SlideShare a Scribd company logo
1 of 46
Download to read offline
THE NEXT GREAT UNDERGROUND
MINE IN CANADA
HORNE 5 FEASIBILITY STUDY PRESENTATION
OCTOBER 16, 2017
WWW.FALCORES.COM | FPC:TSXV
Disclaimer
This presentation contains a review of the Company’s feasibility study. Viewers are cautioned that the Horne 5 project is at a development stage and that estimates and projections contained herein
are based on management’s and consultant’s reasonable assumptions. Therefore, the work results and estimates herein may be considered to be generally indicative only of the nature and quality of
the project. No representation or prediction is intended as to the results of future work, nor can there be any promise that the estimates herein will be confirmed by future exploration, development
or analysis, or that the project will otherwise prove to be economic.
In order to access the Horne 5 deposit, Falco must obtain licenses from the third party owning mining concession CM-156-PTB, which may not be unreasonably withheld, but which may be subject to
conditions that the third party may require in its sole discretion. These conditions may include the provision of a performance bond or other assurance to the third party and the indemnification of the
third party by Falco. An agreement with the third party stipulates, among other things, that licenses shall be subject to reasonable conditions which may include, among other things, that activities at
Horne 5 will be subordinated to the current use of the surface lands and subject to priority, as established in such party’s sole discretion, over such activities. Any license may provide for, among other
things, access to and the right to modify and use the infrastructures owned by the third party, including the Quémont #2 shaft (located on mining concession CM-243 also held by such third party) and
some specific underground infrastructures in the former Quémont and Horne mines.
While Falco believes that it should be able to timely obtain the licenses from the third party, there can be no assurance that any such license will be granted, or if granted will be on terms acceptable to
Falco and in a timely manner.
The foregoing disclaimer hereby qualifies in its entirety the disclosure contained in this investor presentation.
Factors that could cause actual results to differ materially from these forward-looking statements include the reliability of the underlying assumptions used in connection with the feasibility study and
those risks set out in Falco's public documents, including in each management discussion and analysis, filed on SEDAR at www.sedar.com.
The TSX Venture Exchange has not reviewed and does not accept responsibility for the accuracy or adequacy of this presentation, which has been prepared by management.
Past performance is no guarantee of future performance and all investors are urged to consult their investment professionals before making an investment decision.
Forward-Looking Statements
Certain information included in this presentation constitutes forward-looking statements, including any information as to our projects, plans and future performance. All statements, other than
statements of historical fact, are forward-looking statements. The words “expect”, “believe”, “anticipate”, “will”, “intend”, “estimate”, “forecast”, “budget”, “schedule” and similar expressions identify
forward-looking statements. Forward-looking statements are necessarily based upon a number of factors and assumptions that, while considered reasonable by management, are inherently subject to
significant business, economic and competitive uncertainties and contingencies. Known and unknown factors could cause actual results to differ materially from those projected in the forward-looking
statements.
Such factors include, but are not limited to: changes to current estimates of mineral resources; labour availability; litigation; availability of and increased costs associated with contractors and
equipment; the speculative nature of mineral exploration and development, including the risks of obtaining necessary licenses and permits; contests over title to assets; uncertainty with the
Company’s ability to secure capital to execute its business plans; changes in national and local government legislation in Canada; risk of loss due to sabotage and civil disturbances; and business
opportunities that may be pursued by the Company. Many of these uncertainties and contingencies can affect our actual results and could cause actual results to differ materially from those
expressed or implied in any forward-looking statements made by, or on behalf of, the Company. Readers are cautioned that forward-looking statements are not guarantees of future performance.
The Company disclaims any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise, except as required by
applicable law.
Cautionary Note to U.S Investors Concerning Measured, Indicated and Inferred Resources
This presentation uses the terms “measured,” “indicated” and “inferred resources. We advise investors that while those terms are recognized and required by Canadian regulations, the United States
Securities and Exchange commission does not recognize them. Under Canadian rules, estimates of inferred mineral resources may not form the basis of feasibility or other economic studies. United
States investors are cautioned not to assume that all or any part of measured or indicated mineral resources will ever be converted into mineral reserves. United States investors are also cautioned not
to assume that all or any part of an inferred mineral resource exists, or is economically or legally mineable.
CAUTIONARY STATEMENT
TSXV: FPC | WWW.FALCORES.COM | 3
HORNE 5 PROJECT| FEASIBILITY STUDY RESULTS
 HORNE 5 PROJECT FEASIBILITY STUDY COMPLETE
 Focus now shifts towards immediate permitting, development and financing
 Results confirm the Horne 5 project supports an economically viable, robust, low-grade, high bulk
tonnage underground gold mine
 Targeted start of construction in 2019, first gold expected in late 2021
 Further optimization planned which builds on robust Feasibility Study
 HORNE 5 PROJECT IS AMONG THE LARGEST UNDEVELOPED GOLD PROJECTS IN THE WORLD
 Proven & Probable Mineral Reserve – 6.13 million oz AuEq (80.9 mt at 2.37 g/t AuEq)
 Substantial potential to expand existing resource at depth
 LOW ALL-IN SUSTAINING CASH COST
 US$399/oz gold AISC (net of by-products) US$721/oz gold-equivalent AISC
 US$260/oz gold cash costs (net of by-products) US$632/oz gold-equivalent cash cost
 LOW CAPEX INTENSITY PER OUNCE
 US$243 per gold ounce (net of by-products) US$158 per gold-equivalent ounce
 SIGNIFICANT EXPLORATION POTENTIAL IN ROUYN-NORANDA AND IN THE >67,000 HA OF PROPERTIES
 40,000 m drill program initiated on regional exploration camp
 HIGHLY CAPABLE AND EXPERIENCED MANAGEMENT TEAM
TSXV: FPC | WWW.FALCORES.COM | 4
HORNE 5 PROJECT| FEASIBILITY STUDY HIGHLIGHTS – US$
BASE CASE @ SPOT (10/13/2017)
Pre-Tax NPV (5%) & IRR – US$
$1,012 million NPV
18.9% IRR
$1,170 million NPV
20.5% IRR
Post-Tax NPV (5%) & IRR – US$
$602 million NPV
15.3% IRR
$699 million NPV
16.6% IRR
Payback Period (after-tax, start of production) 5.6 years 5.2 years
Life of Mine Gold Production Recovered 3.3 million ozs gold or 5.1 million ozs gold-eq.
Average Annual Metal Production (rounded)
219 koz per year gold
1,752 koz per year silver
67 million lbs per year zinc
16 million lbs per year copper
Mine Life (based on reserves) 15 years
Base Case Metal Prices and Assumed FX – US$
$1,300/oz Au, $19.50/oz Ag,
$1.10/lb Zn, $3.00/lb Cu, CAD:US 0.78
Initial Capital – US$ $802 million
LOM Sustaining Capital – US$ $418 million sustaining
LOM Cash Costs & AISC (net of by-products) – US$
$260/oz cash costs
$399/oz AISC
$166/oz cash costs
$314/oz AISC
LOM Average Process Recovery
88.1% gold, 71.5% silver
72.9% zinc, 75.8% copper
Note: All in US$ otherwise noted, assumes CAD:US 1.28
TSXV: FPC | WWW.FALCORES.COM | 5
HORNE 5 PROJECT| CASH FLOW PROFILE & SENSITIVITY
Note: All in US$ otherwise noted, assumes CAD:US 1.28
Gold Price ($/oz) $1,200 $1,250 $1,300 $1,400 $1,500 $1,600 @ Spot
Pre-Tax 5% NPV US$M $822 $917 $1,012 $1,202 $1,392 $1,582 $1,138
After-Tax 5% NPV US$M $485 $544 $602 $718 $831 $944 $680
Pre-Tax IRR 16.6% 17.7% 18.9% 21.0% 23.1% 25.1% 20.5%
After-Tax IRR 13.5% 14.4% 15.3% 17.1% 18.7% 20.3% 16.6%
Pre-Tax Payback Years 5.7 5.5 5.2 4.8 4.3 4.0 4.8
After-Tax Payback Years 6.1 5.8 5.6 5.2 4.8 4.5 5.2
TSXV: FPC | WWW.FALCORES.COM | 6
HORNE 5 PROJECT| OPTIMIZATION & PROJECT POTENTIAL
 MINE LIFE EXTENSION
 Current mine plan extends only 2,100 metres below surface, potential to reach deeper depths
 HG_F zone in Inferred Resources and not included in Feasibility holds 2.8 M tonnes at 3.38 Au g/t
 Inclusion of additional Mineral Resources currently not included in the mine plan
 40,000 m drill program initiated on regional exploration camp could surface satellite deposits
 MINE PLAN OPTIMIZATION
 Potential to improve cash flow, with further mine plan sequencing
 Life of mine can be increased with additional testing to include remaining tonnes (M&I over 90Mt)
 PROCESSING OPTIMIZATION
 Additional testing is ongoing for new flotation technology to improve metal recovery and achieve
cleaner concentrate (Woodgrove)
 WATER TREATMENT OPTIMIZATION
 Recent test works show lower lime content necessary for treatment, hence reducing mud
generation and treatment cost
 Use of water by a third party option still a viable option
TSXV: FPC | WWW.FALCORES.COM | 7
HORNE 5 PROJECT| BENEFITS TO STAKEHOLDERS
 HORNE 5 EXPECTS TO BE A SIGNIFICANT EMPLOYER IN THE ROUYN-NORANDA REGION, CREATING
LONG TERM EMPLOYMENT
 Peak employment during construction estimated at approximately 800
 Approximately 500 employees are estimated to be required for operations
 Training for semi-skilled and skilled sustainable positions
 Additional indirect jobs created with suppliers, services, etc. to support mine operations
 LOCAL AND REGIONAL INFRASTRUCTURE INVESTMENT
 New school to be built in the centre of Rouyn-Noranda – C$22.5 million investment
 CONTINUED COMMITMENT TO COMMUNITY INVESTMENT PROGRAMS
 ECONOMIC BENEFITS ESTIMATED AT $6.6 BILLION BASED ON $1,300 PER OZ AU, LIFE OF MINE
ROYALTIES & TAXES
Note: All in US$ otherwise noted, assumes CAD:US 1.28
TSXV: FPC | WWW.FALCORES.COM | 8
FEASIBILITY
STUDY DETAILS
TSXV: FPC | WWW.FALCORES.COM | 9
HORNE 5 PROJECT| LOCATION
 Located in Rouyn-Noranda, Québec, Canada
 Access to better & experienced miners due
to better work-life balance & conditions
 Eliminates the need for a camp
 Experienced labour pool
 The region of Abitibi produces some of the
most experienced miners in the world
 Strong presence of experienced mine and
technical staff
 Experienced suppliers
 Access to tier 1 mining equipment suppliers
& mining contractors in the world
 ~80% of required suppliers & contractors
located within 1 hour from project
 Québec Government
 Strong supporter of the mining industry
 Clear permitting process & BAPE process
 Great infrastructure
 Rail & highway access
 Affordable and reliable power source
HORNE 5
MONTREAL
TSXV: FPC | WWW.FALCORES.COM | 10
HORNE 5 PROJECT| MINERALIZATION
 The Horne Mine orebodies (Upper H, Lower H and
Horne 5 deposit)
 Dip subvertically within rhyolitic flows,
breccias, and tuffs that are bounded by the
Andesite and the Horne Creek faults.
 Least-altered rhyolites have low K2O
contents and other geochemical features
that place them within the FII tholeiitic
series (Lesher et al., 1986)
 Graded volcaniclastic beds, metal zoning in
the orebodies, and locations of chloritized-
mineralized rhyolites indicate that the
volcanic sequence youngs to the north.
 The volcanics in the fault wedge are variably
silicified and sericitized, and local zones in
the orebody sidewalls and footwall are
chloritized
 The Horne Block lies between the Horne Creek
Fault and the Andesite Fault
TSXV: FPC | WWW.FALCORES.COM | 11
HORNE 5 PROJECT| MINERAL RESERVES & RESOURCES
PROVEN & PROBABLE
MEASURED & INDICATED + INFERRED (at C$55 NSR cut-off)
Resource
Class
Tonnes
(mm)
Au Equivalent
g/t
Au
g/t
Ag
g/t
Cu
%
Zn
%
Contained Au
EQ (000 oz)
Contained Au
(000 oz)
Contained Ag
(000 oz)
Contained Cu
(mm lbs)
