop Ongoing through March
Retaining walls Swift Drive & Eglinton Ave E Ongoing through March (North)
Road widening Swift Drive to Bermondsey Road Ongoing through mid-March
Barrier curbs East Don River Bridge Ongoing through March
• Shelter structure installation
• Platform curbs
• Handrails
• North sidewalk
Sloane Stop
Completed February
Ongoing through March
Track Works: Overnight OCS wiring
installation
Closures at Sloane Ave March 1 – April 2
• Shelter finishing activities
• Platform curbs
• Platform ramps
O’Connor Stop Ongoing through March
TRACK WORK: OCS WIRING INSTALLATION
16
Overnight, March 1 – April 2
CONSTRUCTION PROGRESS PHOTOS
17
SHELTER INSTALLATION
SLOANE STOP
HANDRAILS INSTALLATION
SLOANE STOP
Brentcliffe to Victoria Park - March 4, 2021

Contenu connexe

Tendances

Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingCrosstown TO
 
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...Crosstown TO
 
Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021Crosstown TO
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)Crosstown TO
 
Pharmacy kennedy clc meeting - deck - march 26,2019
Pharmacy   kennedy clc meeting - deck - march 26,2019Pharmacy   kennedy clc meeting - deck - march 26,2019
Pharmacy kennedy clc meeting - deck - march 26,2019Crosstown TO
 
Spring Virtual Open - Central West - April 21, 2021
Spring Virtual Open - Central West - April 21, 2021Spring Virtual Open - Central West - April 21, 2021
Spring Virtual Open - Central West - April 21, 2021Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingCrosstown TO
 
CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)Crosstown TO
 
CLC Pharmacy to Kennedy 2021
CLC Pharmacy to Kennedy 2021CLC Pharmacy to Kennedy 2021
CLC Pharmacy to Kennedy 2021Crosstown TO
 
Pharmacy to Kennedy CLC - March 2020
Pharmacy to Kennedy CLC - March 2020Pharmacy to Kennedy CLC - March 2020
Pharmacy to Kennedy CLC - March 2020Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Crosstown TO
 
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018 Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018 Crosstown TO
 
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsFall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsCrosstown TO
 
Eastern Virtual Open House Deck
Eastern Virtual Open House DeckEastern Virtual Open House Deck
Eastern Virtual Open House DeckCrosstown TO
 
Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Crosstown TO
 
Fall Central Open House - Oct 21
Fall Central Open House  - Oct 21Fall Central Open House  - Oct 21
Fall Central Open House - Oct 21Crosstown TO
 
Eglinton & Mount Pleasant CLC - 14July2021
Eglinton & Mount Pleasant CLC - 14July2021Eglinton & Mount Pleasant CLC - 14July2021
Eglinton & Mount Pleasant CLC - 14July2021Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020Crosstown TO
 

Tendances (20)

Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
 
Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Pharmacy kennedy clc meeting - deck - march 26,2019
Pharmacy   kennedy clc meeting - deck - march 26,2019Pharmacy   kennedy clc meeting - deck - march 26,2019
Pharmacy kennedy clc meeting - deck - march 26,2019
 
Spring Virtual Open - Central West - April 21, 2021
Spring Virtual Open - Central West - April 21, 2021Spring Virtual Open - Central West - April 21, 2021
Spring Virtual Open - Central West - April 21, 2021
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)CLC pharmacy to Kennedy (Nov24)
CLC pharmacy to Kennedy (Nov24)
 
CLC Pharmacy to Kennedy 2021
CLC Pharmacy to Kennedy 2021CLC Pharmacy to Kennedy 2021
CLC Pharmacy to Kennedy 2021
 
Pharmacy to Kennedy CLC - March 2020
Pharmacy to Kennedy CLC - March 2020Pharmacy to Kennedy CLC - March 2020
Pharmacy to Kennedy CLC - March 2020
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
 
Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021
 
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018 Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
 
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsFall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
 
