SlideShare a Scribd company logo
1 of 28
PLANNING ANDPLANNING AND
PROGRAMMINGPROGRAMMING
helpdesk@construction-productivity.co.ukhelpdesk@construction-productivity.co.uk
htt://www.construction-productivity.co.ukhtt://www.construction-productivity.co.uk
PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING
 Project planning, programming &Project planning, programming &
scheduling is about estimating andscheduling is about estimating and
managing the cost, time, quality, safety,managing the cost, time, quality, safety,
etc.etc.
 Management of a construction firmManagement of a construction firm
determine exactly how long each aspect ofdetermine exactly how long each aspect of
a project should take to complete.a project should take to complete.
 A realistic time estimate ‘programme’ forA realistic time estimate ‘programme’ for
the entire development process is a keythe entire development process is a key
factor for project duration time.factor for project duration time.
PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING
 As the project progress managementAs the project progress management
team constantly monitor progress againstteam constantly monitor progress against
the original time plan;the original time plan;
 Planning and programming is aboutPlanning and programming is about
recovery of lost time;recovery of lost time;
 Recommending management action inRecommending management action in
order to maintain programme (time, cost,order to maintain programme (time, cost,
quality, safety, etc).quality, safety, etc).
PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING
Tender PlanningTender Planning
Tender planning is the first phase of any project.Tender planning is the first phase of any project.
It is important to generate a plan covering items such as:It is important to generate a plan covering items such as:
 clear project directionclear project direction
 budget and schedule before proceeding to avoid makingbudget and schedule before proceeding to avoid making
costly mistakes and causing delayscostly mistakes and causing delays
 Tender programmesTender programmes
 Feasibility StudiesFeasibility Studies
 Budget GenerationBudget Generation
 Design ManagementDesign Management
 Value EngineeringValue Engineering
PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING
On the other hand programming is about:On the other hand programming is about:
 Construction programmes for all siteConstruction programmes for all site
activitiesactivities
 Package and Procurement programmesPackage and Procurement programmes
for each element of worksfor each element of works
 Overall design and ProcurementOverall design and Procurement
programmesprogrammes
 As built programmesAs built programmes
 Critical path analysisCritical path analysis
PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING
So far:
 Once the basic planning and preparation of the
master plan are complete, management should
work on:
 plans, specifications and cost estimates
 tender documents
 selection of contractor and award of work
 construction activities
 project management and control
 handing over for commissioning
PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING
Appropriate construction technology
 The choice of building materials has an effect
both on cost and length of construction.
 Locally available materials
 Traditional building techniques should be given
priority.
 They are usually cheaper and more accessible.
 Selection of materials and future maintenance
must be considered during design stages.
PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING
Building materials should be:
economical
durable
easy to clean
and to maintain or replace.
They should also be easy to handle on the
site and to replace in case of breakage or
damage.
PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING
The designer must choose:
(1) the type of construction of the project:
 indigenous technology
 on-site methods
 prefabricated modules and components
assembled on site
 Or a combination of prefabricated components
and on-site construction.
(2) the level of technology: low, medium or high.
PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING
Construction technology should take in to
consideration factors such as:
 conditions of site
 time constraints
 availability of labour and raw materials
 construction equipment and any other related
factors.
Whenever possible:
 Methods adopted should be within the capability
of local manpower and resources.
PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING
Consideration of innovative methods when
possible
Issue of sustainability
If design professionals are brought in, they
should work in association with:
local architects
engineers so that there is a transfer of
knowledge in the area.
PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING
Tendering
general conditions of contract
technical specifications
tender drawings
bill of quantities.
PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING
General conditions of contract
 This should consist of:
 cover or title sheet
 index
 instructions to bidders
 bidding form
 form of agreement
