A Golden Opportunity In Northern Ireland




               Curraghinalt Deposit



        Investor Presentation November 2011

              Patrick F. N. Anderson
                  Chairman and
              Chief Executive Officer
Forward-Looking Information and Qualified Person


This presentation contains “forward‑looking information” which may include, but is not limited to, statements with respect to the future financial or operating performance of the Company, and
its mineral project, the future price of metals, the estimation of mineral resources, the realization of mineral resource estimates, the timing and amount of estimated future production, costs of
production, capital, operating and exploration expenditures, costs and timing of the development of new deposits, costs and timing of future exploration, requirements for additional capital,
government regulation of mining operations, environmental risks, reclamation expenses, title disputes or claims and limitations of insurance coverage. Often, but not always, forward‑looking
statements can be identified by the use of words and phrases such as “plans,” “expects,” “is expected,” “budget,” “scheduled,” “estimates,” “forecasts,” “intends,” “anticipates,” or “believes” or
variations (including negative variations) of such words and phrases, or state that certain actions, events or results “may,” “could,” “would,” “might” or “will” be taken, occur or be achieved.

Forward-looking statements are based on the opinions and estimates of management as of the date such statements are made and are based on various assumptions such as continued
political stability in Northern Ireland, that permits required for the company s operations will be obtained in a timely basis in order to permit the company to proceed on schedule with its
planned drilling programs, that skilled personnel and contractors will be available as the company s operations continue to grow, that the price of gold will beat levels that render the project
economic, or that the company will be able to continue raising the necessary capital to finance its operations and realize on mineral resource estimates.

Forward‑looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be
materially different from any future results, performance or achievements expressed or implied by the forward‑looking statements. Such factors include, among others, general business,
economic, competitive, political and social uncertainties; the actual results of current exploration activities; actual results of reclamation activities; conclusions of economic evaluations;
changes in project parameters as plans continue to be refined; future prices of metals; possible variations of ore grade or recovery rates; failure of plant, equipment or processes to operate
as anticipated; accidents, labour disputes and other risks of the mining industry; political instability; delays in obtaining governmental approvals or financing or in the completion of
development or construction activities, as well as those factors discussed in the section entitled “Risk Factors” in the company’s Annual Information Form.

Although the company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward‑looking statements,
there may be other factors that cause actions, events or results to differ from those anticipated, estimated or intended. Forward‑looking statements contained herein are made as of the date
of this presentation and the company disclaims any obligation to update any forward‑looking statements, whether as a result of new information, future events or results, except as may be
required by applicable securities laws. There can be no assurance that forward‑looking statements will prove to be accurate, as actual results and future events could differ materially from
those anticipated in such statements. Accordingly, readers should not place undue reliance on forward‑looking statements.

The technical data in this presentation was taken from the technical report entitled “A Mineral Resource Estimate for the Curraghinalt Gold Deposit and a Review of a Proposed Exploration
Program for the Tyrone Project, County Tyrone and County Londonderry, Northern Ireland dated May 10, 2010, prepared by B. Terrence Hennessey, P.Geo., and Dibya Kanti
Mukhopadhyay, M.Sc., MAusIMM, of Micon International Limited (the Technical Report ).

Garth Earls, Eur Geol, Managing Director, Dalradian Gold Limited, is the Qualified Person who supervised the preparation of the technical data in this presentation.




2
Why Invest?

•        High-grade 1.5MM ounce gold resource (all categories) 1
          •  Inferred: 1.16 million – 14.64 g/t Au
          •  Indicated: 400,000 – 13.24 g/t Au
•        6 drills turning
          •  Focus on resource expansion and confirmation
          •  Resource update planned for Q4 2011
•        84,000 ha property
          •  19 regional targets identified
          •  Exploration drilling underway
•        Low political risk
          •  Northern Ireland open for business and resource friendly
•        Experienced management and board
          •  Track record of discovery and development
•        Well funded
          •  Approximately $25 million in cash as at August 10, 2011
          •  Management owns > 8% as at October 4, 2011
 1   Please see the technical report for additional details




3
Corporate Information

•    TSX: DNA

•    IPO issue price: $1.50/share

•    Shares outstanding – 70.4 million


•    Fully diluted – 76.3 million

•    Market cap: $159 million as at Oct. 28,
     2011


•    Average volume (30 day): 123,493


•    Stock price at market close Oct. 28, 2011
     - $2.25


•    52 Week Range: $2.52 - $1.27

•    Analyst coverage
     –  GMP: Andrew Mikitchook                   As at October 28, 2011

     –  Clarus: Jamie Spratt




4
Board:
A Track Record of Discovery and Development

Patrick F. N. Anderson                          Keith D. McKay
Chairman and Chief Executive Officer            Chief Financial Officer
Former CEO of Aurelian Resources Inc.           Former CFO of Aurelian Resources Inc.
Also Director of Colossus Minerals Inc.,        And Director of Noront Resources Ltd.
Malbex Resources Inc. and Continental Gold
Limited                                         Thomas J. Obradovich
                                                Former CEO of Young-Davidson Mines Ltd.
Colin K. Benner                                 Former Director of Aurelian Resources Inc.
Chairman of Capstone Mining Corp.,              Chairman of Lago Dourado Minerals Ltd.
Creston Moly Corp., and Corsa Capital Ltd.
                                                Sean E. O. Roosen
Joseph F. Conway                                CEO of Osisko Mining Corporation
CEO of Primero Mining Corp.                     Also Director of Rio Novo Gold Inc. and
Former CEO of IAMGOLD Corporation               Bowmore Exploration Ltd.
Ronald P. Gagel                                 Ari B. Sussman
Former SVP and CFO of FNX Mining Company Inc.   Chairman and CEO of Colossus Minerals Inc.
Also Director of Adriana Resources Inc. and     CEO of Continental Gold Limited
Stonegate Agricom Ltd.




5
Exploring Northern Ireland


•    Devolved government within the United
     Kingdom

•    Currency: pound sterling

•    Population: approximately 1.8 million

•    The government of Northern Ireland recently
     invested millions of pounds in geological
     surveys to attract investment




                                Tellus Project




6
Northern Ireland: Developing Resources                                                                     U.K.



                                                          Curraghinalt
•  Excellent regional                                         Deposit
   infrastructure
                                                                                               Lonmin
•  Our flagship asset is the      NORTHERN
   Curraghinalt mesothermal       IRELAND

   high grade gold deposit
                                                                                                        Irish Salt
                                                            Gortin                Rousky                Mining

•  Over 84,000 hectares under                     Cavanacaw
   exploration                                    Galantas Gold      Omagh                                BELFAST



•  Potential exists for further
   precious and base metals
   deposits                                                                                Conroy
                                                                                           Diamonds
                                                                                           & Gold




                                  In production                   Exploring for        Platinum and                  Extensive
                                  since late                      gold along a         palladium                     underground
                                  2007                            50 km trend          exploration                   mining




7
Active Resource Industry in County Tyrone

There are approximately 150 open cast operations in Northern Ireland

              Curraghinalt
                  Deposit




    NORTHERN IRELAND




8
Curraghinalt: Open Along Strike

•        September 6, 2011 – Drilling
         at Curraghinalt intersects
         8.34 metres of 5.84 g/t gold
         and 3.2 metres grading 5.34
         g/t gold. Additional parallel
         veins discovered to the
         South of the deposit.

•        June 8, 2011 – Drilling at
         Curraghinalt intersects 2.06
         metres of 111.6 g/t gold and
         1.11 metres grading 26.84 g/
         t gold

•        April 7, 2011 – Hole 11-
         CT-85 cut 2.54 metres of
         20.61 g/t gold

•        February 28, 2011 – Hole 10-
         CT-76 cut 2.74 metres of
         15.27 g/t gold

•        December 2, 2010 – Hole 10-
         CT-73 cut 1.83 metres of
         37.41 g/t gold

•        October 14, 2010 –Two new
         parallel veins discovered




     9
Veins open at depth

•    Longer holes intercept as many as nine veins

•    Proximity favourable for shared infrastructure
                     385,800mN                                                         386,000mN                            386,200mN                  386,400mN      386,600mN        386,800mN




                                                                     E
                                                                                                                                                                                  E'
                                                                                                                                                                 89
                                                                                                                                                               T-
                                                                                                                                                             -C
                                                                                                                                                        11




                                                                                                                                                                                                   200mMSL
                 200mMSL




                                                                                                                                                                                                   0mMSL
                 0mMSL




                                                                                                                                                                                                   -200mMSL
                 -200mMSL




                                                             Curraghinalt Deposit
                                                                     E - E'
                            Date:07/06/2011
                                                              (Section 257050E)                    Legend
                            Author: Dalradian


                            Office: Gortin      Intercepts reported as:                                 Planned drillhole         Shear zone
                            Drawing: SC
                                                True width (m), Au grade (g/t)

                            Scale: 1:4000       Projection: Non-Earth (meters)
                                                                                                        Drillhole                 Vein (projected)
                                                                                                        complete/active




                                                                                                                                                                                                   -400mMSL
                 -400mMSL




                                                0          25          50        100                   Reported drillhole         Vein (intersected)
                                                                   metres


