Royal HaskoningDHV
Project Management
Project Need
Product/Service/Result
Figure : Project Lifecycle Built Environment Projects
Inception
Concept & Feasibility
Design
Development
Procurement
&
Documentation
Construction &
Management
Close Out
Stage 1- Project
Inception
Stage 2-
Concept and
Feasibility
Stage 3 – Design
Development
Stage 4- Tender
documentation &
procurement
Stage 5-
Construction
documentation
& management
Stage 6-
Project
Close out
/Charter
Procurement
Policy
Programme
meetings
and Environmental
Consultant/Client
Agreements
Project
Documentation
and Construction
Programme.
conceptual design
report and
approval by JDA
to proceed to
Stage 3
Consultant/Client
Agreements
& Documentation
Programme
Indicative
Construction
Programme
meetings
Approved
design
development
report and draft
tender docs and
approval by JDA
to proceed to
Stage 4
subcontractors, and
suppliers
Procurement
Strategy
Procurement
Programme
Tender/Contract
Conditions
meetings
Approved tender
report and approval
by JDA of tender
recommendation(s).
Contractor(s)
Agreements
Contract
Programme
and award of
contractual
claims
Construction
Documentatio
n Schedule
progress
payment
certificates
project
progress
reports.
all meetings
of Practical
Completion.
Completion
Certificate
of Final
Completion
all meetings
close out
report
Table : Project Management Deliver Per Phase
Client
Complete
Project Charter
Define the
Scope
Break scope into
manageable work
packages
Complete the
Project
Management Plan
Subsidiary plans
for: integration,
scope, time,
cost, quality,
HR,
communication,
risk and
procurement
Execute
the project
tasks
Close
Phase/Stage
Update lesson
learned
Monitor&Control
Figure: Project Management Methodology
Inception
Phase
Concept &
Feasibility
Design
Development
Procurement &
Documentation
Construction
&
Management
Close out
PROJECT
CHARTER
SCOPE
STATEMENT
PROJECTPLAN
SUBSIDIARY
PLANS
PROCUREMENT
PLAN
ISSUE,CHANGE
&RISKLOGS
PROJECTCLOSE
OUT
PROJECT MANAGEMENT DELIVERABLES
Figure: Project Management Document Deliverables Per Phase
Identify
Stakeholders
Collect stakeholder
requirements
Develop a
stakeholder
register
Trace
requirements
Develop a stakeholder
management strategy
Close out
requirements
KeepStakeholdersupdated
&solicitregularinput
Figure: Royal HaskoningDHV Stakeholder Management Guideline
.
Figure: Summarized Royal HaskoningDHV Value Add Proposition
Figure: Royal HaskoningDHV Customer Service Strategy
STRENGTHS
VALUEPROPOSITION
ENDTOENDSERVICES
CUSTOMER
Satisfaction
People
Solutions
Technology Expertise
Methodologies &
Frameworks
Services
Products
Partners
Best Practices
Quality Processes
Time to Market
Predictability
Reduced RCO
VALUE ADD

Contenu connexe

Tendances (20)

Iktimed operation plan for partner
Iktimed operation plan for partnerIktimed operation plan for partner
Iktimed operation plan for partner
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In Construction
 
Atoosa Samiei-Resume
Atoosa Samiei-ResumeAtoosa Samiei-Resume
Atoosa Samiei-Resume
 
Saad Ali Al Khathami CV 2016
Saad Ali Al Khathami CV 2016Saad Ali Al Khathami CV 2016
Saad Ali Al Khathami CV 2016
 
Civil Supervisor
Civil SupervisorCivil Supervisor
Civil Supervisor
 
Project Charter Template
Project Charter TemplateProject Charter Template
Project Charter Template
 
Cover Letter (Meinhardt)
Cover Letter (Meinhardt)Cover Letter (Meinhardt)
Cover Letter (Meinhardt)
 
How to train your Project Managers
How to train your Project ManagersHow to train your Project Managers
How to train your Project Managers
 
EPC PLANNER
EPC PLANNEREPC PLANNER
EPC PLANNER
 
130125.PROCESS DIAGRAM
130125.PROCESS DIAGRAM130125.PROCESS DIAGRAM
130125.PROCESS DIAGRAM
 
Real Estate Gateways Waleed template
Real Estate Gateways Waleed templateReal Estate Gateways Waleed template
Real Estate Gateways Waleed template
 
012 bussiness planning process
012 bussiness planning process012 bussiness planning process
012 bussiness planning process
 
Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Construction
 
How To Close-Out Your Project Successfully!
How To Close-Out Your Project Successfully!How To Close-Out Your Project Successfully!
How To Close-Out Your Project Successfully!
 
