SlideShare une entreprise Scribd logo
1  sur  159
Télécharger pour lire hors ligne
Bridge Construction, Project Execution Plan
Details of how a Bridge is constructed, and how the progress, safety and quality will be monitored
and controlled. Also the measures to ensure that the site is environmentally friendly.
David H Moloney
8th August 2016
Brief Description
The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to
construct an insitu concrete bridge.
This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the
programme. Also can be used for Induction Training and as a way to capture and share knowledge.
Project Execution Plan (PEP) details how a project will be executed, monitored and controlled. High in
Educational Value and easily understood. Recommended for Continuing Professional Development (CPD)
This Presentation is innovative and has many beneficial uses.
Table of Contents
Introduction
Project Location & Nearby National Roads
Introduction
Location of Bridge on Site
Muscat Airport, Oman
Introduction
Description & Scope
Brief Description & Scope
Four span insitu post-tensioned deck, Piled foundations.
Construction of the Bridge and Handover.
Introduction
General Items
Contractor’s Temporary Site Facilities
ⓒ David H Moloney
GeneralItems
To see animations, see my YouTube Film
Welfare Facilities
ⓒ David H Moloney
GeneralItems
Toilets – Washing
Canteen, Drying Room, Toilet & Generator
Temporary Roads & Entrances
ⓒ David H Moloney
GeneralItems
Site Hoarding examples
ⓒ David H Moloney
GeneralItems
Dust Suppression
ⓒ David H Moloney
GeneralItems
Wheel Wash Drive-through
ⓒ David H Moloney
GeneralItems
Temporary Electricity Supply & Tower Lights
ⓒ David H Moloney
GeneralItems
Contractor’s Temporary Site Facilities
ⓒ David H Moloney
GeneralItems
Brief Description
Contractors Site facilities comprise:
Offices, Canteens, Toilets, Drying Rooms,
Stores, Plant Yard, generators and
Workshops.
Dewatering
ⓒ David H Moloney
GeneralItems
Brief Description
Construction dewatering is the removal or drainage of
groundwater and or surface / rain water usually by
pumping to keep the works dry.
Dewatering
ⓒ David H Moloney
GeneralItems
Brief Description
Construction dewatering is the removal or
drainage of groundwater and or surface /
rain water usually by pumping to keep the
works dry.
Dewatering
ⓒ David H Moloney
GeneralItems
Temporary WorksGeneralItems
FalseworkGeneralItems
Brief Description
Falsework to support Bridge deck formwork until the deck is post-
tensioned and becomes self supporting
Sheet Pile Temporary Shaft
ⓒ David H Moloney
GeneralItems
Brief Description
Sheet Pile Temporary shaft is used to enable an
excavation for a deep structure.
The construction sequence is:
Install sheet-piles.
Excavate and install bracing.
Excavate to final level.
Construct concrete structure.
Backfill, remove bracing and sheet-piles
Sheet pile Temporary Shaft
ⓒ David H Moloney
GeneralItems
3D Animation to show Sequence
Sheet pile Cofferdam for Piers
ⓒ David H Moloney
GeneralItems
Traffic Management
ⓒ David H Moloney
GeneralItems
Brief Description
Traffic management plans are
necessary when working on or beside
roads
Traffic Management – Work on Median
ⓒ David H Moloney
GeneralItems
Earthworks
Much Shifting
Brief Description
Muck Shifting is the process of moving
large quantities of soil and rock.
Earthworks
Excavate & Load, Cart, Tip & Return
Brief Description
Cycle Time for 7km haulage distance
using an Excavator 45 tonne weight
and Dumper with a 40 tonne capacity,
the cycle time is 34 minutes
Earthworks
7 minutes
14 minutes
3 minutes
14 minutes 7 km
7 km
Loading Tipper TrucksEarthworks
Tipping & Spreading FillEarthworks
Spreading & CompactionEarthworks
Spreading & CompactionEarthworks
Excavation for Trench with Stepped FacesEarthworks
Excavation for Trench with Battered FacesEarthworks
Backfill TrenchEarthworks
Rock - Excavability
Brief Description
The excavability of rock depends
mainly on the rock strength and the
layer thickness. This diagram shows
excavation methods for rock of
various strengths and thicknesses,
with a free face.
ⓒ David H Moloney
Earthworks
Earthworks
Excavator with Hydraulic Rock-breaker
Excavator with Hydraulic Rock-breakerEarthworks
Mass Haul DiagramEarthworks
Brief Description
Shows the quantities and location of
excavation and fill quantities for
motorway.
Concrete
Concrete Full Scale Trial Castings of Pier
ⓒ David H Moloney
Brief Description
The full-scale trial casting(s) shall
demonstrate/document that all
requirements to the concrete and the
