SlideShare a Scribd company logo
1 of 42
EGLINTON
CROSSTOWN LRT
Next Phase of Construction
April 25, 2016
Construction of the
Eglinton Crosstown LRT Line
Background
• In September 2008, Metrolinx launched
a regional transportation plan – a 25-
year, $50 billion plan -- to coordinate
and integrate transportation and transit
in the Greater Toronto Area
• In 2010, City of Toronto approved the
project to build the Eglinton Crosstown
from Weston Road in the west to
Kennedy Station in the east.
• Following a competitive process,
Crosslinx Transit Solutions (CTS) was
awarded a contract in July 2015 to
design, build, finance, and maintain the
Eglinton Crosstown Light Rail Transit
(LRT).
Benefits of P3s:
• The Crosstown is being delivered using a public
private partnership model called Alternative
Financing and Procurement (AFP).
• It was procured as one design-build-finance-
maintain project to minimize integration risk –
historically, a factor for project cost overruns
under traditional models.
• Under the AFP model, CTS assumes most project
risks, including:
 design, project management and sub-
contractor coordination
 increases in construction material prices
and labour costs
 schedule and project completion delays
 maintenance and lifecycle replacement of
materials within the stations and stops,
rails, control systems, and vehicles
1
Project Players Roles
2
Safety First – Our #1 Priority
• Always have a site specific safety plan and site specific emergency plan.
• Ensure pre-work hazard assessments are complete and understood.
• Ensure job hazards analyses are complete and understood.
• Do everything possible to protect themselves, co-workers, and members of
the public.
• Stop work if the safety of themselves, co-workers and members of the public
cannot be assured.
• Identify and report unsafe behaviour and coach each other to make
improvements.
• Be prepared and equipped to work safely.
We train and direct staff to:
3
What are we building – a new modern LRT
• 15 underground stations and 10 surface stops
• A maintenance and storage facility
• A 19-kilometre route separated from regular traffic
• Communications system
• Links to 54 bus routes, GO Transit, and UP Express
4
What are we building - Crosstown Segments
The line is divided into six segments along the construction corridor:
5
What are we building - Crosstown Segments
6
Construction Overview
Distinct phases of construction:
• Preparatory works
• Utility relocations
• Handover of tunnel sections
• Support of excavation
• Excavation for underground stations
• Underground construction of the stations
• Track work and systems installation
• Traction power system
• Signalling system
• Testing and commissioning
• Road and area restoration
7
Preparing for Stations Construction
Since fall 2015, CTS has been preparing the line for underground stations
and stops construction.
Preparatory activities:
• Survey and monitor properties for noise and vibrations
• Assess soil condition and measure water levels along the corridor
• Locate and mark underground utilities
• Clearing/grubbing and removing shrubs/trees in the path of the Crosstown
• Demolish buildings and other infrastructure (i.e. bridge)
• Remove and store street furniture
(i.e. benches, bus shelters, planters, garbage bins)
8
Preparing for Stations Construction
Impacts and mitigations:
• Minimal interference to traffic
• Limited, day-by-day lane closures
• Some overnight work
• Access to businesses maintained
• Pedestrians have access to sidewalk
9
What to expect in 2016
10
What to expect in 2016 - Utilities Relocation
• Above and underground utilities will either be relocated and updated before
construction begins at a station or occur at the same time as a station’s
construction.
• To accommodate stations construction, gas, hydro, watermain and sewer,
cable, fibre and telephone lines are relocated.
• Crosstown project is providing upgraded watermains and
sewer systems in communities near these stations:
– Mount Dennis, Keelesdale, Fairbank, Forest Hill, Chaplin, Eglinton, and
Mount Pleasant.
11
What to expect in 2016
– Handover of Tunnels
Spring 2016
• Metrolinx transferred security and
maintenance of western tunnel to
CTS (runs from Mount Dennis to
Cedarvale Stations).
• At handover, CTS inspects the
tunnel, reports concerns to be fixed
by Metrolinx, and accepts it once
the tunnel meets agreed to terms.
• CTS cannot work near a tunnel
section until it responsible for it.
• The handover process will take up
to two months.
Between June 2016 and 2018
• Metrolinx handovers the three
remaining tunnel sections.
12
What to expect in 2016 – Ongoing Design
Features
• About half of the 19 km line is tunneled
• Stations and stops are about 0.6 km
apart
• Features will include:
• time arrival information
• safe access for people walking
and biking to the station
• clear route maps, seating, bike
parking
• Available parking at the start and end
of the LRT line.
Design Approach
• Comply with nine design principles developed
by City of Toronto and Metrolinx.
• Provide a legacy for generations to come.
• Have natural lighting during the day and well-lit
entrances at night.
• Have safe, clean, intuitive wayfinding at
all the stations and stops.
• Put passengers first.
• Provide visible entrances, bicycle facilities and
sustainable practices to ensure all stations
comply with Toronto Green Standard Tier.
• Landscaped entrances, including planters with
trees and ornamental grasses.
• Public plazas and retail components at some
stations.
• Clean and minimalist space at platform level.
• Accessible to passengers with disabilities, strollers,
and bicycles.
13
• The underground stations run
between Weston Road in the west to
Laird Street in the east.
• Construction began at Keelesdale
station, located at Keele Street /
Trethewey Drive and Eglinton Avenue
in March 2016.
• Installing support of excavation is the first step in
constructing an underground station.
• All underground stations will be brand
new, including the three LRT
interchange stations connecting to
other transit modes.
• Most of the underground stations will be
in construction by the end of 2016.
What to expect in 2016
– Start of Stations Construction
14
How we’re building – Three Types of Stations
Cut & Cover Stations
Chaplin
15
How we’re building – Three Types of Stations
Mined Stations
Avenue
16
How we’re building – Three Types of Stations
Interchange Stations
Eglinton
17
How we’re building – Cut and Cover Stations
• Twelve underground stations, including interchange stations will use a cut and cover
method to support excavation. This construction method entails opening a section of
space to allow work below grade. The section is excavated, then covered to allow
traffic to flow above.
• To install support (shoring), a crew will:
– remove the street pavement on one side of Eglinton Avenue
about 130m x 10m, (the size of two hockey rinks)
– A shallow area will be excavated
– install steel piles, braces and tie-backs around the sides to support excavation
– backfill and cover the pit with a wooden deck on the roadway to allow traffic to
travel across it
• After that, the crew moves to the other half of the street to do the same. Installing
