EMLI Training-An introduction to EPC Contract – Clause by clause discussion merupakan materi pembahasan dalam kegiatan Workshop EPC Contract yang diselenggarakan oleh EMLI Training. materi tersebut disampaikan oleh Bapak Dendi Adisuryo, S.H.beliau adalah partner at ADCO Attorneys at Law.
EMLI Training-An introduction to EPC Contract – Clause by clause discussion merupakan materi pembahasan dalam kegiatan Workshop EPC Contract yang diselenggarakan oleh EMLI Training. materi tersebut disampaikan oleh Bapak Dendi Adisuryo, S.H.beliau adalah partner at ADCO Attorneys at Law.
EMLI Training-An introduction to epc contract-clause by clause-Prepared by: Dendi Adisuryo of ADCOLAW Attorneys at Law
1.
Prepared by: Dendi Adisuryo of
ADCOLAW Attorneys at Law
An introduction to EPC
Contract – Clause by clause
discussion
2.
ADCOLAW – experience and expertise
Mining, Energy and Major Projects are core areas of focus for
ADCO Attorneys at Law.
Work for over 40 major clients since our establishment on 2008
and on projects with a cumulative value of over US$500 million
Named as one of Asian Leading Lawyers for Natural Resources
for 2013 – recent.
3.
Project Structure
Loan
Agt
Asuransi Co
Operator and
Manager
Pemerintah
Sponsors
BANK / Non-Bank
Fin Inst
IPP
PLN / BuyerShareholders
Agt
Direct
Agreement
Share
Mortgage
Agt
Security
Documents
EPC Company
EPC Contract
O & M
Agreement
Insurance
Policy
PPA
Direct
Agreement
Direct
Agreement
Licensing Matters
Fuel Supplier Fuel Supply
Agreement
Direct
Agreement
Equipment
Supplier
Equipment Supply
Agreement
Direct
Agreement
4.
A key word - Risks
A “risk” is an uncertain event or condition that, if it occurs,
has a positive or negative effect on the project going
concerns
6.
Types of Construction Contract – Risk Allocation
Force Account (Ind.: swakelola)
EPCM (Engineering Procurement Construction
Management)
EPC (Engineering Procurement Construction)
BOT / BOOT
7.
EPC – by Definition
A particular form of contracting arrangement used in some
industries where the EPC Contractor is made responsible
for all the activities from design, procurement, construction,
to commissioning and handover of the project to the
“Employer”
8.
EPC + /-
Advantages
single point of responsibility
limited interface risk
fixed price (although some variations to pricing structures)
potentially fixed schedule (subject to contractual adjustment
mechanisms)
contractor has design liability
bankability
easier contract administration
single or multiple completion dates for Works or Sections
caps on liability and limitations on liability
9.
EPC + / -
Disadvantages
tender process can be long and costly
prices can be higher – all risks are priced
limited pool of contractors – competitive pressure may not off-set
the risk pricing
contractor default has a significant impact
potentially adversarial relationship
loss of control – less Owner involvement and potential for
intervention
10.
Splitting EPC Contract
Issues to consider
rationale (avoiding local corporate taxation on work carried out offshore, IUJK
requirement)
scope of the onshore/offshore contractor work
Offsore: design, engineering, supply of plants / materials sourced from outside host county
Onshore: installation, construction, testing, commissioning, supply materials from host
country
typical structure (coordination/umbrella agreements)
how do you avoid liability “gaps” between offshore and onshore contractors?
11.
Splitting EPC Contract
Practical messages
undertake tax analysis as early as possible to determine best contract
structure for tax efficiency
(contract split must be driven by tax regime of the deal)
ensure that technical schedules can be split (if necessary)
tender process should reflect the split
12.
EPC – Typical and Critical Issues
Why are issues “typical”?
they represent the balance (levers) between the contract price and the
allocation of risk
for the contractor, a higher price may mean it is prepared to take more risk
for the employer, a lower price may mean it must take on more risk
allocation of risk is critical, even in an EPC contract. Engineering projects are
inherently risky;
who is best placed to take on the risk?
13.
EPC – Typical and Critical Issues
What are the “typical” issues?
quality (standards of work or performance):
warranties and standards of care
performance testing and under-performance remedies
time (schedule) and money (costs and finance):
program, time for completion and delay remedies
grounds for extension of time and cost
consequences if things go wrong:
performance security
termination (including force majeure)
limitations on liability and indemnities
Technology
14.