Contained Zn
(mm lbs)
Measured 9.3 2.59 1.58 16.20 0.19 0.83 770 470 4,824 38.0 168.5
Indicated 81.9 2.56 1.55 14.74 0.18 0.89 6,731 4,070 38,796 325.4 1,599.3
Total M&I 91.2 2.56 1.55 14.89 0.18 0.88 7,501 4,540 43,620 363.4 1,767.8
Inferred 21.5 2.51 1.44 23.04 0.20 0.71 1,736 1,000 15,925 96.3 337.2
Tonnes
(mm)
Au Equivalent
g/t
Au
g/t
Ag
g/t
Cu
%
Zn
%
Contained Au
EQ (000 oz)
Contained Au
(000 oz)
Contained Ag
(000 oz)
Contained Cu
(mm lbs)
Contained Zn
(mm lbs)
Proven 8.4 2.35 1.41 15.75 0.17 0.75 614 368 4,115 31.5 138.9
Probable 72.5 2.37 1.44 13.98 0.17 0.78 5,347 3,247 31,525 271.7 17.6
Total P&P 80.9 2.37 1.44 14.14 0.17 0.77 5,961 3,616 35,640 303.2 156.5
Please refer to appendix for Mineral Reserve and Resource notes
TSXV: FPC | WWW.FALCORES.COM | 12
HORNE 5 PROJECT| MINE DESIGN
HORNE 5
PROJECT
FEASIBILITY
16 M
AuEq Oz
Produced
7.1 M
AuEq Oz
M&I4
1.7 M
AuEq Oz
Inferred
 Mine throughput
 15,790 tpd average at steady-state
 With peak throughput at 16,000 tpd in first 5 years
 Mining method
 Transverse long-hole stoping
 Phase 1 – Stope size 40m X 25m X 20m
(~69,000 t per stope, 83 stopes per year)
 Production drilling in ore at 6.5 inches
 Primary – secondary stope mining sequencing
 Stope paste backfill to ensure stability
 Below 3% dilution
 95% ore recovery
 Quemont Shaft
 Use of existing 1,200 metre shaft
 Dewatering of old workings required
 11 million cubic meters
 Environmentally-friendly disposal of sludges and tailings
in dewatered workings and in production stopes
TSXV: FPC | WWW.FALCORES.COM | 13
HORNE 5 PROJECT| MINING APPROACH FOR FEASIBILITY >17 YEARS OF LIFE
 Phase 1: 2021 –2028
 43.2Mt
 15,700tpd
 Phase 2: 2029 –2035
 37.7Mt
 15,300tpd
 Dewatering Phase (25 months)
 Rehab Shaft
 Build barricades
 Establish Ventilation
 Horizontal Dev. = 4,000m
 Vertical Dev. = 2,000m (not depth)
 Construction (18 months)
 Access Ore Deposit
 Construct Ore Handling System
 Develop levels for start of production
 Horizontal Dev. = 17,500m
 Vertical Dev. = 2,500m (not depth)
PHASE 2
EXISTING SHAFT 
PHASE 1
TSXV: FPC | WWW.FALCORES.COM | 14
HORNE 5 PROJECT| HIGH LEVEL OF AUTOMATION
 STATE-OF-THE-ART OPERATION
 Surface control underground operations:
 Hoist – production and services
 Teleoperation of loaders
 Monitoring and management of ventilation
requirements and paste backfill distribution
 Water pumping monitoring
 Staff & equipment location monitoring
 HIGH CAPACITY PRODUCTION MINING EQUIPMENT
 Scoop tram: 21 metric tonnes
 Haulage truck: 50 metric tonnes
 Conveyor system from deposit to Quemont shaft
 Ability to operate between working shifts
(20h/day vs 14h/day for a conventional mine)
TSXV: FPC | WWW.FALCORES.COM | 15
HORNE 5 PROJECT| PROCESS FLOW SHEET
 Semi-Autogenous-Ball milling-Crushing
 15,790 tpd facility
 92% of mill availability
 Flotation & thickening section divided in
three circuits dedicated to recovering
copper, zinc and pyrite concentrates
 Pyrite concentrate will require a finer grind
to achieve improved gold recovery by
cyanide leaching/CIP
 Paste Backfill Capacity
 60% paste backfill plant availability
 Cyanide destruction circuit
 Process Products
 16% Copper concentrate (+/- 130 tpd)
 52% Zinc concentrate (+/- 200 tpd)
 Ag-Au ingot
 Stockpile live capacity is 12 hours. (8,000 t)
TSXV: FPC | WWW.FALCORES.COM | 16
HORNE 5 PROJECT| LIFE OF MINE GOLD PRODUCTION
LIFE OF MINE
 Contained gold: 3.7 mm ozs
 Recovered gold: 3.3 mm ozs
 Annual gold production: 219,000 ozs
 Steady-state production: 234,000 ozs
 Head Grade:
 Gold equivalent : 2.37 g/t
 Gold : 1.44 g/t
 Peak Year Production (2030-2034)
 5 year avg. : 254,000 gold ozs
 Peak in 2031 : 268,000 gold ozs
 Grade improves as the production
reaches the deeper portions of the
Horne 5 deposit
 HG_F zones currently in Inferred
Resources and not included in
Feasibility holds 2.8 million tonnes at
3.38 Au g/t
 Gold equivalent production metrics
 338,000 AuEq ounces per year
 5.1 mm AuEq recovered ounces
TSXV: FPC | WWW.FALCORES.COM | 17
HORNE 5 PROJECT| OPERATING COSTS – C$ per tonne
Cash Cost (C$/tonne) 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Mining $14.99 $11.91 $12.22 $12.03 $11.97 $12.27 $12.14 $12.12 $12.94 $13.39
Processing $20.66 $20.63 $20.40 $20.42 $20.30 $20.33 $20.72 $20.16 $20.51 $20.51
Tailings and Water $4.62 $4.02 $5.17 $5.16 $5.29 $5.24 $5.27 $5.07 $5.07 $5.06
G&A $2.41 $2.74 $2.76 $2.74 $2.75 $2.75 $2.90 $2.83 $2.81 $2.78
Total Per Tonne Cost $42.68 $39.30 $40.56 $40.36 $40.32 $40.58 $41.03 $40.19 $41.33 $41.75
Ore Milled (000 tonnes) 2,774 5,867 5,821 5,852 5,828 5,842 5,527 5,673 5,721 5,775
TSXV: FPC | WWW.FALCORES.COM | 18
$0
$500
$1,000
$1,500
$2,000
$2,500
2016 Gold Mine, Composite, Total Cash + Sustaining Capex Cost
Grouped By Mine and Ranked By Total Cash plus Sustaining Capex
0 500 1000 1500 2000
Paid Gold (t)
Horne 5 Project AISC of US$399/oz
Mining $241
Processing $392
Tailings and Water $97
G&A $55
Smelting and Refining $150
Royalties $37
By-Product Credit ($710)
Sustaining $127
Closure $10
Total AISC $399
Pre-Production Cost $243
All-In Costs $643
Cash Cost Summary
Source: Wood Mackenzie Ltd. and BMO Capital Markets
Note: Amounts may vary du to rounding
• All-in Sustaining Costs are presented as defined by the World Gold Council ("WGC") less Corporate G&A
• All-in Costs are represented as: (AISC + Capital Costs) / total gold recoverable ounce
HORNE 5 PROJECT| LOW ALL-IN SUSTAINING COST, A TOP QUARTILE ASSET
2016 Gold AISC Cost Curve 0
TSXV: FPC | WWW.FALCORES.COM | 19
HORNE 5 PROJECT | RELOCATION PROGRAM
 Memorandum of Understanding with the Commission scolaire de Rouyn-Noranda
 Relocation and construction costs are estimated at $22.5 million
 Work has already been initiated
 Falco will be the prime contractor
TSXV: FPC | WWW.FALCORES.COM | 20
HORNE 5 PROJECT| ENVIRONMENT, PERMITTING AND SITE RESTORATION
Environmental Plan and Permitting:
 Environmental baseline studies were initiated in 2016
 Continued throughout 2017 to support the permitting process and the project timeline
 Project will require a provincial decree and federal authorisations
 Project is subject to a provincial impact assessment, including public hearings, as forecasted production is
over the 2,000 tpd threshold outlined in the applicable regulation
 Project will also be subject to a federal impact assessment study
 Horne 5 Project EIA expected to be submitted in Q4 2017
Dewatering Program:
 The Company has submitted an application for a certificate of authorization under Sections 22 and 31.75
of the Environmental Quality Act to be issued by the Ministry of Sustainable Development, Environment
and the Fight against Climate Change, to support the dewatering and sludge management strategy
 During the dewatering stage, which is expected to last 25 months, high density sludge from the water
treatment will be stored in the old Donalda and Quemont underground mine openings
During Operations:
 Tailings produced will be stored in old underground openings either in the form of slurry or paste backfill
during the first two years of operations
 Paste backfill will continue to be produced throughout the entire life of mine
 The remainder of the tailings produced will be stored at surface in a tailings management facility
 Identified an old tailings management facility located approximately 11 km from the project
Site Restoration:
 Site restoration costs were estimated at $68 million
TSXV: FPC | WWW.FALCORES.COM | 21
HORNE 5 PROJECT| CAPITAL COST
TOTAL
PRE-PRODUCTION
CAPITAL COSTS
US$802M
Note: Amounts may vary due to rounding.
TSXV: FPC | WWW.FALCORES.COM | 22
HORNE 5 PROJECT| FEASIBILITY – SURFACE
TSXV: FPC | WWW.FALCORES.COM | 23
HORNE 5 PROJECT| FINANCING ALTERNATIVES
Project Financing Alternatives:
 Strong support from several Quebec funds and governmental institutions
 Strong equity support from various funds
 Large available pools of capital to support mining development in the province
 Strong support from Osisko Gold Royalties
 Existing equity holder
 Technical service agreement in place
 Existing right to buy and structure stream as part of the overall project financing
 Strong support from existing shareholders and investors
 Several longstanding relationships have supported the Osisko group for many years
 Strong appetite for mining project debt financing
 Current market dynamic is favourable to builders
 Existing relationships with Export Credit Agencies
TSXV: FPC | WWW.FALCORES.COM | 24
HORNE 5 PROJECT| FROM PEA TO FEASIBILITY
FEASIBILITY PEA Change
Pre-Tax NPV (5%) – US$ $1,012 million NPV $848 million NPV 19%
IRR 18.9% IRR 20.0% IRR (6%)
Post-Tax NPV (5%) – US$ $602 million NPV $500 million NPV 20%
IRR 15.3% IRR 16.0% IRR (4%)
Payback Period (after-tax) 5.6 years 4.1 years +1.5 years
Life of Mine Gold Production 3.3 million oz gold 2.9 million oz gold 13%
Mine Life 15 years 12 years +3 years
Initial Capital $802 $680 18%
Sustaining Capital (million) $418 $283 47%
Closure Cost (million, net of salvage value) $33 $30 11% FX Adjusted
Metals Prices and FX Assumed
Gold $1,300/Au oz $1,250/Au oz +$50/Au oz -$3/Au oz
Silver $19.50/Ag oz $17.00/Ag oz +$2.50/Ag oz +$2.29/Ag oz
Copper $3.00/Cu lb $2.85/Cu lb +$0.15/Cu lb +$0.04/Cu lb
Zinc $1.10/Zn lb $1.00/Zn lb +$0.10/Zn lb +$0.07/Zn lb
FX 1.28 1.33 -$0.05
LIFE OF MINE METRICS
Annual Production
Gold 219 koz 236 koz (7%)
Silver 1,752 koz 1,931 koz (9%)
Copper 16 mm lbs 16 mm lbs 0%
Zinc 67 mm lbs 65 mm lbs 3%
Operating Cost per tonne (C$/t) C$41.00/ tonne C$47.50/ tonne (14%)
Cash Cost per gold ounce $260/ Au oz $237/ Au oz 10%
AISC per gold ounce $399/ Au oz $427/ Au oz (6%)
All-In Cost per gold ounce (CAPEX+OPEX) $643/ Au oz $660/ Au oz (3%)
Recovery
Gold 88.1% 86.8% 1%
Silver 71.5% 74.9% (5%)
Copper 75.8% 74.0% 2%
Zinc 72.9% 67.3% 8%
TSXV: FPC | WWW.FALCORES.COM | 25
HORNE 5 PROJECT|COMPARABLE FEASIBILITIES & CONSTRUCTION PROJECTS
Abitibi Belt Ecuador Nunavut Nunavut
Goldex La Ronde 2
Young-
Davidson
Horne 5
Fruta del
Norte
Meliadine 1.0 Meliadine 2.0
Operator Agnico Eagle Agnico Eagle Northgate Falco Lundin Gold Agnico Eagle Agnico Eagle
Feasibility Study Year 2005 2006 2010 2017 2016 2015 2016
Gold Price per ounce (US$) $400 $450 $825 $1,300 $1,250 $1,300 $1,200
FX 1.30 1.25 1.11 1.28 n/a 1.15 1.25
After-Tax IRR * 15.0% IRR 13.3% IRR 10.3% IRR 15.3% IRR 15.7% IRR 10.3% IRR n/a
Annual Production (Au ozs) * 170,000 320,000 180,000 219,000 340,000 349,000 390,000
CAPEX (US$ million) * $135.0 $210.0 $339.4 $802.0 $669.0 $911.0 $900.0
Cash Cost per ounce (US$) * $205 $230 $351 $260 $553 $531 $590
Operating Cost per tonne (C$) * C$16.97 C$67.00 C$31.63 C$41.00 n/a C$139.00 C$160.00
Life of Mine * 10 Years 10 Years 15 Years 15 Years 13 Years 9 Years 14 Years
Payback * 6 Years n/a 6.9 Years 5.6 Years 4.5 Years 5 Years n/a
Tax Pool or Sunk Cost (US$M) * $600.0 $600.0 $50.5 $28.9 $430.0 $252.0 $447.0
In Operation    2021 2020 2020 2019
Canadian Development Projects – High Level of Attractiveness
 Strong operators looking for long mine lives
 With long mine lives a single bull cycle will pay back the operation multiple times
 Canadian projects support lower IRRs
 Talented labour pool
 Experienced contractors and mine builders
 Great infrastructure
 Safe geopolitical profile
* At the time of feasibility report, reported in press release, technical reports and financial statements
TSXV: FPC | WWW.FALCORES.COM | 26
Source: Company website, technical reports and filings from SEDAR
HORNE 5 PROJECT|COMPARABLE OPERATIONS – CURRENT
Goldex D Zone
(Agnico Eagle)
Young-Davidson
(Alamos)
La Ronde 2
(Agnico Eagle)
Horne 5 PEA
(Falco)
Horne 5 Feasibility
(Falco)
Resource Grade
(g/t AuEq)
1.69 2.69 5.1 2.9 2.6
Mining Method Long hole Transverse long hole
Long. Retreat /
Tr. Open Stoping
Transverse long hole Transverse long hole
Depth (m) 670 - 1,200 750 - 1,500 2,000-3,000 600 – 2,300 600 – 1,800
Stope Size 22 x 30 x 50 12-40 x 20 x 30 5-25 x 15 x 30 38 x 15 x 15 P1: 40 x 20 x25
Mining Rate 6,800 tpd 8,000 tpd 7,200 tpd 15,000 tpd P1: 16,000 tpd
Specific Gravity 2.8 2.69 3.3 3.45 3.45
Mining Dilution 15% 10% 10%-20% < 4% < 3%
Operating Cost/NSR C$35-37/t * C$53.50/t * C$95/t C$47.50/t C$41.00/t
Annual Production
(koz)
113,300 * 200,000 * 230,000 * 236,000* 219,000
IRR ** 15.0% IRR 10.3% IRR 13.3% IRR 16.0% IRR 15.3% IRR
