Eastern Segment 5 works monthly meeting January 2021

  1. 1. January 12, 2021 Eglinton Crosstown LRT Construction Update Victoria Park Avenue to Kennedy Station
  2. 2. Section Three and Four At-Grade: O’Connor Stop to Ionview Stop
  3. 3. CONSTRUCTION ACTIVITIES 3 Location Activity Approx. Date & Duration Section 3 & 4 • All shelters installed • Completed December 2020 O’Connor Stop (Victoria Park Ave) • Concrete works for stop curbs, pedestrian ramps • Ongoing until April 2021 Pharmacy Stop • Concrete works for stop curbs, pedestrian ramps • Ongoing until April 2021 Hakimi Lebovic Stop • Formwork for guard rail • Concrete works for stop curbs, pedestrian ramps • Ongoing through January 2021 • Ongoing until April 2021 Golden Mile Stop (Warden Ave) • Formwork for guard rail • Concrete works for stop curbs, pedestrian ramps • Ongoing through January 2021 • Ongoing until April 2021 Birchmount Stop • Concrete works for stop curbs, pedestrian ramps • Ongoing until April 2021 Massey Creek Culvert • Fill old culvert complete • Build west wing wall • Complete • Ongoing until February 2021 Ionview Stop • Concrete works for stop curbs, pedestrian ramps • Ongoing until April 2021
  4. 4. ROSEMOUNT DRIVE AND EGLINTON AVE E 4 Until as early as February 2021 • North side closure for Massey Creek Construction • Crews will fill the old culvert and then construct the west wing wall
  5. 5. CONSTRUCTION PROGRESS PHOTOS 5 TACTILE PLATES INSTALLED PHARMACY STOP REBAR INSTALLATION FOR RAMP & FORMWORK GOLDEN MILE STOP
  6. 6. CONSTRUCTION PROGRESS PHOTOS 6 SHELTERS INSTALLED IONVIEW STOP GUARDRAIL REBAR INSTALLATION GOLDEN MILE STOP
  7. 7. Kennedy Station
  8. 8. KENNEDY STATION UPDATE 8 Location Activity Approx. Date & Duration Kennedy Station Main Entrance • Conduit installation, plumbing and sheet metal works, tiling, masonry works • Elevator painting • Elevator installation and painting • TPSS & TVS room electrical fit up • Ongoing through 2021 • Completed • Ongoing into 2021 • Ongoing through 2021 Kennedy Station – East of GO • Concrete works • Electrical and mechanical works • Wall pour • Ongoing until early 2021 • Ongoing until late 2021 • Completed Kennedy Station Concourse Level • Concrete works, rebar and shoring • Floor tiling • Ongoing until as early as May 2021 • Ongoing through 2021 Kennedy Portal (west of Kennedy Road) • Railing installation • Track works • Ongoing until early 2021 • Ongoing until early 2021 Kennedy Station Go Platform • Excavation for new east platform • Structural steel erection • Ongoing until early 2021 • Ongoing for approximately one month
  9. 9. KENNEDY CURRENT TRAFFIC CONFIGURATION 9 December 2020 for approx. eight months
  10. 10. GO WEST PLATFORM RELOCATION AND PEDESTRIAN DETOUR 10 • As part of GO Transit improvements at Kennedy GO Station, crews at Kennedy Station have temporarily relocated the west GO Transit platform • Pedestrians will be rerouted through the Kennedy TTC Station • This configuration will remain in place for approximately one year. August 17, 2020 for approx. one year
  11. 11. CONSTRUCTION PROGRESS PHOTOS 11 GO ENTRANCE STRUCTURAL STEEL ERECTION WALL POUR GO EAST PLATFORM
  12. 12. CONSTRUCTION PROGRESS PHOTOS 12 FLOOR TILING CONCOURSE LEVEL INVERT AND FOOTING POUR GO TUNNEL

×