Programme Estimates in the 10th EDF
Decentralised Operations
NDSP4, 28 OCTOBER 2014
Engr. Evans Ohaji
Programme Estimates in the 10th EDF Decentralised Operations
Introducing NDSP4
Programme Estimates in the 10th EDF Decentralised Operations
NDSP4 COMPOSITION
Benin, Edo IFO
(Ondo & Edo)
PIMU/IFO
Owerri, Imo
State
Umuahia, Abia IFO
(Abia & Rivers)
Calabar, Cross-River
IFO (Akwa Ibom &
Cross River)
Asaba, Delta IFO
(Delta &
Bayelsa)
Programme Estimates in the 10th EDF Decentralised Operations
Implementation Modalities
Assistance to the NAO in tendering, evaluation
and supervision
TA/PE
Capacity Building
for CSOs, and
Government Paid
through the TA
budget
Implemented by
PMU staff
Beneficiary:
CSO
PIMU
Beneficiary:
ALL
4 Cluster IFOs one
covering 2 states
respectively: 1 IFO for Imo
Monitoring & Project
Supervision Paid through
the TA contract
Implemented by IFO staff
CSO
Grants
Capacity Building for
and support to
Communities in Paid
through Grants
Implemented by CSO
staff
Beneficiary:
Communities
PLPSM
and/or NPC
PE
Call for
proposal
Specific
Commitment
Beneficiary:
Communities
Beneficiary:
Communities
Construction of
Basic Infrastructure
Micro-Projects
Paid through
Individual
Commitments
Monitored by PIMU
and IFO staff
Construction of Income
generating
Micro-Projects Paid
through Individual
Commitments
Monitored by PIMU
and IFO staff
WORKS
Delegation and NPC supported by TA
in preparation of tenders, evaluation
of bids and supervision of contracts
NAO EU Delegation
Programme Estimates in the 10th EDF Decentralised Operations
What is a Programme Estimate(PE)?
Programme Estimate is:
- a document designed to implement (in principle) one year of a
programme covered by a financing agreement in decentralised
operations.
project or
Programme Estimates in the 10th EDF Decentralised Operations
What is Programme Estimate meant for?
Programme estimate(PE) is meant to allowing a more decentralised financial
implementation of projects and programmes financed by the EU.
Programme Estimates in the 10th EDF Decentralised Operations
What does the Programme Estimate aim to achieved?
Making sure that, Programme objectives are executed within the set time frame.
Making sure that programme indicators areactualised at the end of the
programme.
Making sure that funds made available for the laudable programme is judiciously
utilized in transparent manner.
Programme Estimates in the 10th EDF Decentralised Operations
Why do we need to Validate a Programme Estimate?
Making sure that, direct and useful activities are reflected in the PE in accordance with
sets objectives and results.
It is to eliminate complains from the beneficiaries which may come after endorsement
of the PE.
It is also done, so that, beneficiaries, benefit immensely from the programme
Programme Estimates in the 10th EDF Decentralised Operations
PE1 Objectives
PE1 Objectives
Delivering micro projects targeted to poverty reduction, through community
participatory planning and development;
Promoting the development of transparent and equitable local governance, through
the capacity building of local governments in service delivery to the poor.
Programme Estimates in the 10th EDF Decentralised Operations
PE1 Results
Result 1: Strenghtened Community Governance through adoption of Community
Development Action Plans by Communities and Government authorities
Result 2: Increase equitable access to basic infrastructure services by women, men, boys and
girls.
Result 3: Increases equitable access to income generating options and sustainable livelihood
development by women and men.
Result 4: Improved social cohesion among village Communitites
Programme Estimates in the 10th EDF Decentralised Operations
PE1 Activities
Programme Estimates in the 10th EDF Decentralised Operations