shoring and decking is estimated to take approximately 14 months.
• Once the shoring is installed, the crew may work under the roadway safely,
excavating to a depth of at least 20m for the construction of the station box. This is
where the rail tunnels, associated platforms and rail infrastructure will be housed.
18
Some impacts/mitigations of cut and cover method:
• At least, one lane in each direction will remain open for about 12 months.
• Disturbances (noise, vibration, dust, and traffic) will be communicated in advance and monitored.
• Side streets near to excavation areas may be closed.
• Sidewalks may be rerouted/closed.
• Access to businesses will be maintained
• Vibration monitors will be installed on properties located near areas being excavated to monitor
noise and vibration levels.
• Truck traffic will be routed to well travelled routes.
• Where parking spots have been eliminated, on-street, one-hour parking may be relaxed.
• Bus stops will be relocated.
How we’re building – Cut and Cover Stations
Locations:
Keelesdale (Keele), Caledonia, Fairbank (Dufferin),
Forest Hill (Bathurst), Chaplin, Mount Pleasant, Leaside (Bayview),
Science Centre
19
• Three stations will be mined and one will be
partially mined (Leaside).
• Station entrances will be dug first.
• A crew will install support of excavation
around sides of pits (shoring).
• They will continue working under the roadway
with minimal impact on traffic.
• The excavated area will be lined with
primary concrete “shotcrete” lining (as ground
support).
• A station box will be constructed within the lined
excavated cavern.
• Once the mechanical, electrical and architectural
work starts, the station entrances will be
constructed.
How we’re building – Mined Stations
Courtesy of Rideau Transit Group
20
Some impacts/mitigations of mined method:
• Shoring work will begin at most underground stations in 2016.
• Mining work is scheduled to begin in 2017.
• Long-term road closures are expected.
• We will communicate in advance and monitor activities.
• CTS will comply with noise by-laws.
• Pedestrians have access but some sidewalks may be rerouted.
• Access to businesses will be maintained.
How we’re building – Mined Stations
t
Locations:
Oakwood, Avenue, Leaside (part), Laird
21
• There are four
interchange stations.
• Interchange stations will
allow transit riders to
connect to other transit
modes, such as TTC,
GO and the UP Express
How we’re building – Interchange Stations
Subway Station Longitudinal Section
22
Some impacts/mitigations of interchange stations:
• Utilities relocation will require lane closure.
• Extensive support of excavation work.
• Long-term road closures/lane restrictions.
• Long-term bus stop relocation and detour at Eglinton Station.
• Weekend/overnight closure of a CP/GO rail track at Mount Dennis Station.
• Long-term closure of tunnels connecting to Eglinton subway.
• Station boxes will be built below the existing subway tracks at Eglinton and
cedarvale.
• More truck traffic delivering/removing materials.
How we’re building – Interchange Stations
Locations:
Mount Dennis, Cedarvale (Allen), Eglinton (Yonge), Kennedy
23
Surface stops
• 10 surface stops
• Dedicated right-of-way tracks separate from traffic
• High quality construction
• Amenities will be integrated into the stops (i.e. maps)
• Transparent/open shelters
• Colour and patterns will make stops identifiable to passengers
• Integrated lighting to allow for advertising
24
What else are we building?
– Maintenance and Storage Facility
25
• Located at the most western end of the line on 42 acres of land, north of
Mount Dennis Station.
• It will provide:
– storage for LRVs:
• 76 LRVs initially; 135 LRV capacity
– maintenance and repairs facility
– offices and employee parking
We will:
• integrate site with local neighbourhood
• create complementary uses
• limit impacts on local community
• design and construct the MSF to achieve LEED Silver Certification
• comply with the Toronto Green Standard Tier 1 environmental
requirements
What else are we building?
– Maintenance and Storage Facility
26
• Located at the most western
end of the line on 42 acres of
land.
• Alternate source of power to the
Toronto Hydro Electric System Ltd.
• 10-18 megawatts generation facility
(similar in size to one used at a
hospital).
• Use periodically
– 10 - 40 days per year
– Less than 15% annual usage
• Reduce grid strain on the provincial electrical power network.
• Save approximately 40% on price of electricity annually.
What else are we building?
– Back-up Power Facility
27
Guideways and Tunnel Portals
Guideways
• Crosstown has at-grade, underground, and an elevated guideway (rail).
• The elevated guideway is located at the west end of the line.
• It consists of a viaduct structure with bridge spans.
• Its columns, portals, and retaining walls will be designed to be
aesthetically pleasing.
Portals
• Tunnel entrances where the guideway and light rail vehicles will go from
above-ground to underground.
• There are two portals: the West Portal, located at Mount Dennis Station
and the East Portal, located west of Sunnybrook Park Station.
• Tree groves and grasses will be planted on portals, as well as on station
plazas, open spaces, and stops.
28
Estimated Construction Schedule
– Cut and Cover Stations
29
Estimated Construction Schedule
- Mount Dennis
Estimated Construction Schedule
– Mined Stations
30
Estimated Construction Schedule
– Interchange Stations
31
Stations in construction – Spring 2016
Keelesdale
Laird
Avenue
32
Mount Dennis
Stations in construction – Spring 2016
Oakwood
33
Stations in construction – Summer 2016
Caledonia
Forest Hill (Bathurst)
Fairbank (Dufferin)
34
Leaside (Bayview)
Stations in construction – Summer 2016
Eglinton (Yonge)tCedarvale (Allen)
35
Science Centre
Portal in construction – Fall 2016
West Portal (Eglinton Ave Box Tunnel)
36
CTS will develop and execute plans to:
• Ensure public health and safety
• Manage traffic control
• Coordinate with Emergency Services and transit
• Communicate early and often
• Use technology to share information in a timely way (i.e. a Mobile App to
inform motorists of traffic disruption)
• Maintain access to property and local businesses
• Provide directional signage
• Identify access to local businesses
• Alert motorists of estimated travel time through the corridor
We will manage disruptions
40
Our Guiding Principles:
• Offer meaningful and accurate communication
– background/context so that the public and stakeholders can make informed comments and
provide input on the Project;
• Provide timely and transparent information early and often
• Ensure two-way communication – for a fair and respectful dialogue
• Allow for broad solutions – provide a corridor-wide focus as well as local
outreach to continually inform the public and other stakeholders.
Engaging the community is important to us
41
Stay in touch
416-782-8118
www.thecrosstown.ca
crosstown@metrolinx.com
facebook.com/thecrosstown
twitter.com/crosstownTO
instagram.com/eglinton_crosstown
Crosstown West Office
1848 Eglinton Ave W (at Dufferin)
Crosstown East Office
660 Eglinton Ave E (at Bayview)
42
LRT Construction Enters Next Phase