                                                                                       386,000mN                            386,200mN                  386,400mN      386,600mN




10
3D Schematic of Veins & Adit: Looking West




11
Long Section – T17 Vein


             256600 E




                         256800 E




                                     257000 E




                                                 257200 E




                                                                        257400 E




                                                                                    257600 E




                                                                                                           257800 E




                                                                                                                                 258000 E




                                                                                                                                                                   258200 E




                                                                                                                                                                                                        258400 E
      400                                                                                                                                                                                             400




      300                                                                                                                                                                                             300




      200                                                                                                                                                                                             200




      100                                                                                                                                                                                             100

                                                                                                11-CT-98
                                                                                                0.97
      0                                                                                         14.05                                                                                                    0




      -100                                                                                                                                                                                            -100



                                                                                                                                                                  11-CT-99
      -200                                                                                                                                                                                            -200
                                                                                                                                                                  2.70
                                                                                                                                                                  5.34


      -300                                                                                                                                                                                            -300
                                                             11-CT-90
                                                             0.65                                                      F*-##0"#$:%-;%/0-:%B*$::%*$#$5:$           F*-##0"#$:%"'/:-.$%*$:"'*<$
                                                             33.85                                                     1<".$.%)G%6*5(:%B$*%($/$*2                 1<".$.%)G%6*5(:%B$*%($/$*2

      -400                                                                                                                      !"#$%&'()$*                                    4*5(:%B$*%($/$*%4"#.   -400
                                                                                                                                +*'$%,-./0%1(2%
                                                                                                                                3'%4*5.$%167/2                                      H%I
                                                                                                                                                                                    I%?%@A
                                                                                                                                8*$9-"':%.*-##0"#$:%-;%*$:"'*<$
                                                                                                                                                                                    @A%?%@I
      -500                                                                                                                                                                          JK%@I
                                                                                                                                                                                                      -500
                                                                                                                                8#5;;$.%.*-##0"#$:




      -600
                                                                                                                                   =>?@A@%*$B"*/$.%C;.-<5/$.%D$:"'*<$:%                               -600
                                                                                                                                   =>?@A@%*$B"*/$.%C;E$**$.%D$:"'*<$:
                                                                                                                                                     West East Projection
      -700                                                                                                                                                                                            -700
                                                                                                                                                     Curraghinalt Deposit

                                                                                                                                               Section Northing: 386350
      -800                                                                                                                                                                                            -800
              256600 E




                          256800 E




                                      257000 E




                                                  257200 E




                                                                         257400 E




                                                                                     257600 E




                                                                                                            257800 E




                                                                                                                                  258000 E




                                                                                                                                                                    258200 E




                                                                                                                                                                                                         258400 E
                                                                                                                                                             T17 Vein

                                                                                                                                  Scale 1:7000                                   Date: 30/08/11
      -900                                                                                                                                                                                            -900




12
Long Section – No. 1 Vein

         500



                            256200 E




                                                               256400 E




                                                                                   256600 E




                                                                                                          256800 E




                                                                                                                      257000 E




                                                                                                                                  257200 E




                                                                                                                                              257400 E




                                                                                                                                                                     257600 E




                                                                                                                                                                                 257800 E
                                                                                                                                                                                             500




                                                                                                                                                                                                258000 E
         400                                                                                                                                                                                 400




         300                                                                                                                                                                                 300




         200                                                                                                                                                                                 200



                                                                                               11-CT-95
         100                                                                                                                                                                                 100
                                                                                               0.28
                                                                                               21.52


         0                                                                                                                                                                                     0

                                                                                                                                                          11-CT-94
                                                                                                                                                          7.54
         -100                                                                                                                                             5.84                               -100




         -200                                                                                                                                                                                -200
      F*-##0"#$:%-;%/0-:%B*$::%*$#$5:$               F*-##0"#$:%"'/:-.$%*$:"'*<$
      1<".$.%)G%6*5(:%B$*%($/$*2                     1<".$.%)G%6*5(:%B$*%($/$*2

         -300      !"#$%&'()$*                              4*5(:%B$*%($/$*%4"#.
                                                                                                                                                                                             -300
                   +*'$%,-./0%1(2%                                H%I
                   3'%4*5.$%167/2
                                                                  I%?%@A
                   8*$9-"':%.*-##0"#$:%-;%*$:"'*<$                @A%?%@I
         -400                                                     JK%@I                                                                                                                      -400
                   8#5;;$.%.*-##0"#$:



                   =>?@A@%*$B"*/$.%C;.-<5/$.%D$:"'*<$:%
         -500                                                                                                                                                                                -500
                   =>?@A@%*$B"*/$.%C;E$**$.%D$:"'*<$:

                                        West East Projection
         -600                                                                                                                                                                                -600
                                        Curraghinalt Deposit

                                Section Northing: 386200
         -700                                                                                                                                                                                -700
                             256200 E




                                                                256400 E




                                                                                    256600 E




                                                                                                           256800 E




                                                                                                                       257000 E




                                                                                                                                   257200 E




                                                                                                                                               257400 E




                                                                                                                                                                      257600 E




                                                                                                                                                                                  257800 E




                                                                                                                                                                                                 258000 E
                                             No.1 Vein

                Scale 1:7000                                 Date: 30/08/11
         -800                                                                                                                                                                                -800




13
Curraghinalt Trend




•    Glaciated terrain
     with minimal
     outcrop

•    Drilling is primary
     exploration tool




14
19 Target Areas – 3 Exploration Trends	
  




15
16
Dalradian: A Golden Opportunity in Northern Ireland

•    Initial strategy is to explore and develop Curraghinalt mesothermal gold deposit in
     Northern Ireland

•    Resource update in Q4 2011

•    Dalradian is exploring additional targets on its approximately 84,000-hectare   Tyrone
     Project

•    Well funded to execute on strategy




17
Appendix




18
Curraghinalt NI 43-101 Technical Report


•    Prepared by Micon International Limited

•    Dated May 10, 2010

•    Updated from November 2007 and reflects revised gold price


 Curraghinalt Mesothermal Gold Deposit
 Indicated
 0.95 MT @ 13.24 g/t Au for 0.4 million contained ounces with an average width of 1.35 m
 Inferred
 2.46 MT @ 14.64 g/t Au for 1.16 million contained ounces with an average width of 1.18 m
 Notes:
 §  Subject to a 2% NSR royalty to Minco Plc and a 4% royalty to the Crown Estate on silver and/or gold production
 §  Assumes US$900/oz and an economic cut-off grade of 5 g/t Au over a minimum thickness of 0.10 metres, diluted to 1 metre at 0 grade
 §  Using a cut-off grade of 5 g/t
 §  All veins less than 10 cm were excluded
 §  Width or vein thickness is measured at 90 degrees to the vertical
 §  "Vein thickness" refers to a zone of grade and may not be 100 per cent vein material
 §  Please see "A Mineral Estimate for The Curraghinalt Gold Deposit and A Review of a Proposed Exploration Program for the Tyrone Project, County Tyrone and
     County Londonderry, Northern Ireland" dated May 10, 2010 and available at www.dalradian.com




19
Multiple High Grade Gold Veins – 43-101


Name                                      Width    Grade      Depth
Sheep Dip Vein                            1.1 m   29.3 g/t   149.6 m
                                          1.3 m   31.4 g/t    36.1 m

Mullen Vein                               1.0 m   19.3 g/t   274.0 m
                                          1.3 m   19.6 g/t    49.9 m

T-17 HW Vein                              4.1 m   42.7 g/t    42.9 m
                                          1.6 m   56.3 g/t   416.2 m

T-17 Vein                                 3.4 m   68.1 g/t    39.6 m
                                          1.5 m   27.0 g/t   107.0 m

No. 1 Vein                                2.0 m   48.7 g/t    77.0 m
                                          1.3 m   65.7 g/t   159.8 m

106-16 Vein                               2.0 m   24.0 g/t    41.5 m
                                          3.3 m   16.9 g/t   615.7 m

Road Cut Vein                             1.6 m   14.1 g/t    55.5 m
                                          1.2 m   13.9 g/t   123.1 m



20
Cross-section A to A'

         385,800mN                                                    386,000mN                               386,200mN                  386,400mN                                             386,600mN                             386,800mN




                                                                                                                                                                                                                                                              200mMSL
                                                                                                                                                                                          95
                                                                                                                                                                                     T-
      200mMSL




                                                                                                                                                                                -C
                                                                                                                                                                              11




                                                                                                                                                     0.28m
                                                                                                                                                             @ 21.5
                                                                                                                                                                      2 g/t




                                                                                                                                                                                                                                                              0mMSL
      0mMSL




                                                                                  Hole in progress




                                                                                                                                                                                                                                                              -200mMSL
      -200mMSL




                                                                                             517.00m E.O.H.