Programme Activities, Result 1 Verses Time
2014 2015 2016
October
November
December
January
February
March
April
May
June
July
August
September
October
November
December
January
February
March
Activities Result1
A1.01
Assist stakeholders in
developing/validating the Community
Development action plans(CDAP).
Review existing MoUs.
A1.02
Support revalidation of project priority
after assessing communities' needs
and capacity.
A1.03
Sensitization meetings on MoU and
LGA 25% contribution
A1.04 Signing of MoUs
A1.05 Monitoring support to LGAs
Programme Activities Verses Time
Programme Estimates in the 10th EDF Decentralised Operations
2014 2015 2016
October
November
December
January
February
March
April
May
June
July
August
September
October
November
December
January
February
March
Activities Result1
A1.06
Support to Programme Steering
Committee(PSC) Meetings
A1.07
Support to State Level Programme
Stakeholders Coordination(SLPSCC)
Committee
A1.08
Geographical Mapping of Each of the
Project Sites in the Nine Niger Delta
States
A1.09 Baseline Establishment
A1.10
Evaluate and approve valid Project
Proposal
Programme Activities Verses Time
Programme Estimates in the 10th EDF Decentralised Operations
A1.11
Procurement of Project Monitoring &
Supervision Manuals
A1.12
Capacity building for LGA Works Depts.
on procurement
A1.13
Review workshops on PICs and LGAs
monitoring/supervision activities
A1.14
Launching and publication of tenders
and calls for propopsals
A1.15 Quarterly coordination meetings
2014 2015 2016
Octo
ber
Nov
emb
er
Dece
mbe
r
Janu
ary
Febr
uary
Mar
ch
April
May
June
July
Aug
ust
Sept
emb
er
Octo
ber
Nov
emb
er
Dece
mbe
r
Janu
ary
Febr
uary
Mar
ch
Activitie
s Result1
Programme Activities, Result1 Verses Time
Programme Estimates in the 10th EDF Decentralised Operations
2014 2015 2016
October
November
December
January
February
March
April
May
June
July
August
September
October
November
December
January
February
March
Activities Result1
A1.16
Setting-up of evaluation committees,
receipts and evaluation of tenders
A1.17
Support PIC Meeting at Community
Level
A.1.18 Visibility
Programme Activities, Result 2 Verses Time
Programme Estimates in the 10th EDF Decentralised Operations
2014 2015 2016
October
November
December
January
February
March
April
May
June
July
August
September
October
November
December
January
February
March
Activities Result 2
A2.01 Support Technical Review Meetings
A2.02
Support technically the PIC and PMC
through seminars and Workshops
A2.03
Support Experience sharing forums
with Development Agencies
Programme Activities Result 3 Verses Time
Programme Estimates in the 10th EDF Decentralised Operations
2014 2015 2016
October
November
December
January
February
March
April
May
June
July
August
September
October
November
December
January
February
March
Activities Result 3
A3.01
Training Workshops for the State
Economic Planning Dept on the
Programme
A3.02
Support annual awareness
campaigns on income generating
options and sustainable
livelihoods
A3.03
Technical Supports on Design
and Training(Maintenance) for
sustainability of Programme
Programme Activities, Result 4 Verses Time
Programme Estimates in the 10th EDF Decentralised Operations
2014 2015 2016
October
November
December
January
February
March
April
May
June
July
August
September
October
November
December
January
February
March
Activities Result 4
A4.01
Support training workshops for the
communities in participatory
monitoring and project planning
A4.02
Supports annual communities
awareness campaigns and exchange
visits with high performing LGAs
A4.03
Support feedback mechanism between
Communities and LGAs
Discussions and Inputs
Programme Estimates in the 10th EDF Decentralised Operations