More Related Content

What's hot

Tesla Marketing Strategy case study
Tesla Marketing Strategy case studyTesla Marketing Strategy case study
Tesla Marketing Strategy case studyMuhammad Eddieb
 
Tesla Model 3 Digital Marketing Plan
Tesla Model 3 Digital Marketing PlanTesla Model 3 Digital Marketing Plan
Tesla Model 3 Digital Marketing PlanIbrahim Cevik
 
Marketing Startegy for Volkswagen EV
Marketing Startegy for Volkswagen EVMarketing Startegy for Volkswagen EV
Marketing Startegy for Volkswagen EVAbdullah Saghir Ahmad
 
Appraising kolkata metro rail project case
Appraising kolkata metro rail project caseAppraising kolkata metro rail project case
Appraising kolkata metro rail project caseRahul Pagaria
 
How tesla changed the Auto industry ?
How tesla changed the Auto industry ?How tesla changed the Auto industry ?
How tesla changed the Auto industry ?Ahammad Nihal
 
Value Chain Configuration for Tesla Motors in Brazil
Value Chain Configuration for Tesla Motors in BrazilValue Chain Configuration for Tesla Motors in Brazil
Value Chain Configuration for Tesla Motors in BrazilAntonio Addario
 
Kolkata metro rail via-duct project
Kolkata metro rail via-duct projectKolkata metro rail via-duct project
Kolkata metro rail via-duct projectrajnish singh
 
Bus system reform in India through JnNURM
Bus system reform in India through JnNURMBus system reform in India through JnNURM
Bus system reform in India through JnNURMJaspal Singh
 
Building a social media strategy - TMM Webionar
Building a social media strategy  - TMM WebionarBuilding a social media strategy  - TMM Webionar
Building a social media strategy - TMM WebionarAndy Lambert
 
Wendy's Social Media Strategy
Wendy's Social Media StrategyWendy's Social Media Strategy
Wendy's Social Media StrategySabrina Lopez
 