                                     Dalradian Resources                                                                  Hole in progress


                                           Curraghinalt Deposit
                 Date:30/08/2011              Figure 3: A - A'
                 Author: Dalradian          (Section 256685E)                                                                                                                                              Legend
                 Office: Gortin             Intercepts reported as:
                 Drawing: KB             True width (m), Au grade (g/t)                                                                                                                                         Planned drillhole         Shear zone
                 Scale: 1:4000       Projection: Non-Earth (meters)




                                                                                                                                                                                                                                                              -400mMSL
                                                                                                                                                                                                                Drillhole                Vein (projected)
      -400mMSL




                                                                                                                                                                                                                complete/active
                                                                                                                                                                                                                Reported drillhole       Vein (intersected)
                                                                      386,000mN                               386,200mN                  386,400mN                                             386,600mN




21
Cross-section B to B'

                                   385,600mN                           385,800mN             386,000mN          386,200mN         386,400mN   386,600mN   386,800mN        387,000mN   387,200mN




                                                        B
                                                                                                                                                                      B'




                                                                                                                                                                                                     200mMSL
       200mMSL




                                                                                                                                                                                                     0mMSL
       0mMSL




                                                                                                                                                                                                     -200mMSL
       -200mMSL




                                                                                                                                                                                                     -400mMSL
       -400mMSL




                                                                                                                                                                                                     -600mMSL
       -600mMSL




                                            Curraghinalt Deposit
                                               Figure 4: B - B'
                  Date:30/08/2011
                                             (Section 257280E)
                  Author: Dalradian                                                Legend
                  Office: Gortin            Intercepts reported as:




                                                                                                                                                                                                     -800mMSL
                                         True width (m), Au grade (g/t)                 Planned drillhole    Shear zone
                  Drawing: KB

                  Scale: 1:7000       Projection: Non-Earth (meters)
       -800mMSL




                                                                                        Drillhole            Vein (projected)
                                                                                        complete/active
                       0               75              150                  300
                                                                                        Reported drillhole   Vein (intersected)
                                                     metres


                                      385, 600mN                       385,800mN             386,000mN          386,200mN         386,400mN   386,600mN   386,800mN        387,000mN    387, 200mN




22
Cross-section C to C'

             385,400mN                                    385,600mN          385,800mN                 386,000mN                 386,200mN   386,400mN    386,600mN   386,800mN               387,000mN   387,200mN




                                                                                  C                                                                                                      C'




                                                                                                                                                                94
                                                                                                                                                            CT -
                                                                                                                                                         11-




                                                                                                                                                                                                                      200mMSL
                                                                                                                                                                                      7b
                                                                                                                                                                                    -9
      200mMSL




                                                                                                                                                                                     T
                                                                                                                                                                                  -C
                                                                                                                                                                              11




                                                                                                                                                                                                                      0mMSL
      0mMSL




                                                                                                                                                                                                                      -200mMSL
      -200mMSL




                                                                                                                                                                                                                      -400mMSL
      -400mMSL




                                                                                                                                                                                                                      -600mMSL
      -600mMSL




                                     Dalradian Resources

                                            Curraghinalt Deposit
                 Date:30/08/2011
                                               Figure 5: C - C'
                                             (Section 257470E)
                 Author: Dalradian                                          Legend
                 Office: Gortin           Intercepts reported as:
                                       True width (m), Au grade (g/t)             Planned drillhole         Shear zone




                                                                                                                                                                                                                      -800mMSL
                 Drawing: KB

                 Scale: 1:7000       Projection: Non-Earth (meters)
                                                                                  Drillhole                 Vein (projected)
      -800mMSL




                                                                                  complete/active
                      0                75              150            300
                                                                                  Reported drillhole        Vein (intersected)
                                                     metres


                                                          385,600mN          385,800mN                 386,000mN                 386,200mN   386,400mN    386,600mN   386,800mN               387,000mN




23
Cross-section D to D'
                                           385,400mN                        385,600mN            385,800mN        386,000mN             386,200mN             386,400mN     386,600mN   386,800mN        387,000mN   387,200mN




                                                                        D




                                                                                                                                                                                 8
                                                                                                                                                                                                    D'




                                                                                                                                                                               9
                                                                                                                                                                            T-
                                                                                                                                                                            -C




                                                                                                                                                                                                                                 200mMSL
                                                                                                                                                                          11
      200mMSL




                                                                                                                                                                                                                                 0mMSL
      0mMSL




                                                                                                                                                                                                                                 -200mMSL
      -200mMSL




                                                                                                                                                                                                                                 -400mMSL
      -400mMSL




                                                                                                                                           Hole in progress

                                                                                                 1005.00 E.O.H.




                                                                                                                                                                                                                                 -600mMSL
      -600mMSL




                                                                                                                                                    Planned hole




                                                                                                                                                                                                                                 -800mMSL
      -800mMSL




                                                   Curraghinalt Deposit
                                                      Figure 6: D - D'
                   Date:30/08/2011
                                                    (Section 257680E)
                   Author: Dalradian
                                                                                        Legend
                   Office: Gortin             Intercepts reported as:
                                                                                             Planned drillhole     Shear zone
                   Drawing: KB             True width (m), Au grade (g/t)




                                                                                                                                                                                                                                 -1,000mMSL
                   Scale: 1:8000       Projection: Non-Earth (meters)                        Drillhole             Vein (projected)
      -1,000mMSL




                                                                                                                                                        Planned hole
                                                                                             complete/active
                           0              75             150                  300            Reported drillhole    Vein (intersected)
                                                      metres

                                           385,400mN                        385,600mN            385,800mN        386,000mN             386,200mN             386,400mN     386,600mN   386,800mN        387,000mN




24
Cross-section E to E'

                                        385,400mN                       385,600mN                385,800mN                 386,000mN                     386,200mN              386,400mN   386,600mN   386,800mN        387,000mN   387,200mN




                                                                                                                                                          6
                                                                                                                                              1 1 - C T- 9
                                                                                    E




                                                                                                                                                       92
                                                                                                                                                                                                                    E'




                                                                                                                                                    T-
                                                                                                                                                 -C
                                                                                                                                              11




                                                                                                                                                                                                                                                   200mMSL
       200mMSL




                                                                                                                                                                                                                                                   0mMSL
                                                                                            355.00 E.O.H.
       0mMSL




                                                                                                                 469.00 E.O.H.




                                                                                                                                                                                                                                                   -200mMSL
                                                                                                                                                    Planned hole
       -200mMSL




                                                                                                                                                                                                                                                   -400mMSL
       -400mMSL




                                                                                                                                                          Planned hole




                                                                                                                                                                                                                                                   -600mMSL
       -600mMSL




                                                                                                                                                      Planned hole




                                                                                                                                                                                                                                                   -800mMSL
                                       Dalradian Resources

                                            Curraghinalt Deposit
       -800mMSL




                                               Figure 7: E - E'
                   Date:.30/08/2011
                                             (Section 257850E)                          Legend
                   Author: Dalradian

                   Office: Gortin          Intercepts reported as:
                                                                                             Planned drillhole                   Shear zone
                   Drawing: KB          True width (m), Au grade (g/t)




                                                                                                                                                                                                                                                   -1,000mMSL
                   Scale: 1:8000       Projection: Non-Earth (meters)
                                                                                             Drillhole                           Vein (projected)                        Planned hole
                                                                                             complete/active
      -1,000mMSL




                            0             75            150                300
                                                                                             Reported drillhole                  Vein (intersected)
                                                      metres


                                           385,400mN                    385,600mN                385,800mN                 386,000mN                     386,200mN              386,400mN   386,600mN   386,800mN        387,000mN     387,200mN




25
Cross-section F to F'

                   385,200mN                                         385,400mN              385,600mN                  385,800mN                   386,000mN              386,200mN          386,400mN        386,600mN   386,800mN   387,000mN




                                                                                                                                                                                                              9
                                                                                                                                                                                                          T-9




                                                                                                                                                                                                                                             200mMSL
                                                                                                                                                                                                         -C
                                                                                                                                                                                                         11
     200mMSL




                                                                                                                                                                                                                                             0mMSL
                                                                                                             Planned hole
     0mMSL




                                                                                                                            Planned hole




                                                                                                                                                                                                                                             -200mMSL
                                                                                                                                               Planned hole
     -200mMSL




                                                                                                                                                                                                                                             -400mMSL
     -400mMSL




                                                                                                                                                           Planned hole




                                                                                                                                                                                                                                             -600mMSL
     -600mMSL




                                                Curraghinalt Deposit                                                                    Hole in progress
                                                   Figure 8: F - F'
                Date:30/08/2011
                                                 (Section 258235E)
                Author: Dalradian                                                  Legend
                                             Intercepts reported as:




                                                                                                                                                                                                                                             -800mMSL
                Office: Gortin

                Drawing: KB               True width (m), Au grade (g/t)                Planned drillhole          Shear zone
     -800mMSL




                Scale: 1:7000       Projection: Non-Earth (meters)
                                                                                        Drillhole                  Vein (projected)
                                                                                        complete/active                                                                       Planned hole
                    0                75                  150                 300
                                                                                        Reported drillhole         Vein (intersected)
                                                      metres

                                                                     385,400mN              385,600mN                  385,800mN                   386,000mN              386,200mN          386,400mN        386,600mN   386,800mN




26
Other Regional Prospects – Tyrone Volcanics


     Target              Name                        Peak Results                         Target defined by
                                                                                        Magnetic high, historical drilling,
TVG1          Broughderg            Trench: 1.5m @ 4.36g/t Au
                                                                                           trenching + Geochemistry


TVG3          Mulnafye              Float: 71.5 g/t Au                                          Au Geochemistry


TVG5          Bonnety Bush          Float: 4.54 g/t Au in ironstone               EM, IP, magnetics, Zn-Cu and Au Geochemistry


TVG6          Crosh-Racolpa         Float: 9.34 g/t Au                                 EM + Au geochemistry and outcrop.