* Projected life-of-mine (LOM) and 2017-2019 average for Goldex
** Last available public filings
TSXV: FPC | WWW.FALCORES.COM | 27
ACTIVITIES START COMPLETION
PEA COMPLETED
Feasibility Study COMPLETED
Environmental Impact assessment Q2 2016 Q4 2017
Mine Dewatering Q2 2018 Q2 2020
Detailed engineering Q4 2017 Q2 2020
Head frame and hoist construction (Exploration Phase) Q4 2017 Q3 2018
Public audiences – “BAPE” Q4 2018 Q1 2019
Permits for project construction Q2 2019
Processing plant construction Mid 2019 Q1 2021
First mineralized ore in mine Q2 2021
End of process plant construction / plant commissioning H1 2021
Production achieved in mine (Phase 1) H2 2021
Process plant ramp up H2 2021
Full Commercial Production H1 2022
HORNE 5 PROJECT| PROJECT SCHEDULE
TSXV: FPC | WWW.FALCORES.COM | 28
EV / RESOURCES (US$/OZ AU EQ.)
MARKET CAP. (US$ MM)
IN PRODUCTION OR ACQUIRED
1. Acquisition Multiple
Source: Company websites, filings from SEDAR and Factset
COMPARABLES – PRE-PRODUCTION > 5 M OZS & CAPEX BELOW $1BN
TSXV: FPC | WWW.FALCORES.COM | 29
ALL-IN SUSTAINING CASH COST (US$/OZ AU)
LIFE OF MINE (YEARS)
Source: Company websites, filings from SEDAR and Factset
IN PRODUCTION OR ACQUIRED
RESERVES
COMPARABLES – PRE-PRODUCTION > 5 M OZS & CAPEX BELOW $1BN
TSXV: FPC | WWW.FALCORES.COM | 30
HORNE 5 PROJECT| DEEP EXPLORATION POTENTIAL (VS. LA RONDE VMS)
3,000 M
HG_F zone (Inferred) not included in Feasibility holds:
2.8 m tonnes at 3.38 Au g/t
VS. current Feasibility diluted grade of 1.44 Au g/t
1,000 M
2,000 M
Horne 5 Project La Ronde Complex (Agnico Eagle)
Source: Company websites
TSXV: FPC | WWW.FALCORES.COM | 31
EXPERIENCED SENIOR LEADERSHIP TEAM
 Luc Lessard, President & CEO, Director 
 Vincent Metcalfe, CFO
 Claude Léveillée, VP Community Relations & HR
 Anthony Glavac, VP – Controller
 Helene Cartier, VP – Environment 
 Francois Vezina, VP – Mining 
 Christian Laroche, VP – Processing 
 John-Paul McGrath – Project Manager 
 Claude Bernier, Exploration Manager
 Sylvain Doire, Environment
 Claude Pilote, Senior Geologist
 Daniel Mathieu – Mechanical Design 
EXECUTIVE MANAGEMENT BOARD OF DIRECTORS
 Sean Roosen, Chair 
 Mario Caron, Lead Director
 Bryan Coates 
 Paola Farnesi
 Claude Ferron
 Paul Henri-Girard
 Chantal Sorel
 Denotes former member of Canadian Malartic development, construction and operating team
TSXV: FPC | WWW.FALCORES.COM | 32
CAPITAL SUMMARY & SHAREHOLDER REGISTRY
SHAREHOLDER REGISTRY
Osisko Gold Royalties 13.2%
Tocqueville 9.2%
Government of Quebec 5.2%
Oppenheimer Funds 2.0%
Old Mutual 1.6%
RBIM 1.1%
CIBC Asset Management 1.0%
Caisse de Depot du Quebec 1.0%
Shares Outstanding (basic) 180,145,244
Stock Options 8,651,260
Warrants 28,631,717
Shares Outstanding (fully diluted) 217,428,221
Share Price C$1.24
Market Capitalization C$223.4
Cash Position ~C$42.6 Million
CAPITAL STRUCTURE (AS OF OCT 13, 2017)
Source: Factset, Bloomberg, public filings and Company estimates
TSXV: FPC | WWW.FALCORES.COM | 33
FALCO RESOURCES| CLOSING THOUGHTS
OBSERVATION: WHAT IS LEFT IN THE ABITIBI 10 YEARS FROM NOW?
 Dearth of sizable gold projects in the Abitibi 10 years from now
HORNE 5 PROJECT:
 Long-life Project & Low AISC: >15 years of life with upside & < $399/Au Oz AISC
 State-of-the-art project: A true mine of the future
 Strong Exploration Upside
 Ideal location: Infrastructure & Strong Labour Pool + Strong Government Support
 Strong & Experienced Team to Advance the Project
TSXV: FPC | WWW.FALCORES.COM | 34
Head Office
Falco Resources Ltd.
1100, avenue des
Canadiens-de-Montréal
Bureau 300
Montréal, QC H3B 2S2
Tél. : +1.514.905.3162
Toll Free : +1.888.915.2009
Courriel : info@falcores.com
Investor Inquiries
Vincent Metcalfe, CFO
Tel: +1.514.905.3162
Email: vmetcalfe@falcores.com
CONTACT US
TSXV: FPC | WWW.FALCORES.COM | 35
APPENDIX
Appendix A – Additional Information
Appendix B – Resource & Modeling Notes
TSXV: FPC | WWW.FALCORES.COM | 36
600m
HORNEQUEMONT  Exceptional Drill
Density
 4,384 underground
drill holes at 15 m
spacing (305,788m)
drilled by Noranda
 Very high confidence
in historical drilling
 Great upside at
Depth – limited
drilling vs. upper area
HORNE 5 PROJECT | HISTORICAL DRILL DENSITY
TSXV: FPC | WWW.FALCORES.COM | 37
HORNE 5 PROJECT | CURRENT MINERAL ENVELOPS
TSXV: FPC | WWW.FALCORES.COM | 38
HOISTING | FS HOISTING & SHAFT
TSXV: FPC | WWW.FALCORES.COM | 39
PROCESSING | SAG & Ball Mill with Cyclone Cluster
TSXV: FPC | WWW.FALCORES.COM | 40
PROCESSING | Overall Flotation Tank
TSXV: FPC | WWW.FALCORES.COM | 41
PROCESSING | Regrind Mill
TSXV: FPC | WWW.FALCORES.COM | 42
PROCESSING | Carbon in Pulp
TSXV: FPC | WWW.FALCORES.COM | 43
HORNE 5 PROJECT| Mining Fleet
UNDERGROUND MOBILE EQUIPMENT
Item Total
Scoop 17 Tons 3
Scoop 17 Tons (Spare) 1
Mine Truck 60 Tons 4
Jumbo 2 Booms Automated 4
Bolting Machine 4
Bolting Machine Spare 1
Scoop 21 Tons 4
Scoop 21 Tons (Spare) 1
Mine Truck 60 Tons (Phase 3) 2
Production Drill Automated 4
Production Drill Automated (Spare) 1
Cable Drill + Bolt 2
Shotcrete Machine (wet) 2
REMOTELY CONTROLLED FROM SURFACE
TSXV: FPC | WWW.FALCORES.COM | 44
Project Potash Corp
Ukraine KJRK
Phase 1
Ukraine KJRK
Phase 2
Horne 5
Phase 1
Horne 5
Phase 2
Depth (m) 1,200 1,340 1,800 1,200 1,800
Speed (m/s) 18-20 19 19 18 18
Operating Hours 19-20 22 22 19 19
Skip capacity (t) 40-65 50 50 43 39.4
Productivity
(tpd)
25,000-30,000 22,050 17,640 23,200 16,550
HORNE 5 PROJECT| HOISTING COMPARABLES
43T SKIP – Similar to Horne 5 Sizing
TSXV: FPC | WWW.FALCORES.COM | 45
Appendix B – Mineral Resource Estimates & Modeling Notes
1. The effective date of the mineral resource estimate is July 25, 2017. The Independent QP for the Mineral Resource Estimate as required by National Instrument 43 101 is Carl Pelletier, P. Geo.,
B.Sc., employee of InnovExplo.
2. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability.
3. While the results are presented undiluted and in situ, the reported mineral resources are considered by the QP to have reasonable prospects for economic extraction.
4. These estimates include six low-grade gold-bearing mineralized envelopes.
5. The main low-grade gold-bearing mineralized envelope includes six high-grade gold-bearing zones, one high-grade copper-bearing zone, one high grade zinc-bearing zone, and three high-grade
silver-bearing zones. Note that these high-grade zones may overlap each other.
6. Mineral resources were compiled at NSR cut-offs of (in C$) $40, $45, $50, $55, $60, $65, $70, $75, $80, $85, $90, $95 and $100 per tonne for sensitivity purposes.
7. The official base case mineral resource is reported at a $55 per tonne NSR cut-off.
8. The appropriate NSR cut-off will vary depending on prevailing economic and operational parameters to be determined.
9. NSR estimates are based on the following assumptions: Exchange rate of C$1.00 /0.78 US$; Metal prices as follows: gold $1,300/oz, silver $19.50, copper $2.90/lb, zinc $1.10/lb (inspired from a
long-term analyst consensus price forecast study); Net recoveries are variable in function of grade of each commodity. Smelting cost (including transportation) of C$6.52 per tonne (based on the
cost mine service, as well as a non-public smelter contract obtained from one of the proposed destinations and talks with transport providers).
10. Gold equivalent calculations assume these same metal prices.
11. Inferred Mineral Resources are separate from Indicated Mineral Resources.
12. The quantity and grade of reported Inferred Mineral Resources are uncertain in nature and there has not been sufficient work to define these Inferred Mineral Resources as Indicated or
Measured Mineral Resources. It is uncertain if further work will result in upgrading them to an Indicated or Measured mineral resource category.
13. The mineral resource was estimated using Geovia GEMS 6.8. The estimate is based on 5,980 diamond drill holes (483,254 m) of which 4,141 cut mineralized zones for a total of 178,150 m of core
within these zones. For silver, the estimate also uses the results of an exhaustive metallurgical test comprising 2,112 diamond drill holes assayed for silver over a total length of 75,540 metres. A
minimum true thickness of 7.0 m was applied, using the grade of the adjacent material when assayed, or a value of zero when not assayed. Only the silver interpolation in the Inferred mineral
resources does not use the material when not assayed.
14. The estimate database also contains 14,799 channel samples for a total of 23,791 m from historically sampled drifts. Channel sample data was only used for distance to composite criterion for
mineral resource classification purposes.
15. 91% of density values were estimated using historical iron assay drill hole data and Falco density data for an average of 3.41 g/cm3. The interpolation method uses three passes for the ENV_A
and HG_A to HG_F zones. 8% of the density values were fixed at 2.88 g/cm3 for ENV_B to ENV_E due to the scarcity of the data. 2.88 g/cm3 represents the median of the available data. 1% of
density values were fixed at 2.67 g/cm3 for ENV_F due to the scarcity of the data and to adequately characterize this quartz-rich zone.
16. Compositing was done on drill hole sections falling within the mineralized zones (composite = 3.0 m). Tails shorter than 0.75 m were not generated.
17. Mineral resources were evaluated from drill holes using an ID2 interpolation method in a block model (block size = 5 x 5 x 5 m).
18. High-grade capping was done on raw assay data and established on a per zone basis for gold (Au g/t): (HG_A: 35; HG_B: 35; HG_C: 25; HG_D: 35; HG_E: 25; HG_F: 35; ENV_A: 35; ENV_B: 25;
ENV_C: 25; ENV_D: 20; ENV_E: 35; ENV_F: 25) and for silver (Ag g/t): SG_HG:100; HG_D: 165; HG_F: 165; ENV_A_SG_Low: 110; ENV_B: 100; ENV_C: 100; ENV_D: 100. Capping grade selection is
supported by statistical analysis. No capping was applied to the Cu and Zn data based on statistical analysis.
19. The reported Mineral Resources are categorized as Measured, Indicated and Inferred. The Inferred category is only defined within the areas where blocks were interpolated during pass 1 or pass
2 in areas where continuity is sufficient to avoid isolated blocks. The Indicated category is only defined by blocks interpolated in areas where the maximum distance to the closest drill hole
composite is less than 25 m for blocks interpolated in passes 1 and 2. The Measured category is only defined by blocks classified as Indicated and within sufficient proximity to sampled drifts (<
15m). The average distance to the nearest composite is 6.97 m for the Measured mineral resources, 10.01 m for the Indicated mineral resources and 40.10 m for the Inferred mineral resources.
20. Tonnage estimates were rounded to the nearest hundred tonnes. Any discrepancies in the totals are due to rounding effects. Rounding practice follows the recommendations set forth in Form
43-101F1.
21. CIM definitions and guidelines were followed in estimating mineral resources.
22. InnovExplo is not aware of any known environmental, permitting, legal, title-related, taxation, socio-political, marketing or other relevant issue that could materially affect the mineral resource
estimate.
23. Metal contained in ounces (troy) = metric tonnes x grade / 31.10348. Calculations used metric units (metres, tonnes and g/t). Metal contents are presented in ounces and pounds.
RESOURCE ESTIMATE NOTES
TSXV: FPC | WWW.FALCORES.COM | 46
Appendix B – Mineral Reserve Estimates Notes
1. The QP, as defined below, for the Mineral Reserve estimate is Mr. Patrick Frenette (InnovExplo).
2. Estimated at $2.15/lb Cu, $1.00/lb Zn, $1,300/oz Au and $18.50/oz Ag, using an exchange rate of C$1.00:US$0.77, cut-off NSR value of C$55.00/t. Metallurgical recoveries and other parameters
for the November 2016 MRE are shown in Chapter 6 of the Feasibility Study.
3. Mineral Reserve tonnage and mined metal have been rounded to reflect the accuracy of the estimate and numbers may not add due to rounding.
4. Mineral Reserves presented include both internal and external dilution along with mining recovery. The external dilution is estimated to be 2.3%. The mining recovery factor was set at 95% to
account for mineralized material left in the margins of the deposit in each block.
RESERVE ESTIMATE NOTES