Social Media for Political Communication
Social Media for Political CommunicationSocial Media for Political Communication
Social Media for Political CommunicationUjjwal Acharya
 
Social media influencer marketing a framework for success - michelle goodall
Social media influencer marketing   a framework for success - michelle goodallSocial media influencer marketing   a framework for success - michelle goodall
Social media influencer marketing a framework for success - michelle goodallMichelle Goodall
 
Presentation on social media
Presentation on social mediaPresentation on social media
Presentation on social mediaShahzad Ali
 
Communication Theory Cultivation Analysis
Communication Theory Cultivation AnalysisCommunication Theory Cultivation Analysis
Communication Theory Cultivation AnalysisDada Veloso-Beltran
 

What's hot (17)

Tesla Marketing Strategy case study
Tesla Marketing Strategy case studyTesla Marketing Strategy case study
Tesla Marketing Strategy case study
 
Tesla Model 3 Digital Marketing Plan
Tesla Model 3 Digital Marketing PlanTesla Model 3 Digital Marketing Plan
Tesla Model 3 Digital Marketing Plan
 
Marketing Startegy for Volkswagen EV
Marketing Startegy for Volkswagen EVMarketing Startegy for Volkswagen EV
Marketing Startegy for Volkswagen EV
 
Appraising kolkata metro rail project case
Appraising kolkata metro rail project caseAppraising kolkata metro rail project case
Appraising kolkata metro rail project case
 
How tesla changed the Auto industry ?
How tesla changed the Auto industry ?How tesla changed the Auto industry ?
How tesla changed the Auto industry ?
 
Value Chain Configuration for Tesla Motors in Brazil
Value Chain Configuration for Tesla Motors in BrazilValue Chain Configuration for Tesla Motors in Brazil
Value Chain Configuration for Tesla Motors in Brazil
 
Kolkata metro rail via-duct project
Kolkata metro rail via-duct projectKolkata metro rail via-duct project
Kolkata metro rail via-duct project
 
Tesla Motors Presentation
Tesla Motors PresentationTesla Motors Presentation
Tesla Motors Presentation
 
Bus system reform in India through JnNURM
Bus system reform in India through JnNURMBus system reform in India through JnNURM
Bus system reform in India through JnNURM
 
Building a social media strategy - TMM Webionar
Building a social media strategy  - TMM WebionarBuilding a social media strategy  - TMM Webionar
Building a social media strategy - TMM Webionar
 
Wendy's Social Media Strategy
Wendy's Social Media StrategyWendy's Social Media Strategy
Wendy's Social Media Strategy
 
Social Media for Political Communication
Social Media for Political CommunicationSocial Media for Political Communication
Social Media for Political Communication
 
Social media influencer marketing a framework for success - michelle goodall
Social media influencer marketing   a framework for success - michelle goodallSocial media influencer marketing   a framework for success - michelle goodall
Social media influencer marketing a framework for success - michelle goodall
 
CIPR Excellence Awards case studies
CIPR Excellence Awards case studiesCIPR Excellence Awards case studies
CIPR Excellence Awards case studies
 
Presentation on social media
Presentation on social mediaPresentation on social media
Presentation on social media
 
Communication Theory Cultivation Analysis
Communication Theory Cultivation AnalysisCommunication Theory Cultivation Analysis
Communication Theory Cultivation Analysis
 
Tesla
TeslaTesla
Tesla
 

Viewers also liked

Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017Crosstown TO
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Crosstown TO
 
Science Centre Station and West At-Grade Surface Stops Open House - November ...
Science Centre Station and West At-Grade Surface Stops Open House - November ...Science Centre Station and West At-Grade Surface Stops Open House - November ...
Science Centre Station and West At-Grade Surface Stops Open House - November ...Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017Crosstown TO
 
Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017
Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017
Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017Crosstown TO
 
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017Crosstown TO
 
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2017Crosstown TO
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017Crosstown TO
 
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Crosstown TO
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...Crosstown TO
 
Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Crosstown TO
 
Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017Crosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Crosstown TO
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Crosstown TO
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCrosstown TO
 
Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Crosstown TO
 

Viewers also liked (20)

Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
 
Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017Chaplin and Avenue Stations Open House - October 2017
Chaplin and Avenue Stations Open House - October 2017
 
Science Centre Station and West At-Grade Surface Stops Open House - November ...
Science Centre Station and West At-Grade Surface Stops Open House - November ...Science Centre Station and West At-Grade Surface Stops Open House - November ...
Science Centre Station and West At-Grade Surface Stops Open House - November ...
 