TVG7          Tullybrick            Float: 1.87g/t Au in float                   EM and IP, Zn-Cu and Au geochemistry, + outcrop


                                    Float: 9.66 g/t Au.
TVG8          Formil                Float: 2.87 % Zn, 0.33% Cu and 2.53 % Pb.
                                                                                 EM, IP and Magnetics , Au, Z, Cu geochemistry




                                    Drilling: 52cm at 1.9% Pb+Zn, 0.48 g/t Au.
TVG9          Crouck-Aghascrebagh           And 6cm at 20.5 g/t Au.                EM, drilling and AU, Pb & Zn geochemistry
                                    Float:15.4g/t Au, 1.2% Pb and 8.84 % Zn.




27
Other Regional Prospects – Dalradian

      Target              Name         Most significant samples      Target defined by
     DSG2      Scotch-Town         Float: 10.52g/t Au from float.          Au Geochemistry

     DSG3      Curraghinalt East   Float: 44.96g/t Au                      Au Geochemistry

     DSG4      Alworries           Channel: 0.88m @ 39.43g/t Au.           Au Geochemistry

                                   Drilling: 0.6m @ 61.43g/t Au.
     DSG5      Golan Burn          Float: 13.7 g/t Au
                                                                      Drilling and Geochemistry


     DSG6      Owenkillew Valley   Float: 22.4g/t Au                       Au Geochemistry

     DSG7      Owenreagh Valley    Float: 11.68g/t Au                      Au Geochemistry

     DSG8      Gortin Glen         Float: 202.92 g/t Au             Au in Outcrop and Geochemistry

                                   Outcrop 2.96g/t Au
     DSG9      Bessy Bell          Float: 100.31 g/t Au
                                                                    Au in Outcrop and Geochemistry


     DSG10     Rylagh-Glengawna    Float 150.8 g/t Au.              Au in Outcrop and Geochemistry

                                   Float: 13.4 g/t Au
     DSG11     Coneyglen           Outcrop 3.04 g/t Au
                                                                    Au in Outcrop and Geochemistry


     DSG12     Glenerin            Outcrop: 2.07g/t Au.             Au in Outcrop and Geochemistry

     DSG13     Glenmacoffer        Float: 59.2 g/t Au               Au in Outcrop and Geochemistry




28
3 Exploration Trends - Geochemistry	
  




29
3 Exploration Trends - Magnetics	
  




30
A Golden Opportunity in
       Northern Ireland


      Patrick F. N. Anderson
                Chairman and
       Chief Executive Officer

         Shae-Lynn Mathers
  Director, Investor Relations:
                416-583-5622
    smathers@dalradian.com

            Trading Symbol:
                DNA on TSX

          Corporate Office:
    Dalradian Resources Inc.
  155 Wellington Street West
                  Suite 2920
       Toronto, ON M5V 3H1

          www.dalradian.com

More Related Content

What's hot

DNA AGM Investor Presentation June 20, 2011
DNA AGM Investor Presentation June 20, 2011DNA AGM Investor Presentation June 20, 2011
DNA AGM Investor Presentation June 20, 2011DalradianResource
 
Investor Presentation - February 2011
Investor Presentation - February 2011Investor Presentation - February 2011
Investor Presentation - February 2011dalradianresources
 
Alaska Gold Corp. PowerPoint Presentation
Alaska Gold Corp. PowerPoint PresentationAlaska Gold Corp. PowerPoint Presentation
Alaska Gold Corp. PowerPoint Presentationalaskametalscorp
 
Hawthorne Gold Corp Corporate Presentation
Hawthorne Gold Corp Corporate PresentationHawthorne Gold Corp Corporate Presentation
Hawthorne Gold Corp Corporate PresentationAdnet Communications
 
U.S. Silver and Gold Corporate Presentation - Novemberr 2012
U.S. Silver and Gold Corporate Presentation - Novemberr 2012U.S. Silver and Gold Corporate Presentation - Novemberr 2012
U.S. Silver and Gold Corporate Presentation - Novemberr 2012ussilver
 
March 2022 riley gold presentation
March 2022 riley gold presentationMarch 2022 riley gold presentation
March 2022 riley gold presentationZhalaRahim
 
U.S. Silver and Gold Corporate Presentation - November 2 2012
U.S. Silver and Gold Corporate Presentation - November 2 2012U.S. Silver and Gold Corporate Presentation - November 2 2012
U.S. Silver and Gold Corporate Presentation - November 2 2012ussilver
 
Southern Gold | ASX:SAU | RIS2014 Broken Hill Investor Presentation
Southern Gold | ASX:SAU | RIS2014 Broken Hill Investor PresentationSouthern Gold | ASX:SAU | RIS2014 Broken Hill Investor Presentation
Southern Gold | ASX:SAU | RIS2014 Broken Hill Investor PresentationSymposium
 

What's hot (10)

DNA AGM Investor Presentation June 20, 2011
DNA AGM Investor Presentation June 20, 2011DNA AGM Investor Presentation June 20, 2011
DNA AGM Investor Presentation June 20, 2011
 
Investor Presentation - February 2011
Investor Presentation - February 2011Investor Presentation - February 2011
Investor Presentation - February 2011
 
Alaska Gold Corp. PowerPoint Presentation
Alaska Gold Corp. PowerPoint PresentationAlaska Gold Corp. PowerPoint Presentation
Alaska Gold Corp. PowerPoint Presentation
 
MIL AGM Presentation
MIL AGM PresentationMIL AGM Presentation
MIL AGM Presentation
 
Webshow1
Webshow1Webshow1
Webshow1
 
Hawthorne Gold Corp Corporate Presentation
Hawthorne Gold Corp Corporate PresentationHawthorne Gold Corp Corporate Presentation
Hawthorne Gold Corp Corporate Presentation
 
U.S. Silver and Gold Corporate Presentation - Novemberr 2012
U.S. Silver and Gold Corporate Presentation - Novemberr 2012U.S. Silver and Gold Corporate Presentation - Novemberr 2012
U.S. Silver and Gold Corporate Presentation - Novemberr 2012
 
March 2022 riley gold presentation
March 2022 riley gold presentationMarch 2022 riley gold presentation
March 2022 riley gold presentation
 
U.S. Silver and Gold Corporate Presentation - November 2 2012
U.S. Silver and Gold Corporate Presentation - November 2 2012U.S. Silver and Gold Corporate Presentation - November 2 2012
U.S. Silver and Gold Corporate Presentation - November 2 2012
 
Southern Gold | ASX:SAU | RIS2014 Broken Hill Investor Presentation
Southern Gold | ASX:SAU | RIS2014 Broken Hill Investor PresentationSouthern Gold | ASX:SAU | RIS2014 Broken Hill Investor Presentation
Southern Gold | ASX:SAU | RIS2014 Broken Hill Investor Presentation
 

Viewers also liked

Facebook Page Insights
Facebook Page InsightsFacebook Page Insights
Facebook Page InsightsFarzan Sheikh
 
Evaluating natural based toothpaste
Evaluating natural based toothpasteEvaluating natural based toothpaste
Evaluating natural based toothpasteJojo Asavanamuang
 
State Of Online Video - TIMA presentation
State Of Online Video  - TIMA presentationState Of Online Video  - TIMA presentation
State Of Online Video - TIMA presentationLouise_Gordon
 

Viewers also liked (6)

Facebook Page Insights
Facebook Page InsightsFacebook Page Insights
Facebook Page Insights
 
Evaluating natural based toothpaste
Evaluating natural based toothpasteEvaluating natural based toothpaste
Evaluating natural based toothpaste
 
Presentacion Laura T
Presentacion Laura TPresentacion Laura T
Presentacion Laura T
 
Hands on Ruby on Rails
Hands on Ruby on RailsHands on Ruby on Rails
Hands on Ruby on Rails
 
State Of Online Video - TIMA presentation
State Of Online Video  - TIMA presentationState Of Online Video  - TIMA presentation
State Of Online Video - TIMA presentation
 
Marketing
MarketingMarketing
Marketing
 

Similar to Dna inves pre_november_2011

IR_PPT_Sept_2010
IR_PPT_Sept_2010IR_PPT_Sept_2010
IR_PPT_Sept_2010anandtest
 
DNA_IR_PPT_Sept_2010
DNA_IR_PPT_Sept_2010DNA_IR_PPT_Sept_2010
DNA_IR_PPT_Sept_2010anandtest
 
DNA_IR_PPT_Sept_2010
DNA_IR_PPT_Sept_2010DNA_IR_PPT_Sept_2010
DNA_IR_PPT_Sept_2010anandtest
 
DNA_IR_PPT_Sept_2010
DNA_IR_PPT_Sept_2010DNA_IR_PPT_Sept_2010
DNA_IR_PPT_Sept_2010anandtest
 