RIBA - PLAN OF WORK
RIBA - PLAN OF WORKRIBA - PLAN OF WORK
RIBA - PLAN OF WORK
 
RIBAPlanofWork2013Template
RIBAPlanofWork2013TemplateRIBAPlanofWork2013Template
RIBAPlanofWork2013Template
 
Work Placement 3 Presentation
Work Placement 3 PresentationWork Placement 3 Presentation
Work Placement 3 Presentation
 
Project Management Outsourcing
Project Management OutsourcingProject Management Outsourcing
Project Management Outsourcing
 
Assignment - Case Study Report
Assignment - Case Study ReportAssignment - Case Study Report
Assignment - Case Study Report
 
New Resume for Hays
New Resume for HaysNew Resume for Hays
New Resume for Hays
 

En vedette

Ousainou Demba Resume_6142016
Ousainou Demba Resume_6142016Ousainou Demba Resume_6142016
Ousainou Demba Resume_6142016Ousainou Demba
 
Week 8. educational emphases (i)
Week 8. educational emphases (i)Week 8. educational emphases (i)
Week 8. educational emphases (i)Noor Syamila
 
ветераны
ветераныветераны
ветераныBojarka
 
Curriculum Vitae - EDER GIOVANNI VAZQUEZ HURTADO.-Ingles
Curriculum Vitae - EDER GIOVANNI VAZQUEZ HURTADO.-InglesCurriculum Vitae - EDER GIOVANNI VAZQUEZ HURTADO.-Ingles
Curriculum Vitae - EDER GIOVANNI VAZQUEZ HURTADO.-InglesGio Vazquez
 
Pidrox Presentation
Pidrox PresentationPidrox Presentation
Pidrox PresentationPidrox
 
Stypendści burmistrza-2015
Stypendści burmistrza-2015Stypendści burmistrza-2015
Stypendści burmistrza-2015zpo1
 
UAS Elementary PYP Presentation
UAS Elementary PYP PresentationUAS Elementary PYP Presentation
UAS Elementary PYP Presentationuasdubai
 
Ilmastonmuutos taukojumppa
Ilmastonmuutos taukojumppaIlmastonmuutos taukojumppa
Ilmastonmuutos taukojumppaMarko Seikkula
 
David albon natural leader
David albon natural leaderDavid albon natural leader
David albon natural leaderDavid Albon
 

En vedette (15)

equilbrium
equilbriumequilbrium
equilbrium
 
Ousainou Demba Resume_6142016
Ousainou Demba Resume_6142016Ousainou Demba Resume_6142016
Ousainou Demba Resume_6142016
 
Arshad C.V
Arshad C.VArshad C.V
Arshad C.V
 
Actividad 18 grupo_9
Actividad 18 grupo_9Actividad 18 grupo_9
Actividad 18 grupo_9
 
Week 8. educational emphases (i)
Week 8. educational emphases (i)Week 8. educational emphases (i)
Week 8. educational emphases (i)
 
ветераны
ветераныветераны
ветераны
 
Curriculum Vitae - EDER GIOVANNI VAZQUEZ HURTADO.-Ingles
Curriculum Vitae - EDER GIOVANNI VAZQUEZ HURTADO.-InglesCurriculum Vitae - EDER GIOVANNI VAZQUEZ HURTADO.-Ingles
Curriculum Vitae - EDER GIOVANNI VAZQUEZ HURTADO.-Ingles
 
Childhood
ChildhoodChildhood
Childhood
 
Pidrox Presentation
Pidrox PresentationPidrox Presentation
Pidrox Presentation
 
Stypendści burmistrza-2015
Stypendści burmistrza-2015Stypendści burmistrza-2015
Stypendści burmistrza-2015
 