execution of the work are fulfilled
simultaneously using the actual
methods and performed by personnel as
for the future production.
Concrete
BIM 3D Model Shutter Fibreglass
Concrete Full Scale Trial Castings of Bridge Deck
Brief Description
The full-scale trial casting(s) shall
demonstrate/document that all
requirements to the concrete and the
execution of the work are fulfilled
simultaneously using the actual
methods and performed by personnel as
for the future production.
Concrete
Fresh Concrete Properties Tests
Air Content, Consistence, Density, Initial and Final Setting Time, Temperature
and Bleeding
Chloride Ion Content
Hardening and Hardened Concrete Properties Tests:
Density and Compressive Strength for 1, 3, 7, 14 and 28 Days
Concrete Core Compressive Strength
Tensile Splitting Strength
Modulus of Elasticity
Heat Development
Chloride Migration Coefficient (28 Days)
Reinforcement Cover Measurement Survey
Concrete Tests
ⓒ David H Moloney
Concrete
Trial Grouting of Post-tensioning Duct
ⓒ David H Moloney
Brief Description
The full-scale trial of grouting operation shall
demonstrate/document that all requirements to the grout and the
execution of the work are fulfilled simultaneously using the actual
methods and performed by personnel as for the future production.
Pre-trials were carried out in the site laboratory and by way of a
mock-up to check the following in accordance with BS EN 447:
i Fluidity
ii Bleeding and re-absorption
iii Compressive strength (3 cubes at 28 days, all > 30 N/mm2)
iv Mixing ratio (w/c < 0.40)
v Expansion (-1 % - +5 %). For grouts with expanding admixtures
there shall be no decrease in volume
Concrete
Trial for Waterproofing to Bridge Deck
ⓒ David H Moloney
Brief Description
. The trial for the deck waterproofing
shall demonstrate/document that all
requirements to the waterproofing and
the execution of the work are fulfilled
simultaneously using the actual
methods and performed by personnel as
for the future production.
Concrete
Trial for Waterproofing to Bridge Deck - Tests
Concrete
Concrete Batching Plant David H Moloney
ⓒ David H Moloney
Brief Description
Concrete batching plant comprises -
concrete mixer, control cabin, silos for
cement and fly ash, aggregate bins and
conveyor belt system to feed the mixer.
Also aggregate storage bays and water
storage tanks.
Concrete
Concrete Batching Plant
ⓒ David H Moloney
Concrete
Concrete Batching Plant 3Nr.
ⓒ David H Moloney
Concrete
Concrete Batching Plant – Computer Controlled
ⓒ David H Moloney
Concrete
Concrete Batching Plant - Liebherr Betomix Animation
Concrete
Concrete Batching Plant David H Moloney
ⓒ David H Moloney
Brief Description
.
The mixing is computer controlled
and has a dynamic screen display,
showing the process. The material
storage capacity is, to match two
days concrete production.
Concrete
Concrete Mix Proportions per Cu M
Brief Description
.
Details of Mix for C40
1. Concrete Grade C40
2. Cement Type = OPC
3. Slump =125mm
4. Max size aggregate = 20mm
5. Max water / Cementitious ration =0.42
Concrete
Materials Qty Units
Cement 310 Kgs
Fly ash 100 Kgs
Micro-silica 12 Kgs
Washed Sand 670 Kgs
Fine Sand 106 Kgs
10mm Crushed aggregate 400 Kgs
20mm Crushed aggregates 725 Kgs
Water 145 Ltr.
Additive Rheobuild 7.5 Ltr.
Concrete MixGeneralItems
A concrete mix contains 5 major
elements: cement, water, coarse
aggregates, fine aggregates (sand) and
air in different proportion. Additional
elements such as pozzolanic materials (fly
ash, silica fumes or slag) and chemical
admixtures can also be incorporated to
the mix to increase its properties.
Quarry & Aggregate Production
ⓒ David H Moloney
Concrete
Brief Description
Quarry and Aggregate Production. Rock is
blasted free from a quarry face and fragmented.
The blasted rock is crushed and screened to
produce different size ranges of aggregates
Quarry & Aggregate Production
ⓒ David H Moloney
Concrete
Reinforcement Cutting & Bending Yard
ⓒ David H Moloney
Concrete
Brief Description
Reinforcement in 12 m lengths.
Delivery in 3 ton Bundles
Reinforcement Cutting & Bending
ⓒ David H Moloney
Concrete
Reinforcement Cutting & Bending
ⓒ David H Moloney
Concrete
Reinforcement Cutting & Bending Yard David H Moloney
ⓒ David H Moloney
Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine
Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site
Concrete
Reinforced Wall Construction Sequence
ⓒ David H Moloney
Concrete
Brief Description
The sequence to construct a reinforced concrete wall is as
follows:
