Eglinton & Mt Pleasant Construction Liaison Committee - September 9 2020

  1. 1. September 9, 2020 Eglinton Crosstown LRT Eglinton – Mt Pleasant CLC
  2. 2. Eglinton Station
  3. 3. EGLINTON STATION UPDATE 3 Activity Location Approx. Date/Duration Extended Hours for Deep Excavation Beneath the TTC box Underway through fall 2020 Monday – Friday, 24 hours TTC Line 1 Facility Services Building Construction • South side of Berwick Ave at Yonge St • Periodic closures of Berwick Ave between Duplex Ave and Yonge St • Periodic closures of the westbound lane and north sidewalk on Hillsdale Ave bridge b/w Yonge St and Duplex Ave Periodically through 2020; subject to TTC approval Next scheduled closures: • October 24-25, 2020 Tunnel Ventilation Shaft Construction Center of Yonge St between Eglinton Ave and Roehampton Ave Underway through December 2020 Elevator Construction 2200 Yonge St (former Smoke’s Poutinerie) Underway through fall 2020
  4. 4. CURRENT TRAFFIC CONFIGURATION 4 Through 2020
  5. 5. 5 BERWICK PORTAL
  6. 6. CONSTRUCTION PROGRESS PHOTOS 6 BERWICK PORTAL
  7. 7. Mount Pleasant Station
  8. 8. MOUNT PLEASANT STATION UPDATE 8INSERT FOOTER Activity Location Approx. Date & Duration Tunnel Segment Demolition and Removal Station Box and Entrances Underway for approximately three (3) weeks Deep Excavation and Chipping Underneath the Station Roof Underway for approximately one (1) month Utility Reinstatement Works North and South sides of Eglinton Avenue Underway through 2021 Waterproofing, rebar, steel and conduit installations Secondary Entrance and Station Box Underway through 2021 Concrete Works Secondary Entrance and Station Box Underway through 2021 Above Ground Construction of the Secondary Entrance • Structural Steel Installations North side of Eglinton Avenue, east of Mount Pleasant Road Expected to start late Fall 2020 and continue through to 2021
  9. 9. CURRENT TRAFFIC CONFIGURATION 9 Until Fall 2020
  10. 10. CONSTRUCTION PROGRESS PHOTOS WEST END OF THE STATION BOX 10 1 2 3 4 5
  11. 11. CONSTRUCTION PROGRESS PHOTOS WEST END OF THE STATION BOX 11 Completed Invert Slab inside the Station Box Track Slab – Station Box
  12. 12. CONSTRUCTION PROGRESS PHOTOS 12INSERT FOOTER Concrete Pour – Secondary Entrance Waterproofing – Secondary Entrance

×