PROGRESS
MEASUREMENT
SYSTEM
IN CONSTRUCTION
1.) THE FUTURE OF QATAR
CONTRUCTION INDUSTRY
2.) UPCOMING MEGA PROJECTS
3.) QUANTITY SURVEYING STRATEGIES
4.) TACTICAL OUTLINE OF PMS
PROGRESS MEASUREMENT SYSTEM
2
THE FUTURE OF QATAR
CONTRUCTION INDUSTRY
3
1
THE FUTURE OF QATAR
CONSTRUCTION
depend on:
- The Qatar Economic Growth &
- Visions of the Government
4
QATAR ECONOMIC
GROWTH
5
Qatar had been attracting worldwide attention
due to its position as the world’s 3rd largest
producer/supplier of liquefied natural gas
(LNG) & for being among the top 20 world oil
producers.
Economic Statistics proved that Qatar to be
fastest growing economy in the world in 2011
& the country with the largest disposable
income.
6
QATAR ECONOMIC GROWTH
Qatar Economy
7
GDP per capita = gross domestic product
midyear population
During the review period (2006–2010), the
government invested considerable attempt to
develop the country’s tourism, education and
infrastructure, which led to significant growth in
the Qatar Construction Industry. The general
causes for growth in the industry were Qatar’s
rising population growth, its per capita GDP and its
increased revenue from the abundant gas
resources.
However, the industry’s growth was impeded in
2010 due to the affects of the global economic
crisis, which reduced the demand for residential
and commercial construction projects.
8
VISION OF THE GOVERNMENT
9
The world wide attention caught by Qatar due to the
economy embarking on an ambitious program to gear
up to host the world cup 2022 FIFA football event.
(Furthermore, their intention to host forthcoming
Olympic in Qatar is boosting their vision) .
The hosting of the World Cup is being viewed as a
stepping stone to the long standing vision of the
country outlined in its National Vision 2030 to put
Qatar on the World map as a leading destination for
tourists and investors alike on a sustainable platform
which is environmentally sound and improves the
standards of living of the Qatari citizens at large.
10
Vision
UPCOMING
MEGA PROJECTS
11
2
Activity across its stadia and real estate and
infrastructure upgrades including ports, a
new international airport, a railway network,
roads and highways of which some are new
and some are being upgraded, new hotels
and recreation complexes are also being
built to house the players, tourists and
visitors to the grand event are all likely to
pick up pace between 2013 and 2015 edging
to conclusion by 2017, when the country
plans to host trial events in a run up to the
World Cup.
12
As the country gears to host the World Cup in 2022,
projects and contracts awarded at a moderate pace
through 2011 and 2012 have begun to catch up pace
and are likely to almost double in 2013. Contracts
worth:
QR. 59.21 billion in 2011
QR. 66.32 billion in 2012,
QR. 120.80 billion in 2013,
Projects being readied for the World Cup 2022 event
include 9 stadia, the prestigious metro and other
railway projects, and the roads and highways
expansion and upgrade projects to ease congestion
in the capital city of Doha, are all likely to witness
contract awards for core and associated projects
likely to stretch over a period of 2013 to 2017.
13
 Doha New Port
 Entertainment City - Qatar
 Qatar Railway Project
 Bahrain-Qatar Friendship Bridge
 Urguan Project
 Al-Jawhara City
 Al-Waab City
 Barwa Al-Baraha
14
List of Meja Projects
 Barwa City Development
 Barzan Gas Project
 Doha Festival City
 Doha, Lusail and Dukhan highways
 Education City
 Hamad International Airport
 Local Roads and Drainage Programme
 Lusail City
 Msheireb
15
 Sharq Crossing
 Pearl-Qatar
 Ras Laffan Complex
 Petrochemical Joint Venture
 Transmission project
 World Cup Stadiums
16
17
QUANTITY
SURVEYING
STRATEGIES
3
VITAL QUANTITY SURVEYING
REQUIREMENTS
3.a - Due to increase of construction projects
3.b - Due to unforeseen construction
requirements
3.c - Due to possible changes to conditions of
contract
18
3.a Due to increase of construction projects
According to the projected allocation, expenditure
requirements calculated up to end of 2016 as
follows:
Projected expenditure
QR 210.00 billion in 2014
QR 340.00 billion in 2015
QR 480.00 billion in 2016
It is noted 2016 allocation calculated as 480 billion
which is approximately 4 times compared with the
allocated budget for the year 2013.
It means increase of quantity surveyors requirement is
ESSENTIAL.
19
3.b Due to unforeseen construction requirements
 During the year 2013, it is recorded additional 200,000 people
were employed in Qatar
 Do we have required facilities such as
- hospitals, schools, transportation. ROADS, shops,
accommodations, etc?
 Authorities realize now that there is a mistake of unattended
planning for the supply of required facilities for increasing
construction workers.
To accommodate this requirement, additional Quantity
Surveyors are required.
20
 Most of this international companies (construction/ consultant/
specialist) are familiar with latest version of FIDIC conditions.
 Replacing of using the well refined 4th edition of 1987 FIDIC
version, by unrefined (trial stage) 1999 FIDIC version is a
precarious situation to the construction industry and will
become a disaster to Contract Management.
 This requirement will be adopted in Qatar Construction Industry
in the future.
 Alternative dispute resolution activated.
 The Quantity Service requirement will become more CRUCIAL.
21
3.c Due to possible changes to conditions of
contract
22
QUANTITY
SURVEYORS
AVAILABILITY
Billions in QR
ADDITIONAL
WORKLOAD
CONCLUSION
There are two major problems to be considered as a result of the
discussion we had so far:
1. Can we supply the number of Quantity Surveyors required for the
Qatar Construction industry?
If industry cannot be filled up with required number of Quantity
Surveyors, there is a tendency to seek other solutions to
overcome the situation, affecting the progress of their
construction project , due to cash flow problems.
2. Are we professional enough to take the challenge of quantifying
mega projects and produce/review the monthly payment
certificates without any delay in order to maintain a smooth cash
flow?
End of Part 1