More Related Content

What's hot

Govi ex uranium corporate presentation sep2021
Govi ex uranium corporate presentation sep2021Govi ex uranium corporate presentation sep2021
Govi ex uranium corporate presentation sep2021Adnet Communications
 
Solaris Resources - February 2022
Solaris Resources - February 2022Solaris Resources - February 2022
Solaris Resources - February 2022JacquelineWagenaar1
 
Osisko Development - Corporate Presentation, December 2021
Osisko Development - Corporate Presentation, December 2021Osisko Development - Corporate Presentation, December 2021
Osisko Development - Corporate Presentation, December 2021Kevin Connan
 
Corporate presentation Feb
Corporate presentation FebCorporate presentation Feb
Corporate presentation FebZhalaRahim
 
Solaris Resources - Nov 2021 Corporate Presentation
Solaris Resources - Nov 2021 Corporate PresentationSolaris Resources - Nov 2021 Corporate Presentation
Solaris Resources - Nov 2021 Corporate PresentationJacquelineWagenaar1
 
OZ Corporate Presentation July 2021
OZ Corporate Presentation July 2021OZ Corporate Presentation July 2021
OZ Corporate Presentation July 2021CarolynGraham14
 
Trek Mining - Transaction to Form Equinox Gold
Trek Mining - Transaction to Form Equinox GoldTrek Mining - Transaction to Form Equinox Gold
Trek Mining - Transaction to Form Equinox GoldTrek Mining Inc.
 
Solaris Resources - January 2022
Solaris Resources -  January 2022Solaris Resources -  January 2022
Solaris Resources - January 2022JacquelineWagenaar1
 
GoviEx Corporate Presentation (October 2021)
GoviEx Corporate Presentation (October 2021)GoviEx Corporate Presentation (October 2021)
GoviEx Corporate Presentation (October 2021)Adnet Communications
 
Fortune Bay - Corporate Presentation - January 2022
Fortune Bay - Corporate Presentation - January 2022Fortune Bay - Corporate Presentation - January 2022
Fortune Bay - Corporate Presentation - January 2022Fortune Bay Corp
 
ATAC Resources Ltd. Corporate Presentation November 2021
ATAC Resources Ltd. Corporate Presentation November 2021ATAC Resources Ltd. Corporate Presentation November 2021
ATAC Resources Ltd. Corporate Presentation November 2021ATAC Resources Ltd
 
Augusta Gold - Corporate Update July 2021
Augusta Gold - Corporate Update July 2021Augusta Gold - Corporate Update July 2021
Augusta Gold - Corporate Update July 2021Augusta Gold Corp.
 
Equinox Gold Corporate Presentation
Equinox Gold Corporate PresentationEquinox Gold Corporate Presentation
Equinox Gold Corporate PresentationEquinox Gold Corp.
 
Equinox Gold Corporate Presentation
Equinox Gold Corporate PresentationEquinox Gold Corporate Presentation
Equinox Gold Corporate PresentationEquinox Gold Corp.
 
Fortune bay Corporate presentation
Fortune bay Corporate presentationFortune bay Corporate presentation
Fortune bay Corporate presentationZhalaRahim
 
Equinox Gold Corp Presentation
Equinox Gold Corp PresentationEquinox Gold Corp Presentation
Equinox Gold Corp PresentationEquinox Gold Corp.
 
Ramping Up Brucejack – Presented at the Scotiabank Mining Conference
Ramping Up Brucejack – Presented at the Scotiabank Mining ConferenceRamping Up Brucejack – Presented at the Scotiabank Mining Conference
Ramping Up Brucejack – Presented at the Scotiabank Mining ConferencePretiumR
 
Equinox Gold Corporate Presentation
Equinox Gold Corporate PresentationEquinox Gold Corporate Presentation
Equinox Gold Corporate PresentationEquinox Gold Corp.
 
Equinox Gold Corporate Presentation
Equinox Gold Corporate PresentationEquinox Gold Corporate Presentation
Equinox Gold Corporate PresentationEquinox Gold Corp.
 

What's hot (20)

Govi ex uranium corporate presentation sep2021
Govi ex uranium corporate presentation sep2021Govi ex uranium corporate presentation sep2021
Govi ex uranium corporate presentation sep2021
 
Solaris Resources - February 2022
Solaris Resources - February 2022Solaris Resources - February 2022
Solaris Resources - February 2022
 
Osisko Development - Corporate Presentation, December 2021
Osisko Development - Corporate Presentation, December 2021Osisko Development - Corporate Presentation, December 2021
Osisko Development - Corporate Presentation, December 2021
 
Corporate presentation Feb
Corporate presentation FebCorporate presentation Feb
Corporate presentation Feb
 
Solaris Resources - Nov 2021 Corporate Presentation
Solaris Resources - Nov 2021 Corporate PresentationSolaris Resources - Nov 2021 Corporate Presentation
Solaris Resources - Nov 2021 Corporate Presentation
 
OZ Corporate Presentation July 2021
OZ Corporate Presentation July 2021OZ Corporate Presentation July 2021
OZ Corporate Presentation July 2021
 
Trek Mining - Transaction to Form Equinox Gold
Trek Mining - Transaction to Form Equinox GoldTrek Mining - Transaction to Form Equinox Gold
Trek Mining - Transaction to Form Equinox Gold
 
Solaris Resources - January 2022
Solaris Resources -  January 2022Solaris Resources -  January 2022
Solaris Resources - January 2022
 
GoviEx Corporate Presentation (October 2021)
GoviEx Corporate Presentation (October 2021)GoviEx Corporate Presentation (October 2021)
GoviEx Corporate Presentation (October 2021)
 
Fortune Bay - Corporate Presentation - January 2022
Fortune Bay - Corporate Presentation - January 2022Fortune Bay - Corporate Presentation - January 2022
Fortune Bay - Corporate Presentation - January 2022
 
ATAC Resources Ltd. Corporate Presentation November 2021
ATAC Resources Ltd. Corporate Presentation November 2021ATAC Resources Ltd. Corporate Presentation November 2021
ATAC Resources Ltd. Corporate Presentation November 2021
 
Augusta Gold - Corporate Update July 2021
Augusta Gold - Corporate Update July 2021Augusta Gold - Corporate Update July 2021
Augusta Gold - Corporate Update July 2021
 
Equinox Gold Corporate Presentation
Equinox Gold Corporate PresentationEquinox Gold Corporate Presentation
Equinox Gold Corporate Presentation
 
Equinox Gold Corporate Presentation
Equinox Gold Corporate PresentationEquinox Gold Corporate Presentation
Equinox Gold Corporate Presentation
 
Fortune bay Corporate presentation
Fortune bay Corporate presentationFortune bay Corporate presentation
Fortune bay Corporate presentation
 
Equinox Gold Corp Presentation
Equinox Gold Corp PresentationEquinox Gold Corp Presentation
Equinox Gold Corp Presentation
 
Ramping Up Brucejack – Presented at the Scotiabank Mining Conference
Ramping Up Brucejack – Presented at the Scotiabank Mining ConferenceRamping Up Brucejack – Presented at the Scotiabank Mining Conference
Ramping Up Brucejack – Presented at the Scotiabank Mining Conference
 
Equinox Gold Corporate Presentation
Equinox Gold Corporate PresentationEquinox Gold Corporate Presentation
Equinox Gold Corporate Presentation
 
Solaris Resources - Nov 2021
Solaris Resources - Nov 2021Solaris Resources - Nov 2021
Solaris Resources - Nov 2021
 
Equinox Gold Corporate Presentation
Equinox Gold Corporate PresentationEquinox Gold Corporate Presentation
Equinox Gold Corporate Presentation
 

Similar to Horne 5 Feasibility Study Results

17.7 falco presentation bmo
17.7 falco presentation   bmo17.7 falco presentation   bmo
17.7 falco presentation bmoFalcoCorporate
 
Falco Resources - March 2016 investor presentation
Falco Resources - March 2016 investor presentationFalco Resources - March 2016 investor presentation
Falco Resources - March 2016 investor presentationVincent Metcalfe
 
February 2016 Corporate Presentation
February 2016 Corporate PresentationFebruary 2016 Corporate Presentation
February 2016 Corporate PresentationFalcoCorporate
 
Rebirth of the Horne Mine - A Company Maker
Rebirth of the Horne Mine - A Company MakerRebirth of the Horne Mine - A Company Maker
Rebirth of the Horne Mine - A Company MakerFalcoCorporate
 
12.3 2016 investor presentation
12.3 2016 investor presentation12.3 2016 investor presentation
12.3 2016 investor presentationFalcoCorporate
 
30.2 falco presentation rbc august 2017 100dpi
30.2 falco presentation   rbc august 2017 100dpi30.2 falco presentation   rbc august 2017 100dpi
30.2 falco presentation rbc august 2017 100dpiFalcoCorporate
 
12.6 2016 investor presentation
12.6 2016 investor presentation12.6 2016 investor presentation
12.6 2016 investor presentationFalcoCorporate
 
BeMetals Presentation - January 4, 2022
BeMetals Presentation - January 4, 2022BeMetals Presentation - January 4, 2022
BeMetals Presentation - January 4, 2022DerekIwanaka1
 
August Investor presentation
August Investor presentationAugust Investor presentation
August Investor presentationFalcoCorporate
 
BeMetals Presentation_April 6, 2022.pdf
BeMetals Presentation_April 6, 2022.pdfBeMetals Presentation_April 6, 2022.pdf
BeMetals Presentation_April 6, 2022.pdfDerek Iwanaka
 
presentation COBALT.pdf
presentation COBALT.pdfpresentation COBALT.pdf
presentation COBALT.pdfssuserea6227
 
BeMetals Presentation_July 26, 2022.pdf
BeMetals Presentation_July 26, 2022.pdfBeMetals Presentation_July 26, 2022.pdf
BeMetals Presentation_July 26, 2022.pdfDerekIwanaka1
 
BeMetals Presentation_August 4, 2022.pdf
BeMetals Presentation_August 4, 2022.pdfBeMetals Presentation_August 4, 2022.pdf
BeMetals Presentation_August 4, 2022.pdfDerekIwanaka1
 
Guy april 2018 ir presentation final
Guy april 2018 ir presentation finalGuy april 2018 ir presentation final
Guy april 2018 ir presentation finalguygold2016
 
BeMetals Presentation_May 2022.pdf
BeMetals Presentation_May 2022.pdfBeMetals Presentation_May 2022.pdf
BeMetals Presentation_May 2022.pdfDerek Iwanaka
 
May 2018 ir presentation
May 2018 ir presentationMay 2018 ir presentation
May 2018 ir presentationguygold2016
 
BeMetals Presentation_November 8, 2022.pdf
BeMetals Presentation_November 8, 2022.pdfBeMetals Presentation_November 8, 2022.pdf
BeMetals Presentation_November 8, 2022.pdfDerekIwanaka2
 
BeMetals Presentation_June 1, 2022.pdf
BeMetals Presentation_June 1, 2022.pdfBeMetals Presentation_June 1, 2022.pdf
BeMetals Presentation_June 1, 2022.pdfDerek Iwanaka
 

Similar to Horne 5 Feasibility Study Results (20)

2018 Falco Presentation
2018 Falco Presentation2018 Falco Presentation
2018 Falco Presentation
 
Falco jan2018
Falco jan2018Falco jan2018
Falco jan2018
 
17.7 falco presentation bmo
17.7 falco presentation   bmo17.7 falco presentation   bmo
17.7 falco presentation bmo
 
Falco Resources - March 2016 investor presentation
Falco Resources - March 2016 investor presentationFalco Resources - March 2016 investor presentation
Falco Resources - March 2016 investor presentation
 
February 2016 Corporate Presentation
February 2016 Corporate PresentationFebruary 2016 Corporate Presentation
February 2016 Corporate Presentation
 
Rebirth of the Horne Mine - A Company Maker
Rebirth of the Horne Mine - A Company MakerRebirth of the Horne Mine - A Company Maker
Rebirth of the Horne Mine - A Company Maker
 
12.3 2016 investor presentation
12.3 2016 investor presentation12.3 2016 investor presentation
12.3 2016 investor presentation
 
30.2 falco presentation rbc august 2017 100dpi
30.2 falco presentation   rbc august 2017 100dpi30.2 falco presentation   rbc august 2017 100dpi
30.2 falco presentation rbc august 2017 100dpi
 
12.6 2016 investor presentation
12.6 2016 investor presentation12.6 2016 investor presentation
12.6 2016 investor presentation
 
BeMetals Presentation - January 4, 2022
BeMetals Presentation - January 4, 2022BeMetals Presentation - January 4, 2022
BeMetals Presentation - January 4, 2022
 
August Investor presentation
August Investor presentationAugust Investor presentation
August Investor presentation
 
BeMetals Presentation_April 6, 2022.pdf
BeMetals Presentation_April 6, 2022.pdfBeMetals Presentation_April 6, 2022.pdf
BeMetals Presentation_April 6, 2022.pdf
 
presentation COBALT.pdf
presentation COBALT.pdfpresentation COBALT.pdf
presentation COBALT.pdf
 