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
Eglinton & Mount Pleasant Construction Liaison Committee - November 2017
 
Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017
Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017
Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017
 
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
 
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
Brentcliffe - Victoria Park Construction Liaison Committee - September 2017
 
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
Pharmacy-Kennedy Construction Liaison Committee Meeting - June 2017
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - September 2017
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
 
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
Pharmacy to Kennedy Construction Liaison Committee Meeting - July 2017
 
Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017Leaside & Laird Construction Liaison Committee - November 2017
Leaside & Laird Construction Liaison Committee - November 2017
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
 
Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017Leaside & Laird Stations Open House - October 2017
Leaside & Laird Stations Open House - October 2017
 
Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017Leaside & Laird Stations Construction Liaison Committee - October 2017
Leaside & Laird Stations Construction Liaison Committee - October 2017
 
Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017Leaside - Laird Construction Liaison Committee Meeting - June 2017
Leaside - Laird Construction Liaison Committee Meeting - June 2017
 
Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017Forest Hill Station Open House - June 2017
Forest Hill Station Open House - June 2017
 
Caledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open HouseCaledonia Station, West Portal and Elevated Guideway Open House
Caledonia Station, West Portal and Elevated Guideway Open House
 
Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017Chaplin Station Open House - March 2017
Chaplin Station Open House - March 2017
 

Similar to LRT Construction Enters Next Phase

Leaside station open house
Leaside station open house Leaside station open house
Leaside station open house Crosstown TO
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2Crosstown TO
 
Eglinton Station Open House
Eglinton Station Open HouseEglinton Station Open House
Eglinton Station Open HouseCrosstown TO
 
Laird Station Open House
Laird Station Open HouseLaird Station Open House
Laird Station Open HouseCrosstown TO
 
Forest Hill station open house
Forest Hill station open houseForest Hill station open house
Forest Hill station open houseCrosstown TO
 
Mount Dennis Station Open House
Mount Dennis Station Open HouseMount Dennis Station Open House
Mount Dennis Station Open HouseCrosstown TO
 
Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Crosstown TO
 
Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Crosstown TO
 
Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017Crosstown TO
 
Avenue station open house
Avenue station open house Avenue station open house
Avenue station open house Crosstown TO
 
Avenue station open house presentation
Avenue station open house presentation Avenue station open house presentation
Avenue station open house presentation Crosstown TO
 
Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017Crosstown TO
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Crosstown TO
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Crosstown TO
 
Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018Crosstown TO
 
Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Crosstown TO
 
Keelesdale station open house
Keelesdale station open houseKeelesdale station open house
Keelesdale station open houseCrosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017Crosstown TO
 
Mount pleasant station open house
Mount pleasant station open house  Mount pleasant station open house
Mount pleasant station open house Crosstown TO
 
Fall18 Open House Western Segment Works
Fall18 Open House   Western Segment WorksFall18 Open House   Western Segment Works
Fall18 Open House Western Segment WorksCrosstown TO
 

Similar to LRT Construction Enters Next Phase (20)

Leaside station open house
Leaside station open house Leaside station open house
Leaside station open house
 
Cedarvale station open house for website final2
Cedarvale station open house for website final2Cedarvale station open house for website final2
Cedarvale station open house for website final2
 
Eglinton Station Open House
Eglinton Station Open HouseEglinton Station Open House
Eglinton Station Open House
 
Laird Station Open House
Laird Station Open HouseLaird Station Open House
Laird Station Open House
 
Forest Hill station open house
Forest Hill station open houseForest Hill station open house
Forest Hill station open house
 
Mount Dennis Station Open House
Mount Dennis Station Open HouseMount Dennis Station Open House
Mount Dennis Station Open House
 
Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017Surface Section and Kennedy Station Open House - April 2017
Surface Section and Kennedy Station Open House - April 2017
 
Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017Cedarvale Station Open House - March 2017
Cedarvale Station Open House - March 2017
 
Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017Science Centre Station Open House - June 2017
Science Centre Station Open House - June 2017
 
Avenue station open house
Avenue station open house Avenue station open house
Avenue station open house
 
Avenue station open house presentation
Avenue station open house presentation Avenue station open house presentation
Avenue station open house presentation
 
Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017Eglinton Station Open House - March 2017
Eglinton Station Open House - March 2017
 
Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017Mount Dennis Station and EMSF Open House - March 2017
Mount Dennis Station and EMSF Open House - March 2017
 
Avenue Station Open House - May 2017
Avenue Station Open House - May 2017Avenue Station Open House - May 2017
Avenue Station Open House - May 2017
 
Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018Central Open House (Chaplin Station to Leaside Station) - spring 2018
Central Open House (Chaplin Station to Leaside Station) - spring 2018
 
Leaside Station Open House - March 2017
Leaside Station Open House - March 2017Leaside Station Open House - March 2017
Leaside Station Open House - March 2017
 
Keelesdale station open house
Keelesdale station open houseKeelesdale station open house
Keelesdale station open house
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
 
Mount pleasant station open house
Mount pleasant station open house  Mount pleasant station open house
Mount pleasant station open house
 
Fall18 Open House Western Segment Works
Fall18 Open House   Western Segment WorksFall18 Open House   Western Segment Works
Fall18 Open House Western Segment Works
 

More from Crosstown TO

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfCrosstown TO
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023Crosstown TO
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Crosstown TO
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfCrosstown TO
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCrosstown TO
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxCrosstown TO
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxCrosstown TO
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfCrosstown TO
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxCrosstown TO
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfCrosstown TO
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfCrosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
 

More from Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 

Recently uploaded

The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...nservice241
 
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore EscortsVIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escortsaditipandeya
 
2024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 292024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 29JSchaus & Associates
 
↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...ranjana rawat
 
VIP Call Girl mohali 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl mohali 7001035870 Enjoy Call Girls With Our EscortsVIP Call Girl mohali 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl mohali 7001035870 Enjoy Call Girls With Our Escortssonatiwari757
 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024ARCResearch
 
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...aartirawatdelhi
 
Get Premium Balaji Nagar Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Balaji Nagar Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...Get Premium Balaji Nagar Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Balaji Nagar Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...MOHANI PANDEY
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)Congressional Budget Office
 
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...SUHANI PANDEY
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfSamirsinh Parmar
 
Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Christina Parmionova
 
Top Rated Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated  Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...Top Rated  Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...Call Girls in Nagpur High Profile
 
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...CedZabala
 
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...tanu pandey
 
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfahcitycouncil
 

Recently uploaded (20)

The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
 
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Bhavnagar 7001035870 Whatsapp Number, 24/07 Booking
 
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore EscortsVIP Russian Call Girls in Indore Ishita 💚😋  9256729539 🚀 Indore Escorts
VIP Russian Call Girls in Indore Ishita 💚😋 9256729539 🚀 Indore Escorts
 
2024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 292024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 29
 
↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
↑VVIP celebrity ( Pune ) Serampore Call Girls 8250192130 unlimited shot and a...
 
VIP Call Girl mohali 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl mohali 7001035870 Enjoy Call Girls With Our EscortsVIP Call Girl mohali 7001035870 Enjoy Call Girls With Our Escorts
VIP Call Girl mohali 7001035870 Enjoy Call Girls With Our Escorts
 
Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024Regional Snapshot Atlanta Aging Trends 2024
Regional Snapshot Atlanta Aging Trends 2024
 
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...Night 7k to 12k  Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
Night 7k to 12k Call Girls Service In Navi Mumbai 👉 BOOK NOW 9833363713 👈 ♀️...
 
Get Premium Balaji Nagar Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Balaji Nagar Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...Get Premium Balaji Nagar Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
Get Premium Balaji Nagar Call Girls (8005736733) 24x7 Rate 15999 with A/c Roo...
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)
 
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
VIP Model Call Girls Kiwale ( Pune ) Call ON 8005736733 Starting From 5K to 2...
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdf
 
Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.Global debate on climate change and occupational safety and health.
Global debate on climate change and occupational safety and health.
 
Top Rated Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated  Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...Top Rated  Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated Pune Call Girls Wadgaon Sheri ⟟ 6297143586 ⟟ Call Me For Genuine S...
 
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
Artificial Intelligence in Philippine Local Governance: Challenges and Opport...
 
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Akurdi ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Akurdi ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
(NEHA) Call Girls Nagpur Call Now 8250077686 Nagpur Escorts 24x7
 
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Sangamwadi Call Me 7737669865 Budget Friendly No Advance Booking
 