Contenu connexe

Similaire à Slqs pms part1-final

Are You On The Bench?
Are You On The Bench? Are You On The Bench?
Are You On The Bench? james3b
 
Qatar construction opportunities Market Research Report
Qatar construction opportunities Market Research ReportQatar construction opportunities Market Research Report
Qatar construction opportunities Market Research Reportnishakar
 
Qatar Construction Opportunities q2-2011
Qatar Construction Opportunities  q2-2011Qatar Construction Opportunities  q2-2011
Qatar Construction Opportunities q2-2011shubhamrut
 
Anindya Roychowdhury - The Oil & Gas Year Kuwait 2016
Anindya Roychowdhury - The Oil & Gas Year Kuwait 2016Anindya Roychowdhury - The Oil & Gas Year Kuwait 2016
Anindya Roychowdhury - The Oil & Gas Year Kuwait 2016Anindya Roychowdhury
 
Carlos Alberto Sandoval - Infraestructure Opportunities and FDN's Role
Carlos Alberto Sandoval - Infraestructure Opportunities and FDN's RoleCarlos Alberto Sandoval - Infraestructure Opportunities and FDN's Role
Carlos Alberto Sandoval - Infraestructure Opportunities and FDN's RoleProColombia
 
Rampura-Amulia-Demra Expressway (RAD) Market Awareness Brochure
Rampura-Amulia-Demra Expressway (RAD) Market Awareness BrochureRampura-Amulia-Demra Expressway (RAD) Market Awareness Brochure
Rampura-Amulia-Demra Expressway (RAD) Market Awareness BrochurePratish Halady
 
DMIC Summit – Developing Hub for Investors
DMIC Summit – Developing Hub for Investors DMIC Summit – Developing Hub for Investors
DMIC Summit – Developing Hub for Investors Resurgent India
 
Qatar 2022 World Cup | FlyDoha
Qatar 2022 World Cup | FlyDohaQatar 2022 World Cup | FlyDoha
Qatar 2022 World Cup | FlyDohaFlyDoha
 
New base special 17 february 2014
New base special  17 february 2014New base special  17 february 2014
New base special 17 february 2014Khaled Al Awadi
 
