1
Europeana Generic
Services Projects Meeting
Kyriaki Tragouda
Project Officer @ INEA, Unit C5 - Telecommunications
Hague 29/10/2018
Content
• INEA's expectations
• Reporting
• Costs
• Modifications
• Publicity
• Follow-up
• Answering your questions
2
INEA's expectations towards the
implementation of an Action
The development and delivery of what has been
described in Annex I of the Grant Agreement
Reporting requirements
• Final report and financial statement
• Within 60 days following completion date
• Certification by the concerned Member State(s)
• [Audit certificate (GA Annex VII)]
4
 GA II.23.2
Eligibility of costs (1/2)
5
• Templates for cost claims available on the INEA website
• Eligible costs are costs actually incurred by the beneficiaries,
which:
• Are incurred during the action duration;
• Are indicated in GA Annex III;
• Are necessary for the implementation of the Action;
• Are identifiable and verifiable;
• Comply with tax and social obligations;
• Are reasonable, justified and comply with sound financial
management principles
• Examples of ineligible costs: return on capital, deductible VAT,
indirect costs…
 GA II.19
no R&D !
Eligibility of costs (2/3)
• Direct personnel costs: two possible ways of declaring:
1) Declare actual personnel costs:
 Time recording system required
 Cost of staff must be actual (not average) and should
include all tax and social security contributions. Other
benefits can be included if actually part of remuneration
package. An explanation of how the unit cost (man/day)
was calculated must be provided
 Cost of staff cannot include overheads
 Travel and subsistence can be reported – keep record of
date, place and reason for travelling (keep
documentation, can be included in sample of invoices)
6
Eligibility of costs (3/3)
2) Declare average personnel costs:
 based on the beneficiaries usual costs accounting
practices and in compliance with the conditions laid down
in Commission Decision C(2016)478
 The Commission Decision also provides for the use of unit
costs for SME owners who do not receive any salary. The
hourly rate is based on a fixed monthly allowance
multiplied by a country correction coefficient as defined in
the Appendix of the Decision
 the Decision also establishes the basic conditions
regarding time recording for personnel costs that should
be respected by all CEF beneficiaries
7
Financial documentation
• Need for appropriate accounting system and documentation
to facilitate reporting and readily available upon request:
• No invoices or bank statements to be provided together
with financial reports, but INEA will ask for sampling
• SAP printouts and bank statements accepted for
payment documentation
• Checks/ Audits possible during the GA implementation
and until 5 years after the balance payment [3 years in
case of grant lower than EUR 60,000]
• Procurement documentation will be requested
8
• Award to tender offering best value for money or, as
appropriate, the lowest price
• Contracting authorities/ entities within the meaning of EU
Directives shall follow applicable national / EU Directives
public procurement rules
• For Beneficiaries other than contracting authorities/ entities,
sound financial management
• Procurement will be verified at payment time together with
the verification of the sampled costs (and documentation
should be readily available for audit purposes)
• Non-compliance will lead to rejection of costs or reduction of
support
Procurement
9
 GA II.9
Budget transfers
• Adjustments between budget categories and activities of
each beneficiary are allowed without this being considered
an amendment and provided that activities are fully
completed
• However, amendments are always required for:
• modification to the total estimated CEF contribution,
which beneficiaries are entitled to receive in case of
penalties and recoveries
10
 GA II.22
Amendments
• Shall not have the purpose or the effect of making changes
which would call into question the award of the grant
• Amendments should be an exception. Will only be accepted
in duly justified and substantiated cases
• Request for Amendments must be submitted by specific
letter at the latest 3 months before end date
11
 GA II.12
Publicity regarding the EU funding is an obligation. Please read
Communicating CEF projects guidelines and use Publicity
Guidelines + logos available on our Beneficiaries' Info Point
We expect at least the following:
• Information on beneficiaries’ websites
• Press releases, articles, presentation, etc. of activities co-
financed by CEF must include a reference to EU funding and
display the European Union emblem
• Keep us informed about events (press releases,
inauguration, etc.) as we would like to publicise it too!
Please see our guidelines on publicity and downloads on
INEA's website
Publicity
12
Project follow-up (1/2)
•The formal reporting requirements form the basis to monitor
the implementation of the Action
During the Action the PO will:
• Monitor on a regular basis the implementation of the Action and verify that it is
consistent with the grant agreement.
• Through regular contacts and updates from you ( email where you shortly explain
the status of implementation and achievement of milestones at least every 6
months), consistency of technical and financial progress, etc.
• Deal with ad hoc issues and problems, e.g. delays
After the end of the Action the PO will:
• Assess whether the Action has achieved its objectives (validation milestone will
check the degree of compliance) and verify, together with a financial officer, that
the costs are eligible and relevant, procurement rules have been respected,
publicity measures followed etc. to determine the final amount of the grant
This assessment is based on the final report and financial statement
13
Project follow-up (2/2)
 Contact the INEA project manager immediately when an
issue occurs to agree how to proceed
 Be open and put all facts on the table – otherwise it could
be too late to solve a problem!
 INEA is there to help and support projects – use us !
14
Answering your questions
Always consult Beneficiaries' info point, it contains
important information like:
• FAQs on project implementation;
• CEF Telecom Grant Agreement;
• Forms and templates (Final technical report,
Individual financial statement, Declaration of
personnel cost etc.);
• Publicity Guidelines and logos.
Disclaimer
The content and conditions of the grant agreement always
prevail on any different information, which may be included
in this document and/or in any formal or informal
communication with the beneficiaries such as the approval of
reports (e.g. ASR), exchange of emails, etc.
16
European Commission
Innovation and Networks Executive Agency (INEA)
Chaussée de Wavre 910 - W910 03/02 - B-1049 Brussels
http://inea.ec.europa.eu
Thank you for your attention
• INEA-CEF-ICT@ec.europa.eu
• http://inea.ec.europa.eu/
17