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdf
 

LRT Construction Enters Next Phase

  • 1. EGLINTON CROSSTOWN LRT Next Phase of Construction April 25, 2016
  • 2. Construction of the Eglinton Crosstown LRT Line Background • In September 2008, Metrolinx launched a regional transportation plan – a 25- year, $50 billion plan -- to coordinate and integrate transportation and transit in the Greater Toronto Area • In 2010, City of Toronto approved the project to build the Eglinton Crosstown from Weston Road in the west to Kennedy Station in the east. • Following a competitive process, Crosslinx Transit Solutions (CTS) was awarded a contract in July 2015 to design, build, finance, and maintain the Eglinton Crosstown Light Rail Transit (LRT). Benefits of P3s: • The Crosstown is being delivered using a public private partnership model called Alternative Financing and Procurement (AFP). • It was procured as one design-build-finance- maintain project to minimize integration risk – historically, a factor for project cost overruns under traditional models. • Under the AFP model, CTS assumes most project risks, including:  design, project management and sub- contractor coordination  increases in construction material prices and labour costs  schedule and project completion delays  maintenance and lifecycle replacement of materials within the stations and stops, rails, control systems, and vehicles 1
  • 4. Safety First – Our #1 Priority • Always have a site specific safety plan and site specific emergency plan. • Ensure pre-work hazard assessments are complete and understood. • Ensure job hazards analyses are complete and understood. • Do everything possible to protect themselves, co-workers, and members of the public. • Stop work if the safety of themselves, co-workers and members of the public cannot be assured. • Identify and report unsafe behaviour and coach each other to make improvements. • Be prepared and equipped to work safely. We train and direct staff to: 3
  • 5. What are we building – a new modern LRT • 15 underground stations and 10 surface stops • A maintenance and storage facility • A 19-kilometre route separated from regular traffic • Communications system • Links to 54 bus routes, GO Transit, and UP Express 4
  • 6. What are we building - Crosstown Segments The line is divided into six segments along the construction corridor: 5
  • 7. What are we building - Crosstown Segments 6
  • 8. Construction Overview Distinct phases of construction: • Preparatory works • Utility relocations • Handover of tunnel sections • Support of excavation • Excavation for underground stations • Underground construction of the stations • Track work and systems installation • Traction power system • Signalling system • Testing and commissioning • Road and area restoration 7
  • 9. Preparing for Stations Construction Since fall 2015, CTS has been preparing the line for underground stations and stops construction. Preparatory activities: • Survey and monitor properties for noise and vibrations • Assess soil condition and measure water levels along the corridor • Locate and mark underground utilities • Clearing/grubbing and removing shrubs/trees in the path of the Crosstown • Demolish buildings and other infrastructure (i.e. bridge) • Remove and store street furniture (i.e. benches, bus shelters, planters, garbage bins) 8
  • 10. Preparing for Stations Construction Impacts and mitigations: • Minimal interference to traffic • Limited, day-by-day lane closures • Some overnight work • Access to businesses maintained • Pedestrians have access to sidewalk 9
  • 11. What to expect in 2016 10
  • 12. What to expect in 2016 - Utilities Relocation • Above and underground utilities will either be relocated and updated before construction begins at a station or occur at the same time as a station’s construction. • To accommodate stations construction, gas, hydro, watermain and sewer, cable, fibre and telephone lines are relocated. • Crosstown project is providing upgraded watermains and sewer systems in communities near these stations: – Mount Dennis, Keelesdale, Fairbank, Forest Hill, Chaplin, Eglinton, and Mount Pleasant. 11
  • 13. What to expect in 2016 – Handover of Tunnels Spring 2016 • Metrolinx transferred security and maintenance of western tunnel to CTS (runs from Mount Dennis to Cedarvale Stations). • At handover, CTS inspects the tunnel, reports concerns to be fixed by Metrolinx, and accepts it once the tunnel meets agreed to terms. • CTS cannot work near a tunnel section until it responsible for it. • The handover process will take up to two months. Between June 2016 and 2018 • Metrolinx handovers the three remaining tunnel sections. 12
  • 14. What to expect in 2016 – Ongoing Design Features • About half of the 19 km line is tunneled • Stations and stops are about 0.6 km apart • Features will include: • time arrival information • safe access for people walking and biking to the station • clear route maps, seating, bike parking • Available parking at the start and end of the LRT line. Design Approach • Comply with nine design principles developed by City of Toronto and Metrolinx. • Provide a legacy for generations to come. • Have natural lighting during the day and well-lit entrances at night. • Have safe, clean, intuitive wayfinding at all the stations and stops. • Put passengers first. • Provide visible entrances, bicycle facilities and sustainable practices to ensure all stations comply with Toronto Green Standard Tier. • Landscaped entrances, including planters with trees and ornamental grasses. • Public plazas and retail components at some stations. • Clean and minimalist space at platform level. • Accessible to passengers with disabilities, strollers, and bicycles. 13
  • 15. • The underground stations run between Weston Road in the west to Laird Street in the east. • Construction began at Keelesdale station, located at Keele Street / Trethewey Drive and Eglinton Avenue in March 2016. • Installing support of excavation is the first step in constructing an underground station. • All underground stations will be brand new, including the three LRT interchange stations connecting to other transit modes. • Most of the underground stations will be in construction by the end of 2016. What to expect in 2016 – Start of Stations Construction 14
  • 16. How we’re building – Three Types of Stations Cut & Cover Stations Chaplin 15
  • 17. How we’re building – Three Types of Stations Mined Stations Avenue 16
  • 18. How we’re building – Three Types of Stations Interchange Stations Eglinton 17
  • 19. How we’re building – Cut and Cover Stations • Twelve underground stations, including interchange stations will use a cut and cover method to support excavation. This construction method entails opening a section of space to allow work below grade. The section is excavated, then covered to allow traffic to flow above. • To install support (shoring), a crew will: – remove the street pavement on one side of Eglinton Avenue about 130m x 10m, (the size of two hockey rinks) – A shallow area will be excavated – install steel piles, braces and tie-backs around the sides to support excavation – backfill and cover the pit with a wooden deck on the roadway to allow traffic to travel across it • After that, the crew moves to the other half of the street to do the same. Installing shoring and decking is estimated to take approximately 14 months. • Once the shoring is installed, the crew may work under the roadway safely, excavating to a depth of at least 20m for the construction of the station box. This is where the rail tunnels, associated platforms and rail infrastructure will be housed. 18