DMIC Summit – Developing Hub for Investors - Overview & Approach - Part - 1
DMIC Summit – Developing Hub for Investors - Overview & Approach - Part - 1DMIC Summit – Developing Hub for Investors - Overview & Approach - Part - 1
DMIC Summit – Developing Hub for Investors - Overview & Approach - Part - 1Resurgent India
 
QNBFS Weekly Market Report August 25, 2022
QNBFS Weekly Market Report August 25, 2022QNBFS Weekly Market Report August 25, 2022
QNBFS Weekly Market Report August 25, 2022QNB Group
 
Target audience
Target audienceTarget audience
Target audienceBossGee
 
Vibrant Gujarat Summit on Large/Mega project opportunities in Gujarat
Vibrant Gujarat Summit on Large/Mega project opportunities in GujaratVibrant Gujarat Summit on Large/Mega project opportunities in Gujarat
Vibrant Gujarat Summit on Large/Mega project opportunities in GujaratVibrant Gujarat
 
Rebuilding of Railway Infrastructures during the present crisis by Rajesh Prasad
Rebuilding of Railway Infrastructures during the present crisis by Rajesh PrasadRebuilding of Railway Infrastructures during the present crisis by Rajesh Prasad
Rebuilding of Railway Infrastructures during the present crisis by Rajesh PrasadRajesh Prasad
 
2016_11$thumbimg129_Nov_2016_220207183.pdf
2016_11$thumbimg129_Nov_2016_220207183.pdf2016_11$thumbimg129_Nov_2016_220207183.pdf
2016_11$thumbimg129_Nov_2016_220207183.pdfPayalFirodiya3
 

Similaire à Slqs pms part1-final (20)

Are You On The Bench?
Are You On The Bench? Are You On The Bench?
Are You On The Bench?
 
Qatar construction opportunities Market Research Report
Qatar construction opportunities Market Research ReportQatar construction opportunities Market Research Report
Qatar construction opportunities Market Research Report
 
Qatar Construction Opportunities q2-2011
Qatar Construction Opportunities  q2-2011Qatar Construction Opportunities  q2-2011
Qatar Construction Opportunities q2-2011
 
Anindya Roychowdhury - The Oil & Gas Year Kuwait 2016
Anindya Roychowdhury - The Oil & Gas Year Kuwait 2016Anindya Roychowdhury - The Oil & Gas Year Kuwait 2016
Anindya Roychowdhury - The Oil & Gas Year Kuwait 2016
 
Carlos Alberto Sandoval - Infraestructure Opportunities and FDN's Role
Carlos Alberto Sandoval - Infraestructure Opportunities and FDN's RoleCarlos Alberto Sandoval - Infraestructure Opportunities and FDN's Role
Carlos Alberto Sandoval - Infraestructure Opportunities and FDN's Role
 
Rampura-Amulia-Demra Expressway (RAD) Market Awareness Brochure
Rampura-Amulia-Demra Expressway (RAD) Market Awareness BrochureRampura-Amulia-Demra Expressway (RAD) Market Awareness Brochure
Rampura-Amulia-Demra Expressway (RAD) Market Awareness Brochure
 
LMDsept11_Qatar_spreads
LMDsept11_Qatar_spreadsLMDsept11_Qatar_spreads
LMDsept11_Qatar_spreads
 
DMIC Summit – Developing Hub for Investors
DMIC Summit – Developing Hub for Investors DMIC Summit – Developing Hub for Investors
DMIC Summit – Developing Hub for Investors
 
Qatar_LMDen 2011
Qatar_LMDen 2011Qatar_LMDen 2011
Qatar_LMDen 2011
 
Qatar 2022 World Cup | FlyDoha
Qatar 2022 World Cup | FlyDohaQatar 2022 World Cup | FlyDoha
Qatar 2022 World Cup | FlyDoha
 
New base special 17 february 2014
New base special  17 february 2014New base special  17 february 2014
New base special 17 february 2014
 