Eastern Virtual Open House Deck
Eastern Virtual Open House DeckEastern Virtual Open House Deck
Eastern Virtual Open House Deck
 
Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018
 
Fall Central Open House - Oct 21
Fall Central Open House  - Oct 21Fall Central Open House  - Oct 21
Fall Central Open House - Oct 21
 
Eglinton & Mount Pleasant CLC - 14July2021
Eglinton & Mount Pleasant CLC - 14July2021Eglinton & Mount Pleasant CLC - 14July2021
Eglinton & Mount Pleasant CLC - 14July2021
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
Pharmacy to Kennedy Construction Liaison Committee Meeting - May 2020, 2020
 

Similaire à Brentcliffe to Victoria Park - March 4, 2021

Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021Crosstown TO
 
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021Crosstown TO
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingCrosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)Crosstown TO
 
Fairbank-Oakwood Construction Update - March 2021
Fairbank-Oakwood Construction Update - March 2021Fairbank-Oakwood Construction Update - March 2021
Fairbank-Oakwood Construction Update - March 2021Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Crosstown TO
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingCrosstown TO
 
Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021Crosstown TO
 
Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Crosstown TO
 
Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)Crosstown TO
 
Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021Crosstown TO
 
Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingCrosstown TO
 
Eglinton - Mount Pleasant CLC 13 Jan 2021
Eglinton - Mount Pleasant CLC 13 Jan 2021Eglinton - Mount Pleasant CLC 13 Jan 2021
Eglinton - Mount Pleasant CLC 13 Jan 2021Crosstown TO
 
Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021Crosstown TO
 
Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)Crosstown TO
 
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021 Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021 Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020Crosstown TO
 

Similaire à Brentcliffe to Victoria Park - March 4, 2021 (20)

Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021Brentcliffe to Victoria Park - CLC construction update January 2021
Brentcliffe to Victoria Park - CLC construction update January 2021
 
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
Brentcliffe-Victoria Park CLC Meeting - May 6, 2021
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC Meeting
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
Fairbank-Oakwood Construction Update - March 2021
Fairbank-Oakwood Construction Update - March 2021Fairbank-Oakwood Construction Update - March 2021
Fairbank-Oakwood Construction Update - March 2021
 
Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC Meeting
 
Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021
 
Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021
 
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021
 
Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)
 
Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)
 
Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021Avenue & Chaplin CLC - Construction Update: July 7, 2021
Avenue & Chaplin CLC - Construction Update: July 7, 2021
 
Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Eglinton - Mount Pleasant CLC 13 Jan 2021
Eglinton - Mount Pleasant CLC 13 Jan 2021Eglinton - Mount Pleasant CLC 13 Jan 2021
Eglinton - Mount Pleasant CLC 13 Jan 2021
 
Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021
 
Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)
 
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021 Brentcliffe to Victoria Park CLC Meeting -  Presentation - November 4, 2021
Brentcliffe to Victoria Park CLC Meeting - Presentation - November 4, 2021
 
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
 

Plus de Crosstown TO

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfCrosstown TO
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023Crosstown TO
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Crosstown TO
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfCrosstown TO
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCrosstown TO
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxCrosstown TO
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxCrosstown TO
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfCrosstown TO
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
 

Plus de Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 

Dernier

2024 ECOSOC YOUTH FORUM -logistical information - United Nations Economic an...
2024 ECOSOC YOUTH FORUM -logistical information -  United Nations Economic an...2024 ECOSOC YOUTH FORUM -logistical information -  United Nations Economic an...
2024 ECOSOC YOUTH FORUM -logistical information - United Nations Economic an...Christina Parmionova
 
2024: The FAR, Federal Acquisition Regulations - Part 24
2024: The FAR, Federal Acquisition Regulations - Part 242024: The FAR, Federal Acquisition Regulations - Part 24
2024: The FAR, Federal Acquisition Regulations - Part 24JSchaus & Associates
 