Tie the reinforcement.
Erect stop-ends and the wall shutters.
Pour and vibrate the concrete mix.
Remove the shutters after the concrete has hardened.
.
Cycle Time
Pour per Day
Reinforced Wall Construction Sequence
ⓒ David H Moloney
Concrete
Vibrating Concrete
ⓒ David H Moloney
Concrete
Bridge & Post-tensioning
Concrete
Brief Description
The sequence to post-tension a bridge
deck is as follows;
Fix the ducts and anchorages.
Install the stressing strand.
Concrete the deck.
Stress the strands and lock at
anchorages.
Grout the ducts.
Bridge & Post-tensioning
Concrete
Bridge & Post-tensioning
Concrete
Bridge Concrete Deck
Concrete
Bridge Concrete Deck
Concrete
Bridge Post Tensioning Deck – Install Strand
Concrete
Bridge Post Tensioning Deck
Concrete
Bridge Construction Sequence David H Moloney
ⓒ David H Moloney
Concrete
Piling
Piling Construction - Plant & Methods
Brief Description
Piling Plant, Equipment and Material;
Crawler Crane, Piling Hammer, Temporary Casing,
Piling Rig, Concrete Pump, Concrete Mixer Trucks,
Tremie Pipe and Reinforcement Cage
Piling
Piling Construction - Plant, Methods & SequencePiling
Piling Construction - Plant & MethodsPiling
Piling Construction - Vertical PilesPiling
Piling Construction - Raking PilesPiling
Piling Construction - Raking PilesPiling
Pile Load Test
ⓒ David H Moloney
Piling
Brief Description
A jack is used to load the pile in steps and
gauges measure any settlement.
Pile Load Test
ⓒ David H Moloney
Piling
Roads & Pavings
Asphalt Batching Yard
Roads&Pavings
Brief Description
Asphalt Batching Yard
Capacity of main batching plant is
250 tonnes per hour .
Asphalt Batching Yard
Roads&Pavings
Asphalt Batching Yard
Roads&Pavings
Asphalt Batching Yard
Roads&Pavings
Asphalt Batching Yard
Roads&Pavings
Asphalt Batching Yard
Roads&Pavings
Road Construction
Brief Description
Sequence, methods and plant to construct a
motorway on a high embankment
Roads&Pavings
Road Construction
Roads&Pavings
Road Construction
Roads&Pavings
Asphalt Pavement - Tests
Roads&Pavings
Miscellaneous Works
Fencing
Miscellaneous
Brief Description
Fencing.
Sequence of construction;
1. Clear and grade the ground.
2. Fix corner and straining posts.
3. Fix intermediate posts.
4. Fix line wire, chain-link and razor wire.
5. Construct concrete ground beam
Fencing
Miscellaneous
Fencing
Miscellaneous
Fencing
Miscellaneous
Fencing
Miscellaneous
Setting out & Surveying
Setting out & Surveying
Setting out & Surveying
Safety & Environmental
Emergency Phone Numbers & Response
Health,Safety&Environment
HSE Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of
current HSE Issues and historical trends
Health,Safety&Environment
Site Safety Posters examples
Health,Safety&Environment
Trench - Safety Measures
ⓒ David H Moloney
Health,Safety&Environment
Safety Training on Site
Miscellaneous The purpose of safety training is to provide the knowledge necessary to
perform a job safely
Safety Training Matrix
Miscellaneous The purpose of safety training is to provide the knowledge necessary to
perform a job safely
Emergency Response Drill
HSE
Drills and exercises are used to rehearse anticipated emergency scenarios
Safety Documents
Health,Safety&Environment
Safe System of Work.
To provide a safe system of work is a legal requirement. What this means is that before you ask an employee to do a
job. You ensure that he has received training, has the appropriate personal protective equipment, the work area is safe
and he is unlikely to be injured or cause damage by carrying out the assigned task.
Project Management Plan for Health, Safety, Security and Environment. also Known as (HSSE Plan)
The Project HSSE Management Plan details how safety on site will be managed.
Project Procedures for Health, Safety, Security & Environment
Details the safe way to undertake a task
Methods Statements
Are prepared in advance of starting work, to plan a Safe System of Work on site for all activities that carries a risk. The
contents of a Method Statement, typically include:- Scope & Location of the Works, Programme, Roles & Responsibilities
of Staff. Resources, Work Methodologies and Risk Assessment.
Slide 1 of 2
Safety Documents
Health,Safety&Environment
Safety Risk Assessments
Are prepared to identify and evaluate risks, to adopt control measures to reduce or eliminate risks.
COSHH Sheet
The purpose of the Control Of Substances Hazardous to Health sheet is to identify how to prevent or adequately control
workers exposure to hazardous substances.
Permit to Work.