GITA April 2015 Newsletter
GITA April 2015 NewsletterGITA April 2015 Newsletter
GITA April 2015 Newsletter
 
UAS Elementary PYP Presentation
UAS Elementary PYP PresentationUAS Elementary PYP Presentation
UAS Elementary PYP Presentation
 
Ilmastonmuutos taukojumppa
Ilmastonmuutos taukojumppaIlmastonmuutos taukojumppa
Ilmastonmuutos taukojumppa
 
David albon natural leader
David albon natural leaderDavid albon natural leader
David albon natural leader
 
REFLEXIÓN
REFLEXIÓNREFLEXIÓN
REFLEXIÓN
 

Similaire à Project Lifecycle and PM processes

Project management-project life cycle-pdf
Project management-project life cycle-pdfProject management-project life cycle-pdf
Project management-project life cycle-pdfAditi Garg
 
Construction process
Construction processConstruction process
Construction processMazen Al-Qadi
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
Arrange building applications and approvals.pdf
Arrange building applications and approvals.pdfArrange building applications and approvals.pdf
Arrange building applications and approvals.pdfDereje Jima
 
Sxsw 2011 construction enviroment
Sxsw 2011 construction enviromentSxsw 2011 construction enviroment
Sxsw 2011 construction enviromentjuwes
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentationArchDuty
 
Sunny Mui_X474.3_Contract Closure
Sunny Mui_X474.3_Contract ClosureSunny Mui_X474.3_Contract Closure
Sunny Mui_X474.3_Contract Closuresunnycmui
 
Chap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseChap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseAnand Bobade
 
Pmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aPmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aForbes Chanakira
 
The Program Management Framework—What's New?
The Program Management Framework—What's New? The Program Management Framework—What's New?
The Program Management Framework—What's New? ILRI
 
Event management process
Event management process Event management process
Event management process Anita Sajit
 

Similaire à Project Lifecycle and PM processes (20)

Project management-project life cycle-pdf
Project management-project life cycle-pdfProject management-project life cycle-pdf
Project management-project life cycle-pdf
 
RIBA Revit.pdf
RIBA Revit.pdfRIBA Revit.pdf
RIBA Revit.pdf
 
Real estate investment
Real estate investmentReal estate investment
Real estate investment
 
Construction process
Construction processConstruction process
Construction process
 
012 bussiness planning process
012 bussiness planning process012 bussiness planning process
012 bussiness planning process
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
PM_Project LifeCycle
PM_Project LifeCyclePM_Project LifeCycle
PM_Project LifeCycle
 
Arrange building applications and approvals.pdf
Arrange building applications and approvals.pdfArrange building applications and approvals.pdf
Arrange building applications and approvals.pdf
 
Contract Management
Contract ManagementContract Management
Contract Management
 
Sxsw 2011 construction enviroment
Sxsw 2011 construction enviromentSxsw 2011 construction enviroment
Sxsw 2011 construction enviroment
 
Lecture 2 tender process n documentation
Lecture 2 tender process n documentationLecture 2 tender process n documentation
Lecture 2 tender process n documentation
 
Program management-steps
Program management-stepsProgram management-steps
Program management-steps
 
Enzen CDM Services
Enzen CDM ServicesEnzen CDM Services
Enzen CDM Services
 
Sunny Mui_X474.3_Contract Closure
Sunny Mui_X474.3_Contract ClosureSunny Mui_X474.3_Contract Closure
Sunny Mui_X474.3_Contract Closure
 
Chap 4.7 Project or Phase Close
Chap 4.7 Project or Phase CloseChap 4.7 Project or Phase Close
Chap 4.7 Project or Phase Close
 
Pmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_aPmp t09 project_execution_plan_rev_a
Pmp t09 project_execution_plan_rev_a
 
The Program Management Framework—What's New?
The Program Management Framework—What's New? The Program Management Framework—What's New?
The Program Management Framework—What's New?
 