Contenu connexe

Tendances

FP7 project negotiation, management and financial rules
FP7 project  negotiation, management and financial rulesFP7 project  negotiation, management and financial rules
FP7 project negotiation, management and financial rulesEuropa Media Trainings
 
SEC compliance and disclosure, Form 8-K (sample)
SEC compliance and disclosure, Form 8-K  (sample)SEC compliance and disclosure, Form 8-K  (sample)
SEC compliance and disclosure, Form 8-K (sample)Arthur Mboue
 
Resume for Sandrabusiness
Resume for SandrabusinessResume for Sandrabusiness
Resume for SandrabusinessSandra Singh
 
Update on the EPSAS project - Alexandre Makaronidis, EUROSTAT
Update on the EPSAS project - Alexandre Makaronidis, EUROSTATUpdate on the EPSAS project - Alexandre Makaronidis, EUROSTAT
Update on the EPSAS project - Alexandre Makaronidis, EUROSTATOECD Governance
 
FBT Guide for 2022 - Webinar Slides
FBT Guide for 2022 - Webinar SlidesFBT Guide for 2022 - Webinar Slides
FBT Guide for 2022 - Webinar SlidesMichael Jones
 
Slope wp9, task 9.1, project reporting by Graphitech
Slope wp9, task 9.1, project reporting by GraphitechSlope wp9, task 9.1, project reporting by Graphitech
Slope wp9, task 9.1, project reporting by GraphitechSLOPE Project
 
Ensuring effective delivery of EU energy efficiency targets - monitoring and ...
Ensuring effective delivery of EU energy efficiency targets - monitoring and ...Ensuring effective delivery of EU energy efficiency targets - monitoring and ...
Ensuring effective delivery of EU energy efficiency targets - monitoring and ...Leonardo ENERGY
 
EC financial audits of Horizon 2020 projects
EC financial audits of Horizon 2020 projectsEC financial audits of Horizon 2020 projects
EC financial audits of Horizon 2020 projectsEuropa Media Trainings
 
CIOB Complex Projects Contract 2013 and FIDIC: A Comparison
CIOB Complex Projects Contract 2013 and FIDIC: A ComparisonCIOB Complex Projects Contract 2013 and FIDIC: A Comparison
CIOB Complex Projects Contract 2013 and FIDIC: A ComparisonFrancis Ho
 
Chartered Institute of Building - Launch of Complex Projects Contract 2013 - ...
Chartered Institute of Building - Launch of Complex Projects Contract 2013 - ...Chartered Institute of Building - Launch of Complex Projects Contract 2013 - ...
Chartered Institute of Building - Launch of Complex Projects Contract 2013 - ...Francis Ho
 
6_Link LFA to Full application
6_Link LFA to Full application6_Link LFA to Full application
6_Link LFA to Full applicationcsdialogue
 
Cost control tax planning-Central Excise
Cost control tax planning-Central ExciseCost control tax planning-Central Excise
Cost control tax planning-Central ExciseHiregange
 
revenue and Expense: Recognition - David Bean, GASB, John Stanford, IPSASB
revenue and Expense: Recognition - David Bean, GASB, John Stanford, IPSASBrevenue and Expense: Recognition - David Bean, GASB, John Stanford, IPSASB
revenue and Expense: Recognition - David Bean, GASB, John Stanford, IPSASBOECD Governance
 

Tendances (15)

FP7 project negotiation, management and financial rules
FP7 project  negotiation, management and financial rulesFP7 project  negotiation, management and financial rules
FP7 project negotiation, management and financial rules
 
Kick off dalane vgs SIU
Kick off dalane vgs SIUKick off dalane vgs SIU
Kick off dalane vgs SIU
 
SEC compliance and disclosure, Form 8-K (sample)
SEC compliance and disclosure, Form 8-K  (sample)SEC compliance and disclosure, Form 8-K  (sample)
SEC compliance and disclosure, Form 8-K (sample)
 
Resume for Sandrabusiness
Resume for SandrabusinessResume for Sandrabusiness
Resume for Sandrabusiness
 
Update on the EPSAS project - Alexandre Makaronidis, EUROSTAT
Update on the EPSAS project - Alexandre Makaronidis, EUROSTATUpdate on the EPSAS project - Alexandre Makaronidis, EUROSTAT
Update on the EPSAS project - Alexandre Makaronidis, EUROSTAT
 