IR Presentation September 2010
IR Presentation September 2010IR Presentation September 2010
IR Presentation September 2010anandtest
 
DNAIRPPTSept2010
DNAIRPPTSept2010DNAIRPPTSept2010
DNAIRPPTSept2010anandtest
 
Investor Presentation - November 2010
Investor Presentation - November 2010Investor Presentation - November 2010
Investor Presentation - November 2010dalradianresources
 
Dalradian corporate presentation dec 2013 final
Dalradian corporate presentation dec 2013 finalDalradian corporate presentation dec 2013 final
Dalradian corporate presentation dec 2013 finalDalradianResource
 
Dna invest pre_feb2011_vfinal
Dna invest pre_feb2011_vfinalDna invest pre_feb2011_vfinal
Dna invest pre_feb2011_vfinalDalradianResource
 
Managing Director Presents at Proactive Investors' Investor Luncheons
Managing Director Presents at Proactive Investors' Investor LuncheonsManaging Director Presents at Proactive Investors' Investor Luncheons
Managing Director Presents at Proactive Investors' Investor LuncheonsMinotaur Exploration
 
Galane gold company presentation
Galane gold company presentationGalane gold company presentation
Galane gold company presentationGalaneGold
 
Asx annoucement agm presentation 21.11.11
Asx annoucement agm presentation 21.11.11Asx annoucement agm presentation 21.11.11
Asx annoucement agm presentation 21.11.11QRL
 
Pacton Gold Corporate Presentation
Pacton Gold Corporate PresentationPacton Gold Corporate Presentation
Pacton Gold Corporate PresentationMomentumPR
 
Gold Investment Symposium 2012 - Company presentation - Cortona Resources Lim...
Gold Investment Symposium 2012 - Company presentation - Cortona Resources Lim...Gold Investment Symposium 2012 - Company presentation - Cortona Resources Lim...
Gold Investment Symposium 2012 - Company presentation - Cortona Resources Lim...Symposium
 
Dna inves pre_april2011finalmk
Dna inves pre_april2011finalmkDna inves pre_april2011finalmk
Dna inves pre_april2011finalmkDalradianResource
 
Management Presentation
Management PresentationManagement Presentation
Management PresentationGalaneGold
 
Pinecrest corporatepresentation july2015
Pinecrest corporatepresentation july2015Pinecrest corporatepresentation july2015
Pinecrest corporatepresentation july2015Adnet Communications
 
Teslin River Resources Presentation September 2012
Teslin River Resources Presentation September 2012Teslin River Resources Presentation September 2012
Teslin River Resources Presentation September 2012Freeform Communications Inc.
 

Similar to Dna inves pre_november_2011 (20)

Dna inves pre_september_21_2011_final
Dna  inves pre_september_21_2011_finalDna  inves pre_september_21_2011_final
Dna inves pre_september_21_2011_final
 
IR_PPT_Sept_2010
IR_PPT_Sept_2010IR_PPT_Sept_2010
IR_PPT_Sept_2010
 
DNA_IR_PPT_Sept_2010
DNA_IR_PPT_Sept_2010DNA_IR_PPT_Sept_2010
DNA_IR_PPT_Sept_2010
 
DNA_IR_PPT_Sept_2010
DNA_IR_PPT_Sept_2010DNA_IR_PPT_Sept_2010
DNA_IR_PPT_Sept_2010
 
DNA_IR_PPT_Sept_2010
DNA_IR_PPT_Sept_2010DNA_IR_PPT_Sept_2010
DNA_IR_PPT_Sept_2010
 
IR Presentation September 2010
IR Presentation September 2010IR Presentation September 2010
IR Presentation September 2010
 
DNAIRPPTSept2010
DNAIRPPTSept2010DNAIRPPTSept2010
DNAIRPPTSept2010
 
Investor Presentation - November 2010
Investor Presentation - November 2010Investor Presentation - November 2010
Investor Presentation - November 2010
 
Dalradian corporate presentation dec 2013 final
Dalradian corporate presentation dec 2013 finalDalradian corporate presentation dec 2013 final
Dalradian corporate presentation dec 2013 final
 
Dna invest pre_feb2011_vfinal
Dna invest pre_feb2011_vfinalDna invest pre_feb2011_vfinal
Dna invest pre_feb2011_vfinal
 
Managing Director Presents at Proactive Investors' Investor Luncheons
Managing Director Presents at Proactive Investors' Investor LuncheonsManaging Director Presents at Proactive Investors' Investor Luncheons
Managing Director Presents at Proactive Investors' Investor Luncheons
 
Galane gold company presentation
Galane gold company presentationGalane gold company presentation
Galane gold company presentation
 
Asx annoucement agm presentation 21.11.11
Asx annoucement agm presentation 21.11.11Asx annoucement agm presentation 21.11.11
Asx annoucement agm presentation 21.11.11
 
07 11 12_f
07 11 12_f07 11 12_f
07 11 12_f
 
Pacton Gold Corporate Presentation
Pacton Gold Corporate PresentationPacton Gold Corporate Presentation
Pacton Gold Corporate Presentation
 
Gold Investment Symposium 2012 - Company presentation - Cortona Resources Lim...
Gold Investment Symposium 2012 - Company presentation - Cortona Resources Lim...Gold Investment Symposium 2012 - Company presentation - Cortona Resources Lim...
Gold Investment Symposium 2012 - Company presentation - Cortona Resources Lim...
 
Dna inves pre_april2011finalmk
Dna inves pre_april2011finalmkDna inves pre_april2011finalmk
Dna inves pre_april2011finalmk
 
Management Presentation
Management PresentationManagement Presentation
Management Presentation
 
Pinecrest corporatepresentation july2015
Pinecrest corporatepresentation july2015Pinecrest corporatepresentation july2015
Pinecrest corporatepresentation july2015
 
Teslin River Resources Presentation September 2012
Teslin River Resources Presentation September 2012Teslin River Resources Presentation September 2012
Teslin River Resources Presentation September 2012
 

More from DalradianResource

Dalradian Corporate Presentation May 2018
Dalradian Corporate Presentation May 2018Dalradian Corporate Presentation May 2018
Dalradian Corporate Presentation May 2018DalradianResource
 
Dalradian Corporate Presentation April 2018
Dalradian Corporate Presentation April 2018Dalradian Corporate Presentation April 2018
Dalradian Corporate Presentation April 2018DalradianResource
 
Dalradian Corporate Presentation February 2018
Dalradian Corporate Presentation February 2018Dalradian Corporate Presentation February 2018
Dalradian Corporate Presentation February 2018DalradianResource
 
Dalradian Corporate Presentation January 2018
Dalradian Corporate Presentation January 2018Dalradian Corporate Presentation January 2018
Dalradian Corporate Presentation January 2018DalradianResource
 
Dalradian Corporate Presentation November 2017
Dalradian Corporate Presentation November 2017Dalradian Corporate Presentation November 2017
Dalradian Corporate Presentation November 2017DalradianResource
 
Dalradian Corporate Presentation October 2017
Dalradian Corporate Presentation October 2017Dalradian Corporate Presentation October 2017
Dalradian Corporate Presentation October 2017DalradianResource
 
Dalradian Corporate Presentation September 2017
Dalradian Corporate Presentation September 2017Dalradian Corporate Presentation September 2017
Dalradian Corporate Presentation September 2017DalradianResource
 
Dalradian Resources AGM Presentation 2017
Dalradian Resources AGM Presentation 2017Dalradian Resources AGM Presentation 2017
Dalradian Resources AGM Presentation 2017DalradianResource
 
Dalradian Corporate Presentation March 30, 2017
Dalradian Corporate Presentation March 30, 2017Dalradian Corporate Presentation March 30, 2017
Dalradian Corporate Presentation March 30, 2017DalradianResource
 
Dalradian Corporate Presentation March 1, 2017
Dalradian Corporate Presentation March 1, 2017Dalradian Corporate Presentation March 1, 2017
Dalradian Corporate Presentation March 1, 2017DalradianResource
 
Dalradian Corporate Presentation February 2017
Dalradian Corporate Presentation February 2017Dalradian Corporate Presentation February 2017
Dalradian Corporate Presentation February 2017DalradianResource
 
Dalradian Corporate Presentation January 10, 2017
Dalradian Corporate Presentation January 10, 2017Dalradian Corporate Presentation January 10, 2017
Dalradian Corporate Presentation January 10, 2017DalradianResource
 
Dalradian Corporate Presentation December 12, 2016
Dalradian Corporate Presentation December 12, 2016Dalradian Corporate Presentation December 12, 2016
Dalradian Corporate Presentation December 12, 2016DalradianResource
 
Dalradian Presentation at Mines and Money London
Dalradian Presentation at Mines and Money London Dalradian Presentation at Mines and Money London
Dalradian Presentation at Mines and Money London DalradianResource
 
Dalradian presentation november 8 2016 final
Dalradian presentation november 8 2016 finalDalradian presentation november 8 2016 final
Dalradian presentation november 8 2016 finalDalradianResource
 