 performance bond and bidding bond forms
 description of the site
 Client CDM
 Cost matrix.
PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING
2) Technical specifications
These should supplement the drawings to
provide a full description on:
capacities
workmanship
finishes and other characteristics of all
materials and equipment
codes of practices and standards
PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING
Also:
Tender drawings
Bill of quantities
Project management
PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING
The basic Management Principles described byThe basic Management Principles described by
Henri Fayol are:Henri Fayol are:
 To planTo plan
 To organiseTo organise
 To co-ordinateTo co-ordinate
 To controlTo control
 To leadTo lead
The function of Project Management in moreThe function of Project Management in more
detail; are:detail; are:
brief formulationbrief formulation
PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING
client organisationclient organisation
approval powersapproval powers
Design Project Organisation such as:Design Project Organisation such as:
 organisation chartorganisation chart
 decision pointdecision point
 relationshipsrelationships
 feed backfeed back
PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING
Integrate Client into the projectIntegrate Client into the project
 Client organisation integrated into projectClient organisation integrated into project
organisationorganisation
 People responsibilitiesPeople responsibilities
 Decision processesDecision processes
Selection and appointment of contributorsSelection and appointment of contributors
 Identify contributorsIdentify contributors
 Identify input requiredIdentify input required
 Identify when input required and durationIdentify when input required and duration
 Record types of appointmentRecord types of appointment
PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING
Full brief formulation processFull brief formulation process
 Establish need, budget, cost plan, cost limit,Establish need, budget, cost plan, cost limit,
procurement route, start value engineeringprocurement route, start value engineering
Programme formulationProgramme formulation
 The overall project programmeThe overall project programme
 The phase or stage programmeThe phase or stage programme
 The design programmeThe design programme
 The procurement programmeThe procurement programme
 The construction programmeThe construction programme
 The commissioning programmeThe commissioning programme
PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING
Activation of the relationships betweenActivation of the relationships between
contributorscontributors
 Ensure contributors are brought in, andEnsure contributors are brought in, and
integrated into the project organisationintegrated into the project organisation
 Ensure contributors can perform asEnsure contributors can perform as
requiredrequired
Establish appropriate information andEstablish appropriate information and
communication structure by establishing acommunication structure by establishing a
full project procedures manual containing;full project procedures manual containing;
PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING
 Description of formal communicationDescription of formal communication
cannelcannel
 Change requests and instructionsChange requests and instructions
 Drawings frameworkDrawings framework
 Co-ordination project information systemCo-ordination project information system
 Address index of all contributorsAddress index of all contributors
 Convening and chairing meetings ofConvening and chairing meetings of
contributors at all stagescontributors at all stages
 Judging the need and frequencyJudging the need and frequency
PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING
Monitoring and controllingMonitoring and controlling
 Pro-active rolePro-active role
 Obtaining feedback and under takingObtaining feedback and under taking
analysisanalysis
 Testing outcomes to objectives and takingTesting outcomes to objectives and taking
corrective actioncorrective action
 ForecastingForecasting
 Integrating and controlling contributorsIntegrating and controlling contributors
PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING
Contribution to primary and key decisionsContribution to primary and key decisions
 Information/advice/reports/recommendationInformation/advice/reports/recommendation
 To assist clients in decision makingTo assist clients in decision making
Managing completionManaging completion
 Commissioning programmeCommissioning programme
 Training of userTraining of user
 As built drawings-user maintenanceAs built drawings-user maintenance
manualsmanuals
 Strategy for occupation or disposalStrategy for occupation or disposal
PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING
Evaluation of outcomesEvaluation of outcomes
 Success in achieving objectivesSuccess in achieving objectives
 The final feedback loopThe final feedback loop
THE DESIGN OF MANAGEMENT
STRUCTURE
THE DESIGN OF MANAGEMENT
STRUCTURE
GROUP STRUCTUREGROUP STRUCTURE
GROUP STRUCTUREGROUP STRUCTURE

