  1. 1. July 29, 2020 Eglinton Crosstown-LRT Cedarvale – Forest Hill CLC
  2. 2. Cedarvale Station
  3. 3. CEDARVALE STATION UPDATE 3CEDARVALE –FOREST HILL CLC Activity Location Approx. Date & Duration Deep Excavation & Tieback Installation Station’s Main Entrance Underway through to late-August 2020; 6:00 a.m. – 11:00 p.m. Major Concrete Pours Throughout all station areas Underway throughout 2020 into 2021 Starting as early as 5:00 a.m. ranging from 12-18 hours Geotechnical Monitoring Eastbound curb lane of Eglinton Ave between Winnett Ave and Allen Rd N January 2020 – September 2020 Tuesdays between 11:00 a.m. – 2:00 p.m. Pedestrian Tunnel Construction Area surrounding Eglinton West Station Underway through to 2021 Monday – Saturday; 6:00 a.m. – 2:00 a.m. Eglinton West Station Support of Excavation and Underpinning Works Eglinton West Station Underway through 2020 Monday – Saturday; 6:00 a.m. – 5:00 p.m. Eglinton West Station Bus Loop Closure for Roof Construction Eglinton West Station Underway – late Summer 2020 Temporary Traffic Deck Removal, Roof Construction, and Permanent Utility Installation Eglinton Avenue West March 29, 2020 – early 2021
  4. 4. UPCOMING CONCRETE POUR AT CEDARVALE STATION 4 From Friday July 31 – Saturday August 1, 2020 crews at Cedarvale Station will perform a 36-hour long concrete pour on the north side of Eglinton Avenue, between Allen Rd S and Park Hill Rd. • The concrete will form the permanent base for the track slab that the future LRT will travel on. • Over 1200m3 of concrete will be poured. • To ensure the integrity and continuity of the pour, work will start as early as 4:00 a.m. on Friday July 31 and continue through to 12:00 p.m. on Saturday August 1. • To perform this work safely, Eglinton Avenue will be reduced to one lane in each direction, while the pour takes place. • No changes to pedestrian routes are expected. • Access to Eglinton Avenue West Station and TTC will be maintained at all times. • Overnight noise from construction activities can be expected, while the pour takes place. CEDARVALE –FOREST HILL CLC PREVIOUS CONCRETE POUR – CEDARVALE STATION
  5. 5. CURRENT TRAFFIC CONFIGURATION 5 Through late summer 2020 CEDARVALE –FOREST HILL CLC
  6. 6. CONCRETE POUR TRAFFIC CONFIGURATION 6 Friday July 31 – Saturday August 1, 2020 CEDARVALE –FOREST HILL CLC
  7. 7. UPDATE RESUMPTION OF EXTENDED CONSTRUCTION HOURS 7 • In spring 2019, crews began working extended construction hours to accelerate construction of Cedarvale Station • In July 2020 crews will resume extended construction hours to complete construction of the pedestrian tunnels in the area surrounding Eglinton West Station. • The tunnels will connect TTC’s Eglinton West Subway Station to the future Cedarvale LRT Station. • This work will take place Monday – Saturday from 6:00 a.m. – 2:00 a.m. • Construction activities include: • Excavation (hauling will continue to take place between 6:00 a.m. – 11:00 p.m. only) • Support of Excavation Works • Stockpiling of excavated materials • Welding • Concrete works • Site-level mitigation measures are in place to minimize disruption. CENTRAL WEST WORKS MONTHLY MEETING RENDERING CEDARVALE STATION
  8. 8. CONSTRUCTION PROGRESS PHOTOS 8CEDARVALE –FOREST HILL CLC DECKING REMOVAL & STEEL INSTALLATION – EAST SIDE OF THE BUS LOOP REBAR & FORMWORK INSTALLATION - STATION BOX
  9. 9. Forest Hill Station
  10. 10. FOREST HILL STATION UPDATE 10CENTRAL WEST WORKS MONTHLY MEETING Activity Location Approx. Date & Duration Deep Excavation Beneath the station roof from the Main Entrance Underway through summer 2020 Main Entrance Construction Excavation, installation of struts, lagging and tie-backs Northeast corner of Bathurst St and Eglinton Ave Underway through 2020 Secondary Entrance Construction Formwork, rebar, conduit installation and beam excavation North side of Eglinton Ave, west of Bathurst St Underway through fall 2020 Station Box Construction Waterproofing, shotcrete application and duct bank construction Beneath Eglinton Ave Underway through 2020 Concrete Pours Secondary Entrance • Friday August 14, 2020 at 5:00 a.m. for approx. 12 hours • Two pours in late August 2020 (dates TBD) Resumption of Extended Construction Hours for Installation of Structural Steel and Pre-cast Panels Secondary Entrance August – October 2020 (Hours of work TBC)
  11. 11. CURRENT TRAFFIC CONFIGURATION 11CENTRAL WEST WORKS MONTHLY MEETING Until late summer 2020
  12. 12. CONSTRUCTION PROGRESS PHOTOS 12CENTRAL WEST WORKS MONTHLY MEETING TIE-BACK INSTALLATION MAIN ENTRANCE WATERPROOFING STATION BOX

×