FBT Guide for 2022 - Webinar Slides
FBT Guide for 2022 - Webinar SlidesFBT Guide for 2022 - Webinar Slides
FBT Guide for 2022 - Webinar Slides
 
Slope wp9, task 9.1, project reporting by Graphitech
Slope wp9, task 9.1, project reporting by GraphitechSlope wp9, task 9.1, project reporting by Graphitech
Slope wp9, task 9.1, project reporting by Graphitech
 
Ensuring effective delivery of EU energy efficiency targets - monitoring and ...
Ensuring effective delivery of EU energy efficiency targets - monitoring and ...Ensuring effective delivery of EU energy efficiency targets - monitoring and ...
Ensuring effective delivery of EU energy efficiency targets - monitoring and ...
 
EC financial audits of Horizon 2020 projects
EC financial audits of Horizon 2020 projectsEC financial audits of Horizon 2020 projects
EC financial audits of Horizon 2020 projects
 
CIOB Complex Projects Contract 2013 and FIDIC: A Comparison
CIOB Complex Projects Contract 2013 and FIDIC: A ComparisonCIOB Complex Projects Contract 2013 and FIDIC: A Comparison
CIOB Complex Projects Contract 2013 and FIDIC: A Comparison
 
Chartered Institute of Building - Launch of Complex Projects Contract 2013 - ...
Chartered Institute of Building - Launch of Complex Projects Contract 2013 - ...Chartered Institute of Building - Launch of Complex Projects Contract 2013 - ...
Chartered Institute of Building - Launch of Complex Projects Contract 2013 - ...
 
6_Link LFA to Full application
6_Link LFA to Full application6_Link LFA to Full application
6_Link LFA to Full application
 
National Reporting
National ReportingNational Reporting
National Reporting
 
Cost control tax planning-Central Excise
Cost control tax planning-Central ExciseCost control tax planning-Central Excise
Cost control tax planning-Central Excise
 
revenue and Expense: Recognition - David Bean, GASB, John Stanford, IPSASB
revenue and Expense: Recognition - David Bean, GASB, John Stanford, IPSASBrevenue and Expense: Recognition - David Bean, GASB, John Stanford, IPSASB
revenue and Expense: Recognition - David Bean, GASB, John Stanford, IPSASB
 

Similaire à Europeana Generic Services Projects Meeting, 29-30 October 2018, The Hague, Europeana Generic Services Projects Meeting

Slope wp9 - task 9.2, overview on the finacial guidelines by Graphitech
Slope wp9  - task 9.2, overview on the finacial guidelines by GraphitechSlope wp9  - task 9.2, overview on the finacial guidelines by Graphitech
Slope wp9 - task 9.2, overview on the finacial guidelines by GraphitechSLOPE Project
 
3. Kick-off TOJ - Final report
3. Kick-off TOJ - Final report3. Kick-off TOJ - Final report
3. Kick-off TOJ - Final reportRaffaella Battella
 
2015 Call Key Action 2 VET, adult ed and youth Start Up Seminar presentation
2015 Call Key Action 2 VET, adult ed and youth Start Up Seminar presentation2015 Call Key Action 2 VET, adult ed and youth Start Up Seminar presentation
2015 Call Key Action 2 VET, adult ed and youth Start Up Seminar presentationErasmus+ UK National Agency
 
Contribution agreement cic presentation oct 2012 english
Contribution agreement cic presentation oct  2012   englishContribution agreement cic presentation oct  2012   english
Contribution agreement cic presentation oct 2012 englishOCASI
 
Contribution agreement cic presentation oct 2012 english
Contribution agreement cic presentation oct  2012   englishContribution agreement cic presentation oct  2012   english
Contribution agreement cic presentation oct 2012 englishOCASI
 
A6 contribution agreement oct 23 semhar and carly
A6   contribution agreement oct 23 semhar and carlyA6   contribution agreement oct 23 semhar and carly
A6 contribution agreement oct 23 semhar and carlyocasiconference
 
INVESTMENT OPPORTUNITIES - PPP FISCALIA GENERAL DE LA NACIÓN –CALI
INVESTMENT OPPORTUNITIES - PPP FISCALIA GENERAL DE LA NACIÓN –CALIINVESTMENT OPPORTUNITIES - PPP FISCALIA GENERAL DE LA NACIÓN –CALI
INVESTMENT OPPORTUNITIES - PPP FISCALIA GENERAL DE LA NACIÓN –CALIProColombia
 
BEPS Webcast #5 - Update on project
BEPS Webcast #5 - Update on projectBEPS Webcast #5 - Update on project
BEPS Webcast #5 - Update on projectOECDtax
 
2016 Call Key Action 2 school-only Strategic Partnership project start-up pre...
2016 Call Key Action 2 school-only Strategic Partnership project start-up pre...2016 Call Key Action 2 school-only Strategic Partnership project start-up pre...
2016 Call Key Action 2 school-only Strategic Partnership project start-up pre...Erasmus+ UK National Agency
 