More Related Content

What's hot

Construction Project management
Construction Project management Construction Project management
Construction Project management Anupama holla
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Managementjohnkirth1898
 
Project management PPT
Project management  PPTProject management  PPT
Project management PPTRaj Sampat
 
Project Management Summary 2012
Project Management Summary 2012Project Management Summary 2012
Project Management Summary 2012CPA Australia
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project ManagementSlav Karaslavov
 
Project management in construction
Project management in constructionProject management in construction
Project management in constructionNAVNEET KUMAR JHA
 
Introduction-to-project-management
Introduction-to-project-managementIntroduction-to-project-management
Introduction-to-project-managementSavaş Şakar
 
Project Planning and Management Notes
Project Planning and Management NotesProject Planning and Management Notes
Project Planning and Management NotesHaris Hassan
 
8.project management chapter 8
8.project management chapter 88.project management chapter 8
8.project management chapter 8Warui Maina
 
04 project integration management
04  project integration management04  project integration management
04 project integration managementAla Ibrahim
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenetAla Ibrahim
 
Project management in construction
Project management in constructionProject management in construction
Project management in constructionNAVNEET KUMAR JHA
 
009. project communication management
009. project communication management009. project communication management
009. project communication managementBoobalan G
 
Project Management Project 1
Project Management Project 1Project Management Project 1
Project Management Project 1Ho Yen Liang
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management FundamentalsOxfordCambridge
 

What's hot (20)

Construction Project management
Construction Project management Construction Project management
Construction Project management
 
012 bussiness planning process
012 bussiness planning process012 bussiness planning process
012 bussiness planning process
 
Phases of a Project
Phases of a ProjectPhases of a Project
Phases of a Project
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Project management PPT
Project management  PPTProject management  PPT
Project management PPT
 
Practical project management based on PMBOK5
Practical project management based on PMBOK5Practical project management based on PMBOK5
Practical project management based on PMBOK5
 
Project Management Summary 2012
Project Management Summary 2012Project Management Summary 2012
Project Management Summary 2012
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
 
Project management
Project managementProject management
Project management
 
Introduction-to-project-management
Introduction-to-project-managementIntroduction-to-project-management
Introduction-to-project-management
 
Project Planning and Management Notes
Project Planning and Management NotesProject Planning and Management Notes
Project Planning and Management Notes
 
8.project management chapter 8
8.project management chapter 88.project management chapter 8
8.project management chapter 8
 
04 project integration management
04  project integration management04  project integration management
04 project integration management
 
7 cost managmenet
7 cost managmenet7 cost managmenet
7 cost managmenet
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
 
009. project communication management
009. project communication management009. project communication management
009. project communication management
 
Overview of project management in engineering environment
Overview of project management in engineering environmentOverview of project management in engineering environment
Overview of project management in engineering environment
 
Project Management Project 1
Project Management Project 1Project Management Project 1
Project Management Project 1
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 

Viewers also liked

Planning for work experience
Planning for work experiencePlanning for work experience
Planning for work experienceJohn Iona
 
Audit Process, Planning,Field work,Audit report,Audit follow up,Audit program...
Audit Process, Planning,Field work,Audit report,Audit follow up,Audit program...Audit Process, Planning,Field work,Audit report,Audit follow up,Audit program...
Audit Process, Planning,Field work,Audit report,Audit follow up,Audit program...Advance Business Consulting
 
The 24th Thing: What's Next? - IL 2010
The 24th Thing: What's Next? - IL 2010The 24th Thing: What's Next? - IL 2010
The 24th Thing: What's Next? - IL 2010Christa Porter
 
Workplace Diversity
Workplace DiversityWorkplace Diversity
Workplace Diversityakkouto
 
Chapter03 diversity in the workplace.
Chapter03 diversity in the workplace.Chapter03 diversity in the workplace.
Chapter03 diversity in the workplace.Hafeez Abdullah
 
Diversity in the workplace
Diversity in the workplaceDiversity in the workplace
Diversity in the workplaceKatie York
 
Diversity in the Workplace - MBA 423 Human Resource Management
Diversity in the Workplace - MBA 423 Human Resource ManagementDiversity in the Workplace - MBA 423 Human Resource Management
Diversity in the Workplace - MBA 423 Human Resource ManagementStuart Gow
 
Cultural Diversity in the Workplace by The Cultural Diversity Committee
Cultural Diversity in the Workplace by The Cultural Diversity CommitteeCultural Diversity in the Workplace by The Cultural Diversity Committee
Cultural Diversity in the Workplace by The Cultural Diversity CommitteeAtlantic Training, LLC.
 
Time management ppt
Time management pptTime management ppt
Time management pptshukla1986
 
Time Management & Productivity - Best Practices
Time Management & Productivity -  Best PracticesTime Management & Productivity -  Best Practices
Time Management & Productivity - Best PracticesVit Horky
 

Viewers also liked (15)

Fjsc
FjscFjsc
Fjsc
 
Planning for work experience
Planning for work experiencePlanning for work experience
Planning for work experience
 
Audit Process, Planning,Field work,Audit report,Audit follow up,Audit program...
Audit Process, Planning,Field work,Audit report,Audit follow up,Audit program...Audit Process, Planning,Field work,Audit report,Audit follow up,Audit program...
Audit Process, Planning,Field work,Audit report,Audit follow up,Audit program...
 