Dalradian presentation october 20 2016 final
Dalradian presentation october 20 2016 finalDalradian presentation october 20 2016 final
Dalradian presentation october 20 2016 finalDalradianResource
 
Dalradian presentation september 14 2016 final
Dalradian presentation september 14 2016 finalDalradian presentation september 14 2016 final
Dalradian presentation september 14 2016 finalDalradianResource
 
Investor Presentation - August 2016
Investor Presentation - August 2016Investor Presentation - August 2016
Investor Presentation - August 2016DalradianResource
 
Dalradian presentation july 25 2016
Dalradian presentation july 25 2016Dalradian presentation july 25 2016
Dalradian presentation july 25 2016DalradianResource
 
Dalradian presentation july 18 2016 final
Dalradian presentation july 18 2016 finalDalradian presentation july 18 2016 final
Dalradian presentation july 18 2016 finalDalradianResource
 

More from DalradianResource (20)

Dalradian Corporate Presentation May 2018
Dalradian Corporate Presentation May 2018Dalradian Corporate Presentation May 2018
Dalradian Corporate Presentation May 2018
 
Dalradian Corporate Presentation April 2018
Dalradian Corporate Presentation April 2018Dalradian Corporate Presentation April 2018
Dalradian Corporate Presentation April 2018
 
Dalradian Corporate Presentation February 2018
Dalradian Corporate Presentation February 2018Dalradian Corporate Presentation February 2018
Dalradian Corporate Presentation February 2018
 
Dalradian Corporate Presentation January 2018
Dalradian Corporate Presentation January 2018Dalradian Corporate Presentation January 2018
Dalradian Corporate Presentation January 2018
 
Dalradian Corporate Presentation November 2017
Dalradian Corporate Presentation November 2017Dalradian Corporate Presentation November 2017
Dalradian Corporate Presentation November 2017
 
Dalradian Corporate Presentation October 2017
Dalradian Corporate Presentation October 2017Dalradian Corporate Presentation October 2017
Dalradian Corporate Presentation October 2017
 
Dalradian Corporate Presentation September 2017
Dalradian Corporate Presentation September 2017Dalradian Corporate Presentation September 2017
Dalradian Corporate Presentation September 2017
 
Dalradian Resources AGM Presentation 2017
Dalradian Resources AGM Presentation 2017Dalradian Resources AGM Presentation 2017
Dalradian Resources AGM Presentation 2017
 
Dalradian Corporate Presentation March 30, 2017
Dalradian Corporate Presentation March 30, 2017Dalradian Corporate Presentation March 30, 2017
Dalradian Corporate Presentation March 30, 2017
 
Dalradian Corporate Presentation March 1, 2017
Dalradian Corporate Presentation March 1, 2017Dalradian Corporate Presentation March 1, 2017
Dalradian Corporate Presentation March 1, 2017
 
Dalradian Corporate Presentation February 2017
Dalradian Corporate Presentation February 2017Dalradian Corporate Presentation February 2017
Dalradian Corporate Presentation February 2017
 
Dalradian Corporate Presentation January 10, 2017
Dalradian Corporate Presentation January 10, 2017Dalradian Corporate Presentation January 10, 2017
Dalradian Corporate Presentation January 10, 2017
 
Dalradian Corporate Presentation December 12, 2016
Dalradian Corporate Presentation December 12, 2016Dalradian Corporate Presentation December 12, 2016
Dalradian Corporate Presentation December 12, 2016
 
Dalradian Presentation at Mines and Money London
Dalradian Presentation at Mines and Money London Dalradian Presentation at Mines and Money London
Dalradian Presentation at Mines and Money London
 
Dalradian presentation november 8 2016 final
Dalradian presentation november 8 2016 finalDalradian presentation november 8 2016 final
Dalradian presentation november 8 2016 final
 
Dalradian presentation october 20 2016 final
Dalradian presentation october 20 2016 finalDalradian presentation october 20 2016 final
Dalradian presentation october 20 2016 final
 
Dalradian presentation september 14 2016 final
Dalradian presentation september 14 2016 finalDalradian presentation september 14 2016 final
Dalradian presentation september 14 2016 final
 
Investor Presentation - August 2016
Investor Presentation - August 2016Investor Presentation - August 2016
Investor Presentation - August 2016
 
Dalradian presentation july 25 2016
Dalradian presentation july 25 2016Dalradian presentation july 25 2016
Dalradian presentation july 25 2016
 
Dalradian presentation july 18 2016 final
Dalradian presentation july 18 2016 finalDalradian presentation july 18 2016 final
Dalradian presentation july 18 2016 final
 

Recently uploaded

The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxmbikashkanyari
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menzaictsugar
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environmentelijahj01012
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Peter Ward
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 

Recently uploaded (20)

The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptxThe-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
The-Ethical-issues-ghhhhhhhhjof-Byjus.pptx
 
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environment
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 