Event management process
Event management process Event management process
Event management process
 
111
111111
111
 
CV-Kunwar Aftab Ahmad Khan-29Oct2015
CV-Kunwar Aftab Ahmad Khan-29Oct2015CV-Kunwar Aftab Ahmad Khan-29Oct2015
CV-Kunwar Aftab Ahmad Khan-29Oct2015
 

Plus de Denzel Maduray, PMP, Pr C Mentor, Pr.CM (7)

ND Civil Eng
ND Civil EngND Civil Eng
ND Civil Eng
 
B Tech Civil Eng
B Tech Civil EngB Tech Civil Eng
B Tech Civil Eng
 
Bsc Hon Degree Technology Man
Bsc Hon Degree Technology ManBsc Hon Degree Technology Man
Bsc Hon Degree Technology Man
 
Royal Haskoning Client questionaire for SARS Mthatha
Royal Haskoning Client questionaire for SARS MthathaRoyal Haskoning Client questionaire for SARS Mthatha
Royal Haskoning Client questionaire for SARS Mthatha
 
Client Letter _ GDE - 16 Schools - Graham Appel
Client Letter _ GDE - 16 Schools - Graham AppelClient Letter _ GDE - 16 Schools - Graham Appel
Client Letter _ GDE - 16 Schools - Graham Appel
 
M01.JNB.000159_EC 6 Schools Marketing Project Reference
M01.JNB.000159_EC 6 Schools Marketing Project ReferenceM01.JNB.000159_EC 6 Schools Marketing Project Reference
M01.JNB.000159_EC 6 Schools Marketing Project Reference
 
POQ AG _NL Presentation- 07 Jan 2015
POQ AG _NL Presentation- 07 Jan 2015POQ AG _NL Presentation- 07 Jan 2015
POQ AG _NL Presentation- 07 Jan 2015
 

Project Lifecycle and PM processes

  • 2. Project Need Product/Service/Result Figure : Project Lifecycle Built Environment Projects Inception Concept & Feasibility Design Development Procurement & Documentation Construction & Management Close Out
  • 3. Stage 1- Project Inception Stage 2- Concept and Feasibility Stage 3 – Design Development Stage 4- Tender documentation & procurement Stage 5- Construction documentation & management Stage 6- Project Close out /Charter Procurement Policy Programme meetings and Environmental Consultant/Client Agreements Project Documentation and Construction Programme. conceptual design report and approval by JDA to proceed to Stage 3 Consultant/Client Agreements & Documentation Programme Indicative Construction Programme meetings Approved design development report and draft tender docs and approval by JDA to proceed to Stage 4 subcontractors, and suppliers Procurement Strategy Procurement Programme Tender/Contract Conditions meetings Approved tender report and approval by JDA of tender recommendation(s). Contractor(s) Agreements Contract Programme and award of contractual claims Construction Documentatio n Schedule progress payment certificates project progress reports. all meetings of Practical Completion. Completion Certificate of Final Completion all meetings close out report Table : Project Management Deliver Per Phase
  • 4. Client Complete Project Charter Define the Scope Break scope into manageable work packages Complete the Project Management Plan Subsidiary plans for: integration, scope, time, cost, quality, HR, communication, risk and procurement Execute the project tasks Close Phase/Stage Update lesson learned Monitor&Control Figure: Project Management Methodology Inception Phase Concept & Feasibility Design Development Procurement & Documentation Construction & Management Close out PROJECT CHARTER SCOPE STATEMENT PROJECTPLAN SUBSIDIARY PLANS PROCUREMENT PLAN ISSUE,CHANGE &RISKLOGS PROJECTCLOSE OUT PROJECT MANAGEMENT DELIVERABLES Figure: Project Management Document Deliverables Per Phase
  • 5. Identify Stakeholders Collect stakeholder requirements Develop a stakeholder register Trace requirements Develop a stakeholder management strategy Close out requirements KeepStakeholdersupdated &solicitregularinput Figure: Royal HaskoningDHV Stakeholder Management Guideline
  • 6. . Figure: Summarized Royal HaskoningDHV Value Add Proposition Figure: Royal HaskoningDHV Customer Service Strategy STRENGTHS VALUEPROPOSITION ENDTOENDSERVICES CUSTOMER Satisfaction People Solutions Technology Expertise Methodologies & Frameworks Services Products Partners Best Practices Quality Processes Time to Market Predictability Reduced RCO VALUE ADD