The 24th Thing: What's Next? - IL 2010
The 24th Thing: What's Next? - IL 2010The 24th Thing: What's Next? - IL 2010
The 24th Thing: What's Next? - IL 2010
 
Jennifer | Work Planning
Jennifer | Work PlanningJennifer | Work Planning
Jennifer | Work Planning
 
Workplace Diversity
Workplace DiversityWorkplace Diversity
Workplace Diversity
 
Chapter03 diversity in the workplace.
Chapter03 diversity in the workplace.Chapter03 diversity in the workplace.
Chapter03 diversity in the workplace.
 
Diversity in the workplace
Diversity in the workplaceDiversity in the workplace
Diversity in the workplace
 
Diversity in the Workplace - MBA 423 Human Resource Management
Diversity in the Workplace - MBA 423 Human Resource ManagementDiversity in the Workplace - MBA 423 Human Resource Management
Diversity in the Workplace - MBA 423 Human Resource Management
 
Time management
Time managementTime management
Time management
 
Cultural Diversity in the Workplace by The Cultural Diversity Committee
Cultural Diversity in the Workplace by The Cultural Diversity CommitteeCultural Diversity in the Workplace by The Cultural Diversity Committee
Cultural Diversity in the Workplace by The Cultural Diversity Committee
 
Time management ppt
Time management pptTime management ppt
Time management ppt
 
Time Management Presentation
Time Management PresentationTime Management Presentation
Time Management Presentation
 
Time Management
Time ManagementTime Management
Time Management
 
Time Management & Productivity - Best Practices
Time Management & Productivity -  Best PracticesTime Management & Productivity -  Best Practices
Time Management & Productivity - Best Practices
 

Similar to 136 work planning and programming

Contemporary management
Contemporary managementContemporary management
Contemporary managementNikunj Gabani
 
COVER PAGE-Amit Anand
COVER PAGE-Amit AnandCOVER PAGE-Amit Anand
COVER PAGE-Amit AnandAmit Anand
 
projectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptxprojectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptxChandrasen Sharma
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01samansari22
 
140704 project planning presentation
140704 project planning presentation140704 project planning presentation
140704 project planning presentationMadhusudan Kashyap
 
P&Cc Module3 Cc1
P&Cc Module3 Cc1P&Cc Module3 Cc1
P&Cc Module3 Cc1MACDANIELLES
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01samansari22
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01petch phanpha
 
Project Feasibility [DECEMBER 2006]
Project Feasibility [DECEMBER 2006]Project Feasibility [DECEMBER 2006]
Project Feasibility [DECEMBER 2006]Fahad Mahmud Mirza
 
The project plan
The project planThe project plan
The project planVatsalaPG
 
Resume - PROJECTS PLANNING, PROJECTS CONTROL LEAD-ENGINEER
Resume - PROJECTS PLANNING, PROJECTS CONTROL LEAD-ENGINEERResume - PROJECTS PLANNING, PROJECTS CONTROL LEAD-ENGINEER
Resume - PROJECTS PLANNING, PROJECTS CONTROL LEAD-ENGINEERAbd~el Hakim mohamed izran
 
File 2 extra slide 1
File 2 extra slide 1File 2 extra slide 1
File 2 extra slide 1test prod1
 
File 2 extra slide 2
File 2 extra slide 2File 2 extra slide 2
File 2 extra slide 2test prod1
 

Similar to 136 work planning and programming (20)

012 bussiness planning process
012 bussiness planning process012 bussiness planning process
012 bussiness planning process
 
Project Management
Project ManagementProject Management
Project Management
 
Contemporary management
Contemporary managementContemporary management
Contemporary management
 
bingsusu.pptx
bingsusu.pptxbingsusu.pptx
bingsusu.pptx
 
COVER PAGE-Amit Anand
COVER PAGE-Amit AnandCOVER PAGE-Amit Anand
COVER PAGE-Amit Anand
 
projectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptxprojectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptx
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
 