EPC - Warranties
Typical EPC warranties
compliance with “Good Industry Practice” and contract requirements, including performance –
consider specific performance requirements
“fitness for purpose”, as specified in the Contract – there may be issues in negotiating this
standard as may need to define purposes clearly
free from defects in design and workmanship
obtaining required third party IP rights and no infringement
compliance with laws, relevant codes of practice and ethics (which ones?)
designed for minimum specified working life
15.
Performance Test
Issues to consider
matching up the technical schedules in the contract with the language in the conditions (often
different workstreams)
performance liquidated damages must be a genuine pre-estimate of loss
performance liquidated damages only achieve so much; difficulties of achieving practical
sanction if plant falls below the minimum standards where rejection is not realistic
Performance testing and damages mechanisms; the EPC contract should include
testing regimes and performance liquidated damages in respect of key criteria (eg. product
quality, capacity, utility consumption etc.)
mechanisms to recover performance liquidated damages within specified parameters, but
right to reject or reduce price if performance is below minimum standards
clear program for testing – whether testing takes place before or after taking-over by Owner
(e.g. on Mechanical Completion or after commissioning or both)
16.
Time and Cost
Contract program and time for completion
critical issue – importance of completion on time to preserve revenue stream
program – role, adjustment and legal status under the EPC contract; project to be completed
as a whole or in sections?
–defects liability period – purpose, effect and extension
Grounds for extending time and cost
acceleration and expediting – ability to require Contractor to accelerate or expedite and the
consequences of doing so
extensions of time; allocation of delay risks may be heavily negotiated
17.
Time and Cost
Contract program and time for completion
critical issue – importance of completion on time to preserve revenue stream
program – role, adjustment and legal status under the EPC contract; project to be completed
as a whole or in sections?
defects liability period – purpose, effect and extension
Grounds for extending time and cost
acceleration and expediting – ability to require Contractor to accelerate or expedite and the
consequences of doing so
extensions of time; allocation of delay risks may be heavily negotiated
18.
Time and Cost
Delay liquidated damages
delay liquidated damages for failure to meet Time for Completion for works or relevant section
daily or weekly rate to be set out in Contract
setting and claiming - must not exceed a “genuine pre-estimate” of loss (cf. modeling)
19.
Perfomance Security
Issues to consider
From whom should the security be sought?
for how much?
for how long?
Types of security
advance payment guarantee
performance bond
parent company guarantee
retention / retention bond
subcontractor indemnities
…or a combination
21.
Termination Rights
Issues to consider
termination is a last resort, but if it happens all parties need to understand the
consequences
the consequences of termination will differ depending on the circumstances
remember that if termination occurs, handover may be required
22.
Termination
Termination by Employer for Contractor Default
Termination by Contractor for Employer Default
Termination for Employer convinience
Termination by both Parties for Force Majeure
Termination by both Parties for certain conditions
27.
Force Majeure
Broad definition under the ICC so contractual definition is important
General tests plus non-exhaustive list of events or narrower test (perhaps with specific
exclusions)
Consequences for parties‟ obligations – time and cost
Possible termination for prolonged delay
28.
See you next in clause by clause discussion.....
Il semblerait que vous ayez déjà ajouté cette diapositive à .
Créer un clipboard
Vous avez clippé votre première diapositive !
En clippant ainsi les diapos qui vous intéressent, vous pourrez les revoir plus tard. Personnalisez le nom d’un clipboard pour mettre de côté vos diapositives.
Créer un clipboard
Partager ce SlideShare
Vous avez les pubs en horreur?
Obtenez SlideShare sans publicité
Bénéficiez d'un accès à des millions de présentations, documents, e-books, de livres audio, de magazines et bien plus encore, sans la moindre publicité.
Offre spéciale pour les lecteurs de SlideShare
Juste pour vous: Essai GRATUIT de 60 jours dans la plus grande bibliothèque numérique du monde.
La famille SlideShare vient de s'agrandir. Profitez de l'accès à des millions de livres numériques, livres audio, magazines et bien plus encore sur Scribd.
Apparemment, vous utilisez un bloqueur de publicités qui est en cours d'exécution. En ajoutant SlideShare à la liste blanche de votre bloqueur de publicités, vous soutenez notre communauté de créateurs de contenu.
Vous détestez les publicités?
Nous avons mis à jour notre politique de confidentialité.
Nous avons mis à jour notre politique de confidentialité pour nous conformer à l'évolution des réglementations mondiales en matière de confidentialité et pour vous informer de la manière dont nous utilisons vos données de façon limitée.
Vous pouvez consulter les détails ci-dessous. En cliquant sur Accepter, vous acceptez la politique de confidentialité mise à jour.