Dna inves pre_november_2011

  • 1. A Golden Opportunity In Northern Ireland Curraghinalt Deposit Investor Presentation November 2011 Patrick F. N. Anderson Chairman and Chief Executive Officer
  • 2. Forward-Looking Information and Qualified Person This presentation contains “forward‑looking information” which may include, but is not limited to, statements with respect to the future financial or operating performance of the Company, and its mineral project, the future price of metals, the estimation of mineral resources, the realization of mineral resource estimates, the timing and amount of estimated future production, costs of production, capital, operating and exploration expenditures, costs and timing of the development of new deposits, costs and timing of future exploration, requirements for additional capital, government regulation of mining operations, environmental risks, reclamation expenses, title disputes or claims and limitations of insurance coverage. Often, but not always, forward‑looking statements can be identified by the use of words and phrases such as “plans,” “expects,” “is expected,” “budget,” “scheduled,” “estimates,” “forecasts,” “intends,” “anticipates,” or “believes” or variations (including negative variations) of such words and phrases, or state that certain actions, events or results “may,” “could,” “would,” “might” or “will” be taken, occur or be achieved. Forward-looking statements are based on the opinions and estimates of management as of the date such statements are made and are based on various assumptions such as continued political stability in Northern Ireland, that permits required for the company s operations will be obtained in a timely basis in order to permit the company to proceed on schedule with its planned drilling programs, that skilled personnel and contractors will be available as the company s operations continue to grow, that the price of gold will beat levels that render the project economic, or that the company will be able to continue raising the necessary capital to finance its operations and realize on mineral resource estimates. Forward‑looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by the forward‑looking statements. Such factors include, among others, general business, economic, competitive, political and social uncertainties; the actual results of current exploration activities; actual results of reclamation activities; conclusions of economic evaluations; changes in project parameters as plans continue to be refined; future prices of metals; possible variations of ore grade or recovery rates; failure of plant, equipment or processes to operate as anticipated; accidents, labour disputes and other risks of the mining industry; political instability; delays in obtaining governmental approvals or financing or in the completion of development or construction activities, as well as those factors discussed in the section entitled “Risk Factors” in the company’s Annual Information Form. Although the company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in forward‑looking statements, there may be other factors that cause actions, events or results to differ from those anticipated, estimated or intended. Forward‑looking statements contained herein are made as of the date of this presentation and the company disclaims any obligation to update any forward‑looking statements, whether as a result of new information, future events or results, except as may be required by applicable securities laws. There can be no assurance that forward‑looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward‑looking statements. The technical data in this presentation was taken from the technical report entitled “A Mineral Resource Estimate for the Curraghinalt Gold Deposit and a Review of a Proposed Exploration Program for the Tyrone Project, County Tyrone and County Londonderry, Northern Ireland dated May 10, 2010, prepared by B. Terrence Hennessey, P.Geo., and Dibya Kanti Mukhopadhyay, M.Sc., MAusIMM, of Micon International Limited (the Technical Report ). Garth Earls, Eur Geol, Managing Director, Dalradian Gold Limited, is the Qualified Person who supervised the preparation of the technical data in this presentation. 2
  • 3. Why Invest? •  High-grade 1.5MM ounce gold resource (all categories) 1 •  Inferred: 1.16 million – 14.64 g/t Au •  Indicated: 400,000 – 13.24 g/t Au •  6 drills turning •  Focus on resource expansion and confirmation •  Resource update planned for Q4 2011 •  84,000 ha property •  19 regional targets identified •  Exploration drilling underway •  Low political risk •  Northern Ireland open for business and resource friendly •  Experienced management and board •  Track record of discovery and development •  Well funded •  Approximately $25 million in cash as at August 10, 2011 •  Management owns > 8% as at October 4, 2011 1 Please see the technical report for additional details 3
  • 4. Corporate Information •  TSX: DNA •  IPO issue price: $1.50/share •  Shares outstanding – 70.4 million •  Fully diluted – 76.3 million •  Market cap: $159 million as at Oct. 28, 2011 •  Average volume (30 day): 123,493 •  Stock price at market close Oct. 28, 2011 - $2.25 •  52 Week Range: $2.52 - $1.27 •  Analyst coverage –  GMP: Andrew Mikitchook As at October 28, 2011 –  Clarus: Jamie Spratt 4
  • 5. Board: A Track Record of Discovery and Development Patrick F. N. Anderson Keith D. McKay Chairman and Chief Executive Officer Chief Financial Officer Former CEO of Aurelian Resources Inc. Former CFO of Aurelian Resources Inc. Also Director of Colossus Minerals Inc., And Director of Noront Resources Ltd. Malbex Resources Inc. and Continental Gold Limited Thomas J. Obradovich Former CEO of Young-Davidson Mines Ltd. Colin K. Benner Former Director of Aurelian Resources Inc. Chairman of Capstone Mining Corp., Chairman of Lago Dourado Minerals Ltd. Creston Moly Corp., and Corsa Capital Ltd. Sean E. O. Roosen Joseph F. Conway CEO of Osisko Mining Corporation CEO of Primero Mining Corp. Also Director of Rio Novo Gold Inc. and Former CEO of IAMGOLD Corporation Bowmore Exploration Ltd. Ronald P. Gagel Ari B. Sussman Former SVP and CFO of FNX Mining Company Inc. Chairman and CEO of Colossus Minerals Inc. Also Director of Adriana Resources Inc. and CEO of Continental Gold Limited Stonegate Agricom Ltd. 5
  • 6. Exploring Northern Ireland •  Devolved government within the United Kingdom •  Currency: pound sterling •  Population: approximately 1.8 million •  The government of Northern Ireland recently invested millions of pounds in geological surveys to attract investment Tellus Project 6
  • 7. Northern Ireland: Developing Resources U.K. Curraghinalt •  Excellent regional Deposit infrastructure Lonmin •  Our flagship asset is the NORTHERN Curraghinalt mesothermal IRELAND high grade gold deposit Irish Salt Gortin Rousky Mining •  Over 84,000 hectares under Cavanacaw exploration Galantas Gold Omagh BELFAST •  Potential exists for further precious and base metals deposits Conroy Diamonds & Gold In production Exploring for Platinum and Extensive since late gold along a palladium underground 2007 50 km trend exploration mining 7
  • 8. Active Resource Industry in County Tyrone There are approximately 150 open cast operations in Northern Ireland Curraghinalt Deposit NORTHERN IRELAND 8
  • 9. Curraghinalt: Open Along Strike •  September 6, 2011 – Drilling at Curraghinalt intersects 8.34 metres of 5.84 g/t gold and 3.2 metres grading 5.34 g/t gold. Additional parallel veins discovered to the South of the deposit. •  June 8, 2011 – Drilling at Curraghinalt intersects 2.06 metres of 111.6 g/t gold and 1.11 metres grading 26.84 g/ t gold •  April 7, 2011 – Hole 11- CT-85 cut 2.54 metres of 20.61 g/t gold •  February 28, 2011 – Hole 10- CT-76 cut 2.74 metres of 15.27 g/t gold •  December 2, 2010 – Hole 10- CT-73 cut 1.83 metres of 37.41 g/t gold •  October 14, 2010 –Two new parallel veins discovered 9
  • 10. Veins open at depth •  Longer holes intercept as many as nine veins •  Proximity favourable for shared infrastructure 385,800mN 386,000mN 386,200mN 386,400mN 386,600mN 386,800mN E E' 89 T- -C 11 200mMSL 200mMSL 0mMSL 0mMSL -200mMSL -200mMSL Curraghinalt Deposit E - E' Date:07/06/2011 (Section 257050E) Legend Author: Dalradian Office: Gortin Intercepts reported as: Planned drillhole Shear zone Drawing: SC True width (m), Au grade (g/t) Scale: 1:4000 Projection: Non-Earth (meters) Drillhole Vein (projected) complete/active -400mMSL -400mMSL 0 25 50 100 Reported drillhole Vein (intersected) metres 386,000mN 386,200mN 386,400mN 386,600mN 10
  • 11. 3D Schematic of Veins & Adit: Looking West 11
  • 12. Long Section – T17 Vein 256600 E 256800 E 257000 E 257200 E 257400 E 257600 E 257800 E 258000 E 258200 E 258400 E 400 400 300 300 200 200 100 100 11-CT-98 0.97 0 14.05 0 -100 -100 11-CT-99 -200 -200 2.70 5.34 -300 -300 11-CT-90 0.65 F*-##0"#$:%-;%/0-:%B*$::%*$#$5:$ F*-##0"#$:%"'/:-.$%*$:"'*<$ 33.85 1<".$.%)G%6*5(:%B$*%($/$*2 1<".$.%)G%6*5(:%B$*%($/$*2 -400 !"#$%&'()$* 4*5(:%B$*%($/$*%4"#. -400 +*'$%,-./0%1(2% 3'%4*5.$%167/2 H%I I%?%@A 8*$9-"':%.*-##0"#$:%-;%*$:"'*<$ @A%?%@I -500 JK%@I -500 8#5;;$.%.*-##0"#$: -600 =>?@A@%*$B"*/$.%C;.-<5/$.%D$:"'*<$:% -600 =>?@A@%*$B"*/$.%C;E$**$.%D$:"'*<$: West East Projection -700 -700 Curraghinalt Deposit Section Northing: 386350 -800 -800 256600 E 256800 E 257000 E 257200 E 257400 E 257600 E 257800 E 258000 E 258200 E 258400 E T17 Vein Scale 1:7000 Date: 30/08/11 -900 -900 12