140704 project planning presentation
140704 project planning presentation140704 project planning presentation
140704 project planning presentation
 
Project management
Project managementProject management
Project management
 
Project Mangement
Project MangementProject Mangement
Project Mangement
 
P&Cc Module3 Cc1
P&Cc Module3 Cc1P&Cc Module3 Cc1
P&Cc Module3 Cc1
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
 
Project Feasibility [DECEMBER 2006]
Project Feasibility [DECEMBER 2006]Project Feasibility [DECEMBER 2006]
Project Feasibility [DECEMBER 2006]
 
COMPANY PORTFOLIO
COMPANY PORTFOLIOCOMPANY PORTFOLIO
COMPANY PORTFOLIO
 
PM Services
PM ServicesPM Services
PM Services
 
The project plan
The project planThe project plan
The project plan
 
Resume - PROJECTS PLANNING, PROJECTS CONTROL LEAD-ENGINEER
Resume - PROJECTS PLANNING, PROJECTS CONTROL LEAD-ENGINEERResume - PROJECTS PLANNING, PROJECTS CONTROL LEAD-ENGINEER
Resume - PROJECTS PLANNING, PROJECTS CONTROL LEAD-ENGINEER
 
File 2 extra slide 1
File 2 extra slide 1File 2 extra slide 1
File 2 extra slide 1
 
File 2 extra slide 2
File 2 extra slide 2File 2 extra slide 2
File 2 extra slide 2
 

More from Dr Fereidoun Dejahang

27 j20 my news punch -dr f dejahang 27-01-2020
27 j20 my news punch -dr f dejahang  27-01-202027 j20 my news punch -dr f dejahang  27-01-2020
27 j20 my news punch -dr f dejahang 27-01-2020Dr Fereidoun Dejahang
 
028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrunDr Fereidoun Dejahang
 
026 fast react-productivity improvement
026 fast react-productivity improvement026 fast react-productivity improvement
026 fast react-productivity improvementDr Fereidoun Dejahang
 
022 b construction productivity-write
022 b construction productivity-write022 b construction productivity-write
022 b construction productivity-writeDr Fereidoun Dejahang
 
016 communication in construction sector
016 communication in construction sector016 communication in construction sector
016 communication in construction sectorDr Fereidoun Dejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDr Fereidoun Dejahang
 
013 changes in construction projects
013 changes in construction projects013 changes in construction projects
013 changes in construction projectsDr Fereidoun Dejahang
 

More from Dr Fereidoun Dejahang (20)

27 j20 my news punch -dr f dejahang 27-01-2020
27 j20 my news punch -dr f dejahang  27-01-202027 j20 my news punch -dr f dejahang  27-01-2020
27 j20 my news punch -dr f dejahang 27-01-2020
 
28 dej my news punch rev 28-12-2019
28 dej my news punch rev 28-12-201928 dej my news punch rev 28-12-2019
28 dej my news punch rev 28-12-2019
 
16 fd my news punch rev 16-12-2019
16 fd my news punch rev 16-12-201916 fd my news punch rev 16-12-2019
16 fd my news punch rev 16-12-2019
 
029 fast-tracking projects
029 fast-tracking projects029 fast-tracking projects
029 fast-tracking projects
 
028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun
 
027 fast-tracked projects-materials
027 fast-tracked projects-materials027 fast-tracked projects-materials
027 fast-tracked projects-materials
 
026 fast react-productivity improvement
026 fast react-productivity improvement026 fast react-productivity improvement
026 fast react-productivity improvement
 
025 enterprise resources management
025 enterprise resources management025 enterprise resources management
025 enterprise resources management
 
022 b construction productivity-write
022 b construction productivity-write022 b construction productivity-write
022 b construction productivity-write
 
022 a construction productivity (2)
022 a construction productivity (2)022 a construction productivity (2)
022 a construction productivity (2)
 
021 construction productivity (1)
021 construction productivity (1)021 construction productivity (1)
021 construction productivity (1)
 
019 competencies-managers
019 competencies-managers019 competencies-managers
019 competencies-managers
 
018 company productivity
018 company productivity018 company productivity
018 company productivity
 
017 communication
017 communication017 communication
017 communication
 
016 communication in construction sector
016 communication in construction sector016 communication in construction sector
016 communication in construction sector
 