BeMetals Presentation_July 26, 2022.pdf
BeMetals Presentation_July 26, 2022.pdfBeMetals Presentation_July 26, 2022.pdf
BeMetals Presentation_July 26, 2022.pdf
 
BeMetals Presentation_August 4, 2022.pdf
BeMetals Presentation_August 4, 2022.pdfBeMetals Presentation_August 4, 2022.pdf
BeMetals Presentation_August 4, 2022.pdf
 
Guy april 2018 ir presentation final
Guy april 2018 ir presentation finalGuy april 2018 ir presentation final
Guy april 2018 ir presentation final
 
BeMetals Presentation_May 2022.pdf
BeMetals Presentation_May 2022.pdfBeMetals Presentation_May 2022.pdf
BeMetals Presentation_May 2022.pdf
 
May 2018 ir presentation
May 2018 ir presentationMay 2018 ir presentation
May 2018 ir presentation
 
BeMetals Presentation_November 8, 2022.pdf
BeMetals Presentation_November 8, 2022.pdfBeMetals Presentation_November 8, 2022.pdf
BeMetals Presentation_November 8, 2022.pdf
 
BeMetals Presentation_June 1, 2022.pdf
BeMetals Presentation_June 1, 2022.pdfBeMetals Presentation_June 1, 2022.pdf
BeMetals Presentation_June 1, 2022.pdf
 

More from FalcoCorporate

50.1 falco presentation feasibility - final(1)
50.1 falco presentation   feasibility - final(1)50.1 falco presentation   feasibility - final(1)
50.1 falco presentation feasibility - final(1)FalcoCorporate
 
30.3 falco presentation osisko days - sept 2017 125dpi
30.3 falco presentation   osisko days - sept 2017 125dpi30.3 falco presentation   osisko days - sept 2017 125dpi
30.3 falco presentation osisko days - sept 2017 125dpiFalcoCorporate
 
21.1 falco presentation august 2017 100dpi
21.1 falco presentation   august 2017 100dpi21.1 falco presentation   august 2017 100dpi
21.1 falco presentation august 2017 100dpiFalcoCorporate
 
20.1 falco presentation may 2017
20.1 falco presentation   may 201720.1 falco presentation   may 2017
20.1 falco presentation may 2017FalcoCorporate
 
10.3 2016 investor presentation pea
10.3 2016 investor presentation   pea10.3 2016 investor presentation   pea
10.3 2016 investor presentation peaFalcoCorporate
 
9.2 2016 investor presentation
9.2 2016 investor presentation9.2 2016 investor presentation
9.2 2016 investor presentationFalcoCorporate
 
9.1 2016 investor presentation
9.1 2016 investor presentation9.1 2016 investor presentation
9.1 2016 investor presentationFalcoCorporate
 
Septembre 2015 Présentation
Septembre 2015 PrésentationSeptembre 2015 Présentation
Septembre 2015 PrésentationFalcoCorporate
 
September 2015 Corporate Presentation
September 2015 Corporate PresentationSeptember 2015 Corporate Presentation
September 2015 Corporate PresentationFalcoCorporate
 
2015 presentation-investisseurs-juin
2015 presentation-investisseurs-juin2015 presentation-investisseurs-juin
2015 presentation-investisseurs-juinFalcoCorporate
 
2015 investor presentation june
2015 investor presentation   june2015 investor presentation   june
2015 investor presentation juneFalcoCorporate
 
2015 investor-presentation-vancouver-april v001-s68iw2
2015 investor-presentation-vancouver-april v001-s68iw22015 investor-presentation-vancouver-april v001-s68iw2
2015 investor-presentation-vancouver-april v001-s68iw2FalcoCorporate
 
2015 Investor Presentation - Vancouver
2015 Investor Presentation - Vancouver2015 Investor Presentation - Vancouver
2015 Investor Presentation - VancouverFalcoCorporate
 
March 2015 Corporate Presentation
March 2015 Corporate Presentation March 2015 Corporate Presentation
March 2015 Corporate Presentation FalcoCorporate
 
March 2015 investor presentation revised cover
March 2015 investor presentation revised coverMarch 2015 investor presentation revised cover
March 2015 investor presentation revised coverFalcoCorporate
 
March 2015 investor presentation fr
March 2015 investor presentation frMarch 2015 investor presentation fr
March 2015 investor presentation frFalcoCorporate
 
March 2015 investor presentation revised cover
March 2015 investor presentation revised coverMarch 2015 investor presentation revised cover
March 2015 investor presentation revised coverFalcoCorporate
 
March 2015 investor presentation revised cover
March 2015 investor presentation revised coverMarch 2015 investor presentation revised cover
March 2015 investor presentation revised coverFalcoCorporate
 
March 2015 investor presentation fr
March 2015 investor presentation frMarch 2015 investor presentation fr
March 2015 investor presentation frFalcoCorporate
 
March 2015 Corporate Presentation
March 2015 Corporate Presentation March 2015 Corporate Presentation
March 2015 Corporate Presentation FalcoCorporate
 

More from FalcoCorporate (20)

50.1 falco presentation feasibility - final(1)
50.1 falco presentation   feasibility - final(1)50.1 falco presentation   feasibility - final(1)
50.1 falco presentation feasibility - final(1)
 
30.3 falco presentation osisko days - sept 2017 125dpi
30.3 falco presentation   osisko days - sept 2017 125dpi30.3 falco presentation   osisko days - sept 2017 125dpi
30.3 falco presentation osisko days - sept 2017 125dpi
 
21.1 falco presentation august 2017 100dpi
21.1 falco presentation   august 2017 100dpi21.1 falco presentation   august 2017 100dpi
21.1 falco presentation august 2017 100dpi
 
20.1 falco presentation may 2017
20.1 falco presentation   may 201720.1 falco presentation   may 2017
20.1 falco presentation may 2017
 
10.3 2016 investor presentation pea
10.3 2016 investor presentation   pea10.3 2016 investor presentation   pea
10.3 2016 investor presentation pea
 
9.2 2016 investor presentation
9.2 2016 investor presentation9.2 2016 investor presentation
9.2 2016 investor presentation
 
9.1 2016 investor presentation
9.1 2016 investor presentation9.1 2016 investor presentation
9.1 2016 investor presentation
 
Septembre 2015 Présentation
Septembre 2015 PrésentationSeptembre 2015 Présentation
Septembre 2015 Présentation
 
September 2015 Corporate Presentation
September 2015 Corporate PresentationSeptember 2015 Corporate Presentation
September 2015 Corporate Presentation
 
2015 presentation-investisseurs-juin
2015 presentation-investisseurs-juin2015 presentation-investisseurs-juin
2015 presentation-investisseurs-juin
 
2015 investor presentation june
2015 investor presentation   june2015 investor presentation   june
2015 investor presentation june
 
2015 investor-presentation-vancouver-april v001-s68iw2
2015 investor-presentation-vancouver-april v001-s68iw22015 investor-presentation-vancouver-april v001-s68iw2
2015 investor-presentation-vancouver-april v001-s68iw2
 
2015 Investor Presentation - Vancouver
2015 Investor Presentation - Vancouver2015 Investor Presentation - Vancouver
2015 Investor Presentation - Vancouver
 
March 2015 Corporate Presentation
March 2015 Corporate Presentation March 2015 Corporate Presentation
March 2015 Corporate Presentation
 
March 2015 investor presentation revised cover
March 2015 investor presentation revised coverMarch 2015 investor presentation revised cover
March 2015 investor presentation revised cover
 
March 2015 investor presentation fr
March 2015 investor presentation frMarch 2015 investor presentation fr
March 2015 investor presentation fr
 
March 2015 investor presentation revised cover
March 2015 investor presentation revised coverMarch 2015 investor presentation revised cover
March 2015 investor presentation revised cover
 
March 2015 investor presentation revised cover
March 2015 investor presentation revised coverMarch 2015 investor presentation revised cover
March 2015 investor presentation revised cover
 
March 2015 investor presentation fr
March 2015 investor presentation frMarch 2015 investor presentation fr
March 2015 investor presentation fr
 
March 2015 Corporate Presentation
March 2015 Corporate Presentation March 2015 Corporate Presentation
March 2015 Corporate Presentation
 

Recently uploaded

Nicola Mining Inc. Corporate Presentation April 2024
Nicola Mining Inc. Corporate Presentation April 2024Nicola Mining Inc. Corporate Presentation April 2024
Nicola Mining Inc. Corporate Presentation April 2024nicola_mining
 
slideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfslideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfsansanir
 
Q1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdfQ1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdfProbe Gold
 
WheelTug PLC Pitch Deck | Investor Insights | April 2024
WheelTug PLC Pitch Deck | Investor Insights | April 2024WheelTug PLC Pitch Deck | Investor Insights | April 2024
WheelTug PLC Pitch Deck | Investor Insights | April 2024Hector Del Castillo, CPM, CPMM
 
Best investment platform in india - falcon invoice discounting
Best investment platform in india - falcon invoice discountingBest investment platform in india - falcon invoice discounting
Best investment platform in india - falcon invoice discountingFalcon Invoice Discounting
 
Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024CollectiveMining1
 
the 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfthe 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfFrancenel Paul
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfProbe Gold
 
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...USDAReapgrants.com
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfProbe Gold
 
9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR
9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR
9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCRSapana Sha
 
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 60009654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000Sapana Sha
 
The Concept of Humanity in Islam and its effects at future of humanity
The Concept of Humanity in Islam and its effects at future of humanityThe Concept of Humanity in Islam and its effects at future of humanity
The Concept of Humanity in Islam and its effects at future of humanityJohanAspro
 
Basic Accountants in|TaxlinkConcept.pdf
Basic  Accountants in|TaxlinkConcept.pdfBasic  Accountants in|TaxlinkConcept.pdf
Basic Accountants in|TaxlinkConcept.pdftaxlinkcpa
 

Recently uploaded (19)

Nicola Mining Inc. Corporate Presentation April 2024
Nicola Mining Inc. Corporate Presentation April 2024Nicola Mining Inc. Corporate Presentation April 2024
Nicola Mining Inc. Corporate Presentation April 2024
 
slideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdfslideshare_2404_presentation materials_en.pdf
slideshare_2404_presentation materials_en.pdf
 
Q1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdfQ1 Quarterly Update - April 16, 2024.pdf
Q1 Quarterly Update - April 16, 2024.pdf
 
WheelTug PLC Pitch Deck | Investor Insights | April 2024
WheelTug PLC Pitch Deck | Investor Insights | April 2024WheelTug PLC Pitch Deck | Investor Insights | April 2024
WheelTug PLC Pitch Deck | Investor Insights | April 2024
 
Best investment platform in india - falcon invoice discounting
Best investment platform in india - falcon invoice discountingBest investment platform in india - falcon invoice discounting
Best investment platform in india - falcon invoice discounting
 
Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024Collective Mining | Corporate Presentation - April 2024
Collective Mining | Corporate Presentation - April 2024
 
the 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdfthe 25 most beautiful words for a loving and lasting relationship.pdf
the 25 most beautiful words for a loving and lasting relationship.pdf
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdf
 
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
Leveraging USDA Rural Development Grants for Community Growth and Sustainabil...
 
Corporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdfCorporate Presentation Probe April 2024.pdf
Corporate Presentation Probe April 2024.pdf
 
9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR
9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR
9654467111 Low Rate Call Girls In Tughlakabad, Delhi NCR
 
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 60009654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
9654467111 Call Girls In Katwaria Sarai Short 1500 Night 6000
 
young call girls in Hauz Khas,🔝 9953056974 🔝 escort Service
young call girls in Hauz Khas,🔝 9953056974 🔝 escort Serviceyoung call girls in Hauz Khas,🔝 9953056974 🔝 escort Service
young call girls in Hauz Khas,🔝 9953056974 🔝 escort Service
 
young call girls in Govindpuri 🔝 9953056974 🔝 Delhi escort Service
young call girls in Govindpuri 🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Govindpuri 🔝 9953056974 🔝 Delhi escort Service
young call girls in Govindpuri 🔝 9953056974 🔝 Delhi escort Service
 
Call Girls in South Ex⎝⎝9953056974⎝⎝ Escort Delhi NCR
Call Girls in South Ex⎝⎝9953056974⎝⎝ Escort Delhi NCRCall Girls in South Ex⎝⎝9953056974⎝⎝ Escort Delhi NCR
Call Girls in South Ex⎝⎝9953056974⎝⎝ Escort Delhi NCR
 
young Call girls in Dwarka sector 1🔝 9953056974 🔝 Delhi escort Service
young Call girls in Dwarka sector 1🔝 9953056974 🔝 Delhi escort Serviceyoung Call girls in Dwarka sector 1🔝 9953056974 🔝 Delhi escort Service
young Call girls in Dwarka sector 1🔝 9953056974 🔝 Delhi escort Service
 
The Concept of Humanity in Islam and its effects at future of humanity
The Concept of Humanity in Islam and its effects at future of humanityThe Concept of Humanity in Islam and its effects at future of humanity
The Concept of Humanity in Islam and its effects at future of humanity
 
Basic Accountants in|TaxlinkConcept.pdf
Basic  Accountants in|TaxlinkConcept.pdfBasic  Accountants in|TaxlinkConcept.pdf
Basic Accountants in|TaxlinkConcept.pdf
 
young call girls in Yamuna Vihar 🔝 9953056974 🔝 Delhi escort Service
young  call girls in   Yamuna Vihar 🔝 9953056974 🔝 Delhi escort Serviceyoung  call girls in   Yamuna Vihar 🔝 9953056974 🔝 Delhi escort Service
young call girls in Yamuna Vihar 🔝 9953056974 🔝 Delhi escort Service
 