Contenu connexe

En vedette

практическая работа №3
практическая работа №3практическая работа №3
практическая работа №3TBo9I_MaMa
 
Поступаев Сергей,9 3
Поступаев Сергей,9 3Поступаев Сергей,9 3
Поступаев Сергей,9 3TBo9I_MaMa
 
Romanticism part 2
Romanticism part 2Romanticism part 2
Romanticism part 2phebeshen
 
How to Prioritize When Everything is Pri1
How to Prioritize When Everything is Pri1How to Prioritize When Everything is Pri1
How to Prioritize When Everything is Pri1Ruth Tomandl
 
Phụ nữ trên 70 cần khám những bệnh gì
Phụ nữ trên 70 cần khám những bệnh gìPhụ nữ trên 70 cần khám những bệnh gì
Phụ nữ trên 70 cần khám những bệnh gìpablo778
 
English Idioms
English IdiomsEnglish Idioms
English IdiomsScribendi
 
Digital Marketing Revolution Adequate Witold Wrodarczyk
Digital Marketing Revolution Adequate Witold Wrodarczyk Digital Marketing Revolution Adequate Witold Wrodarczyk
Digital Marketing Revolution Adequate Witold Wrodarczyk Witold Wrodarczyk
 
2015/6_Database Management_Final Project
2015/6_Database Management_Final Project2015/6_Database Management_Final Project
2015/6_Database Management_Final ProjectSean Cherng
 

En vedette (11)

Omnes medium20
Omnes medium20Omnes medium20
Omnes medium20
 
практическая работа №3
практическая работа №3практическая работа №3
практическая работа №3
 
Ple
PlePle
Ple
 
Поступаев Сергей,9 3
Поступаев Сергей,9 3Поступаев Сергей,9 3
Поступаев Сергей,9 3
 
Romanticism part 2
Romanticism part 2Romanticism part 2
Romanticism part 2
 
How to Prioritize When Everything is Pri1
How to Prioritize When Everything is Pri1How to Prioritize When Everything is Pri1
How to Prioritize When Everything is Pri1
 
Phụ nữ trên 70 cần khám những bệnh gì
Phụ nữ trên 70 cần khám những bệnh gìPhụ nữ trên 70 cần khám những bệnh gì
Phụ nữ trên 70 cần khám những bệnh gì
 
English Idioms
English IdiomsEnglish Idioms
English Idioms
 
Digital Marketing Revolution Adequate Witold Wrodarczyk
Digital Marketing Revolution Adequate Witold Wrodarczyk Digital Marketing Revolution Adequate Witold Wrodarczyk
Digital Marketing Revolution Adequate Witold Wrodarczyk
 
2015/6_Database Management_Final Project
2015/6_Database Management_Final Project2015/6_Database Management_Final Project
2015/6_Database Management_Final Project
 
Romantic Intimacy
Romantic Intimacy
Romantic Intimacy
Romantic Intimacy
 

Similaire à Programme Estimates_Evans Ohaji Presentation

Promoting the African Development Agenda through NEPAD initiatives
Promoting the African Development Agenda through NEPAD initiativesPromoting the African Development Agenda through NEPAD initiatives
Promoting the African Development Agenda through NEPAD initiativesDr Lendy Spires
 
Pp presentation liberia 2012
Pp presentation liberia 2012Pp presentation liberia 2012
Pp presentation liberia 2012Emmett Crayton
 
JAR review presentation
JAR review presentationJAR review presentation
JAR review presentationict4devwg
 
Assessing Impact of Investments in Agricultural Water Management in African C...
Assessing Impact of Investments in Agricultural Water Management in African C...Assessing Impact of Investments in Agricultural Water Management in African C...
Assessing Impact of Investments in Agricultural Water Management in African C...FAO
 
Assessing Impact of Investments in Agricultural Water Management in African C...
Assessing Impact of Investments in Agricultural Water Management in African C...Assessing Impact of Investments in Agricultural Water Management in African C...
Assessing Impact of Investments in Agricultural Water Management in African C...NENAwaterscarcity
 
IMPACT EVALUATION OF KDDAUK PROGRAMME SEPT 2012 to SEPT 2016 b
IMPACT EVALUATION OF KDDAUK PROGRAMME SEPT 2012 to SEPT 2016 bIMPACT EVALUATION OF KDDAUK PROGRAMME SEPT 2012 to SEPT 2016 b
IMPACT EVALUATION OF KDDAUK PROGRAMME SEPT 2012 to SEPT 2016 bSahr O Fasuluku
 
AFAAS Strategic Plan and Result Framework
AFAAS Strategic Plan and Result Framework AFAAS Strategic Plan and Result Framework
AFAAS Strategic Plan and Result Framework AFAAS
 
Session 3B Finance - Getenet community development funds ethiopia (pp tminimi...
Session 3B Finance - Getenet community development funds ethiopia (pp tminimi...Session 3B Finance - Getenet community development funds ethiopia (pp tminimi...
Session 3B Finance - Getenet community development funds ethiopia (pp tminimi...IRC
 