015 changes-process model
015 changes-process model015 changes-process model
015 changes-process model
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
013 changes in construction projects
013 changes in construction projects013 changes in construction projects
013 changes in construction projects
 
011 business performance management
011 business performance management011 business performance management
011 business performance management
 
010 bmw tpm management training
010 bmw tpm management training010 bmw tpm management training
010 bmw tpm management training
 

Recently uploaded

complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadaditya806802
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Crushers to screens in aggregate production
Crushers to screens in aggregate productionCrushers to screens in aggregate production
Crushers to screens in aggregate productionChinnuNinan
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating SystemRashmi Bhat
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
Autonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptAutonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptbibisarnayak0
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptNarmatha D
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Erbil Polytechnic University
 

Recently uploaded (20)

complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasad
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Crushers to screens in aggregate production
Crushers to screens in aggregate productionCrushers to screens in aggregate production
Crushers to screens in aggregate production
 
Main Memory Management in Operating System
Main Memory Management in Operating SystemMain Memory Management in Operating System
Main Memory Management in Operating System
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
Autonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptAutonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.ppt
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.ppt
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
Comparative study of High-rise Building Using ETABS,SAP200 and SAFE., SAFE an...
 

136 work planning and programming

  • 2. PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING  Project planning, programming &Project planning, programming & scheduling is about estimating andscheduling is about estimating and managing the cost, time, quality, safety,managing the cost, time, quality, safety, etc.etc.  Management of a construction firmManagement of a construction firm determine exactly how long each aspect ofdetermine exactly how long each aspect of a project should take to complete.a project should take to complete.  A realistic time estimate ‘programme’ forA realistic time estimate ‘programme’ for the entire development process is a keythe entire development process is a key factor for project duration time.factor for project duration time.
  • 3. PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING  As the project progress managementAs the project progress management team constantly monitor progress againstteam constantly monitor progress against the original time plan;the original time plan;  Planning and programming is aboutPlanning and programming is about recovery of lost time;recovery of lost time;  Recommending management action inRecommending management action in order to maintain programme (time, cost,order to maintain programme (time, cost, quality, safety, etc).quality, safety, etc).
  • 4. PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING Tender PlanningTender Planning Tender planning is the first phase of any project.Tender planning is the first phase of any project. It is important to generate a plan covering items such as:It is important to generate a plan covering items such as:  clear project directionclear project direction  budget and schedule before proceeding to avoid makingbudget and schedule before proceeding to avoid making costly mistakes and causing delayscostly mistakes and causing delays  Tender programmesTender programmes  Feasibility StudiesFeasibility Studies  Budget GenerationBudget Generation  Design ManagementDesign Management  Value EngineeringValue Engineering
  • 5. PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING On the other hand programming is about:On the other hand programming is about:  Construction programmes for all siteConstruction programmes for all site activitiesactivities  Package and Procurement programmesPackage and Procurement programmes for each element of worksfor each element of works  Overall design and ProcurementOverall design and Procurement programmesprogrammes  As built programmesAs built programmes  Critical path analysisCritical path analysis
  • 6. PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING So far:  Once the basic planning and preparation of the master plan are complete, management should work on:  plans, specifications and cost estimates  tender documents  selection of contractor and award of work  construction activities  project management and control  handing over for commissioning
  • 7. PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING Appropriate construction technology  The choice of building materials has an effect both on cost and length of construction.  Locally available materials  Traditional building techniques should be given priority.  They are usually cheaper and more accessible.  Selection of materials and future maintenance must be considered during design stages.
  • 8. PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING Building materials should be: economical durable easy to clean and to maintain or replace. They should also be easy to handle on the site and to replace in case of breakage or damage.
  • 9. PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING The designer must choose: (1) the type of construction of the project:  indigenous technology  on-site methods  prefabricated modules and components assembled on site  Or a combination of prefabricated components and on-site construction. (2) the level of technology: low, medium or high.