Horne 5 Feasibility Study Results

  • 1. THE NEXT GREAT UNDERGROUND MINE IN CANADA HORNE 5 FEASIBILITY STUDY PRESENTATION OCTOBER 16, 2017 WWW.FALCORES.COM | FPC:TSXV
  • 2. Disclaimer This presentation contains a review of the Company’s feasibility study. Viewers are cautioned that the Horne 5 project is at a development stage and that estimates and projections contained herein are based on management’s and consultant’s reasonable assumptions. Therefore, the work results and estimates herein may be considered to be generally indicative only of the nature and quality of the project. No representation or prediction is intended as to the results of future work, nor can there be any promise that the estimates herein will be confirmed by future exploration, development or analysis, or that the project will otherwise prove to be economic. In order to access the Horne 5 deposit, Falco must obtain licenses from the third party owning mining concession CM-156-PTB, which may not be unreasonably withheld, but which may be subject to conditions that the third party may require in its sole discretion. These conditions may include the provision of a performance bond or other assurance to the third party and the indemnification of the third party by Falco. An agreement with the third party stipulates, among other things, that licenses shall be subject to reasonable conditions which may include, among other things, that activities at Horne 5 will be subordinated to the current use of the surface lands and subject to priority, as established in such party’s sole discretion, over such activities. Any license may provide for, among other things, access to and the right to modify and use the infrastructures owned by the third party, including the Quémont #2 shaft (located on mining concession CM-243 also held by such third party) and some specific underground infrastructures in the former Quémont and Horne mines. While Falco believes that it should be able to timely obtain the licenses from the third party, there can be no assurance that any such license will be granted, or if granted will be on terms acceptable to Falco and in a timely manner. The foregoing disclaimer hereby qualifies in its entirety the disclosure contained in this investor presentation. Factors that could cause actual results to differ materially from these forward-looking statements include the reliability of the underlying assumptions used in connection with the feasibility study and those risks set out in Falco's public documents, including in each management discussion and analysis, filed on SEDAR at www.sedar.com. The TSX Venture Exchange has not reviewed and does not accept responsibility for the accuracy or adequacy of this presentation, which has been prepared by management. Past performance is no guarantee of future performance and all investors are urged to consult their investment professionals before making an investment decision. Forward-Looking Statements Certain information included in this presentation constitutes forward-looking statements, including any information as to our projects, plans and future performance. All statements, other than statements of historical fact, are forward-looking statements. The words “expect”, “believe”, “anticipate”, “will”, “intend”, “estimate”, “forecast”, “budget”, “schedule” and similar expressions identify forward-looking statements. Forward-looking statements are necessarily based upon a number of factors and assumptions that, while considered reasonable by management, are inherently subject to significant business, economic and competitive uncertainties and contingencies. Known and unknown factors could cause actual results to differ materially from those projected in the forward-looking statements. Such factors include, but are not limited to: changes to current estimates of mineral resources; labour availability; litigation; availability of and increased costs associated with contractors and equipment; the speculative nature of mineral exploration and development, including the risks of obtaining necessary licenses and permits; contests over title to assets; uncertainty with the Company’s ability to secure capital to execute its business plans; changes in national and local government legislation in Canada; risk of loss due to sabotage and civil disturbances; and business opportunities that may be pursued by the Company. Many of these uncertainties and contingencies can affect our actual results and could cause actual results to differ materially from those expressed or implied in any forward-looking statements made by, or on behalf of, the Company. Readers are cautioned that forward-looking statements are not guarantees of future performance. The Company disclaims any intention or obligation to update or revise any forward-looking statements whether as a result of new information, future events or otherwise, except as required by applicable law. Cautionary Note to U.S Investors Concerning Measured, Indicated and Inferred Resources This presentation uses the terms “measured,” “indicated” and “inferred resources. We advise investors that while those terms are recognized and required by Canadian regulations, the United States Securities and Exchange commission does not recognize them. Under Canadian rules, estimates of inferred mineral resources may not form the basis of feasibility or other economic studies. United States investors are cautioned not to assume that all or any part of measured or indicated mineral resources will ever be converted into mineral reserves. United States investors are also cautioned not to assume that all or any part of an inferred mineral resource exists, or is economically or legally mineable. CAUTIONARY STATEMENT
  • 3. TSXV: FPC | WWW.FALCORES.COM | 3 HORNE 5 PROJECT| FEASIBILITY STUDY RESULTS  HORNE 5 PROJECT FEASIBILITY STUDY COMPLETE  Focus now shifts towards immediate permitting, development and financing  Results confirm the Horne 5 project supports an economically viable, robust, low-grade, high bulk tonnage underground gold mine  Targeted start of construction in 2019, first gold expected in late 2021  Further optimization planned which builds on robust Feasibility Study  HORNE 5 PROJECT IS AMONG THE LARGEST UNDEVELOPED GOLD PROJECTS IN THE WORLD  Proven & Probable Mineral Reserve – 6.13 million oz AuEq (80.9 mt at 2.37 g/t AuEq)  Substantial potential to expand existing resource at depth  LOW ALL-IN SUSTAINING CASH COST  US$399/oz gold AISC (net of by-products) US$721/oz gold-equivalent AISC  US$260/oz gold cash costs (net of by-products) US$632/oz gold-equivalent cash cost  LOW CAPEX INTENSITY PER OUNCE  US$243 per gold ounce (net of by-products) US$158 per gold-equivalent ounce  SIGNIFICANT EXPLORATION POTENTIAL IN ROUYN-NORANDA AND IN THE >67,000 HA OF PROPERTIES  40,000 m drill program initiated on regional exploration camp  HIGHLY CAPABLE AND EXPERIENCED MANAGEMENT TEAM
  • 4. TSXV: FPC | WWW.FALCORES.COM | 4 HORNE 5 PROJECT| FEASIBILITY STUDY HIGHLIGHTS – US$ BASE CASE @ SPOT (10/13/2017) Pre-Tax NPV (5%) & IRR – US$ $1,012 million NPV 18.9% IRR $1,170 million NPV 20.5% IRR Post-Tax NPV (5%) & IRR – US$ $602 million NPV 15.3% IRR $699 million NPV 16.6% IRR Payback Period (after-tax, start of production) 5.6 years 5.2 years Life of Mine Gold Production Recovered 3.3 million ozs gold or 5.1 million ozs gold-eq. Average Annual Metal Production (rounded) 219 koz per year gold 1,752 koz per year silver 67 million lbs per year zinc 16 million lbs per year copper Mine Life (based on reserves) 15 years Base Case Metal Prices and Assumed FX – US$ $1,300/oz Au, $19.50/oz Ag, $1.10/lb Zn, $3.00/lb Cu, CAD:US 0.78 Initial Capital – US$ $802 million LOM Sustaining Capital – US$ $418 million sustaining LOM Cash Costs & AISC (net of by-products) – US$ $260/oz cash costs $399/oz AISC $166/oz cash costs $314/oz AISC LOM Average Process Recovery 88.1% gold, 71.5% silver 72.9% zinc, 75.8% copper Note: All in US$ otherwise noted, assumes CAD:US 1.28
  • 5. TSXV: FPC | WWW.FALCORES.COM | 5 HORNE 5 PROJECT| CASH FLOW PROFILE & SENSITIVITY Note: All in US$ otherwise noted, assumes CAD:US 1.28 Gold Price ($/oz) $1,200 $1,250 $1,300 $1,400 $1,500 $1,600 @ Spot Pre-Tax 5% NPV US$M $822 $917 $1,012 $1,202 $1,392 $1,582 $1,138 After-Tax 5% NPV US$M $485 $544 $602 $718 $831 $944 $680 Pre-Tax IRR 16.6% 17.7% 18.9% 21.0% 23.1% 25.1% 20.5% After-Tax IRR 13.5% 14.4% 15.3% 17.1% 18.7% 20.3% 16.6% Pre-Tax Payback Years 5.7 5.5 5.2 4.8 4.3 4.0 4.8 After-Tax Payback Years 6.1 5.8 5.6 5.2 4.8 4.5 5.2
  • 6. TSXV: FPC | WWW.FALCORES.COM | 6 HORNE 5 PROJECT| OPTIMIZATION & PROJECT POTENTIAL  MINE LIFE EXTENSION  Current mine plan extends only 2,100 metres below surface, potential to reach deeper depths  HG_F zone in Inferred Resources and not included in Feasibility holds 2.8 M tonnes at 3.38 Au g/t  Inclusion of additional Mineral Resources currently not included in the mine plan  40,000 m drill program initiated on regional exploration camp could surface satellite deposits  MINE PLAN OPTIMIZATION  Potential to improve cash flow, with further mine plan sequencing  Life of mine can be increased with additional testing to include remaining tonnes (M&I over 90Mt)  PROCESSING OPTIMIZATION  Additional testing is ongoing for new flotation technology to improve metal recovery and achieve cleaner concentrate (Woodgrove)  WATER TREATMENT OPTIMIZATION  Recent test works show lower lime content necessary for treatment, hence reducing mud generation and treatment cost  Use of water by a third party option still a viable option
  • 7. TSXV: FPC | WWW.FALCORES.COM | 7 HORNE 5 PROJECT| BENEFITS TO STAKEHOLDERS  HORNE 5 EXPECTS TO BE A SIGNIFICANT EMPLOYER IN THE ROUYN-NORANDA REGION, CREATING LONG TERM EMPLOYMENT  Peak employment during construction estimated at approximately 800  Approximately 500 employees are estimated to be required for operations  Training for semi-skilled and skilled sustainable positions  Additional indirect jobs created with suppliers, services, etc. to support mine operations  LOCAL AND REGIONAL INFRASTRUCTURE INVESTMENT  New school to be built in the centre of Rouyn-Noranda – C$22.5 million investment  CONTINUED COMMITMENT TO COMMUNITY INVESTMENT PROGRAMS  ECONOMIC BENEFITS ESTIMATED AT $6.6 BILLION BASED ON $1,300 PER OZ AU, LIFE OF MINE ROYALTIES & TAXES Note: All in US$ otherwise noted, assumes CAD:US 1.28
  • 8. TSXV: FPC | WWW.FALCORES.COM | 8 FEASIBILITY STUDY DETAILS
  • 9. TSXV: FPC | WWW.FALCORES.COM | 9 HORNE 5 PROJECT| LOCATION  Located in Rouyn-Noranda, Québec, Canada  Access to better & experienced miners due to better work-life balance & conditions  Eliminates the need for a camp  Experienced labour pool  The region of Abitibi produces some of the most experienced miners in the world  Strong presence of experienced mine and technical staff  Experienced suppliers  Access to tier 1 mining equipment suppliers & mining contractors in the world  ~80% of required suppliers & contractors located within 1 hour from project  Québec Government  Strong supporter of the mining industry  Clear permitting process & BAPE process  Great infrastructure  Rail & highway access  Affordable and reliable power source HORNE 5 MONTREAL
  • 10. TSXV: FPC | WWW.FALCORES.COM | 10 HORNE 5 PROJECT| MINERALIZATION  The Horne Mine orebodies (Upper H, Lower H and Horne 5 deposit)  Dip subvertically within rhyolitic flows, breccias, and tuffs that are bounded by the Andesite and the Horne Creek faults.  Least-altered rhyolites have low K2O contents and other geochemical features that place them within the FII tholeiitic series (Lesher et al., 1986)  Graded volcaniclastic beds, metal zoning in the orebodies, and locations of chloritized- mineralized rhyolites indicate that the volcanic sequence youngs to the north.  The volcanics in the fault wedge are variably silicified and sericitized, and local zones in the orebody sidewalls and footwall are chloritized  The Horne Block lies between the Horne Creek Fault and the Andesite Fault
