Final Class Presentation on Project Audit and Closure.ppt
24 Mar 2023•0 j'aime
0 j'aime
Soyez le premier à aimer ceci
afficher plus
•7 vues
vues
Nombre de vues
0
Sur Slideshare
0
À partir des intégrations
0
Nombre d'intégrations
0
Télécharger pour lire hors ligne
Signaler
Formation
Project auditing can be defined as the process of detailed inspection of the management of a project, its methodology, its techniques, its procedures, its documents, its properties, its budgets, its expenses and its level of completion.
To understand the process
of project audit
To recognize the value of
an audit to project
management
To determine when to
terminate a project
To identify various reasons
why a project is terminated
To identify checklist
Objectives
What is an audit?
Management
Methodology and
procedures
Records
Properties
Budgets and
expenditures
Degree of completion
Project
Audit
1. Evaluate if the project
delivered the expected benefits
to all stakeholders.
Was the project managed
well?
Was the customer satisfied?
2. Assess what was done wrong
and what contributed to
successes.
3. Identify changes to improve
the delivery of future projects.
Project
Audit
Tasks
Actual vs. planned
Schedule changes
Nature of changes
Progress of specific
tasks
Potential of failure
Lessons learned
Data assumptions
Project
Audit
Report
1.Does the work actually completed
match the planned level of
completion?
2.Are significant schedule changes
likely? If so, indicate the nature of
changes.
3.What progress has been made on
tasks that could decide the success
or failure of project?
4.What is the potential for project
failure or monetary loss?
Project
Audit
Report
cont.
5. What lessons learned from the
project being audited can be
applied to other projects being
undertaken by organization?
6. What assumptions or limitations
affect data in audit?
7. First audit should be done early
and focused on technical issues.
From then on audits may be done
after major milestones (important
to team). An audit at the end
would be value to parent
organization.
Project
Audit
Report
cont.
Audit Life Cycle
Preliminary Analysis = compares
gathered information to standards
and judges project performance
Report preparation = preparing
audit report and recommendations
for improvement
Termination = review of audit
process and recommendations for
improvement
NB: Project audit is not like a financial
audit. A financial audit is limited in
scope and focuses of organization’s
assets while a project audit is broader in
scope and either deals with whole,
partial, or individual component of
project.
Audit Initiation = id.
Purpose and scope of audit
and determination of
methodology. Team should
have access to all records
and reports.
Baseline = performance
standards
Database = accumulation
of information
Project
Closure
Close-out Plan:
Questions to be Asked
What tasks are required
to close the project?
Who will be responsible
for these tasks?
When will closure begin
and end?
How will the project be
delivered?
1. Getting delivery acceptance
from the customer.
2. Shutting down resources and
releasing to new uses.
3. Reassigning project team
members.
4. Closing accounts and seeing all
bills are paid.
5. Evaluating the project team,
project team members, and
the project manager.
Closure
Ensure completion of work
Notify essential contacts of project
completion
Ensure documentation is complete
Clear final billings and oversee
preparation of final invoices,
paperwork, etc.
Redistribute resources
Ensure proper storage and
distribution of documents
Ascertain product support
requirements
Oversee closing of project
notebook and other books
Primary
Duties of
Project
Leader