Is a management system used to control high risk activities by ensuring safety measures are in place prior to starting
work.
Types of work for which permits will be required include:
Excavation and the digging of trenches.
Working at height, including on roofs.
Working in confined spaces, for example entering a manhole.
Hot work, which is welding, soldering or cutting steel with angle grinders or by gas torch.
Slide 2 of 2
Hazardous Substances Symbols
Health,Safety&Environment
COSHH stands for the
Control of Substances
Hazardous to Health
Shown are the new
hazard symbols
Safety Precautions
Health,Safety&Environment
Signs Examples
Health,Safety&Environment
Environmentally Friendly Site Air, Noise, Water & Soil PollutionHealth,Safety&Environment
Segregation of WasteHealth,Safety&Environment
Segregation of waste for proper disposal and
recycling. Less waste goes to landfill and
hazardous waste is treated to make it safe.
Colour Code for Skips & Bins
Water Pollution PreventionHealth,Safety&Environment
Concrete Washout & Settlement TanksHealth,Safety&Environment
Existing Underground Utilities
ⓒ David H Moloney
Brief Description
Before digging establish the
location and route of
underground utilities.
Locator to find Utilities
Spray Paint to mark pavement
Health,Safety&Environment
Existing Underground Utilities & Overhead Cables - Safety Measures
ⓒ David H Moloney
Health,Safety&Environment
Trench - Safety Measures
Health,Safety&Environment
Trench - Safety Measures
ⓒ David H Moloney
Health,Safety&Environment
Quality Assurance
Quality Assurance Dashboard Dashboard is a single page, graphical representation of
current statistics and historical trends
Runway Asphalt Pavement - Tests
Roads&Pavings
Quality Assurance Tests
Runway Concrete Pavement - Tests
Roads&Pavings
Runway Laboratory
Roads&Pavings
Laboratory
ⓒ David H Moloney
AsphaltPaving
Administration
Staff Directory
Brief Description
List of staff and their
contact details
Daily Work Record
Brief Description
Daily Work Records showing the
allocation of resources, materials and
work activities carried out daily.
Organogram
Brief Description
Shown are the line and
lateral relationships
between the various team
members and their relative
position in the site
organisation.
Staff Responsibility Matrix
Filing System
Quotations Comparison Sheet
Programme & Progress Monitoring
Progress Monthly, Monitoring & Reporting - Dashboard
Dashboard is a single page, graphical representation of current
progress and historical trends
Programme for Construction
Gantt Charts to plan and schedule projects
Bridge Construction Stages, Images & Timeline
Concrete
Bridge Construction Stages, Images & Timeline
Concrete
Bridge Construction Stages, Images & Timeline
Concrete
Bridge Construction Stages, Images & Timeline
Concrete
Bridge Construction Stages, Images & Timeline
Concrete
Bridge Construction Stages, Images & Timeline
Concrete
Bridge Construction Stages, Images & Timeline
Concrete
Bridge Construction Stages, Images & Timeline
Concrete
Bridge Construction Stages, Images & Timeline
Concrete
Bridge Construction Stages, Images & Timeline
Concrete
Bridge Construction Stages, Images & Timeline
Concrete
Time Chainage Diagram
Brief Description
The chart has two axis: one for time and the other for location
A legend explains meaning of the colours, symbols and line types
Legend
Histogram Charts for Resources & Outputs
Manpower per Discipline
Concrete per Location
Man-hours for each month of the Project
Quantity for each month of the Project
ⓒ David H Moloney
Brief Description
Histograms shows resources etc. for each month of a project.
Plant & Equipment List & Worker’s Job Titles
ⓒ David H Moloney
Other Bridge Projects
Other Projects – Kuwait Causeway
Brief Description Marine Piling for Causeway in Kuwait
Other Projects – Kuwait Causeway
Brief Description Full Deck Span Precast 1,800 tonnes by 60m long
Precast Yard Straddle Carriers loading Deck onto
Multi Wheeled Transporters
Multi Wheeled Transporters
moving deck to Jetty
Jetty for loading Barge Barge Crane Placing Deck Barge Crane Placing Deck
Other Projects
Brief Description St. Croix Crossing, Minnesota, USA. Extradosed bridge design
Other Projects - Dubai Metro Viaduct
Brief Description
Precast Yard for Viaduct Segments Transport Viaduct Segments
Overhead Launching Gantry to
place Viaduct Segments
Construction Sequence
Completed Project
Other Projects - Dubai Metro Programme
Brief Description
Production by David H Moloney
My YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ

Contenu connexe

Tendances

Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019David H Moloney
 
Building Construction
Building ConstructionBuilding Construction
Building ConstructionWilden How
 
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRODESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PROAli Meer
 
62617938 launching-girder
62617938 launching-girder62617938 launching-girder
62617938 launching-girderlotuseye
 
Building Construction Report
Building Construction ReportBuilding Construction Report
Building Construction ReportSheau Hui Tan
 
Construction methods and equipments
Construction methods and equipmentsConstruction methods and equipments
Construction methods and equipmentsR VIJAYAKUMAR
 
Runway Construction Project Execution Plan
Runway Construction Project Execution PlanRunway Construction Project Execution Plan
Runway Construction Project Execution PlanDavid H Moloney
 
Airport Runway Construction
Airport Runway ConstructionAirport Runway Construction
Airport Runway ConstructionHafizullah Sadat
 
Analysis and design of multi-storey building using staad.Pro
Analysis and design of multi-storey building using staad.ProAnalysis and design of multi-storey building using staad.Pro
Analysis and design of multi-storey building using staad.Progsharda123
 
Report on Pile Foundation
Report on Pile FoundationReport on Pile Foundation
Report on Pile FoundationSubham Kundu
 
Construction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdfConstruction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdfMeleseMengistu
 
RESIDENTIAL CONSTRUCTION BUILDING
RESIDENTIAL CONSTRUCTION BUILDING RESIDENTIAL CONSTRUCTION BUILDING
RESIDENTIAL CONSTRUCTION BUILDING Vikas Sukhwal
 
02 Construction Projects
02 Construction Projects02 Construction Projects
02 Construction Projectsakashpadole
 
Motorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanMotorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanDavid H Moloney
 
FOOTING CONSTRUCTION
FOOTING CONSTRUCTIONFOOTING CONSTRUCTION
FOOTING CONSTRUCTIONMd Shadab
 
bridge report
bridge reportbridge report
bridge reportabc def
 
Muscat Airport Construction
Muscat Airport ConstructionMuscat Airport Construction
Muscat Airport ConstructionDavid H Moloney
 
Project Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanProject Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanDavid H Moloney
 

Tendances (20)

Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
 
Pile load test
Pile load testPile load test
Pile load test
 
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRODESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PRO
 
62617938 launching-girder
62617938 launching-girder62617938 launching-girder
62617938 launching-girder
 
Airport Construction
Airport ConstructionAirport Construction
Airport Construction
 
Building Construction Report
Building Construction ReportBuilding Construction Report
Building Construction Report
 
Construction methods and equipments
Construction methods and equipmentsConstruction methods and equipments
Construction methods and equipments
 
Runway Construction Project Execution Plan
Runway Construction Project Execution PlanRunway Construction Project Execution Plan
Runway Construction Project Execution Plan
 
Airport Runway Construction
Airport Runway ConstructionAirport Runway Construction
Airport Runway Construction
 
Analysis and design of multi-storey building using staad.Pro
Analysis and design of multi-storey building using staad.ProAnalysis and design of multi-storey building using staad.Pro
Analysis and design of multi-storey building using staad.Pro
 
Report on Pile Foundation
Report on Pile FoundationReport on Pile Foundation
Report on Pile Foundation
 
Construction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdfConstruction Management full lecture note-By Melese Mengistu.pdf
Construction Management full lecture note-By Melese Mengistu.pdf
 
RESIDENTIAL CONSTRUCTION BUILDING
RESIDENTIAL CONSTRUCTION BUILDING RESIDENTIAL CONSTRUCTION BUILDING
RESIDENTIAL CONSTRUCTION BUILDING
 
02 Construction Projects
02 Construction Projects02 Construction Projects
02 Construction Projects
 
Motorway Construction, Project Execution Plan
Motorway Construction, Project Execution PlanMotorway Construction, Project Execution Plan
Motorway Construction, Project Execution Plan
 
FOOTING CONSTRUCTION
FOOTING CONSTRUCTIONFOOTING CONSTRUCTION
FOOTING CONSTRUCTION
 
bridge report
bridge reportbridge report
bridge report
 
Muscat Airport Construction
Muscat Airport ConstructionMuscat Airport Construction
Muscat Airport Construction
 
Project Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, OmanProject Execution Plan for Muscat Runway Construction, Oman
Project Execution Plan for Muscat Runway Construction, Oman
 

En vedette

Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve Satish Yadavalli
 
Spring Framework Petclinic sample application
Spring Framework Petclinic sample applicationSpring Framework Petclinic sample application
Spring Framework Petclinic sample applicationAntoine Rey
 
high rise building (BURJ KHALIFA)
high rise building (BURJ KHALIFA)high rise building (BURJ KHALIFA)
high rise building (BURJ KHALIFA)suraj kumar
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONatchitect and design
 
Bridge Construction & Its Types
Bridge Construction & Its TypesBridge Construction & Its Types
Bridge Construction & Its TypesZakaria Yahya
 