  • 11. TSXV: FPC | WWW.FALCORES.COM | 11 HORNE 5 PROJECT| MINERAL RESERVES & RESOURCES PROVEN & PROBABLE MEASURED & INDICATED + INFERRED (at C$55 NSR cut-off) Resource Class Tonnes (mm) Au Equivalent g/t Au g/t Ag g/t Cu % Zn % Contained Au EQ (000 oz) Contained Au (000 oz) Contained Ag (000 oz) Contained Cu (mm lbs) Contained Zn (mm lbs) Measured 9.3 2.59 1.58 16.20 0.19 0.83 770 470 4,824 38.0 168.5 Indicated 81.9 2.56 1.55 14.74 0.18 0.89 6,731 4,070 38,796 325.4 1,599.3 Total M&I 91.2 2.56 1.55 14.89 0.18 0.88 7,501 4,540 43,620 363.4 1,767.8 Inferred 21.5 2.51 1.44 23.04 0.20 0.71 1,736 1,000 15,925 96.3 337.2 Tonnes (mm) Au Equivalent g/t Au g/t Ag g/t Cu % Zn % Contained Au EQ (000 oz) Contained Au (000 oz) Contained Ag (000 oz) Contained Cu (mm lbs) Contained Zn (mm lbs) Proven 8.4 2.35 1.41 15.75 0.17 0.75 614 368 4,115 31.5 138.9 Probable 72.5 2.37 1.44 13.98 0.17 0.78 5,347 3,247 31,525 271.7 17.6 Total P&P 80.9 2.37 1.44 14.14 0.17 0.77 5,961 3,616 35,640 303.2 156.5 Please refer to appendix for Mineral Reserve and Resource notes
  • 12. TSXV: FPC | WWW.FALCORES.COM | 12 HORNE 5 PROJECT| MINE DESIGN HORNE 5 PROJECT FEASIBILITY 16 M AuEq Oz Produced 7.1 M AuEq Oz M&I4 1.7 M AuEq Oz Inferred  Mine throughput  15,790 tpd average at steady-state  With peak throughput at 16,000 tpd in first 5 years  Mining method  Transverse long-hole stoping  Phase 1 – Stope size 40m X 25m X 20m (~69,000 t per stope, 83 stopes per year)  Production drilling in ore at 6.5 inches  Primary – secondary stope mining sequencing  Stope paste backfill to ensure stability  Below 3% dilution  95% ore recovery  Quemont Shaft  Use of existing 1,200 metre shaft  Dewatering of old workings required  11 million cubic meters  Environmentally-friendly disposal of sludges and tailings in dewatered workings and in production stopes
  • 13. TSXV: FPC | WWW.FALCORES.COM | 13 HORNE 5 PROJECT| MINING APPROACH FOR FEASIBILITY >17 YEARS OF LIFE  Phase 1: 2021 –2028  43.2Mt  15,700tpd  Phase 2: 2029 –2035  37.7Mt  15,300tpd  Dewatering Phase (25 months)  Rehab Shaft  Build barricades  Establish Ventilation  Horizontal Dev. = 4,000m  Vertical Dev. = 2,000m (not depth)  Construction (18 months)  Access Ore Deposit  Construct Ore Handling System  Develop levels for start of production  Horizontal Dev. = 17,500m  Vertical Dev. = 2,500m (not depth) PHASE 2 EXISTING SHAFT  PHASE 1
  • 14. TSXV: FPC | WWW.FALCORES.COM | 14 HORNE 5 PROJECT| HIGH LEVEL OF AUTOMATION  STATE-OF-THE-ART OPERATION  Surface control underground operations:  Hoist – production and services  Teleoperation of loaders  Monitoring and management of ventilation requirements and paste backfill distribution  Water pumping monitoring  Staff & equipment location monitoring  HIGH CAPACITY PRODUCTION MINING EQUIPMENT  Scoop tram: 21 metric tonnes  Haulage truck: 50 metric tonnes  Conveyor system from deposit to Quemont shaft  Ability to operate between working shifts (20h/day vs 14h/day for a conventional mine)
  • 15. TSXV: FPC | WWW.FALCORES.COM | 15 HORNE 5 PROJECT| PROCESS FLOW SHEET  Semi-Autogenous-Ball milling-Crushing  15,790 tpd facility  92% of mill availability  Flotation & thickening section divided in three circuits dedicated to recovering copper, zinc and pyrite concentrates  Pyrite concentrate will require a finer grind to achieve improved gold recovery by cyanide leaching/CIP  Paste Backfill Capacity  60% paste backfill plant availability  Cyanide destruction circuit  Process Products  16% Copper concentrate (+/- 130 tpd)  52% Zinc concentrate (+/- 200 tpd)  Ag-Au ingot  Stockpile live capacity is 12 hours. (8,000 t)
  • 16. TSXV: FPC | WWW.FALCORES.COM | 16 HORNE 5 PROJECT| LIFE OF MINE GOLD PRODUCTION LIFE OF MINE  Contained gold: 3.7 mm ozs  Recovered gold: 3.3 mm ozs  Annual gold production: 219,000 ozs  Steady-state production: 234,000 ozs  Head Grade:  Gold equivalent : 2.37 g/t  Gold : 1.44 g/t  Peak Year Production (2030-2034)  5 year avg. : 254,000 gold ozs  Peak in 2031 : 268,000 gold ozs  Grade improves as the production reaches the deeper portions of the Horne 5 deposit  HG_F zones currently in Inferred Resources and not included in Feasibility holds 2.8 million tonnes at 3.38 Au g/t  Gold equivalent production metrics  338,000 AuEq ounces per year  5.1 mm AuEq recovered ounces
  • 17. TSXV: FPC | WWW.FALCORES.COM | 17 HORNE 5 PROJECT| OPERATING COSTS – C$ per tonne Cash Cost (C$/tonne) 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 Mining $14.99 $11.91 $12.22 $12.03 $11.97 $12.27 $12.14 $12.12 $12.94 $13.39 Processing $20.66 $20.63 $20.40 $20.42 $20.30 $20.33 $20.72 $20.16 $20.51 $20.51 Tailings and Water $4.62 $4.02 $5.17 $5.16 $5.29 $5.24 $5.27 $5.07 $5.07 $5.06 G&A $2.41 $2.74 $2.76 $2.74 $2.75 $2.75 $2.90 $2.83 $2.81 $2.78 Total Per Tonne Cost $42.68 $39.30 $40.56 $40.36 $40.32 $40.58 $41.03 $40.19 $41.33 $41.75 Ore Milled (000 tonnes) 2,774 5,867 5,821 5,852 5,828 5,842 5,527 5,673 5,721 5,775
  • 18. TSXV: FPC | WWW.FALCORES.COM | 18 $0 $500 $1,000 $1,500 $2,000 $2,500 2016 Gold Mine, Composite, Total Cash + Sustaining Capex Cost Grouped By Mine and Ranked By Total Cash plus Sustaining Capex 0 500 1000 1500 2000 Paid Gold (t) Horne 5 Project AISC of US$399/oz Mining $241 Processing $392 Tailings and Water $97 G&A $55 Smelting and Refining $150 Royalties $37 By-Product Credit ($710) Sustaining $127 Closure $10 Total AISC $399 Pre-Production Cost $243 All-In Costs $643 Cash Cost Summary Source: Wood Mackenzie Ltd. and BMO Capital Markets Note: Amounts may vary du to rounding • All-in Sustaining Costs are presented as defined by the World Gold Council ("WGC") less Corporate G&A • All-in Costs are represented as: (AISC + Capital Costs) / total gold recoverable ounce HORNE 5 PROJECT| LOW ALL-IN SUSTAINING COST, A TOP QUARTILE ASSET 2016 Gold AISC Cost Curve 0
  • 19. TSXV: FPC | WWW.FALCORES.COM | 19 HORNE 5 PROJECT | RELOCATION PROGRAM  Memorandum of Understanding with the Commission scolaire de Rouyn-Noranda  Relocation and construction costs are estimated at $22.5 million  Work has already been initiated  Falco will be the prime contractor
  • 20. TSXV: FPC | WWW.FALCORES.COM | 20 HORNE 5 PROJECT| ENVIRONMENT, PERMITTING AND SITE RESTORATION Environmental Plan and Permitting:  Environmental baseline studies were initiated in 2016  Continued throughout 2017 to support the permitting process and the project timeline  Project will require a provincial decree and federal authorisations  Project is subject to a provincial impact assessment, including public hearings, as forecasted production is over the 2,000 tpd threshold outlined in the applicable regulation  Project will also be subject to a federal impact assessment study  Horne 5 Project EIA expected to be submitted in Q4 2017 Dewatering Program:  The Company has submitted an application for a certificate of authorization under Sections 22 and 31.75 of the Environmental Quality Act to be issued by the Ministry of Sustainable Development, Environment and the Fight against Climate Change, to support the dewatering and sludge management strategy  During the dewatering stage, which is expected to last 25 months, high density sludge from the water treatment will be stored in the old Donalda and Quemont underground mine openings During Operations:  Tailings produced will be stored in old underground openings either in the form of slurry or paste backfill during the first two years of operations  Paste backfill will continue to be produced throughout the entire life of mine  The remainder of the tailings produced will be stored at surface in a tailings management facility  Identified an old tailings management facility located approximately 11 km from the project Site Restoration:  Site restoration costs were estimated at $68 million
  • 21. TSXV: FPC | WWW.FALCORES.COM | 21 HORNE 5 PROJECT| CAPITAL COST TOTAL PRE-PRODUCTION CAPITAL COSTS US$802M Note: Amounts may vary due to rounding.
  • 22. TSXV: FPC | WWW.FALCORES.COM | 22 HORNE 5 PROJECT| FEASIBILITY – SURFACE
  • 23. TSXV: FPC | WWW.FALCORES.COM | 23 HORNE 5 PROJECT| FINANCING ALTERNATIVES Project Financing Alternatives:  Strong support from several Quebec funds and governmental institutions  Strong equity support from various funds  Large available pools of capital to support mining development in the province  Strong support from Osisko Gold Royalties  Existing equity holder  Technical service agreement in place  Existing right to buy and structure stream as part of the overall project financing  Strong support from existing shareholders and investors  Several longstanding relationships have supported the Osisko group for many years  Strong appetite for mining project debt financing  Current market dynamic is favourable to builders  Existing relationships with Export Credit Agencies
  • 24. TSXV: FPC | WWW.FALCORES.COM | 24 HORNE 5 PROJECT| FROM PEA TO FEASIBILITY FEASIBILITY PEA Change Pre-Tax NPV (5%) – US$ $1,012 million NPV $848 million NPV 19% IRR 18.9% IRR 20.0% IRR (6%) Post-Tax NPV (5%) – US$ $602 million NPV $500 million NPV 20% IRR 15.3% IRR 16.0% IRR (4%) Payback Period (after-tax) 5.6 years 4.1 years +1.5 years Life of Mine Gold Production 3.3 million oz gold 2.9 million oz gold 13% Mine Life 15 years 12 years +3 years Initial Capital $802 $680 18% Sustaining Capital (million) $418 $283 47% Closure Cost (million, net of salvage value) $33 $30 11% FX Adjusted Metals Prices and FX Assumed Gold $1,300/Au oz $1,250/Au oz +$50/Au oz -$3/Au oz Silver $19.50/Ag oz $17.00/Ag oz +$2.50/Ag oz +$2.29/Ag oz Copper $3.00/Cu lb $2.85/Cu lb +$0.15/Cu lb +$0.04/Cu lb Zinc $1.10/Zn lb $1.00/Zn lb +$0.10/Zn lb +$0.07/Zn lb FX 1.28 1.33 -$0.05 LIFE OF MINE METRICS Annual Production Gold 219 koz 236 koz (7%) Silver 1,752 koz 1,931 koz (9%) Copper 16 mm lbs 16 mm lbs 0% Zinc 67 mm lbs 65 mm lbs 3% Operating Cost per tonne (C$/t) C$41.00/ tonne C$47.50/ tonne (14%) Cash Cost per gold ounce $260/ Au oz $237/ Au oz 10% AISC per gold ounce $399/ Au oz $427/ Au oz (6%) All-In Cost per gold ounce (CAPEX+OPEX) $643/ Au oz $660/ Au oz (3%) Recovery Gold 88.1% 86.8% 1% Silver 71.5% 74.9% (5%) Copper 75.8% 74.0% 2% Zinc 72.9% 67.3% 8%
  • 25. TSXV: FPC | WWW.FALCORES.COM | 25 HORNE 5 PROJECT|COMPARABLE FEASIBILITIES & CONSTRUCTION PROJECTS Abitibi Belt Ecuador Nunavut Nunavut Goldex La Ronde 2 Young- Davidson Horne 5 Fruta del Norte Meliadine 1.0 Meliadine 2.0 Operator Agnico Eagle Agnico Eagle Northgate Falco Lundin Gold Agnico Eagle Agnico Eagle Feasibility Study Year 2005 2006 2010 2017 2016 2015 2016 Gold Price per ounce (US$) $400 $450 $825 $1,300 $1,250 $1,300 $1,200 FX 1.30 1.25 1.11 1.28 n/a 1.15 1.25 After-Tax IRR * 15.0% IRR 13.3% IRR 10.3% IRR 15.3% IRR 15.7% IRR 10.3% IRR n/a Annual Production (Au ozs) * 170,000 320,000 180,000 219,000 340,000 349,000 390,000 CAPEX (US$ million) * $135.0 $210.0 $339.4 $802.0 $669.0 $911.0 $900.0 Cash Cost per ounce (US$) * $205 $230 $351 $260 $553 $531 $590 Operating Cost per tonne (C$) * C$16.97 C$67.00 C$31.63 C$41.00 n/a C$139.00 C$160.00 Life of Mine * 10 Years 10 Years 15 Years 15 Years 13 Years 9 Years 14 Years Payback * 6 Years n/a 6.9 Years 5.6 Years 4.5 Years 5 Years n/a Tax Pool or Sunk Cost (US$M) * $600.0 $600.0 $50.5 $28.9 $430.0 $252.0 $447.0 In Operation    2021 2020 2020 2019 Canadian Development Projects – High Level of Attractiveness  Strong operators looking for long mine lives  With long mine lives a single bull cycle will pay back the operation multiple times  Canadian projects support lower IRRs  Talented labour pool  Experienced contractors and mine builders  Great infrastructure  Safe geopolitical profile * At the time of feasibility report, reported in press release, technical reports and financial statements
  • 26. TSXV: FPC | WWW.FALCORES.COM | 26 Source: Company website, technical reports and filings from SEDAR HORNE 5 PROJECT|COMPARABLE OPERATIONS – CURRENT Goldex D Zone (Agnico Eagle) Young-Davidson (Alamos) La Ronde 2 (Agnico Eagle) Horne 5 PEA (Falco) Horne 5 Feasibility (Falco) Resource Grade (g/t AuEq) 1.69 2.69 5.1 2.9 2.6 Mining Method Long hole Transverse long hole Long. Retreat / Tr. Open Stoping Transverse long hole Transverse long hole Depth (m) 670 - 1,200 750 - 1,500 2,000-3,000 600 – 2,300 600 – 1,800 Stope Size 22 x 30 x 50 12-40 x 20 x 30 5-25 x 15 x 30 38 x 15 x 15 P1: 40 x 20 x25 Mining Rate 6,800 tpd 8,000 tpd 7,200 tpd 15,000 tpd P1: 16,000 tpd Specific Gravity 2.8 2.69 3.3 3.45 3.45 Mining Dilution 15% 10% 10%-20% < 4% < 3% Operating Cost/NSR C$35-37/t * C$53.50/t * C$95/t C$47.50/t C$41.00/t Annual Production (koz) 113,300 * 200,000 * 230,000 * 236,000* 219,000 IRR ** 15.0% IRR 10.3% IRR 13.3% IRR 16.0% IRR 15.3% IRR * Projected life-of-mine (LOM) and 2017-2019 average for Goldex ** Last available public filings