Kickoff Adore-it - Intelligent Energy Europe
Kickoff Adore-it - Intelligent Energy EuropeKickoff Adore-it - Intelligent Energy Europe
Kickoff Adore-it - Intelligent Energy Europeadoreit
 
Short introduction to Horizon 2020 finances
Short introduction to Horizon 2020 financesShort introduction to Horizon 2020 finances
Short introduction to Horizon 2020 financesEuropa Media Trainings
 
4. Stay on track- communication and amendments updated april 2014
4. Stay on track- communication and amendments updated april 20144. Stay on track- communication and amendments updated april 2014
4. Stay on track- communication and amendments updated april 2014Raffaella Battella
 
Innovate UK's monitoring services procurement - full briefing pack
Innovate UK's monitoring services procurement - full briefing packInnovate UK's monitoring services procurement - full briefing pack
Innovate UK's monitoring services procurement - full briefing packInnovate UK
 
OECD Tax Talks #14 - 31 January 2020
OECD Tax Talks #14 - 31 January 2020OECD Tax Talks #14 - 31 January 2020
OECD Tax Talks #14 - 31 January 2020OECDtax
 
2017 Call Key Action 2 Schools Education Partnerships start-up workshop
2017 Call Key Action 2 Schools Education Partnerships start-up workshop2017 Call Key Action 2 Schools Education Partnerships start-up workshop
2017 Call Key Action 2 Schools Education Partnerships start-up workshopErasmus+ UK National Agency
 
Innovation Loans Competition Briefing: April 2021
Innovation Loans Competition Briefing: April 2021Innovation Loans Competition Briefing: April 2021
Innovation Loans Competition Briefing: April 2021KTN
 

Similaire à Europeana Generic Services Projects Meeting, 29-30 October 2018, The Hague, Europeana Generic Services Projects Meeting (20)

KA3 start up seminar 2015
KA3 start up seminar 2015KA3 start up seminar 2015
KA3 start up seminar 2015
 
Slope wp9 - task 9.2, overview on the finacial guidelines by Graphitech
Slope wp9  - task 9.2, overview on the finacial guidelines by GraphitechSlope wp9  - task 9.2, overview on the finacial guidelines by Graphitech
Slope wp9 - task 9.2, overview on the finacial guidelines by Graphitech
 
3. Kick-off TOJ - Final report
3. Kick-off TOJ - Final report3. Kick-off TOJ - Final report
3. Kick-off TOJ - Final report
 
2016 Key Action 2 AE and VET start up seminar
2016 Key Action 2 AE and VET start up seminar2016 Key Action 2 AE and VET start up seminar
2016 Key Action 2 AE and VET start up seminar
 
2015 Call Key Action 2 VET, adult ed and youth Start Up Seminar presentation
2015 Call Key Action 2 VET, adult ed and youth Start Up Seminar presentation2015 Call Key Action 2 VET, adult ed and youth Start Up Seminar presentation
2015 Call Key Action 2 VET, adult ed and youth Start Up Seminar presentation
 
Contribution agreement cic presentation oct 2012 english
Contribution agreement cic presentation oct  2012   englishContribution agreement cic presentation oct  2012   english
Contribution agreement cic presentation oct 2012 english
 
Contribution agreement cic presentation oct 2012 english
Contribution agreement cic presentation oct  2012   englishContribution agreement cic presentation oct  2012   english
Contribution agreement cic presentation oct 2012 english
 
A6 contribution agreement oct 23 semhar and carly
A6   contribution agreement oct 23 semhar and carlyA6   contribution agreement oct 23 semhar and carly
A6 contribution agreement oct 23 semhar and carly
 
INVESTMENT OPPORTUNITIES - PPP FISCALIA GENERAL DE LA NACIÓN –CALI
INVESTMENT OPPORTUNITIES - PPP FISCALIA GENERAL DE LA NACIÓN –CALIINVESTMENT OPPORTUNITIES - PPP FISCALIA GENERAL DE LA NACIÓN –CALI
INVESTMENT OPPORTUNITIES - PPP FISCALIA GENERAL DE LA NACIÓN –CALI
 
BEPS Webcast #5 - Update on project
BEPS Webcast #5 - Update on projectBEPS Webcast #5 - Update on project
BEPS Webcast #5 - Update on project
 
2016 Call Key Action 2 school-only Strategic Partnership project start-up pre...
2016 Call Key Action 2 school-only Strategic Partnership project start-up pre...2016 Call Key Action 2 school-only Strategic Partnership project start-up pre...
2016 Call Key Action 2 school-only Strategic Partnership project start-up pre...
 