  • 20. Some impacts/mitigations of cut and cover method: • At least, one lane in each direction will remain open for about 12 months. • Disturbances (noise, vibration, dust, and traffic) will be communicated in advance and monitored. • Side streets near to excavation areas may be closed. • Sidewalks may be rerouted/closed. • Access to businesses will be maintained • Vibration monitors will be installed on properties located near areas being excavated to monitor noise and vibration levels. • Truck traffic will be routed to well travelled routes. • Where parking spots have been eliminated, on-street, one-hour parking may be relaxed. • Bus stops will be relocated. How we’re building – Cut and Cover Stations Locations: Keelesdale (Keele), Caledonia, Fairbank (Dufferin), Forest Hill (Bathurst), Chaplin, Mount Pleasant, Leaside (Bayview), Science Centre 19
  • 21. • Three stations will be mined and one will be partially mined (Leaside). • Station entrances will be dug first. • A crew will install support of excavation around sides of pits (shoring). • They will continue working under the roadway with minimal impact on traffic. • The excavated area will be lined with primary concrete “shotcrete” lining (as ground support). • A station box will be constructed within the lined excavated cavern. • Once the mechanical, electrical and architectural work starts, the station entrances will be constructed. How we’re building – Mined Stations Courtesy of Rideau Transit Group 20
  • 22. Some impacts/mitigations of mined method: • Shoring work will begin at most underground stations in 2016. • Mining work is scheduled to begin in 2017. • Long-term road closures are expected. • We will communicate in advance and monitor activities. • CTS will comply with noise by-laws. • Pedestrians have access but some sidewalks may be rerouted. • Access to businesses will be maintained. How we’re building – Mined Stations t Locations: Oakwood, Avenue, Leaside (part), Laird 21
  • 23. • There are four interchange stations. • Interchange stations will allow transit riders to connect to other transit modes, such as TTC, GO and the UP Express How we’re building – Interchange Stations Subway Station Longitudinal Section 22
  • 24. Some impacts/mitigations of interchange stations: • Utilities relocation will require lane closure. • Extensive support of excavation work. • Long-term road closures/lane restrictions. • Long-term bus stop relocation and detour at Eglinton Station. • Weekend/overnight closure of a CP/GO rail track at Mount Dennis Station. • Long-term closure of tunnels connecting to Eglinton subway. • Station boxes will be built below the existing subway tracks at Eglinton and cedarvale. • More truck traffic delivering/removing materials. How we’re building – Interchange Stations Locations: Mount Dennis, Cedarvale (Allen), Eglinton (Yonge), Kennedy 23
  • 25. Surface stops • 10 surface stops • Dedicated right-of-way tracks separate from traffic • High quality construction • Amenities will be integrated into the stops (i.e. maps) • Transparent/open shelters • Colour and patterns will make stops identifiable to passengers • Integrated lighting to allow for advertising 24
  • 26. What else are we building? – Maintenance and Storage Facility 25
  • 27. • Located at the most western end of the line on 42 acres of land, north of Mount Dennis Station. • It will provide: – storage for LRVs: • 76 LRVs initially; 135 LRV capacity – maintenance and repairs facility – offices and employee parking We will: • integrate site with local neighbourhood • create complementary uses • limit impacts on local community • design and construct the MSF to achieve LEED Silver Certification • comply with the Toronto Green Standard Tier 1 environmental requirements What else are we building? – Maintenance and Storage Facility 26
  • 28. • Located at the most western end of the line on 42 acres of land. • Alternate source of power to the Toronto Hydro Electric System Ltd. • 10-18 megawatts generation facility (similar in size to one used at a hospital). • Use periodically – 10 - 40 days per year – Less than 15% annual usage • Reduce grid strain on the provincial electrical power network. • Save approximately 40% on price of electricity annually. What else are we building? – Back-up Power Facility 27
  • 29. Guideways and Tunnel Portals Guideways • Crosstown has at-grade, underground, and an elevated guideway (rail). • The elevated guideway is located at the west end of the line. • It consists of a viaduct structure with bridge spans. • Its columns, portals, and retaining walls will be designed to be aesthetically pleasing. Portals • Tunnel entrances where the guideway and light rail vehicles will go from above-ground to underground. • There are two portals: the West Portal, located at Mount Dennis Station and the East Portal, located west of Sunnybrook Park Station. • Tree groves and grasses will be planted on portals, as well as on station plazas, open spaces, and stops. 28
  • 30. Estimated Construction Schedule – Cut and Cover Stations 29
  • 33. Estimated Construction Schedule – Interchange Stations 31
  • 34. Stations in construction – Spring 2016 Keelesdale Laird Avenue 32 Mount Dennis
  • 35. Stations in construction – Spring 2016 Oakwood 33
  • 36. Stations in construction – Summer 2016 Caledonia Forest Hill (Bathurst) Fairbank (Dufferin) 34 Leaside (Bayview)
  • 37. Stations in construction – Summer 2016 Eglinton (Yonge)tCedarvale (Allen) 35 Science Centre
  • 38. Portal in construction – Fall 2016 West Portal (Eglinton Ave Box Tunnel) 36
  • 39. CTS will develop and execute plans to: • Ensure public health and safety • Manage traffic control • Coordinate with Emergency Services and transit • Communicate early and often • Use technology to share information in a timely way (i.e. a Mobile App to inform motorists of traffic disruption) • Maintain access to property and local businesses • Provide directional signage • Identify access to local businesses • Alert motorists of estimated travel time through the corridor We will manage disruptions 40
  • 40. Our Guiding Principles: • Offer meaningful and accurate communication – background/context so that the public and stakeholders can make informed comments and provide input on the Project; • Provide timely and transparent information early and often • Ensure two-way communication – for a fair and respectful dialogue • Allow for broad solutions – provide a corridor-wide focus as well as local outreach to continually inform the public and other stakeholders. Engaging the community is important to us 41