GOVERNMENT OF NCT OF DELHI DIRECTORATE OF EDUCATION
GOVERNMENT OF NCT OF DELHI DIRECTORATE OF EDUCATIONGOVERNMENT OF NCT OF DELHI DIRECTORATE OF EDUCATION
GOVERNMENT OF NCT OF DELHI DIRECTORATE OF EDUCATIONShivamShukla147857
 
Item # 6 - TBG Partners Landscape Architectural Design Services
Item # 6 - TBG Partners Landscape Architectural Design ServicesItem # 6 - TBG Partners Landscape Architectural Design Services
Item # 6 - TBG Partners Landscape Architectural Design Servicesahcitycouncil
 
Digital Transformation of the Heritage Sector and its Practical Implications
Digital Transformation of the Heritage Sector and its Practical ImplicationsDigital Transformation of the Heritage Sector and its Practical Implications
Digital Transformation of the Heritage Sector and its Practical ImplicationsBeat Estermann
 
Item # 4&5 - 415 & 423 Evans Ave. Replat
Item # 4&5 - 415 & 423 Evans Ave. ReplatItem # 4&5 - 415 & 423 Evans Ave. Replat
Item # 4&5 - 415 & 423 Evans Ave. Replatahcitycouncil
 
UN DESA: Finance for Development 2024 Report
UN DESA: Finance for Development 2024 ReportUN DESA: Finance for Development 2024 Report
UN DESA: Finance for Development 2024 ReportEnergy for One World
 
Madison Cat Project Foster Training - Lesson 1
Madison Cat Project Foster Training - Lesson 1Madison Cat Project Foster Training - Lesson 1
Madison Cat Project Foster Training - Lesson 1KelleyWasmund
 
1- Phase 8 Hope For Venezuelan Refugees Soup Program-Periods 4-6.pdf
1- Phase 8 Hope For Venezuelan Refugees Soup Program-Periods 4-6.pdf1- Phase 8 Hope For Venezuelan Refugees Soup Program-Periods 4-6.pdf
1- Phase 8 Hope For Venezuelan Refugees Soup Program-Periods 4-6.pdfCristal Montañéz
 
2023 Barangay Officials pre assumption PPT.pptx
2023 Barangay Officials pre assumption PPT.pptx2023 Barangay Officials pre assumption PPT.pptx
2023 Barangay Officials pre assumption PPT.pptxMariaFionaDuranMerqu
 
In War and conflict, health workers, facilities and supplies are off limits.
In War and conflict, health workers, facilities and supplies are off limits.In War and conflict, health workers, facilities and supplies are off limits.
In War and conflict, health workers, facilities and supplies are off limits.Christina Parmionova
 
Build Tomorrow’s India Today By Making Charity For Poor Students
Build Tomorrow’s India Today By Making Charity For Poor StudentsBuild Tomorrow’s India Today By Making Charity For Poor Students
Build Tomorrow’s India Today By Making Charity For Poor StudentsSERUDS INDIA
 
Actions to take at the global, national and local levels to realize the right...
Actions to take at the global, national and local levels to realize the right...Actions to take at the global, national and local levels to realize the right...
Actions to take at the global, national and local levels to realize the right...Christina Parmionova
 
ECOSOC YOUTH FORUM 2024 - Side Events Schedule -17 April.
ECOSOC YOUTH FORUM 2024 - Side Events Schedule -17 April.ECOSOC YOUTH FORUM 2024 - Side Events Schedule -17 April.
ECOSOC YOUTH FORUM 2024 - Side Events Schedule -17 April.Christina Parmionova
 
Youth shaping sustainable and innovative solution - Reinforcing the 2030 agen...
Youth shaping sustainable and innovative solution - Reinforcing the 2030 agen...Youth shaping sustainable and innovative solution - Reinforcing the 2030 agen...
Youth shaping sustainable and innovative solution - Reinforcing the 2030 agen...Christina Parmionova
 