Kickoff Adore-it - Intelligent Energy Europe
Kickoff Adore-it - Intelligent Energy EuropeKickoff Adore-it - Intelligent Energy Europe
Kickoff Adore-it - Intelligent Energy Europe
 
Slideshow procurement policyv5
Slideshow procurement policyv5Slideshow procurement policyv5
Slideshow procurement policyv5
 
Short introduction to Horizon 2020 finances
Short introduction to Horizon 2020 financesShort introduction to Horizon 2020 finances
Short introduction to Horizon 2020 finances
 
4. Stay on track- communication and amendments updated april 2014
4. Stay on track- communication and amendments updated april 20144. Stay on track- communication and amendments updated april 2014
4. Stay on track- communication and amendments updated april 2014
 
Innovate UK's monitoring services procurement - full briefing pack
Innovate UK's monitoring services procurement - full briefing packInnovate UK's monitoring services procurement - full briefing pack
Innovate UK's monitoring services procurement - full briefing pack
 
Gsa timing-rx-webinar Presentation
Gsa timing-rx-webinar Presentation Gsa timing-rx-webinar Presentation
Gsa timing-rx-webinar Presentation
 
OECD Tax Talks #14 - 31 January 2020
OECD Tax Talks #14 - 31 January 2020OECD Tax Talks #14 - 31 January 2020
OECD Tax Talks #14 - 31 January 2020
 
2017 Call Key Action 2 Schools Education Partnerships start-up workshop
2017 Call Key Action 2 Schools Education Partnerships start-up workshop2017 Call Key Action 2 Schools Education Partnerships start-up workshop
2017 Call Key Action 2 Schools Education Partnerships start-up workshop
 
Innovation Loans Competition Briefing: April 2021
Innovation Loans Competition Briefing: April 2021Innovation Loans Competition Briefing: April 2021
Innovation Loans Competition Briefing: April 2021
 

Plus de Europeana

Europeana Climate Action Community meetup 29_03_2022.pdf
Europeana Climate Action Community meetup 29_03_2022.pdfEuropeana Climate Action Community meetup 29_03_2022.pdf
Europeana Climate Action Community meetup 29_03_2022.pdfEuropeana
 
French Presidency - 1 march 2022
French Presidency - 1 march 2022French Presidency - 1 march 2022
French Presidency - 1 march 2022Europeana
 
Europeana Aggregators' Fair day 1
Europeana Aggregators' Fair day 1Europeana Aggregators' Fair day 1
Europeana Aggregators' Fair day 1Europeana
 
Europeana Aggregators' Fair day 2
Europeana Aggregators' Fair day 2Europeana Aggregators' Fair day 2
Europeana Aggregators' Fair day 2Europeana
 
Europeana web conference portuguese presidency of the council of the eu - jun...
Europeana web conference portuguese presidency of the council of the eu - jun...Europeana web conference portuguese presidency of the council of the eu - jun...
Europeana web conference portuguese presidency of the council of the eu - jun...Europeana
 
Europeana 2019 - Connect Communities - 27-28 November 2019 - Auditorium
Europeana 2019 - Connect Communities - 27-28 November 2019 - AuditoriumEuropeana 2019 - Connect Communities - 27-28 November 2019 - Auditorium
Europeana 2019 - Connect Communities - 27-28 November 2019 - AuditoriumEuropeana
 
Europeana 2019 - Connect Communities - 29 November 2019 - Auditorium
Europeana 2019 - Connect Communities - 29 November 2019 - AuditoriumEuropeana 2019 - Connect Communities - 29 November 2019 - Auditorium
Europeana 2019 - Connect Communities - 29 November 2019 - AuditoriumEuropeana
 
Europeana 2019 - Connect Communities - Pitch your project
Europeana 2019 - Connect Communities - Pitch your projectEuropeana 2019 - Connect Communities - Pitch your project
Europeana 2019 - Connect Communities - Pitch your projectEuropeana
 
Europeana 2019 - Connect Communities
Europeana 2019 - Connect CommunitiesEuropeana 2019 - Connect Communities
Europeana 2019 - Connect CommunitiesEuropeana
 
Europeana 2019 - Connect Communities
Europeana 2019 - Connect CommunitiesEuropeana 2019 - Connect Communities
Europeana 2019 - Connect CommunitiesEuropeana
 
Europeana meeting under Finland’s Presidency of the Council of the EU - Day 2...
Europeana meeting under Finland’s Presidency of the Council of the EU - Day 2...Europeana meeting under Finland’s Presidency of the Council of the EU - Day 2...
Europeana meeting under Finland’s Presidency of the Council of the EU - Day 2...Europeana
 
Europeana meeting under Finland’s Presidency of the Council of the EU - Day 1...
Europeana meeting under Finland’s Presidency of the Council of the EU - Day 1...Europeana meeting under Finland’s Presidency of the Council of the EU - Day 1...
Europeana meeting under Finland’s Presidency of the Council of the EU - Day 1...Europeana
 
The Europeana meeting under the Romanian Presidency, “Exposing Online the Eur...
The Europeana meeting under the Romanian Presidency, “Exposing Online the Eur...The Europeana meeting under the Romanian Presidency, “Exposing Online the Eur...
The Europeana meeting under the Romanian Presidency, “Exposing Online the Eur...Europeana
 
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...Europeana
 
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...Europeana
 
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...Europeana
 
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...Europeana
 
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...Europeana
 
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...Europeana
 
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...Europeana
 

Plus de Europeana (20)

Europeana Climate Action Community meetup 29_03_2022.pdf
Europeana Climate Action Community meetup 29_03_2022.pdfEuropeana Climate Action Community meetup 29_03_2022.pdf
Europeana Climate Action Community meetup 29_03_2022.pdf
 
