  1. 1. September 3, 2020 Eglinton Crosstown LRT Construction Liaison Meeting Brentcliffe Road to Victoria Park Avenue
  2. 2. Section One At-Grade: Brentcliffe Portal to Sunnybrook Park Stop
  3. 3. SECTION ONE AT-GRADE UPDATE 3 Activity Location Approx. Date & Duration Road widening and reconstruction, final curbs and sidewalks. Brentcliffe Road to East Portal – North Side Early August 2020 for to mid-September 2020 Boulevard works, final curbs and sidewalks. West of Brentcliffe Road– South Side September 20, 2020 for two weeks Clearing and grubbing complete. Excavation and block installation has started. Retaining Wall (East of Brentcliffe Road) Early August – December 2020 Multi-use path construction Serena Gundy Park – West of Leslie St. Mid-July – December 2020 Construction of duct bank under bridge West Don River Bridge Early September for one month Bridge Rehabilitation CP Bridge, east of Leslie St. August 24 for 13 weeks ROAD WORKS - EAST OF BRENTCLIFFE, NORTH SIDE
  4. 4. BRENTCLIFFE PORTAL TO LESLIE STREET 4 August 7, 2020 through to September 20, 2020 • The pedestrian sidewalk will remain on the south side of Eglington Avenue East only. • The traffic configuration will accommodate road works on the north side of Eglinton Avenue East between Brentcliffe Road and the east portal. • Construction activities include: • Wet utility installations • Saw cutting and concrete removals • Excavation • Backfill • Compaction • Curb and sidewalk construction • Asphalt and final paving
  5. 5. BRENTCLIFFE PORTAL TO LESLIE STREET 5 September 20, 2020 for two weeks • The pedestrian sidewalk will remain on the south side of Eglington Avenue East only. • The traffic configuration will accommodate road works on the south side of Eglinton Avenue East west of Brencliffe Road and in the centre of Eglinton Avenue, east of Brentcliffe Road. • Construction activities include: • Concrete removals • Construction of new sidewalk and curbs • Installation of new pavers • Installation of new traffic lighting elements • Asphalt and final paving
  6. 6. RETAINING WALL CONSTRUCTION NORTH SIDE OF EGLINTON, EAST OF BRENTCLIFFE ROAD 6 • This retaining wall is required to hold and stabilize the embankment created from the newly widened road. • Construction is expected to begin early August 2020 for a period of 4 months. • Construction activities will include: • Excavation: Excavators, dump trucks and loaders • Hydrovacing • Backfill and compaction: Loader and vibratory roller/compactor • Concrete works: concrete trucks and pumps • Installation of concrete blocks with mobile crane
  7. 7. RAMP CONSTRUCTION, WEST OF LESLIE STREET MULTI-USE PATH CONNECTING EGLINTON AVE E TO SERENA GUNDY PARK 7 • Crews will be removing three (3) trees near the West Don River Bridge prior to the construction of the new path. • Archaeological assessment of section of work zone on City property will take place on September 9, 2020. • Construction activities for path construction include: • Excavation • Backfill • Installation of topsoil • Landscaping will take place in 2021 as part of the final restoration plan. Mid-July 2020 through to December 2020
  8. 8. CP BRIDGE REHABILITATION EAST OF LESLIE STREET 8 • A working platform will be set up at the bridge in advance of the activities. • Crews will be removing rust, painting, replacing structural steel elements and performing concrete repairs. • Noise can be expected from concrete chipping and other rehabilitation works. August 24, 2020 for 13 weeks
  9. 9. Science Centre Station
  10. 10. SCIENCE CENTRE STATION UPDATE 10 Area Current Activities Station Box • Installation of Mechanical plumbing and HVAC duct is ongoing • First elevator installation is ongoing • Drywall installation • Installation of electrical equipment continues • Ceiling installation • Floor and wall tiling Main Entrance • Wall tiling and ceiling works are in progress • Drywall installation is ongoing • Elevator and louver installation is ongoing • Civil works have started Pedestrian Tunnel/Bus Terminal • Civil works and ceiling installation are ongoing at the pedestrian tunnel • Glazing continues at the bus terminal • Masonry works, drywall and civil works are in progress at the bus terminal • Wall tiling, and roofing are ongoing at the bus terminal Don Mills/Eglinton Intersection • Decking removal is complete • Road reconstruction and utilities works are ongoing
  11. 11. CURRENT TRAFFIC CONFIGURATION – DECKING REMOVAL 11 Through to late September 2020 • Science Centre Station has advanced to a state to allow the temporary traffic deck to be removed. • The removal will take place in two stages, with the second stage beginning early May 2020. • The road will be restored to an improved surface. • North south traffic will be reduced to two lanes and aligned to the west side of Don Mills Road. • Northbound, southbound and eastbound left turns will be restricted. Bus Detours: • Route 34C diverting to Ferrand and Rochefort.
  12. 12. CONSTRUCTION PROGRESS PHOTOS 12 FLOOR TILING AT THE PEDESTRIAN TUNNEL TILING WORKS AT THE BUS TERMINAL
  13. 13. Section Two At-Grade Aga Khan Park & Museum Stop to O’Connor Stop
  14. 14. SECTION TWO AT-GRADE UPDATE 14 Activity Location Approx. Date & Duration Road widening, asphalt paving and sidewalks East Don River Bridge to Wynford Bridge – North Side Ongoing through to Mid-September 2020 Boulevard, curbs and sidewalk works Bermondsey Road/Sloane – 4 corners of intersection Sept 8, 2020 for two weeks Creek realignment Sidewalk construction north side Wilson Brook Culvert Complete September 8, 2020 for one week Road Widening and reconstruction West of Bermondsey Rd (Esso Driveway) Complete Shelter Installation O’Connor Stop (Victoria Park) September 21 – September 28, 2020 Track Works: Overnight concrete pours Wynford Drive to Victoria Park August 13 through to late September 2020
  15. 15. LATE NIGHT CONCRETE POURS WYNFORD DRIVE AND VICTORIA PARK AVENUE 15 August 13, 2020 for approximately 6 weeks • Late night concrete pours between Wynford Drive and the East Don River Bridge, and between Jonesville Crescent and Victoria Park Avenue. • Pours will occur 2-3 times per week, starting as early as Thursday August 13, 2020, for approximately six (6) weeks between the hours of 10:00 p.m. – 3:00 a.m. • Rolling lane closures on Eglinton Avenue East, between Wynford Drive and Victoria Park Avenue. • Traffic control personnel and/or a paid duty officer will be present, while these works take place. • The concrete will form the plinths that will support the future tracks of the Eglinton Crosstown LRT.
  16. 16. O’CONNOR STOP SHELTER INSTALLATION (NORTH AND SOUTH PLATFORMS) 16 September 21 for approximately one week • A crane will be installed within the guideway work zone to facilitate shelter installation. • The structures will be delivered and lifted into place by the crane. • Concrete works will also take place as part of shelter installation. • Daily lane closures will be required at the work zone.
  17. 17. ROAD AND DRIVEWAY WORKS COMPLETE – WEST OF BERMONDSEY CONSTRUCTION PROGRESS PHOTOS 17 SCEINCE CENTRE TRANSITION WALLS ONOING EAST DON RIVER BRIDGE WIDENING – NORTH SIDE

×