Golden gate bridge construction
Golden gate bridge constructionGolden gate bridge construction
Golden gate bridge constructionNouman Tahir
 
Steel concrete composite bridges
Steel concrete composite bridges Steel concrete composite bridges
Steel concrete composite bridges David Collings
 
Training Report on Bridge Construction
Training Report on Bridge ConstructionTraining Report on Bridge Construction
Training Report on Bridge ConstructionMAHAVIR MEENA
 
Precast Bridges slides
Precast Bridges slidesPrecast Bridges slides
Precast Bridges slidesWaqas Javaid
 
Basics of bridge construction
Basics of bridge constructionBasics of bridge construction
Basics of bridge constructionsymphonyjo
 
Bridge
Bridge Bridge
Bridge illpa
 

En vedette (13)

Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve
 
Spring Framework Petclinic sample application
Spring Framework Petclinic sample applicationSpring Framework Petclinic sample application
Spring Framework Petclinic sample application
 
high rise building (BURJ KHALIFA)
high rise building (BURJ KHALIFA)high rise building (BURJ KHALIFA)
high rise building (BURJ KHALIFA)
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
 
Burj khalifa
Burj khalifaBurj khalifa
Burj khalifa
 
Bridge Construction & Its Types
Bridge Construction & Its TypesBridge Construction & Its Types
Bridge Construction & Its Types
 
Golden gate bridge construction
Golden gate bridge constructionGolden gate bridge construction
Golden gate bridge construction
 
Steel concrete composite bridges
Steel concrete composite bridges Steel concrete composite bridges
Steel concrete composite bridges
 
Fundamentals of-psc-bridge
Fundamentals of-psc-bridgeFundamentals of-psc-bridge
Fundamentals of-psc-bridge
 
Training Report on Bridge Construction
Training Report on Bridge ConstructionTraining Report on Bridge Construction
Training Report on Bridge Construction
 
Precast Bridges slides
Precast Bridges slidesPrecast Bridges slides
Precast Bridges slides
 
Basics of bridge construction
Basics of bridge constructionBasics of bridge construction
Basics of bridge construction
 
Bridge
Bridge Bridge
Bridge
 

Similaire à Project Execution Plan for Bridge Construction

Route 2020 Metro Dubai Construction Details
Route 2020 Metro Dubai   Construction DetailsRoute 2020 Metro Dubai   Construction Details
Route 2020 Metro Dubai Construction DetailsDavid H Moloney
 
Metro North, Dublin - Construction Explained
Metro North, Dublin  - Construction ExplainedMetro North, Dublin  - Construction Explained
Metro North, Dublin - Construction ExplainedDavid H Moloney
 
Sea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution PlanSea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution PlanDavid H Moloney
 
Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingDavid H Moloney
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanDavid H Moloney
 
Heathrow 3rd Runway Construction
Heathrow 3rd Runway ConstructionHeathrow 3rd Runway Construction
Heathrow 3rd Runway ConstructionDavid H Moloney
 
Dart Underground, Dublin - Light Rail Network in Tunnels
Dart Underground, Dublin - Light Rail Network in TunnelsDart Underground, Dublin - Light Rail Network in Tunnels
Dart Underground, Dublin - Light Rail Network in TunnelsDavid H Moloney
 
Demolition, Deconstruction & Dismantling
Demolition, Deconstruction & Dismantling Demolition, Deconstruction & Dismantling
Demolition, Deconstruction & Dismantling Emma Attwood
 
Tilt up-concrete-06a
Tilt up-concrete-06aTilt up-concrete-06a
Tilt up-concrete-06aMazhar Syed
 
Site visit report
Site visit reportSite visit report
Site visit reportWen Crystal
 
light weight concrete.pdf
light weight concrete.pdflight weight concrete.pdf
light weight concrete.pdfSanjayS980435
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001Minh Bui Si
 
Cellular Lightweight Concrete Blocks, CLC Blocks Manufacturing Plant, Foamed ...
Cellular Lightweight Concrete Blocks, CLC Blocks Manufacturing Plant, Foamed ...Cellular Lightweight Concrete Blocks, CLC Blocks Manufacturing Plant, Foamed ...
Cellular Lightweight Concrete Blocks, CLC Blocks Manufacturing Plant, Foamed ...Ajjay Kumar Gupta
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016Ali Issa
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02Minh Bui Si
 
Site visit report
Site visit reportSite visit report
Site visit reportDoreen Yeo
 

Similaire à Project Execution Plan for Bridge Construction (20)

Route 2020 Metro Dubai Construction Details
Route 2020 Metro Dubai   Construction DetailsRoute 2020 Metro Dubai   Construction Details
Route 2020 Metro Dubai Construction Details
 