AWF Work on Water security Issues presented by Akiça Bahri , Coordinater ,AW...
AWF Work on Water security Issues  presented by Akiça Bahri , Coordinater ,AW...AWF Work on Water security Issues  presented by Akiça Bahri , Coordinater ,AW...
AWF Work on Water security Issues presented by Akiça Bahri , Coordinater ,AW...Global Water Partnership
 
Support To The Pre- And Post-CAADP Compact Process For Improved AWM
Support To The Pre- And Post-CAADP Compact Process For Improved AWMSupport To The Pre- And Post-CAADP Compact Process For Improved AWM
Support To The Pre- And Post-CAADP Compact Process For Improved AWMFAO
 
Sustaining CAADP Momentum
Sustaining CAADP MomentumSustaining CAADP Momentum
Sustaining CAADP MomentumDr Lendy Spires
 
Everlink Presentation on Env Sanitation Partnership Phase II to FMENV - 15.0...
Everlink Presentation on Env Sanitation Partnership Phase II to FMENV  - 15.0...Everlink Presentation on Env Sanitation Partnership Phase II to FMENV  - 15.0...
Everlink Presentation on Env Sanitation Partnership Phase II to FMENV - 15.0...Benjamin Ogbalor
 
Evaluation capacity development news
Evaluation capacity development newsEvaluation capacity development news
Evaluation capacity development newsDr Lendy Spires
 
public expenditure
public expenditurepublic expenditure
public expenditurenetwas
 

Similaire à Programme Estimates_Evans Ohaji Presentation (20)

Promoting the African Development Agenda through NEPAD initiatives
Promoting the African Development Agenda through NEPAD initiativesPromoting the African Development Agenda through NEPAD initiatives
Promoting the African Development Agenda through NEPAD initiatives
 
A case of rural finance programme - Zambia
A case of rural finance programme - Zambia A case of rural finance programme - Zambia
A case of rural finance programme - Zambia
 
Pp presentation liberia 2012
Pp presentation liberia 2012Pp presentation liberia 2012
Pp presentation liberia 2012
 
JAR review presentation
JAR review presentationJAR review presentation
JAR review presentation
 
Assessing Impact of Investments in Agricultural Water Management in African C...
Assessing Impact of Investments in Agricultural Water Management in African C...Assessing Impact of Investments in Agricultural Water Management in African C...
Assessing Impact of Investments in Agricultural Water Management in African C...
 
Assessing Impact of Investments in Agricultural Water Management in African C...
Assessing Impact of Investments in Agricultural Water Management in African C...Assessing Impact of Investments in Agricultural Water Management in African C...
Assessing Impact of Investments in Agricultural Water Management in African C...
 
IMPACT EVALUATION OF KDDAUK PROGRAMME SEPT 2012 to SEPT 2016 b
IMPACT EVALUATION OF KDDAUK PROGRAMME SEPT 2012 to SEPT 2016 bIMPACT EVALUATION OF KDDAUK PROGRAMME SEPT 2012 to SEPT 2016 b
IMPACT EVALUATION OF KDDAUK PROGRAMME SEPT 2012 to SEPT 2016 b
 
AFAAS Strategic Plan and Result Framework
AFAAS Strategic Plan and Result Framework AFAAS Strategic Plan and Result Framework
AFAAS Strategic Plan and Result Framework
 
Uganda - NAP Climate Change Adaptation Experiences
Uganda  - NAP Climate Change Adaptation ExperiencesUganda  - NAP Climate Change Adaptation Experiences
Uganda - NAP Climate Change Adaptation Experiences
 
Program-for-Results - An Overview and experiences in results-based funding
Program-for-Results - An Overview and experiences in results-based fundingProgram-for-Results - An Overview and experiences in results-based funding
Program-for-Results - An Overview and experiences in results-based funding
 
Session 3B Finance - Getenet community development funds ethiopia (pp tminimi...
Session 3B Finance - Getenet community development funds ethiopia (pp tminimi...Session 3B Finance - Getenet community development funds ethiopia (pp tminimi...
Session 3B Finance - Getenet community development funds ethiopia (pp tminimi...
 
AWF Work on Water security Issues presented by Akiça Bahri , Coordinater ,AW...
AWF Work on Water security Issues  presented by Akiça Bahri , Coordinater ,AW...AWF Work on Water security Issues  presented by Akiça Bahri , Coordinater ,AW...
AWF Work on Water security Issues presented by Akiça Bahri , Coordinater ,AW...
 