DMIC Summit – Developing Hub for Investors - Overview & Approach - Part - 1
DMIC Summit – Developing Hub for Investors - Overview & Approach - Part - 1DMIC Summit – Developing Hub for Investors - Overview & Approach - Part - 1
DMIC Summit – Developing Hub for Investors - Overview & Approach - Part - 1
 
Qatar - a wealth of opportunities
Qatar - a wealth of opportunitiesQatar - a wealth of opportunities
Qatar - a wealth of opportunities
 
Capital Programs - O'Hare 21
Capital Programs - O'Hare 21 Capital Programs - O'Hare 21
Capital Programs - O'Hare 21
 
QNBFS Weekly Market Report August 25, 2022
QNBFS Weekly Market Report August 25, 2022QNBFS Weekly Market Report August 25, 2022
QNBFS Weekly Market Report August 25, 2022
 
Target audience
Target audienceTarget audience
Target audience
 
Itransporte No 49 - Jan 14 - Q8
Itransporte No 49 - Jan 14 - Q8Itransporte No 49 - Jan 14 - Q8
Itransporte No 49 - Jan 14 - Q8
 
Vibrant Gujarat Summit on Large/Mega project opportunities in Gujarat
Vibrant Gujarat Summit on Large/Mega project opportunities in GujaratVibrant Gujarat Summit on Large/Mega project opportunities in Gujarat
Vibrant Gujarat Summit on Large/Mega project opportunities in Gujarat
 
Rebuilding of Railway Infrastructures during the present crisis by Rajesh Prasad
Rebuilding of Railway Infrastructures during the present crisis by Rajesh PrasadRebuilding of Railway Infrastructures during the present crisis by Rajesh Prasad
Rebuilding of Railway Infrastructures during the present crisis by Rajesh Prasad
 
2016_11$thumbimg129_Nov_2016_220207183.pdf
2016_11$thumbimg129_Nov_2016_220207183.pdf2016_11$thumbimg129_Nov_2016_220207183.pdf
2016_11$thumbimg129_Nov_2016_220207183.pdf
 

Dernier

Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectDM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectssuserb6619e
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfChristianCDAM
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solidnamansinghjarodiya
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Coursebim.edu.pl
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadaditya806802
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptNarmatha D
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
Risk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectRisk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectErbil Polytechnic University
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the weldingMuhammadUzairLiaqat
 
"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...Erbil Polytechnic University
 

Dernier (20)

Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectDM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdf
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solid
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Course
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasad
 
Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.ppt
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
Risk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectRisk Management in Engineering Construction Project
Risk Management in Engineering Construction Project
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the welding
 
"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...
 