  • 10. PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING Construction technology should take in to consideration factors such as:  conditions of site  time constraints  availability of labour and raw materials  construction equipment and any other related factors. Whenever possible:  Methods adopted should be within the capability of local manpower and resources.
  • 11. PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING Consideration of innovative methods when possible Issue of sustainability If design professionals are brought in, they should work in association with: local architects engineers so that there is a transfer of knowledge in the area.
  • 12. PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING Tendering general conditions of contract technical specifications tender drawings bill of quantities.
  • 13. PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING General conditions of contract  This should consist of:  cover or title sheet  index  instructions to bidders  bidding form  form of agreement  performance bond and bidding bond forms  description of the site  Client CDM  Cost matrix.
  • 14. PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING 2) Technical specifications These should supplement the drawings to provide a full description on: capacities workmanship finishes and other characteristics of all materials and equipment codes of practices and standards
  • 15. PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING Also: Tender drawings Bill of quantities Project management
  • 16. PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING The basic Management Principles described byThe basic Management Principles described by Henri Fayol are:Henri Fayol are:  To planTo plan  To organiseTo organise  To co-ordinateTo co-ordinate  To controlTo control  To leadTo lead The function of Project Management in moreThe function of Project Management in more detail; are:detail; are: brief formulationbrief formulation
  • 17. PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING client organisationclient organisation approval powersapproval powers Design Project Organisation such as:Design Project Organisation such as:  organisation chartorganisation chart  decision pointdecision point  relationshipsrelationships  feed backfeed back
  • 18. PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING Integrate Client into the projectIntegrate Client into the project  Client organisation integrated into projectClient organisation integrated into project organisationorganisation  People responsibilitiesPeople responsibilities  Decision processesDecision processes Selection and appointment of contributorsSelection and appointment of contributors  Identify contributorsIdentify contributors  Identify input requiredIdentify input required  Identify when input required and durationIdentify when input required and duration  Record types of appointmentRecord types of appointment
  • 19. PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING Full brief formulation processFull brief formulation process  Establish need, budget, cost plan, cost limit,Establish need, budget, cost plan, cost limit, procurement route, start value engineeringprocurement route, start value engineering Programme formulationProgramme formulation  The overall project programmeThe overall project programme  The phase or stage programmeThe phase or stage programme  The design programmeThe design programme  The procurement programmeThe procurement programme  The construction programmeThe construction programme  The commissioning programmeThe commissioning programme
  • 20. PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING Activation of the relationships betweenActivation of the relationships between contributorscontributors  Ensure contributors are brought in, andEnsure contributors are brought in, and integrated into the project organisationintegrated into the project organisation  Ensure contributors can perform asEnsure contributors can perform as requiredrequired Establish appropriate information andEstablish appropriate information and communication structure by establishing acommunication structure by establishing a full project procedures manual containing;full project procedures manual containing;
  • 21. PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING  Description of formal communicationDescription of formal communication cannelcannel  Change requests and instructionsChange requests and instructions  Drawings frameworkDrawings framework  Co-ordination project information systemCo-ordination project information system  Address index of all contributorsAddress index of all contributors  Convening and chairing meetings ofConvening and chairing meetings of contributors at all stagescontributors at all stages  Judging the need and frequencyJudging the need and frequency
  • 22. PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING Monitoring and controllingMonitoring and controlling  Pro-active rolePro-active role  Obtaining feedback and under takingObtaining feedback and under taking analysisanalysis  Testing outcomes to objectives and takingTesting outcomes to objectives and taking corrective actioncorrective action  ForecastingForecasting  Integrating and controlling contributorsIntegrating and controlling contributors
  • 23. PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING Contribution to primary and key decisionsContribution to primary and key decisions  Information/advice/reports/recommendationInformation/advice/reports/recommendation  To assist clients in decision makingTo assist clients in decision making Managing completionManaging completion  Commissioning programmeCommissioning programme  Training of userTraining of user  As built drawings-user maintenanceAs built drawings-user maintenance manualsmanuals  Strategy for occupation or disposalStrategy for occupation or disposal
  • 24. PLANNING AND PROGRAMMINGPLANNING AND PROGRAMMING Evaluation of outcomesEvaluation of outcomes  Success in achieving objectivesSuccess in achieving objectives  The final feedback loopThe final feedback loop
  • 25. THE DESIGN OF MANAGEMENT STRUCTURE
  • 26. THE DESIGN OF MANAGEMENT STRUCTURE