Support To The Pre- And Post-CAADP Compact Process For Improved AWM
Support To The Pre- And Post-CAADP Compact Process For Improved AWMSupport To The Pre- And Post-CAADP Compact Process For Improved AWM
Support To The Pre- And Post-CAADP Compact Process For Improved AWM
 
Sustaining CAADP Momentum
Sustaining CAADP MomentumSustaining CAADP Momentum
Sustaining CAADP Momentum
 
M&E Logic Model1
M&E Logic Model1M&E Logic Model1
M&E Logic Model1
 
Mohammed Hourani CV 2016
Mohammed Hourani CV 2016Mohammed Hourani CV 2016
Mohammed Hourani CV 2016
 
Everlink Presentation on Env Sanitation Partnership Phase II to FMENV - 15.0...
Everlink Presentation on Env Sanitation Partnership Phase II to FMENV  - 15.0...Everlink Presentation on Env Sanitation Partnership Phase II to FMENV  - 15.0...
Everlink Presentation on Env Sanitation Partnership Phase II to FMENV - 15.0...
 
Duplicate jdhfihq
Duplicate jdhfihqDuplicate jdhfihq
Duplicate jdhfihq
 
Evaluation capacity development news
Evaluation capacity development newsEvaluation capacity development news
Evaluation capacity development news
 