French Presidency - 1 march 2022
French Presidency - 1 march 2022French Presidency - 1 march 2022
French Presidency - 1 march 2022
 
Europeana Aggregators' Fair day 1
Europeana Aggregators' Fair day 1Europeana Aggregators' Fair day 1
Europeana Aggregators' Fair day 1
 
Europeana Aggregators' Fair day 2
Europeana Aggregators' Fair day 2Europeana Aggregators' Fair day 2
Europeana Aggregators' Fair day 2
 
Europeana web conference portuguese presidency of the council of the eu - jun...
Europeana web conference portuguese presidency of the council of the eu - jun...Europeana web conference portuguese presidency of the council of the eu - jun...
Europeana web conference portuguese presidency of the council of the eu - jun...
 
Europeana 2019 - Connect Communities - 27-28 November 2019 - Auditorium
Europeana 2019 - Connect Communities - 27-28 November 2019 - AuditoriumEuropeana 2019 - Connect Communities - 27-28 November 2019 - Auditorium
Europeana 2019 - Connect Communities - 27-28 November 2019 - Auditorium
 
Europeana 2019 - Connect Communities - 29 November 2019 - Auditorium
Europeana 2019 - Connect Communities - 29 November 2019 - AuditoriumEuropeana 2019 - Connect Communities - 29 November 2019 - Auditorium
Europeana 2019 - Connect Communities - 29 November 2019 - Auditorium
 
Europeana 2019 - Connect Communities - Pitch your project
Europeana 2019 - Connect Communities - Pitch your projectEuropeana 2019 - Connect Communities - Pitch your project
Europeana 2019 - Connect Communities - Pitch your project
 
Europeana 2019 - Connect Communities
Europeana 2019 - Connect CommunitiesEuropeana 2019 - Connect Communities
Europeana 2019 - Connect Communities
 
Europeana 2019 - Connect Communities
Europeana 2019 - Connect CommunitiesEuropeana 2019 - Connect Communities
Europeana 2019 - Connect Communities
 
Europeana meeting under Finland’s Presidency of the Council of the EU - Day 2...
Europeana meeting under Finland’s Presidency of the Council of the EU - Day 2...Europeana meeting under Finland’s Presidency of the Council of the EU - Day 2...
Europeana meeting under Finland’s Presidency of the Council of the EU - Day 2...
 
Europeana meeting under Finland’s Presidency of the Council of the EU - Day 1...
Europeana meeting under Finland’s Presidency of the Council of the EU - Day 1...Europeana meeting under Finland’s Presidency of the Council of the EU - Day 1...
Europeana meeting under Finland’s Presidency of the Council of the EU - Day 1...
 
The Europeana meeting under the Romanian Presidency, “Exposing Online the Eur...
The Europeana meeting under the Romanian Presidency, “Exposing Online the Eur...The Europeana meeting under the Romanian Presidency, “Exposing Online the Eur...
The Europeana meeting under the Romanian Presidency, “Exposing Online the Eur...
 
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
 
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
 
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
 
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
 
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
 
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
 
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
The Europeana meeting under the Romanian Presidency, Exposing Online the Euro...
 

Dernier

General Elections Final Press Noteas per M
General Elections Final Press Noteas per MGeneral Elections Final Press Noteas per M
General Elections Final Press Noteas per MVidyaAdsule1
 
Application of GIS in Landslide Disaster Response.pptx
Application of GIS in Landslide Disaster Response.pptxApplication of GIS in Landslide Disaster Response.pptx
Application of GIS in Landslide Disaster Response.pptxRoquia Salam
 
GESCO SE Press and Analyst Conference on Financial Results 2024
GESCO SE Press and Analyst Conference on Financial Results 2024GESCO SE Press and Analyst Conference on Financial Results 2024
GESCO SE Press and Analyst Conference on Financial Results 2024GESCO SE
 
Scootsy Overview Deck - Pan City Delivery
Scootsy Overview Deck - Pan City DeliveryScootsy Overview Deck - Pan City Delivery
Scootsy Overview Deck - Pan City Deliveryrishi338139
 
cse-csp batch4 review-1.1.pptx cyber security
cse-csp batch4 review-1.1.pptx cyber securitycse-csp batch4 review-1.1.pptx cyber security
cse-csp batch4 review-1.1.pptx cyber securitysandeepnani2260
 
Engaging Eid Ul Fitr Presentation for Kindergartners.pptx
Engaging Eid Ul Fitr Presentation for Kindergartners.pptxEngaging Eid Ul Fitr Presentation for Kindergartners.pptx
Engaging Eid Ul Fitr Presentation for Kindergartners.pptxAsifArshad8
 
05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx
05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx
05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptxerickamwana1
 
Sunlight Spectacle 2024 Practical Action Launch Event 2024-04-08
Sunlight Spectacle 2024 Practical Action Launch Event 2024-04-08Sunlight Spectacle 2024 Practical Action Launch Event 2024-04-08
Sunlight Spectacle 2024 Practical Action Launch Event 2024-04-08LloydHelferty
 
Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...
Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...
Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...Sebastiano Panichella
 
Don't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunity
Don't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunityDon't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunity
Don't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunityApp Ethena
 
INDIAN GCP GUIDELINE. for Regulatory affair 1st sem CRR
INDIAN GCP GUIDELINE. for Regulatory  affair 1st sem CRRINDIAN GCP GUIDELINE. for Regulatory  affair 1st sem CRR
INDIAN GCP GUIDELINE. for Regulatory affair 1st sem CRRsarwankumar4524
 
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATIONRACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATIONRachelAnnTenibroAmaz
 
Understanding Post Production changes (PPC) in Clinical Data Management (CDM)...
Understanding Post Production changes (PPC) in Clinical Data Management (CDM)...Understanding Post Production changes (PPC) in Clinical Data Management (CDM)...
Understanding Post Production changes (PPC) in Clinical Data Management (CDM)...soumyapottola
 
Testing with Fewer Resources: Toward Adaptive Approaches for Cost-effective ...
Testing with Fewer Resources:  Toward Adaptive Approaches for Cost-effective ...Testing with Fewer Resources:  Toward Adaptive Approaches for Cost-effective ...
Testing with Fewer Resources: Toward Adaptive Approaches for Cost-effective ...Sebastiano Panichella
 

Dernier (14)

General Elections Final Press Noteas per M
General Elections Final Press Noteas per MGeneral Elections Final Press Noteas per M
General Elections Final Press Noteas per M
 
Application of GIS in Landslide Disaster Response.pptx
Application of GIS in Landslide Disaster Response.pptxApplication of GIS in Landslide Disaster Response.pptx
Application of GIS in Landslide Disaster Response.pptx
 
GESCO SE Press and Analyst Conference on Financial Results 2024
GESCO SE Press and Analyst Conference on Financial Results 2024GESCO SE Press and Analyst Conference on Financial Results 2024
GESCO SE Press and Analyst Conference on Financial Results 2024
 
Scootsy Overview Deck - Pan City Delivery
Scootsy Overview Deck - Pan City DeliveryScootsy Overview Deck - Pan City Delivery
Scootsy Overview Deck - Pan City Delivery
 
cse-csp batch4 review-1.1.pptx cyber security
cse-csp batch4 review-1.1.pptx cyber securitycse-csp batch4 review-1.1.pptx cyber security
cse-csp batch4 review-1.1.pptx cyber security
 
Engaging Eid Ul Fitr Presentation for Kindergartners.pptx
Engaging Eid Ul Fitr Presentation for Kindergartners.pptxEngaging Eid Ul Fitr Presentation for Kindergartners.pptx
Engaging Eid Ul Fitr Presentation for Kindergartners.pptx
 
05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx
05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx
05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx
 
Sunlight Spectacle 2024 Practical Action Launch Event 2024-04-08
Sunlight Spectacle 2024 Practical Action Launch Event 2024-04-08Sunlight Spectacle 2024 Practical Action Launch Event 2024-04-08
Sunlight Spectacle 2024 Practical Action Launch Event 2024-04-08
 
Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...
Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...
Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...
 
Don't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunity
Don't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunityDon't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunity
Don't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunity
 
INDIAN GCP GUIDELINE. for Regulatory affair 1st sem CRR
INDIAN GCP GUIDELINE. for Regulatory  affair 1st sem CRRINDIAN GCP GUIDELINE. for Regulatory  affair 1st sem CRR
INDIAN GCP GUIDELINE. for Regulatory affair 1st sem CRR
 
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATIONRACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
RACHEL-ANN M. TENIBRO PRODUCT RESEARCH PRESENTATION
 
Understanding Post Production changes (PPC) in Clinical Data Management (CDM)...
Understanding Post Production changes (PPC) in Clinical Data Management (CDM)...Understanding Post Production changes (PPC) in Clinical Data Management (CDM)...
Understanding Post Production changes (PPC) in Clinical Data Management (CDM)...
 
Testing with Fewer Resources: Toward Adaptive Approaches for Cost-effective ...
Testing with Fewer Resources:  Toward Adaptive Approaches for Cost-effective ...Testing with Fewer Resources:  Toward Adaptive Approaches for Cost-effective ...
Testing with Fewer Resources: Toward Adaptive Approaches for Cost-effective ...
 

Europeana Generic Services Projects Meeting, 29-30 October 2018, The Hague, Europeana Generic Services Projects Meeting

