  1. 1. January 11, 2021 Eglinton Crosstown LRT Leaside-Laird CLC
  2. 2. ACTION ITEM #1 January 19, 2021 CYCLE LANE BIKE PARKING
  3. 3. ACTION ITEM 2 3 CTS to share a picture of the rendering of the area of Eglinton Avenue at the Brentcliffe portal, including the road that will open onto Eglinton Eastbound at the portal.
  4. 4. Leaside Station
  5. 5. LEASIDE STATION UPDATE 5 Activity Location Approx. Date & Duration Station Box Construction • Waterproofing • Rebar, steel, and conduit installations • Formwork • Concrete pours • Masonry block installations Underneath Eglinton Avenue within the Station Box Underway through mid 2021 Main Entrance Construction • Rebar, steel and M&E installations • Formwork installations • Concrete pours • Masonry block installations South east corner of Bayview Ave and Eglinton Ave Underway through early 2021 Secondary Entrance Construction • Waterproofing • Rebar, steel, and conduit installations • Formwork • Concrete pours North west corner of Bayview Ave and Eglinton Ave Underway through early 2021
  6. 6. LEASIDE STATION LOOK-AHEAD 6 Year What to Expect 2021 • Extended construction hours will continue through 2021. • Periodic lane closures may be required to facilitate deliveries, dewatering and concrete works. • Permanent works are ongoing within the station box and entrances, and will continue into early 2021, including waterproofing, formwork, rebar installation and concrete works. • Above ground construction of the Main Entrance is underway, with crews completing the concrete pour for the floor slab and south wall. • Architectural works, including masonry block installations, have begun at the Main Entrance. Structural steel and pre-cast panel installations are expected to start in Spring 2021. • Construction of the Secondary Entrance is progressing upwards and is expected to reach street level in Spring 2021.
  7. 7. CURRENT TRAFFIC CONFIGURATION 7 Through Summer 2021.
  8. 8. CONSTRUCTION PROGRESS PHOTOS 8 M&E WORKS - MAIN ENTRANCE FORMWORK INSTALLATIONS - STATION BOX
  9. 9. CONSTRUCTION PROGRESS PHOTOS MAIN ENTRANCE OVERVIEW 9 2020 2021
  10. 10. Laird Station
  11. 11. LAIRD STATION UPDATE 11 Activity Location Approx. Date & Duration Main Entrance Construction Forming, concrete works, deliveries, rebar and structural steel Main Entrance Monday – Sunday, 6:00 a.m. – 1:00 a.m. through March 2021 Secondary Entrance Construction Forming, concrete works and back-fill Secondary Entrance Monday – Sunday, 24 hours through March 2021 Station Box and Tunnel Works Track installation, rebar installation Beneath Eglinton Ave Underway through January 2021 Crane Demobilization Short-term traffic change Main Entrance As early as mid-February 2021 for one (1) week Escalator Delivery Short-term traffic change (same as crane demobilization configuration) Main Entrance As early as mid-February 2021 for two (2) weeks
  12. 12. CURRENT TRAFFIC CONFIGURATION 12 Through mid-February 2021
  13. 13. UPCOMING TRAFFIC CONFIGURATION 13 Mid-February 2021 – March 2021
  14. 14. CONSTRUCTION PROGRESS PHOTOS 14 SECONDARY ENTRANCE MAIN ENTRANCE
  15. 15. RETAINING WALL CONSTRUCTION NORTH SIDE OF EGLINTON EAST OF BRENTCLIFFE ROAD 15 • This retaining wall is required to hold the embankment created from the widened Eglinton Ave. • Retaining wall construction is on hold while slope remediation work takes place • Remedial work will continue into February 2021, and includes installation of steel anchors, application of shotcrete and back-filling • Retaining wall construction will resume in 2021 • Slope restoration design is with the City of Toronto for review

×