Item # 7 - Demolition & Replacement Structure Processes
Item # 7 - Demolition & Replacement Structure ProcessesItem # 7 - Demolition & Replacement Structure Processes
Item # 7 - Demolition & Replacement Structure Processesahcitycouncil
 
Phase 8 Hope For Venezuelan Refugees Soup Meal Program-Periods 4-6.
Phase 8 Hope For Venezuelan Refugees Soup Meal Program-Periods 4-6.Phase 8 Hope For Venezuelan Refugees Soup Meal Program-Periods 4-6.
Phase 8 Hope For Venezuelan Refugees Soup Meal Program-Periods 4-6.Cristal Montañéz
 
Madison Cat Project - Foster Training: Lesson 1
Madison Cat Project - Foster Training: Lesson 1Madison Cat Project - Foster Training: Lesson 1
Madison Cat Project - Foster Training: Lesson 1KelleyWasmund
 
2024: The FAR, Federal Acquisition Regulations - Part 23
2024: The FAR, Federal Acquisition Regulations - Part 232024: The FAR, Federal Acquisition Regulations - Part 23
2024: The FAR, Federal Acquisition Regulations - Part 23JSchaus & Associates
 

Dernier (20)

2024 ECOSOC YOUTH FORUM -logistical information - United Nations Economic an...
2024 ECOSOC YOUTH FORUM -logistical information -  United Nations Economic an...2024 ECOSOC YOUTH FORUM -logistical information -  United Nations Economic an...
2024 ECOSOC YOUTH FORUM -logistical information - United Nations Economic an...
 
2024: The FAR, Federal Acquisition Regulations - Part 24
2024: The FAR, Federal Acquisition Regulations - Part 242024: The FAR, Federal Acquisition Regulations - Part 24
2024: The FAR, Federal Acquisition Regulations - Part 24
 
GOVERNMENT OF NCT OF DELHI DIRECTORATE OF EDUCATION
GOVERNMENT OF NCT OF DELHI DIRECTORATE OF EDUCATIONGOVERNMENT OF NCT OF DELHI DIRECTORATE OF EDUCATION
GOVERNMENT OF NCT OF DELHI DIRECTORATE OF EDUCATION
 
Item # 6 - TBG Partners Landscape Architectural Design Services
Item # 6 - TBG Partners Landscape Architectural Design ServicesItem # 6 - TBG Partners Landscape Architectural Design Services
Item # 6 - TBG Partners Landscape Architectural Design Services
 
Digital Transformation of the Heritage Sector and its Practical Implications
Digital Transformation of the Heritage Sector and its Practical ImplicationsDigital Transformation of the Heritage Sector and its Practical Implications
Digital Transformation of the Heritage Sector and its Practical Implications
 
Item # 4&5 - 415 & 423 Evans Ave. Replat
Item # 4&5 - 415 & 423 Evans Ave. ReplatItem # 4&5 - 415 & 423 Evans Ave. Replat
Item # 4&5 - 415 & 423 Evans Ave. Replat
 
UN DESA: Finance for Development 2024 Report
UN DESA: Finance for Development 2024 ReportUN DESA: Finance for Development 2024 Report
UN DESA: Finance for Development 2024 Report
 
Madison Cat Project Foster Training - Lesson 1
Madison Cat Project Foster Training - Lesson 1Madison Cat Project Foster Training - Lesson 1
Madison Cat Project Foster Training - Lesson 1
 
1- Phase 8 Hope For Venezuelan Refugees Soup Program-Periods 4-6.pdf
1- Phase 8 Hope For Venezuelan Refugees Soup Program-Periods 4-6.pdf1- Phase 8 Hope For Venezuelan Refugees Soup Program-Periods 4-6.pdf
1- Phase 8 Hope For Venezuelan Refugees Soup Program-Periods 4-6.pdf
 
2023 Barangay Officials pre assumption PPT.pptx
2023 Barangay Officials pre assumption PPT.pptx2023 Barangay Officials pre assumption PPT.pptx
2023 Barangay Officials pre assumption PPT.pptx
 
In War and conflict, health workers, facilities and supplies are off limits.
In War and conflict, health workers, facilities and supplies are off limits.In War and conflict, health workers, facilities and supplies are off limits.
In War and conflict, health workers, facilities and supplies are off limits.
 