  • 1. 1 Europeana Generic Services Projects Meeting Kyriaki Tragouda Project Officer @ INEA, Unit C5 - Telecommunications Hague 29/10/2018
  • 2. Content • INEA's expectations • Reporting • Costs • Modifications • Publicity • Follow-up • Answering your questions 2
  • 3. INEA's expectations towards the implementation of an Action The development and delivery of what has been described in Annex I of the Grant Agreement
  • 4. Reporting requirements • Final report and financial statement • Within 60 days following completion date • Certification by the concerned Member State(s) • [Audit certificate (GA Annex VII)] 4  GA II.23.2
  • 5. Eligibility of costs (1/2) 5 • Templates for cost claims available on the INEA website • Eligible costs are costs actually incurred by the beneficiaries, which: • Are incurred during the action duration; • Are indicated in GA Annex III; • Are necessary for the implementation of the Action; • Are identifiable and verifiable; • Comply with tax and social obligations; • Are reasonable, justified and comply with sound financial management principles • Examples of ineligible costs: return on capital, deductible VAT, indirect costs…  GA II.19 no R&D !
  • 6. Eligibility of costs (2/3) • Direct personnel costs: two possible ways of declaring: 1) Declare actual personnel costs:  Time recording system required  Cost of staff must be actual (not average) and should include all tax and social security contributions. Other benefits can be included if actually part of remuneration package. An explanation of how the unit cost (man/day) was calculated must be provided  Cost of staff cannot include overheads  Travel and subsistence can be reported – keep record of date, place and reason for travelling (keep documentation, can be included in sample of invoices) 6
  • 7. Eligibility of costs (3/3) 2) Declare average personnel costs:  based on the beneficiaries usual costs accounting practices and in compliance with the conditions laid down in Commission Decision C(2016)478  The Commission Decision also provides for the use of unit costs for SME owners who do not receive any salary. The hourly rate is based on a fixed monthly allowance multiplied by a country correction coefficient as defined in the Appendix of the Decision  the Decision also establishes the basic conditions regarding time recording for personnel costs that should be respected by all CEF beneficiaries 7
  • 8. Financial documentation • Need for appropriate accounting system and documentation to facilitate reporting and readily available upon request: • No invoices or bank statements to be provided together with financial reports, but INEA will ask for sampling • SAP printouts and bank statements accepted for payment documentation • Checks/ Audits possible during the GA implementation and until 5 years after the balance payment [3 years in case of grant lower than EUR 60,000] • Procurement documentation will be requested 8
  • 9. • Award to tender offering best value for money or, as appropriate, the lowest price • Contracting authorities/ entities within the meaning of EU Directives shall follow applicable national / EU Directives public procurement rules • For Beneficiaries other than contracting authorities/ entities, sound financial management • Procurement will be verified at payment time together with the verification of the sampled costs (and documentation should be readily available for audit purposes) • Non-compliance will lead to rejection of costs or reduction of support Procurement 9  GA II.9
  • 10. Budget transfers • Adjustments between budget categories and activities of each beneficiary are allowed without this being considered an amendment and provided that activities are fully completed • However, amendments are always required for: • modification to the total estimated CEF contribution, which beneficiaries are entitled to receive in case of penalties and recoveries 10  GA II.22
  • 11. Amendments • Shall not have the purpose or the effect of making changes which would call into question the award of the grant • Amendments should be an exception. Will only be accepted in duly justified and substantiated cases • Request for Amendments must be submitted by specific letter at the latest 3 months before end date 11  GA II.12
  • 12. Publicity regarding the EU funding is an obligation. Please read Communicating CEF projects guidelines and use Publicity Guidelines + logos available on our Beneficiaries' Info Point We expect at least the following: • Information on beneficiaries’ websites • Press releases, articles, presentation, etc. of activities co- financed by CEF must include a reference to EU funding and display the European Union emblem • Keep us informed about events (press releases, inauguration, etc.) as we would like to publicise it too! Please see our guidelines on publicity and downloads on INEA's website Publicity 12
  • 13. Project follow-up (1/2) •The formal reporting requirements form the basis to monitor the implementation of the Action During the Action the PO will: • Monitor on a regular basis the implementation of the Action and verify that it is consistent with the grant agreement. • Through regular contacts and updates from you ( email where you shortly explain the status of implementation and achievement of milestones at least every 6 months), consistency of technical and financial progress, etc. • Deal with ad hoc issues and problems, e.g. delays After the end of the Action the PO will: • Assess whether the Action has achieved its objectives (validation milestone will check the degree of compliance) and verify, together with a financial officer, that the costs are eligible and relevant, procurement rules have been respected, publicity measures followed etc. to determine the final amount of the grant This assessment is based on the final report and financial statement 13
  • 14. Project follow-up (2/2)  Contact the INEA project manager immediately when an issue occurs to agree how to proceed  Be open and put all facts on the table – otherwise it could be too late to solve a problem!  INEA is there to help and support projects – use us ! 14
  • 15. Answering your questions Always consult Beneficiaries' info point, it contains important information like: • FAQs on project implementation; • CEF Telecom Grant Agreement; • Forms and templates (Final technical report, Individual financial statement, Declaration of personnel cost etc.); • Publicity Guidelines and logos.
  • 16. Disclaimer The content and conditions of the grant agreement always prevail on any different information, which may be included in this document and/or in any formal or informal communication with the beneficiaries such as the approval of reports (e.g. ASR), exchange of emails, etc. 16 European Commission Innovation and Networks Executive Agency (INEA) Chaussée de Wavre 910 - W910 03/02 - B-1049 Brussels http://inea.ec.europa.eu
  • 17. Thank you for your attention • INEA-CEF-ICT@ec.europa.eu • http://inea.ec.europa.eu/ 17