Slqs pms part1-final

  • 2. 1.) THE FUTURE OF QATAR CONTRUCTION INDUSTRY 2.) UPCOMING MEGA PROJECTS 3.) QUANTITY SURVEYING STRATEGIES 4.) TACTICAL OUTLINE OF PMS PROGRESS MEASUREMENT SYSTEM 2
  • 3. THE FUTURE OF QATAR CONTRUCTION INDUSTRY 3 1
  • 4. THE FUTURE OF QATAR CONSTRUCTION depend on: - The Qatar Economic Growth & - Visions of the Government 4
  • 6. Qatar had been attracting worldwide attention due to its position as the world’s 3rd largest producer/supplier of liquefied natural gas (LNG) & for being among the top 20 world oil producers. Economic Statistics proved that Qatar to be fastest growing economy in the world in 2011 & the country with the largest disposable income. 6 QATAR ECONOMIC GROWTH
  • 7. Qatar Economy 7 GDP per capita = gross domestic product midyear population
  • 8. During the review period (2006–2010), the government invested considerable attempt to develop the country’s tourism, education and infrastructure, which led to significant growth in the Qatar Construction Industry. The general causes for growth in the industry were Qatar’s rising population growth, its per capita GDP and its increased revenue from the abundant gas resources. However, the industry’s growth was impeded in 2010 due to the affects of the global economic crisis, which reduced the demand for residential and commercial construction projects. 8
  • 9. VISION OF THE GOVERNMENT 9
  • 10. The world wide attention caught by Qatar due to the economy embarking on an ambitious program to gear up to host the world cup 2022 FIFA football event. (Furthermore, their intention to host forthcoming Olympic in Qatar is boosting their vision) . The hosting of the World Cup is being viewed as a stepping stone to the long standing vision of the country outlined in its National Vision 2030 to put Qatar on the World map as a leading destination for tourists and investors alike on a sustainable platform which is environmentally sound and improves the standards of living of the Qatari citizens at large. 10 Vision
  • 12. Activity across its stadia and real estate and infrastructure upgrades including ports, a new international airport, a railway network, roads and highways of which some are new and some are being upgraded, new hotels and recreation complexes are also being built to house the players, tourists and visitors to the grand event are all likely to pick up pace between 2013 and 2015 edging to conclusion by 2017, when the country plans to host trial events in a run up to the World Cup. 12
  • 13. As the country gears to host the World Cup in 2022, projects and contracts awarded at a moderate pace through 2011 and 2012 have begun to catch up pace and are likely to almost double in 2013. Contracts worth: QR. 59.21 billion in 2011 QR. 66.32 billion in 2012, QR. 120.80 billion in 2013, Projects being readied for the World Cup 2022 event include 9 stadia, the prestigious metro and other railway projects, and the roads and highways expansion and upgrade projects to ease congestion in the capital city of Doha, are all likely to witness contract awards for core and associated projects likely to stretch over a period of 2013 to 2017. 13
  • 14.  Doha New Port  Entertainment City - Qatar  Qatar Railway Project  Bahrain-Qatar Friendship Bridge  Urguan Project  Al-Jawhara City  Al-Waab City  Barwa Al-Baraha 14 List of Meja Projects
  • 15.  Barwa City Development  Barzan Gas Project  Doha Festival City  Doha, Lusail and Dukhan highways  Education City  Hamad International Airport  Local Roads and Drainage Programme  Lusail City  Msheireb 15
  • 16.  Sharq Crossing  Pearl-Qatar  Ras Laffan Complex  Petrochemical Joint Venture  Transmission project  World Cup Stadiums 16
  • 18. VITAL QUANTITY SURVEYING REQUIREMENTS 3.a - Due to increase of construction projects 3.b - Due to unforeseen construction requirements 3.c - Due to possible changes to conditions of contract 18
  • 19. 3.a Due to increase of construction projects According to the projected allocation, expenditure requirements calculated up to end of 2016 as follows: Projected expenditure QR 210.00 billion in 2014 QR 340.00 billion in 2015 QR 480.00 billion in 2016 It is noted 2016 allocation calculated as 480 billion which is approximately 4 times compared with the allocated budget for the year 2013. It means increase of quantity surveyors requirement is ESSENTIAL. 19
  • 20. 3.b Due to unforeseen construction requirements  During the year 2013, it is recorded additional 200,000 people were employed in Qatar  Do we have required facilities such as - hospitals, schools, transportation. ROADS, shops, accommodations, etc?  Authorities realize now that there is a mistake of unattended planning for the supply of required facilities for increasing construction workers. To accommodate this requirement, additional Quantity Surveyors are required. 20
  • 21.  Most of this international companies (construction/ consultant/ specialist) are familiar with latest version of FIDIC conditions.  Replacing of using the well refined 4th edition of 1987 FIDIC version, by unrefined (trial stage) 1999 FIDIC version is a precarious situation to the construction industry and will become a disaster to Contract Management.  This requirement will be adopted in Qatar Construction Industry in the future.  Alternative dispute resolution activated.  The Quantity Service requirement will become more CRUCIAL. 21 3.c Due to possible changes to conditions of contract
  • 23. CONCLUSION There are two major problems to be considered as a result of the discussion we had so far: 1. Can we supply the number of Quantity Surveyors required for the Qatar Construction industry? If industry cannot be filled up with required number of Quantity Surveyors, there is a tendency to seek other solutions to overcome the situation, affecting the progress of their construction project , due to cash flow problems. 2. Are we professional enough to take the challenge of quantifying mega projects and produce/review the monthly payment certificates without any delay in order to maintain a smooth cash flow? End of Part 1