  • 27. TSXV: FPC | WWW.FALCORES.COM | 27 ACTIVITIES START COMPLETION PEA COMPLETED Feasibility Study COMPLETED Environmental Impact assessment Q2 2016 Q4 2017 Mine Dewatering Q2 2018 Q2 2020 Detailed engineering Q4 2017 Q2 2020 Head frame and hoist construction (Exploration Phase) Q4 2017 Q3 2018 Public audiences – “BAPE” Q4 2018 Q1 2019 Permits for project construction Q2 2019 Processing plant construction Mid 2019 Q1 2021 First mineralized ore in mine Q2 2021 End of process plant construction / plant commissioning H1 2021 Production achieved in mine (Phase 1) H2 2021 Process plant ramp up H2 2021 Full Commercial Production H1 2022 HORNE 5 PROJECT| PROJECT SCHEDULE
  • 28. TSXV: FPC | WWW.FALCORES.COM | 28 EV / RESOURCES (US$/OZ AU EQ.) MARKET CAP. (US$ MM) IN PRODUCTION OR ACQUIRED 1. Acquisition Multiple Source: Company websites, filings from SEDAR and Factset COMPARABLES – PRE-PRODUCTION > 5 M OZS & CAPEX BELOW $1BN
  • 29. TSXV: FPC | WWW.FALCORES.COM | 29 ALL-IN SUSTAINING CASH COST (US$/OZ AU) LIFE OF MINE (YEARS) Source: Company websites, filings from SEDAR and Factset IN PRODUCTION OR ACQUIRED RESERVES COMPARABLES – PRE-PRODUCTION > 5 M OZS & CAPEX BELOW $1BN
  • 30. TSXV: FPC | WWW.FALCORES.COM | 30 HORNE 5 PROJECT| DEEP EXPLORATION POTENTIAL (VS. LA RONDE VMS) 3,000 M HG_F zone (Inferred) not included in Feasibility holds: 2.8 m tonnes at 3.38 Au g/t VS. current Feasibility diluted grade of 1.44 Au g/t 1,000 M 2,000 M Horne 5 Project La Ronde Complex (Agnico Eagle) Source: Company websites
  • 31. TSXV: FPC | WWW.FALCORES.COM | 31 EXPERIENCED SENIOR LEADERSHIP TEAM  Luc Lessard, President & CEO, Director   Vincent Metcalfe, CFO  Claude Léveillée, VP Community Relations & HR  Anthony Glavac, VP – Controller  Helene Cartier, VP – Environment   Francois Vezina, VP – Mining   Christian Laroche, VP – Processing   John-Paul McGrath – Project Manager   Claude Bernier, Exploration Manager  Sylvain Doire, Environment  Claude Pilote, Senior Geologist  Daniel Mathieu – Mechanical Design  EXECUTIVE MANAGEMENT BOARD OF DIRECTORS  Sean Roosen, Chair   Mario Caron, Lead Director  Bryan Coates   Paola Farnesi  Claude Ferron  Paul Henri-Girard  Chantal Sorel  Denotes former member of Canadian Malartic development, construction and operating team
  • 32. TSXV: FPC | WWW.FALCORES.COM | 32 CAPITAL SUMMARY & SHAREHOLDER REGISTRY SHAREHOLDER REGISTRY Osisko Gold Royalties 13.2% Tocqueville 9.2% Government of Quebec 5.2% Oppenheimer Funds 2.0% Old Mutual 1.6% RBIM 1.1% CIBC Asset Management 1.0% Caisse de Depot du Quebec 1.0% Shares Outstanding (basic) 180,145,244 Stock Options 8,651,260 Warrants 28,631,717 Shares Outstanding (fully diluted) 217,428,221 Share Price C$1.24 Market Capitalization C$223.4 Cash Position ~C$42.6 Million CAPITAL STRUCTURE (AS OF OCT 13, 2017) Source: Factset, Bloomberg, public filings and Company estimates
  • 33. TSXV: FPC | WWW.FALCORES.COM | 33 FALCO RESOURCES| CLOSING THOUGHTS OBSERVATION: WHAT IS LEFT IN THE ABITIBI 10 YEARS FROM NOW?  Dearth of sizable gold projects in the Abitibi 10 years from now HORNE 5 PROJECT:  Long-life Project & Low AISC: >15 years of life with upside & < $399/Au Oz AISC  State-of-the-art project: A true mine of the future  Strong Exploration Upside  Ideal location: Infrastructure & Strong Labour Pool + Strong Government Support  Strong & Experienced Team to Advance the Project
  • 34. TSXV: FPC | WWW.FALCORES.COM | 34 Head Office Falco Resources Ltd. 1100, avenue des Canadiens-de-Montréal Bureau 300 Montréal, QC H3B 2S2 Tél. : +1.514.905.3162 Toll Free : +1.888.915.2009 Courriel : info@falcores.com Investor Inquiries Vincent Metcalfe, CFO Tel: +1.514.905.3162 Email: vmetcalfe@falcores.com CONTACT US
  • 35. TSXV: FPC | WWW.FALCORES.COM | 35 APPENDIX Appendix A – Additional Information Appendix B – Resource & Modeling Notes
  • 36. TSXV: FPC | WWW.FALCORES.COM | 36 600m HORNEQUEMONT  Exceptional Drill Density  4,384 underground drill holes at 15 m spacing (305,788m) drilled by Noranda  Very high confidence in historical drilling  Great upside at Depth – limited drilling vs. upper area HORNE 5 PROJECT | HISTORICAL DRILL DENSITY
  • 37. TSXV: FPC | WWW.FALCORES.COM | 37 HORNE 5 PROJECT | CURRENT MINERAL ENVELOPS
  • 38. TSXV: FPC | WWW.FALCORES.COM | 38 HOISTING | FS HOISTING & SHAFT
  • 39. TSXV: FPC | WWW.FALCORES.COM | 39 PROCESSING | SAG & Ball Mill with Cyclone Cluster
  • 40. TSXV: FPC | WWW.FALCORES.COM | 40 PROCESSING | Overall Flotation Tank
  • 41. TSXV: FPC | WWW.FALCORES.COM | 41 PROCESSING | Regrind Mill
  • 42. TSXV: FPC | WWW.FALCORES.COM | 42 PROCESSING | Carbon in Pulp
  • 43. TSXV: FPC | WWW.FALCORES.COM | 43 HORNE 5 PROJECT| Mining Fleet UNDERGROUND MOBILE EQUIPMENT Item Total Scoop 17 Tons 3 Scoop 17 Tons (Spare) 1 Mine Truck 60 Tons 4 Jumbo 2 Booms Automated 4 Bolting Machine 4 Bolting Machine Spare 1 Scoop 21 Tons 4 Scoop 21 Tons (Spare) 1 Mine Truck 60 Tons (Phase 3) 2 Production Drill Automated 4 Production Drill Automated (Spare) 1 Cable Drill + Bolt 2 Shotcrete Machine (wet) 2 REMOTELY CONTROLLED FROM SURFACE
  • 44. TSXV: FPC | WWW.FALCORES.COM | 44 Project Potash Corp Ukraine KJRK Phase 1 Ukraine KJRK Phase 2 Horne 5 Phase 1 Horne 5 Phase 2 Depth (m) 1,200 1,340 1,800 1,200 1,800 Speed (m/s) 18-20 19 19 18 18 Operating Hours 19-20 22 22 19 19 Skip capacity (t) 40-65 50 50 43 39.4 Productivity (tpd) 25,000-30,000 22,050 17,640 23,200 16,550 HORNE 5 PROJECT| HOISTING COMPARABLES 43T SKIP – Similar to Horne 5 Sizing
  • 45. TSXV: FPC | WWW.FALCORES.COM | 45 Appendix B – Mineral Resource Estimates & Modeling Notes 1. The effective date of the mineral resource estimate is July 25, 2017. The Independent QP for the Mineral Resource Estimate as required by National Instrument 43 101 is Carl Pelletier, P. Geo., B.Sc., employee of InnovExplo. 2. Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability. 3. While the results are presented undiluted and in situ, the reported mineral resources are considered by the QP to have reasonable prospects for economic extraction. 4. These estimates include six low-grade gold-bearing mineralized envelopes. 5. The main low-grade gold-bearing mineralized envelope includes six high-grade gold-bearing zones, one high-grade copper-bearing zone, one high grade zinc-bearing zone, and three high-grade silver-bearing zones. Note that these high-grade zones may overlap each other. 6. Mineral resources were compiled at NSR cut-offs of (in C$) $40, $45, $50, $55, $60, $65, $70, $75, $80, $85, $90, $95 and $100 per tonne for sensitivity purposes. 7. The official base case mineral resource is reported at a $55 per tonne NSR cut-off. 8. The appropriate NSR cut-off will vary depending on prevailing economic and operational parameters to be determined. 9. NSR estimates are based on the following assumptions: Exchange rate of C$1.00 /0.78 US$; Metal prices as follows: gold $1,300/oz, silver $19.50, copper $2.90/lb, zinc $1.10/lb (inspired from a long-term analyst consensus price forecast study); Net recoveries are variable in function of grade of each commodity. Smelting cost (including transportation) of C$6.52 per tonne (based on the cost mine service, as well as a non-public smelter contract obtained from one of the proposed destinations and talks with transport providers). 10. Gold equivalent calculations assume these same metal prices. 11. Inferred Mineral Resources are separate from Indicated Mineral Resources. 12. The quantity and grade of reported Inferred Mineral Resources are uncertain in nature and there has not been sufficient work to define these Inferred Mineral Resources as Indicated or Measured Mineral Resources. It is uncertain if further work will result in upgrading them to an Indicated or Measured mineral resource category. 13. The mineral resource was estimated using Geovia GEMS 6.8. The estimate is based on 5,980 diamond drill holes (483,254 m) of which 4,141 cut mineralized zones for a total of 178,150 m of core within these zones. For silver, the estimate also uses the results of an exhaustive metallurgical test comprising 2,112 diamond drill holes assayed for silver over a total length of 75,540 metres. A minimum true thickness of 7.0 m was applied, using the grade of the adjacent material when assayed, or a value of zero when not assayed. Only the silver interpolation in the Inferred mineral resources does not use the material when not assayed. 14. The estimate database also contains 14,799 channel samples for a total of 23,791 m from historically sampled drifts. Channel sample data was only used for distance to composite criterion for mineral resource classification purposes. 15. 91% of density values were estimated using historical iron assay drill hole data and Falco density data for an average of 3.41 g/cm3. The interpolation method uses three passes for the ENV_A and HG_A to HG_F zones. 8% of the density values were fixed at 2.88 g/cm3 for ENV_B to ENV_E due to the scarcity of the data. 2.88 g/cm3 represents the median of the available data. 1% of density values were fixed at 2.67 g/cm3 for ENV_F due to the scarcity of the data and to adequately characterize this quartz-rich zone. 16. Compositing was done on drill hole sections falling within the mineralized zones (composite = 3.0 m). Tails shorter than 0.75 m were not generated. 17. Mineral resources were evaluated from drill holes using an ID2 interpolation method in a block model (block size = 5 x 5 x 5 m). 18. High-grade capping was done on raw assay data and established on a per zone basis for gold (Au g/t): (HG_A: 35; HG_B: 35; HG_C: 25; HG_D: 35; HG_E: 25; HG_F: 35; ENV_A: 35; ENV_B: 25; ENV_C: 25; ENV_D: 20; ENV_E: 35; ENV_F: 25) and for silver (Ag g/t): SG_HG:100; HG_D: 165; HG_F: 165; ENV_A_SG_Low: 110; ENV_B: 100; ENV_C: 100; ENV_D: 100. Capping grade selection is supported by statistical analysis. No capping was applied to the Cu and Zn data based on statistical analysis. 19. The reported Mineral Resources are categorized as Measured, Indicated and Inferred. The Inferred category is only defined within the areas where blocks were interpolated during pass 1 or pass 2 in areas where continuity is sufficient to avoid isolated blocks. The Indicated category is only defined by blocks interpolated in areas where the maximum distance to the closest drill hole composite is less than 25 m for blocks interpolated in passes 1 and 2. The Measured category is only defined by blocks classified as Indicated and within sufficient proximity to sampled drifts (< 15m). The average distance to the nearest composite is 6.97 m for the Measured mineral resources, 10.01 m for the Indicated mineral resources and 40.10 m for the Inferred mineral resources. 20. Tonnage estimates were rounded to the nearest hundred tonnes. Any discrepancies in the totals are due to rounding effects. Rounding practice follows the recommendations set forth in Form 43-101F1. 21. CIM definitions and guidelines were followed in estimating mineral resources. 22. InnovExplo is not aware of any known environmental, permitting, legal, title-related, taxation, socio-political, marketing or other relevant issue that could materially affect the mineral resource estimate. 23. Metal contained in ounces (troy) = metric tonnes x grade / 31.10348. Calculations used metric units (metres, tonnes and g/t). Metal contents are presented in ounces and pounds. RESOURCE ESTIMATE NOTES
  • 46. TSXV: FPC | WWW.FALCORES.COM | 46 Appendix B – Mineral Reserve Estimates Notes 1. The QP, as defined below, for the Mineral Reserve estimate is Mr. Patrick Frenette (InnovExplo). 2. Estimated at $2.15/lb Cu, $1.00/lb Zn, $1,300/oz Au and $18.50/oz Ag, using an exchange rate of C$1.00:US$0.77, cut-off NSR value of C$55.00/t. Metallurgical recoveries and other parameters for the November 2016 MRE are shown in Chapter 6 of the Feasibility Study. 3. Mineral Reserve tonnage and mined metal have been rounded to reflect the accuracy of the estimate and numbers may not add due to rounding. 4. Mineral Reserves presented include both internal and external dilution along with mining recovery. The external dilution is estimated to be 2.3%. The mining recovery factor was set at 95% to account for mineralized material left in the margins of the deposit in each block. RESERVE ESTIMATE NOTES