Housing For All - Fair Housing Choice Report
Housing For All - Fair Housing Choice ReportHousing For All - Fair Housing Choice Report
Housing For All - Fair Housing Choice Report
 
Build Tomorrow’s India Today By Making Charity For Poor Students
Build Tomorrow’s India Today By Making Charity For Poor StudentsBuild Tomorrow’s India Today By Making Charity For Poor Students
Build Tomorrow’s India Today By Making Charity For Poor Students
 
Actions to take at the global, national and local levels to realize the right...
Actions to take at the global, national and local levels to realize the right...Actions to take at the global, national and local levels to realize the right...
Actions to take at the global, national and local levels to realize the right...
 
ECOSOC YOUTH FORUM 2024 - Side Events Schedule -17 April.
ECOSOC YOUTH FORUM 2024 - Side Events Schedule -17 April.ECOSOC YOUTH FORUM 2024 - Side Events Schedule -17 April.
ECOSOC YOUTH FORUM 2024 - Side Events Schedule -17 April.
 
Youth shaping sustainable and innovative solution - Reinforcing the 2030 agen...
Youth shaping sustainable and innovative solution - Reinforcing the 2030 agen...Youth shaping sustainable and innovative solution - Reinforcing the 2030 agen...
Youth shaping sustainable and innovative solution - Reinforcing the 2030 agen...
 
Item # 7 - Demolition & Replacement Structure Processes
Item # 7 - Demolition & Replacement Structure ProcessesItem # 7 - Demolition & Replacement Structure Processes
Item # 7 - Demolition & Replacement Structure Processes
 
Phase 8 Hope For Venezuelan Refugees Soup Meal Program-Periods 4-6.
Phase 8 Hope For Venezuelan Refugees Soup Meal Program-Periods 4-6.Phase 8 Hope For Venezuelan Refugees Soup Meal Program-Periods 4-6.
Phase 8 Hope For Venezuelan Refugees Soup Meal Program-Periods 4-6.
 
Madison Cat Project - Foster Training: Lesson 1
Madison Cat Project - Foster Training: Lesson 1Madison Cat Project - Foster Training: Lesson 1
Madison Cat Project - Foster Training: Lesson 1
 
2024: The FAR, Federal Acquisition Regulations - Part 23
2024: The FAR, Federal Acquisition Regulations - Part 232024: The FAR, Federal Acquisition Regulations - Part 23
2024: The FAR, Federal Acquisition Regulations - Part 23
 

