  1. 1. September 29, 2020 Eglinton Crosstown LRT Construction Liaison Committee Victoria Park Avenue to Kennedy Station
  2. 2. Section Three and Four At-Grade: O’Connor Stop to Ionview Stop
  3. 3. CONSTRUCTION ACTIVITIES 3 Location Activity Approx. Date & Duration O’Connor Stop • Shelter Installation Complete Pharmacy Stop • Rebar installation for ramps • Installing guard rails Complete Ongoing to early October 2020 Golden Mile Stop • Shelter Installation • Formwork and concrete works (east of Warden Ave) October 14 for one week Ongoing to late October 2020 Birchmount Stop • Shelter Installation • Rebar installation, formwork and concrete works for ramp installation Complete Early October 2020 for three weeks Massey Creek Culvert • Concrete works for culvert roof • Wet utility connections Complete Early October 2020 for 3-4 weeks Ionview Stop • Formwork, concrete and rebar installation for platform construction Ongoing through to late October 2020 Ionview Road to Kennedy Road (North Side) • Permanent sidewalk and curb installation, boulevard restoration and driveway tie-ins. • THESL Pole Relocation Ongoing through to early October 2020 Mid-October to Mid-November 2020 Birchmount Road to Ionview Road Hakimi Ave to Warden Ave • Track Work • OCS Cable installation Ongoing through to Late October 2020 Sept 21 – 24 and Sept 28 – Oct 1, 2020
  4. 4. OCS CABLE INSTALLATION ON EGLINTON AVE AT HAKIMI AND WARDEN AVENUE INTERSECTIONS 4 • Crews will be installing OCS (Overhead Catenary System) cables along Eglinton Avenue East between Hakimi/Lebovic and Warden Avenue. • Overhead catenary is the system installed overtop of the rails of a light rail system, to provide operational power to the LRVs (Light Rail Vehicles). • A 15-minute closure of each intersection will be required as the high rail vehicle passes through the intersections. • Paid duty officers will be onsite nightly to assist with traffic management.
  5. 5. GOLDEN MILE STOP SHELTER INSTALLATION 5 October 14 for one week • Westbound traffic on Eglinton Ave E will be restricted to one lane west of Warden Ave for the north shelter installation. • Eastbound traffic on Eglinton Ave E will be restricted to one lane east of Warden Ave the south shelter installation.
  6. 6. ROSEMOUNT DRIVE AND EGLINTON AVE E 6 Early January – Late October 2020 • North side closure for Massey Creek Construction • Creek realignment continues • Concrete works are ongoing for culvert roof MASSEY CREEK ROOF SLAB CONSTRUCTION IS NOW COMPLETE
  7. 7. IONVIEW ROAD TO KENNEDY ROAD – NORTH SIDE 7 • Boulevard restoration works include: • Removal of existing asphalt and curbs • Construction of new sidewalks and curbs • Driveway tie-ins to the newly widened road • Partial or full driveway closures of up to one week will be required to complete the work. • Driveway closures will be alternating, and vehicular access will be maintained for the duration of the work. Boulevard Restoration Works Ongoing through early October 2020
  8. 8. IONVIEW ROAD TO KENNEDY ROAD 8 • Crews will be relocating Toronto Hydro- Electric System (THESL) poles to their permanent positions. • Work will be completed in sections. • Temporary power outages (4-8 hours) will be required as this work progresses. A separate notification will be provided to affected addresses in advance of each outage. • Closure of the eastbound or westbound curb lane in between Ionview and Kennedy Road on Eglinton Ave E. THESL (Toronto Hydro Electric System) pole relocation between Ionview and Kennedy Road Mid-October through to Mid-November 2020
  9. 9. CONSTRUCTION PROGRESS PHOTOS 9 REBAR INSTALLATION FOR RAMPS AND CONCRETE – PHARMACY STOP REBAR INSTALLATION FOR RAMPS AND CONCRETE – PHARMACY STOP TRACK WORK WEST OF BIRCHMOUNT CONCRETE WORKS GOLDEN MILE EASTBOUND STOP
  10. 10. CONSTRUCTION PROGRESS PHOTOS 10 O’CONNOR STOP SHELTER INSTALL BIRCHMOUNT STOP SHELTER INSTALL
  11. 11. Kennedy Station
  12. 12. KENNEDY STATION UPDATE 12 Location Activity Approx. Date & Duration Kennedy Station Main Entrance • Concrete and masonry works • Conduit installation, plumbing and sheet metal works, tiling, masonry works • Structural steel and decking • Elevator installation and painting Ongoing through to late 2020 Kennedy Station – East of GO • Concrete works • Electrical and mechanical works Ongoing through to late 2020 Kennedy Station Concourse Level • Excavation and waterproofing • Concrete works, rebar and shoring Ongoing through to late 2020 Kennedy Portal (west of Kennedy Road) • Railing installation • Installation of light fixtures • Track works Ongoing through to late 2020 Kennedy Station Go Platform • Curtain wall and glazing • Demolition of east platform • Installation of metal railing • Roofing at GO shelters, painting of shelter and railing • Mechanical and electrical works Ongoing through to late 2020 Eglinton Ave E and Kennedy Road intersection • Roadworks (four corners of the intersection) • North west corner complete • North east corner • South east corner Complete Ongoing for 2 weeks Mid-October for 2 weeks
  13. 13. CURRENT TRAFFIC CONFIGURATION EGLINTON AVENUE EAST AND KENNEDY ROAD INTERSECTION 13 • Crews will be performing road works within the four corners of the Eglinton Ave East and Kennedy Road intersection. • A shared through and right turn lane will be implemented for northbound and southbound traffic at the intersection. • Periodic crosswalk closures will be required to complete the work. A minimum of three crosswalks will be maintained all times. Signage will be installed directing pedestrians to available crosswalks. Mid July – Late October 2020
  14. 14. TRAFFIC CHANGE AT KENNEDY STATION, EAST OF KENNEDY ROAD LATE OCTOBER, 2020 FOR 9 MONTHS 14 Traffic Details: • Vehicles entering Transway Crescent will not be permitted beyond the Kennedy Station Passenger Pick-Up and south parking lot access points. • Signal timing will be changed at Kennedy Road as well as the North and South Service Road to accommodate these changes. • Right turn from eastbound lane on Eglinton and left turn from westbound lane on Eglinton onto South Service Rd will be prohibited. • Left turn from eastbound lane on Eglinton onto North Service Rd will be prohibited. • Traffic entering South Service Road will be restricted to TTC vehicles only.
  15. 15. GO WEST PLATFORM RELOCATION AND PEDESTRIAN DETOUR KENNEDY STATION AUGUST 17, 2020 15 • As part of GO Transit improvements at Kennedy GO Station, crews at Kennedy Station will be temporarily relocating the west GO Transit platform as early as August 17, 2020. • Pedestrians will be rerouted through the Kennedy TTC Station • This configuration will remain in place for approximately one year.
  16. 16. CONSTRUCTION PROGRESS PHOTOS 16 EXCAVATION AT GO EAST PLATFORM STATION BOX REBAR INSTALLATION

×