  • 13. Long Section – No. 1 Vein 500 256200 E 256400 E 256600 E 256800 E 257000 E 257200 E 257400 E 257600 E 257800 E 500 258000 E 400 400 300 300 200 200 11-CT-95 100 100 0.28 21.52 0 0 11-CT-94 7.54 -100 5.84 -100 -200 -200 F*-##0"#$:%-;%/0-:%B*$::%*$#$5:$ F*-##0"#$:%"'/:-.$%*$:"'*<$ 1<".$.%)G%6*5(:%B$*%($/$*2 1<".$.%)G%6*5(:%B$*%($/$*2 -300 !"#$%&'()$* 4*5(:%B$*%($/$*%4"#. -300 +*'$%,-./0%1(2% H%I 3'%4*5.$%167/2 I%?%@A 8*$9-"':%.*-##0"#$:%-;%*$:"'*<$ @A%?%@I -400 JK%@I -400 8#5;;$.%.*-##0"#$: =>?@A@%*$B"*/$.%C;.-<5/$.%D$:"'*<$:% -500 -500 =>?@A@%*$B"*/$.%C;E$**$.%D$:"'*<$: West East Projection -600 -600 Curraghinalt Deposit Section Northing: 386200 -700 -700 256200 E 256400 E 256600 E 256800 E 257000 E 257200 E 257400 E 257600 E 257800 E 258000 E No.1 Vein Scale 1:7000 Date: 30/08/11 -800 -800 13
  • 14. Curraghinalt Trend •  Glaciated terrain with minimal outcrop •  Drilling is primary exploration tool 14
  • 15. 19 Target Areas – 3 Exploration Trends   15
  • 16. 16
  • 17. Dalradian: A Golden Opportunity in Northern Ireland •  Initial strategy is to explore and develop Curraghinalt mesothermal gold deposit in Northern Ireland •  Resource update in Q4 2011 •  Dalradian is exploring additional targets on its approximately 84,000-hectare Tyrone Project •  Well funded to execute on strategy 17
  • 19. Curraghinalt NI 43-101 Technical Report •  Prepared by Micon International Limited •  Dated May 10, 2010 •  Updated from November 2007 and reflects revised gold price Curraghinalt Mesothermal Gold Deposit Indicated 0.95 MT @ 13.24 g/t Au for 0.4 million contained ounces with an average width of 1.35 m Inferred 2.46 MT @ 14.64 g/t Au for 1.16 million contained ounces with an average width of 1.18 m Notes: §  Subject to a 2% NSR royalty to Minco Plc and a 4% royalty to the Crown Estate on silver and/or gold production §  Assumes US$900/oz and an economic cut-off grade of 5 g/t Au over a minimum thickness of 0.10 metres, diluted to 1 metre at 0 grade §  Using a cut-off grade of 5 g/t §  All veins less than 10 cm were excluded §  Width or vein thickness is measured at 90 degrees to the vertical §  "Vein thickness" refers to a zone of grade and may not be 100 per cent vein material §  Please see "A Mineral Estimate for The Curraghinalt Gold Deposit and A Review of a Proposed Exploration Program for the Tyrone Project, County Tyrone and County Londonderry, Northern Ireland" dated May 10, 2010 and available at www.dalradian.com 19
  • 20. Multiple High Grade Gold Veins – 43-101 Name Width Grade Depth Sheep Dip Vein 1.1 m 29.3 g/t 149.6 m 1.3 m 31.4 g/t 36.1 m Mullen Vein 1.0 m 19.3 g/t 274.0 m 1.3 m 19.6 g/t 49.9 m T-17 HW Vein 4.1 m 42.7 g/t 42.9 m 1.6 m 56.3 g/t 416.2 m T-17 Vein 3.4 m 68.1 g/t 39.6 m 1.5 m 27.0 g/t 107.0 m No. 1 Vein 2.0 m 48.7 g/t 77.0 m 1.3 m 65.7 g/t 159.8 m 106-16 Vein 2.0 m 24.0 g/t 41.5 m 3.3 m 16.9 g/t 615.7 m Road Cut Vein 1.6 m 14.1 g/t 55.5 m 1.2 m 13.9 g/t 123.1 m 20
  • 21. Cross-section A to A' 385,800mN 386,000mN 386,200mN 386,400mN 386,600mN 386,800mN 200mMSL 95 T- 200mMSL -C 11 0.28m @ 21.5 2 g/t 0mMSL 0mMSL Hole in progress -200mMSL -200mMSL 517.00m E.O.H. Dalradian Resources Hole in progress Curraghinalt Deposit Date:30/08/2011 Figure 3: A - A' Author: Dalradian (Section 256685E) Legend Office: Gortin Intercepts reported as: Drawing: KB True width (m), Au grade (g/t) Planned drillhole Shear zone Scale: 1:4000 Projection: Non-Earth (meters) -400mMSL Drillhole Vein (projected) -400mMSL complete/active Reported drillhole Vein (intersected) 386,000mN 386,200mN 386,400mN 386,600mN 21
  • 22. Cross-section B to B' 385,600mN 385,800mN 386,000mN 386,200mN 386,400mN 386,600mN 386,800mN 387,000mN 387,200mN B B' 200mMSL 200mMSL 0mMSL 0mMSL -200mMSL -200mMSL -400mMSL -400mMSL -600mMSL -600mMSL Curraghinalt Deposit Figure 4: B - B' Date:30/08/2011 (Section 257280E) Author: Dalradian Legend Office: Gortin Intercepts reported as: -800mMSL True width (m), Au grade (g/t) Planned drillhole Shear zone Drawing: KB Scale: 1:7000 Projection: Non-Earth (meters) -800mMSL Drillhole Vein (projected) complete/active 0 75 150 300 Reported drillhole Vein (intersected) metres 385, 600mN 385,800mN 386,000mN 386,200mN 386,400mN 386,600mN 386,800mN 387,000mN 387, 200mN 22
  • 23. Cross-section C to C' 385,400mN 385,600mN 385,800mN 386,000mN 386,200mN 386,400mN 386,600mN 386,800mN 387,000mN 387,200mN C C' 94 CT - 11- 200mMSL 7b -9 200mMSL T -C 11 0mMSL 0mMSL -200mMSL -200mMSL -400mMSL -400mMSL -600mMSL -600mMSL Dalradian Resources Curraghinalt Deposit Date:30/08/2011 Figure 5: C - C' (Section 257470E) Author: Dalradian Legend Office: Gortin Intercepts reported as: True width (m), Au grade (g/t) Planned drillhole Shear zone -800mMSL Drawing: KB Scale: 1:7000 Projection: Non-Earth (meters) Drillhole Vein (projected) -800mMSL complete/active 0 75 150 300 Reported drillhole Vein (intersected) metres 385,600mN 385,800mN 386,000mN 386,200mN 386,400mN 386,600mN 386,800mN 387,000mN 23
  • 24. Cross-section D to D' 385,400mN 385,600mN 385,800mN 386,000mN 386,200mN 386,400mN 386,600mN 386,800mN 387,000mN 387,200mN D 8 D' 9 T- -C 200mMSL 11 200mMSL 0mMSL 0mMSL -200mMSL -200mMSL -400mMSL -400mMSL Hole in progress 1005.00 E.O.H. -600mMSL -600mMSL Planned hole -800mMSL -800mMSL Curraghinalt Deposit Figure 6: D - D' Date:30/08/2011 (Section 257680E) Author: Dalradian Legend Office: Gortin Intercepts reported as: Planned drillhole Shear zone Drawing: KB True width (m), Au grade (g/t) -1,000mMSL Scale: 1:8000 Projection: Non-Earth (meters) Drillhole Vein (projected) -1,000mMSL Planned hole complete/active 0 75 150 300 Reported drillhole Vein (intersected) metres 385,400mN 385,600mN 385,800mN 386,000mN 386,200mN 386,400mN 386,600mN 386,800mN 387,000mN 24
  • 25. Cross-section E to E' 385,400mN 385,600mN 385,800mN 386,000mN 386,200mN 386,400mN 386,600mN 386,800mN 387,000mN 387,200mN 6 1 1 - C T- 9 E 92 E' T- -C 11 200mMSL 200mMSL 0mMSL 355.00 E.O.H. 0mMSL 469.00 E.O.H. -200mMSL Planned hole -200mMSL -400mMSL -400mMSL Planned hole -600mMSL -600mMSL Planned hole -800mMSL Dalradian Resources Curraghinalt Deposit -800mMSL Figure 7: E - E' Date:.30/08/2011 (Section 257850E) Legend Author: Dalradian Office: Gortin Intercepts reported as: Planned drillhole Shear zone Drawing: KB True width (m), Au grade (g/t) -1,000mMSL Scale: 1:8000 Projection: Non-Earth (meters) Drillhole Vein (projected) Planned hole complete/active -1,000mMSL 0 75 150 300 Reported drillhole Vein (intersected) metres 385,400mN 385,600mN 385,800mN 386,000mN 386,200mN 386,400mN 386,600mN 386,800mN 387,000mN 387,200mN 25
  • 26. Cross-section F to F' 385,200mN 385,400mN 385,600mN 385,800mN 386,000mN 386,200mN 386,400mN 386,600mN 386,800mN 387,000mN 9 T-9 200mMSL -C 11 200mMSL 0mMSL Planned hole 0mMSL Planned hole -200mMSL Planned hole -200mMSL -400mMSL -400mMSL Planned hole -600mMSL -600mMSL Curraghinalt Deposit Hole in progress Figure 8: F - F' Date:30/08/2011 (Section 258235E) Author: Dalradian Legend Intercepts reported as: -800mMSL Office: Gortin Drawing: KB True width (m), Au grade (g/t) Planned drillhole Shear zone -800mMSL Scale: 1:7000 Projection: Non-Earth (meters) Drillhole Vein (projected) complete/active Planned hole 0 75 150 300 Reported drillhole Vein (intersected) metres 385,400mN 385,600mN 385,800mN 386,000mN 386,200mN 386,400mN 386,600mN 386,800mN 26
  • 27. Other Regional Prospects – Tyrone Volcanics Target Name Peak Results Target defined by Magnetic high, historical drilling, TVG1 Broughderg Trench: 1.5m @ 4.36g/t Au trenching + Geochemistry TVG3 Mulnafye Float: 71.5 g/t Au Au Geochemistry TVG5 Bonnety Bush Float: 4.54 g/t Au in ironstone EM, IP, magnetics, Zn-Cu and Au Geochemistry TVG6 Crosh-Racolpa Float: 9.34 g/t Au EM + Au geochemistry and outcrop. TVG7 Tullybrick Float: 1.87g/t Au in float EM and IP, Zn-Cu and Au geochemistry, + outcrop Float: 9.66 g/t Au. TVG8 Formil Float: 2.87 % Zn, 0.33% Cu and 2.53 % Pb. EM, IP and Magnetics , Au, Z, Cu geochemistry Drilling: 52cm at 1.9% Pb+Zn, 0.48 g/t Au. TVG9 Crouck-Aghascrebagh And 6cm at 20.5 g/t Au. EM, drilling and AU, Pb & Zn geochemistry Float:15.4g/t Au, 1.2% Pb and 8.84 % Zn. 27
  • 28. Other Regional Prospects – Dalradian Target Name Most significant samples Target defined by DSG2 Scotch-Town Float: 10.52g/t Au from float. Au Geochemistry DSG3 Curraghinalt East Float: 44.96g/t Au Au Geochemistry DSG4 Alworries Channel: 0.88m @ 39.43g/t Au. Au Geochemistry Drilling: 0.6m @ 61.43g/t Au. DSG5 Golan Burn Float: 13.7 g/t Au Drilling and Geochemistry DSG6 Owenkillew Valley Float: 22.4g/t Au Au Geochemistry DSG7 Owenreagh Valley Float: 11.68g/t Au Au Geochemistry DSG8 Gortin Glen Float: 202.92 g/t Au Au in Outcrop and Geochemistry Outcrop 2.96g/t Au DSG9 Bessy Bell Float: 100.31 g/t Au Au in Outcrop and Geochemistry DSG10 Rylagh-Glengawna Float 150.8 g/t Au. Au in Outcrop and Geochemistry Float: 13.4 g/t Au DSG11 Coneyglen Outcrop 3.04 g/t Au Au in Outcrop and Geochemistry DSG12 Glenerin Outcrop: 2.07g/t Au. Au in Outcrop and Geochemistry DSG13 Glenmacoffer Float: 59.2 g/t Au Au in Outcrop and Geochemistry 28
  • 29. 3 Exploration Trends - Geochemistry   29
  • 30. 3 Exploration Trends - Magnetics   30
  • 31. A Golden Opportunity in Northern Ireland Patrick F. N. Anderson Chairman and Chief Executive Officer Shae-Lynn Mathers Director, Investor Relations: 416-583-5622 smathers@dalradian.com Trading Symbol: DNA on TSX Corporate Office: Dalradian Resources Inc. 155 Wellington Street West Suite 2920 Toronto, ON M5V 3H1 www.dalradian.com