Brentcliffe to Victoria Park - March 4, 2021

  • 1. March 4, 2021 Eglinton Crosstown LRT Construction Liaison Meeting Brentcliffe Road to Victoria Park Avenue
  • 2. Section One At-Grade: Brentcliffe Portal to Sunnybrook Park Stop
  • 3. SECTION ONE AT-GRADE UPDATE 3 Activity Location Approx. Date & Duration Brentcliffe Retaining Wall Construction North side of Eglinton Ave, east of Brentcliffe Rd On hold North curb concrete pour Waterproofing West Don River Bridge Completed February Ongoing through March • Shelter finishing activities • Platform ramps • Platform walls • Handrails Sunnybrook Park Stop Ongoing through March Track Works: Overnight OCS wiring installation Closures at Leslie Rd March 1 – April 2 Multi-use path construction: backfill and compaction Serena Gundy Park – West of Leslie St. Ongoing through Spring 2021 Pedestrian staircase installation Backfill on Leslie Trail Eglinton and Leslie St. – South side Ongoing through Spring 2021 Concrete and road works Don Mills Rd & Eglinton Ave E Ongoing through 2021
  • 4. RETAINING WALL CONSTRUCTION NORTH SIDE OF EGLINTON EAST OF BRENTCLIFFE ROAD 4 • This retaining wall is required to hold the embankment created from the widened Eglinton Ave. • Retaining wall construction was put on hold while temporary slope stabilization work took place • Slope stabilization work is now complete and retaining wall construction will resume in March 2021 • Slope restoration design is in review by CTS and the City of Toronto
  • 5. TRACK WORK: OCS WIRING INSTALLATION 5 Overnight, March 1 – April 2
  • 6. RAMP CONSTRUCTION, WEST OF LESLIE STREET MULTI-USE PATH CONNECTING EGLINTON AVE E TO SERENA GUNDY PARK 6 • Construction activities for path construction include: Excavation, backfill and installation of topsoil • Landscaping will take place this year as part of the final restoration plan Mid-July 2020 through Spring 2021
  • 7. PARKING LOT CLOSURE FOR NEW PEDESTRIAN STAIRCASE INSTALLATION EGLINTON AVENUE EAST AT LESLIE STREET – SOUTH SIDE 7 • Crews will be installing structural steel to form the new pedestrian staircase. A crane is installed installed at the work zone to lift materials into place. • To accommodate these activities, a section of the E.T Seton Park north parking lot will be closed. Access for pedestrian, cyclists and vehicles will be maintained. • No changes to traffic on Eglinton Avenue East. Ongoing until Spring 2021
  • 8. CONSTRUCTION PROGRESS PHOTOS 8 BACKFILLING LESLIE TRAIL CURBS COMPLETE EAST DON RIVER BRIDGE
  • 10. SCIENCE CENTRE STATION UPDATE 10 Activity Location Approx. Date & Duration Artwork tiling Electrical equipment installation Station box Completed February Roofing installation Bus terminal Completed February Wall tiling Elevator installation Main entrance Completed February Ceiling grid & tile installation Pedestrian tunnel Bus terminal Main entrance Station box Ongoing through Spring 2021 Wall & floor tiling Second art wall installation Mechanical and electrical installation Station box Ongoing through Spring 2021 Drywall installation Wall & floor tiling Sliding door installation Bus terminal Ongoing through Spring 2021 Electrical finishes Floor tiling Sliding door installation Main entrance Ongoing through Spring 2021
  • 11. SCIENCE CENTRE TRAFFIC CONFIGURATION 11 December 6, 2020 for approx. eight months
  • 12. CONSTRUCTION PROGRESS PHOTOS 12 STAIR TILE AND RAILING INSTALLATION CONCOURSE LEVEL ARCHITECTURAL FINISHES PEDESTRIAN TUNNEL
  • 13. CONSTRUCTION PROGRESS PHOTOS 13 GLASS RAILING INSTALLATION MAIN ENTRANCE LIGHT PORTAL INSTALLATION BUS TERMINAL
  • 14. Section Two At-Grade Aga Khan Park & Museum Stop to O’Connor Stop
  • 15. SECTION TWO AT-GRADE UPDATE 15 Activity Location Approx. Date & Duration • Shelter finishing activities • Platform curbs Aga Khan Park & Museum Stop Ongoing through March Retaining walls Swift Drive & Eglinton Ave E Ongoing through March (North) Road widening Swift Drive to Bermondsey Road Ongoing through mid-March Barrier curbs East Don River Bridge Ongoing through March • Shelter structure installation • Platform curbs • Handrails • North sidewalk Sloane Stop Completed February Ongoing through March Track Works: Overnight OCS wiring installation Closures at Sloane Ave March 1 – April 2 • Shelter finishing activities • Platform curbs • Platform ramps O’Connor Stop Ongoing through March
  • 16. TRACK WORK: OCS WIRING INSTALLATION 16 Overnight, March 1 – April 2
  • 17. CONSTRUCTION PROGRESS PHOTOS 17 SHELTER INSTALLATION SLOANE STOP HANDRAILS INSTALLATION SLOANE STOP