  1. 1. CROSSTOWN LRT CLC Meeting Brentcliffe to Victoria Park Stop March 2020
  2. 2. 2 Section 1 At-Grade Updates Brentcliffe Portal to Sunnybrook Park Stop Brentcliffe Portal 2
  3. 3. 3 Extended Construction Hours Continue • Starting November 11, 2019, crews will work extended hours to accelerate construction (4:30 a.m. – 11:00 p.m.). Construction activities may include, guideway construction, road widening, retaining wall construction, hydro utility installation and bridge rehabilitation. • The period between 4:30 a.m. – 7:00 a.m. will be primarily used to perform less noisy work, such as site and traffic staging, preparatory works, excavation, concrete pours, deliveries and hauling What to Expect • Daily temporary lane closures along Eglinton Ave E and cross streets between theWest Don River Bridge andVictoria Park Ave will be in effect to facilitate construction and deliveries • Short-term pedestrian rerouting as well as temporary sidewalk and crosswalk closures may be required to safely facilitate construction • Noise from construction activities and equipment, such as removal of asphalt, excavation, trucks and generators can be expected • Site lighting can be expected
  4. 4. 4 Brentcliffe Portal to Leslie Street December 19 through to Summer 2020 • The configuration will accommodate: • Guideway construction on the West Don River Bridge and portal. • Retaining wall construction on the north side of Eglinton Avenue East. • The pedestrian sidewalk will be available on the south side of Eglington Avenue East only.
  5. 5. 5 Sunnybrook Park Stop (Leslie Street) Ongoing Activities • Concrete works are ongoing for the new pedestrian staircase on the south side of Eglinton at Leslie began January 2020. Construction will continue through to spring 2020. • Guideway construction will continue east and west of the intersection. • Rebar installation for the track slab is ongoing from the West Don River Bridge to the Leslie intersection. • Formwork installation is taking place at the Sunnybrook Park stop. • Guideway construction and trackwork is advancing between the Leslie St. intersection to Celestica Bridge. DUCT BANK EXCAVATION AT WEST DON RIVER BRIDGE LESLIE STREET TO CP BRIDGE
  6. 6. 6 Science Centre Station Don Mills Road
  7. 7. 7 Science Centre Station Traffic Confuguration Decking Removal February 7 2020 for approximately 2 months • Science Centre Station has advanced to a state to allow the temporary traffic deck to be removed. • The removal will take place in two stages. The second stage on the opposite side will take place early April. • The road will be restored to an improved surface. • North south traffic will be reduced to two lanes and aligned to the right side of Don Mills Road. • Northbound, southbound and eastbound left turns will be restricted. Bus Detours: • Route 34C diverting to Ferrand and Rochefort.
  8. 8. 8 Science Centre Station Construction Activities Area Current Activities Station Box • Backfill of the roof slab is complete • Interior works are ongoing • Formwork and rebar installations are in progress • Masonry works in progress • All escalators are installed at the Station Box Main Entrance • Glazing is ongoing • Installation of architectural precast curb is in progress • Painting is complete in the elevator shaft Pedestrian Tunnel/Bus Terminal • All concrete are rebar works are complete at the bus terminal • Installation of mechanical, plumbing and fire protection is ongoing at the bus terminal • Ceiling is in progress at the pedestrian tunnel and the architectural curb is complete Portals • Waterproofing is ongoing • Installation of lighting fixtures is ongoing at the west and east portals • Installation of mechanical, plumbing and fire protection is ongoing at the east portal
  9. 9. 9 Science Centre Station Progress Photos GLAZING AT THE MAIN ENTRANCE ESCALATOR INSTALLATION AT THE STATION BOX REBAR INSTALLATION OF STAIRWELL AT THE STATION BOX ELECTRICAL WORKS AT THE STATION BOX
  10. 10. 10 Section 2 At-Grade Updates Aga Khan Park & Museum Stop to O’Connor Stop
  11. 11. 11 Section 2 At-Grade Ongoing Construction Activities Area Activities Date East Don River Bridge • Construction of plinths Early March 2020 Wynford Bridge • Ductbank installation under the deck Early March 2020 Wilson Brook Culvert • East wing wall construction • Parapet Wall • Creek realignment Ongoing Early March 2020 Spring 2020 Swift to Bermondsey • Guideway retaining wall • Guideway construction Early March 2020 East Don River Bridge to Swift • Guideway construction Ongoing Bermondsey to Wilson Brook Culvert • Guideway construction Ongoing Wilson Brook Culvert to Victoria Park • Guideway construction Ongoing Aga Khan Stop • Excavation, structural and wet utilities Ongoing Wynford Stop • Excavation, structural and wet utilities Ongoing
  12. 12. 12 Aga Khan Park Stop Traffic Configuration Current through 2020
  13. 13. 13 Wynford Stop (Wynford Drive) Current through 2020
  14. 14. 14 Credit Union and Swift Drive Traffic Configuration Traffic movements reflect the permanent intersection configuration. The westbound left turn movement will be permanently prohibited. Guideway construction will continue east and west of the intersection. Permanent Configuration
  15. 15. 15 Sloane Stop Traffic Configuration Mid December 2019 through to spring 2020  Guideway construction continues east and west of the Sloane/Bermondsey intersection. o Concrete barriers may be temporarily removed for construction vehicles entering and exiting the guideway work zone. o Temporary lane closures may be required.
  16. 16. 16 Progress Photos DELIVERY OF TPSS 10 WILSON BROOK CULVERT TRACK WORK AT CELESTICA BRIDGE DELIVERY OF TPSS 10
  17. 17. 17 416-782-8118 or 416-482-7411 24 hours/7days a week www.thecrosstown.ca crosstown@metrolinx.com facebook.com/thecrosstown twitter.com/crosstownTO instagram.com/eglinton_crosstown Crosstown West Office 1848 Eglinton Ave W (at Dufferin) Crosstown East Office 660 Eglinton Ave E (at Bayview) Stay in Touch

×