Metro North, Dublin - Construction Explained
Metro North, Dublin  - Construction ExplainedMetro North, Dublin  - Construction Explained
Metro North, Dublin - Construction Explained
 
Sea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution PlanSea Port Construction, Project Execution Plan
Sea Port Construction, Project Execution Plan
 
Project Execution Plan for High Rise Building
Project Execution Plan for High Rise BuildingProject Execution Plan for High Rise Building
Project Execution Plan for High Rise Building
 
Oil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution PlanOil & Gas Plant Construction, Project Execution Plan
Oil & Gas Plant Construction, Project Execution Plan
 
Heathrow 3rd Runway Construction
Heathrow 3rd Runway ConstructionHeathrow 3rd Runway Construction
Heathrow 3rd Runway Construction
 
Dart Underground, Dublin - Light Rail Network in Tunnels
Dart Underground, Dublin - Light Rail Network in TunnelsDart Underground, Dublin - Light Rail Network in Tunnels
Dart Underground, Dublin - Light Rail Network in Tunnels
 
Demolition, Deconstruction & Dismantling
Demolition, Deconstruction & Dismantling Demolition, Deconstruction & Dismantling
Demolition, Deconstruction & Dismantling
 
Tilt up-concrete-06a
Tilt up-concrete-06aTilt up-concrete-06a
Tilt up-concrete-06a
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Ez
EzEz
Ez
 
Pathak resume
Pathak resumePathak resume
Pathak resume
 
light weight concrete.pdf
light weight concrete.pdflight weight concrete.pdf
light weight concrete.pdf
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001
 
Evocrete Booklet
Evocrete BookletEvocrete Booklet
Evocrete Booklet
 
Cellular Lightweight Concrete Blocks, CLC Blocks Manufacturing Plant, Foamed ...
Cellular Lightweight Concrete Blocks, CLC Blocks Manufacturing Plant, Foamed ...Cellular Lightweight Concrete Blocks, CLC Blocks Manufacturing Plant, Foamed ...
Cellular Lightweight Concrete Blocks, CLC Blocks Manufacturing Plant, Foamed ...
 
Railway over bridge
Railway over bridgeRailway over bridge
Railway over bridge
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02
 
Site visit report
Site visit reportSite visit report
Site visit report
 

Plus de David H Moloney

Farm Life & Creameries from 1900
Farm Life & Creameries from 1900 Farm Life & Creameries from 1900
Farm Life & Creameries from 1900 David H Moloney
 
Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824David H Moloney
 
Coshh Assessments 97 pages
Coshh  Assessments 97 pagesCoshh  Assessments 97 pages
Coshh Assessments 97 pagesDavid H Moloney
 
Risk Assessments 96 pages
Risk Assessments 96 pagesRisk Assessments 96 pages
Risk Assessments 96 pagesDavid H Moloney
 
Photo Album of Cork Runway Reconstruction
Photo Album of Cork Runway ReconstructionPhoto Album of Cork Runway Reconstruction
Photo Album of Cork Runway ReconstructionDavid H Moloney
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan David H Moloney
 
Airport Buildings & Structures Construction
Airport Buildings & Structures ConstructionAirport Buildings & Structures Construction
Airport Buildings & Structures ConstructionDavid H Moloney
 
Risk Assessments for Airside Construction
Risk Assessments for Airside ConstructionRisk Assessments for Airside Construction
Risk Assessments for Airside ConstructionDavid H Moloney
 
Construction Environmental Awareness and Training POSTER
Construction Environmental Awareness and Training  POSTERConstruction Environmental Awareness and Training  POSTER
Construction Environmental Awareness and Training POSTERDavid H Moloney
 
Project Planning Organising Tracking Construction
Project Planning Organising Tracking  ConstructionProject Planning Organising Tracking  Construction
Project Planning Organising Tracking ConstructionDavid H Moloney
 
Oil pipeline 42 inch by 455 km
Oil pipeline 42 inch by  455 kmOil pipeline 42 inch by  455 km
Oil pipeline 42 inch by 455 kmDavid H Moloney
 
Metro Tunnels Programme 3D Visualisation
Metro Tunnels Programme 3D VisualisationMetro Tunnels Programme 3D Visualisation
Metro Tunnels Programme 3D VisualisationDavid H Moloney
 
Rock excavability, drill & blast, marine & haulage
Rock excavability, drill & blast, marine & haulageRock excavability, drill & blast, marine & haulage
Rock excavability, drill & blast, marine & haulageDavid H Moloney
 
Bridge Construction Methods
Bridge Construction MethodsBridge Construction Methods
Bridge Construction MethodsDavid H Moloney
 

Plus de David H Moloney (14)

Farm Life & Creameries from 1900
Farm Life & Creameries from 1900 Farm Life & Creameries from 1900
Farm Life & Creameries from 1900
 
Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824Book of Derbys Irish Estate 1824
Book of Derbys Irish Estate 1824
 
Coshh Assessments 97 pages
Coshh  Assessments 97 pagesCoshh  Assessments 97 pages
Coshh Assessments 97 pages
 
Risk Assessments 96 pages
Risk Assessments 96 pagesRisk Assessments 96 pages
Risk Assessments 96 pages
 
Photo Album of Cork Runway Reconstruction
Photo Album of Cork Runway ReconstructionPhoto Album of Cork Runway Reconstruction
Photo Album of Cork Runway Reconstruction
 
Runway construction project execution plan
Runway construction project execution plan Runway construction project execution plan
Runway construction project execution plan
 
Airport Buildings & Structures Construction
Airport Buildings & Structures ConstructionAirport Buildings & Structures Construction
Airport Buildings & Structures Construction
 
Risk Assessments for Airside Construction
Risk Assessments for Airside ConstructionRisk Assessments for Airside Construction
Risk Assessments for Airside Construction
 
Construction Environmental Awareness and Training POSTER
Construction Environmental Awareness and Training  POSTERConstruction Environmental Awareness and Training  POSTER
Construction Environmental Awareness and Training POSTER
 
Project Planning Organising Tracking Construction
Project Planning Organising Tracking  ConstructionProject Planning Organising Tracking  Construction
Project Planning Organising Tracking Construction
 
Oil pipeline 42 inch by 455 km
Oil pipeline 42 inch by  455 kmOil pipeline 42 inch by  455 km
Oil pipeline 42 inch by 455 km
 
Metro Tunnels Programme 3D Visualisation
Metro Tunnels Programme 3D VisualisationMetro Tunnels Programme 3D Visualisation
Metro Tunnels Programme 3D Visualisation
 
Rock excavability, drill & blast, marine & haulage
Rock excavability, drill & blast, marine & haulageRock excavability, drill & blast, marine & haulage
Rock excavability, drill & blast, marine & haulage
 
Bridge Construction Methods
Bridge Construction MethodsBridge Construction Methods
Bridge Construction Methods
 

Dernier

Levelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodLevelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodManicka Mamallan Andavar
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating SystemRashmi Bhat
 
Prach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism CommunityPrach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism Communityprachaibot
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solidnamansinghjarodiya
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfChristianCDAM
 
Python Programming for basic beginners.pptx
Python Programming for basic beginners.pptxPython Programming for basic beginners.pptx
Python Programming for basic beginners.pptxmohitesoham12
 
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...Stork
 
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfModule-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfManish Kumar
 
Robotics Group 10 (Control Schemes) cse.pdf
Robotics Group 10  (Control Schemes) cse.pdfRobotics Group 10  (Control Schemes) cse.pdf
Robotics Group 10 (Control Schemes) cse.pdfsahilsajad201
 
Industrial Applications of Centrifugal Compressors
Industrial Applications of Centrifugal CompressorsIndustrial Applications of Centrifugal Compressors
Industrial Applications of Centrifugal CompressorsAlirezaBagherian3
 
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESCME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESkarthi keyan
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Coursebim.edu.pl
 
Novel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsNovel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsResearcher Researcher
 
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptJohnWilliam111370
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 
Cost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based questionCost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based questionSneha Padhiar
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
Artificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewArtificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewsandhya757531
 
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSHigh Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSsandhya757531
 

Dernier (20)

Levelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodLevelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument method
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating System
 
Prach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism CommunityPrach: A Feature-Rich Platform Empowering the Autism Community
Prach: A Feature-Rich Platform Empowering the Autism Community
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solid
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdf
 
Python Programming for basic beginners.pptx
Python Programming for basic beginners.pptxPython Programming for basic beginners.pptx
Python Programming for basic beginners.pptx
 
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
Stork Webinar | APM Transformational planning, Tool Selection & Performance T...
 
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdfModule-1-(Building Acoustics) Noise Control (Unit-3). pdf
Module-1-(Building Acoustics) Noise Control (Unit-3). pdf
 
Robotics Group 10 (Control Schemes) cse.pdf
Robotics Group 10  (Control Schemes) cse.pdfRobotics Group 10  (Control Schemes) cse.pdf
Robotics Group 10 (Control Schemes) cse.pdf
 
Industrial Applications of Centrifugal Compressors
Industrial Applications of Centrifugal CompressorsIndustrial Applications of Centrifugal Compressors
Industrial Applications of Centrifugal Compressors
 
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESCME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Course
 
Novel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsNovel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending Actuators
 
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 
Cost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based questionCost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based question
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Artificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewArtificial Intelligence in Power System overview
Artificial Intelligence in Power System overview
 
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSHigh Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
 

Project Execution Plan for Bridge Construction