public expenditure
public expenditurepublic expenditure
public expenditure
 

Programme Estimates_Evans Ohaji Presentation

  • 1. Programme Estimates in the 10th EDF Decentralised Operations NDSP4, 28 OCTOBER 2014 Engr. Evans Ohaji
  • 2. Programme Estimates in the 10th EDF Decentralised Operations Introducing NDSP4
  • 3. Programme Estimates in the 10th EDF Decentralised Operations NDSP4 COMPOSITION Benin, Edo IFO (Ondo & Edo) PIMU/IFO Owerri, Imo State Umuahia, Abia IFO (Abia & Rivers) Calabar, Cross-River IFO (Akwa Ibom & Cross River) Asaba, Delta IFO (Delta & Bayelsa)
  • 4. Programme Estimates in the 10th EDF Decentralised Operations Implementation Modalities Assistance to the NAO in tendering, evaluation and supervision TA/PE Capacity Building for CSOs, and Government Paid through the TA budget Implemented by PMU staff Beneficiary: CSO PIMU Beneficiary: ALL 4 Cluster IFOs one covering 2 states respectively: 1 IFO for Imo Monitoring & Project Supervision Paid through the TA contract Implemented by IFO staff CSO Grants Capacity Building for and support to Communities in Paid through Grants Implemented by CSO staff Beneficiary: Communities PLPSM and/or NPC PE Call for proposal Specific Commitment Beneficiary: Communities Beneficiary: Communities Construction of Basic Infrastructure Micro-Projects Paid through Individual Commitments Monitored by PIMU and IFO staff Construction of Income generating Micro-Projects Paid through Individual Commitments Monitored by PIMU and IFO staff WORKS Delegation and NPC supported by TA in preparation of tenders, evaluation of bids and supervision of contracts NAO EU Delegation
  • 5. Programme Estimates in the 10th EDF Decentralised Operations What is a Programme Estimate(PE)? Programme Estimate is: - a document designed to implement (in principle) one year of a programme covered by a financing agreement in decentralised operations. project or
  • 6. Programme Estimates in the 10th EDF Decentralised Operations What is Programme Estimate meant for? Programme estimate(PE) is meant to allowing a more decentralised financial implementation of projects and programmes financed by the EU.
  • 7. Programme Estimates in the 10th EDF Decentralised Operations What does the Programme Estimate aim to achieved? Making sure that, Programme objectives are executed within the set time frame. Making sure that programme indicators areactualised at the end of the programme. Making sure that funds made available for the laudable programme is judiciously utilized in transparent manner.
  • 8. Programme Estimates in the 10th EDF Decentralised Operations Why do we need to Validate a Programme Estimate? Making sure that, direct and useful activities are reflected in the PE in accordance with sets objectives and results. It is to eliminate complains from the beneficiaries which may come after endorsement of the PE. It is also done, so that, beneficiaries, benefit immensely from the programme
  • 9. Programme Estimates in the 10th EDF Decentralised Operations PE1 Objectives PE1 Objectives Delivering micro projects targeted to poverty reduction, through community participatory planning and development; Promoting the development of transparent and equitable local governance, through the capacity building of local governments in service delivery to the poor.
  • 10. Programme Estimates in the 10th EDF Decentralised Operations PE1 Results Result 1: Strenghtened Community Governance through adoption of Community Development Action Plans by Communities and Government authorities Result 2: Increase equitable access to basic infrastructure services by women, men, boys and girls. Result 3: Increases equitable access to income generating options and sustainable livelihood development by women and men. Result 4: Improved social cohesion among village Communitites
  • 11. Programme Estimates in the 10th EDF Decentralised Operations PE1 Activities
  • 12. Programme Estimates in the 10th EDF Decentralised Operations Programme Activities, Result 1 Verses Time 2014 2015 2016 October November December January February March April May June July August September October November December January February March Activities Result1 A1.01 Assist stakeholders in developing/validating the Community Development action plans(CDAP). Review existing MoUs. A1.02 Support revalidation of project priority after assessing communities' needs and capacity. A1.03 Sensitization meetings on MoU and LGA 25% contribution A1.04 Signing of MoUs A1.05 Monitoring support to LGAs
  • 13. Programme Activities Verses Time Programme Estimates in the 10th EDF Decentralised Operations 2014 2015 2016 October November December January February March April May June July August September October November December January February March Activities Result1 A1.06 Support to Programme Steering Committee(PSC) Meetings A1.07 Support to State Level Programme Stakeholders Coordination(SLPSCC) Committee A1.08 Geographical Mapping of Each of the Project Sites in the Nine Niger Delta States A1.09 Baseline Establishment A1.10 Evaluate and approve valid Project Proposal
  • 14. Programme Activities Verses Time Programme Estimates in the 10th EDF Decentralised Operations A1.11 Procurement of Project Monitoring & Supervision Manuals A1.12 Capacity building for LGA Works Depts. on procurement A1.13 Review workshops on PICs and LGAs monitoring/supervision activities A1.14 Launching and publication of tenders and calls for propopsals A1.15 Quarterly coordination meetings 2014 2015 2016 Octo ber Nov emb er Dece mbe r Janu ary Febr uary Mar ch April May June July Aug ust Sept emb er Octo ber Nov emb er Dece mbe r Janu ary Febr uary Mar ch Activitie s Result1
  • 15. Programme Activities, Result1 Verses Time Programme Estimates in the 10th EDF Decentralised Operations 2014 2015 2016 October November December January February March April May June July August September October November December January February March Activities Result1 A1.16 Setting-up of evaluation committees, receipts and evaluation of tenders A1.17 Support PIC Meeting at Community Level A.1.18 Visibility
  • 16. Programme Activities, Result 2 Verses Time Programme Estimates in the 10th EDF Decentralised Operations 2014 2015 2016 October November December January February March April May June July August September October November December January February March Activities Result 2 A2.01 Support Technical Review Meetings A2.02 Support technically the PIC and PMC through seminars and Workshops A2.03 Support Experience sharing forums with Development Agencies
  • 17. Programme Activities Result 3 Verses Time Programme Estimates in the 10th EDF Decentralised Operations 2014 2015 2016 October November December January February March April May June July August September October November December January February March Activities Result 3 A3.01 Training Workshops for the State Economic Planning Dept on the Programme A3.02 Support annual awareness campaigns on income generating options and sustainable livelihoods A3.03 Technical Supports on Design and Training(Maintenance) for sustainability of Programme
  • 18. Programme Activities, Result 4 Verses Time Programme Estimates in the 10th EDF Decentralised Operations 2014 2015 2016 October November December January February March April May June July August September October November December January February March Activities Result 4 A4.01 Support training workshops for the communities in participatory monitoring and project planning A4.02 Supports annual communities awareness campaigns and exchange visits with high performing LGAs A4.03 Support feedback mechanism between Communities and LGAs
  • 19. Discussions and Inputs Programme Estimates in the 10th EDF Decentralised Operations