SlideShare a Scribd company logo
1 of 7
Download to read offline
Construction Tips
                                           • cordless drill and drill bits (plus

H        oop house construction can be
         as exacting or casual as you
         like. However, not paying
attention to initial details can cost
                                             spares) for the various size
                                             fasteners you plan to use;
                                           • good step ladder;
                                                                                      confidence whenever you are ready.
                                                                                      There is nothing worse than grabbing
                                                                                      an hour here or there to work on a
                                                                                      high tunnel only to find that someone
extra time in the long run, and the        • socket set;                              bumped the stake and all your work is
resulting structure may not look as        • drift punch or pipe wrench;              now out of line.
nice or stand as long.                     • miter saw or circular saw;
                                           • speed square;                            Ground Posts
Two people with good construction                                                     As farmers, we are striving for a
                                           • hacksaw or saws-all;
skills can erect a 30' x 96' high tunnel                                              loose, well-structured soil in which to
                                           • power cord; and
in about a week. The 75 to 100 hour                                                   grow our plants. But we need a
                                           • tape measures (12', 25', and 100').
estimated completion time assumes                                                     medium with the opposite
that all materials are on site. Setting                                               characteristics to support a building.
                                           An experienced high tunnel builder
up the metal frame, installing                                                        (If you have concerns about your site
                                           advises: “a cordless drill (preferably
baseboards and hipboards, roll-up                                                     and its ability to support a high tunnel,
                                           one with ample batteries) will be your
sides, and building endwalls are                                                      check with a qualified professional.)
                                           best friend for fastening those millions
included. Additional time will be
                                           of quarter inch bolts and nuts.”
required for site preparation, utility                                                A high tunnel’s foundation is
installation and covering the tunnel                                                  provided by ground posts, which are
with polyethylene film.                    Batter Boards                              steel pipes partially buried in the
                                           It is important to set up batter boards
                                                                                      ground. On rocky ground, in high
Most manufacturers provide                 at the start of high tunnel construction
                                                                                      wind areas, or where significant
instruction manuals with the frame         (see Diagram 4 below). The small
                                                                                      ground disturbance occurred during
and technical support if needed.           amount of extra time involved will be
                                                                                      site preparation, a little additional
Some, however, are less helpful than       well-rewarded by the increased ease
                                                                                      support may be warranted. In these
others in their support so inquire         of construction. The use of these
                                                                                      specific situations or for extra
before selecting a company. The most       semi-permanent building markers is
                                                                                      stability, a couple shovels of cement
important step is to make certain that     described at
                                                                                      will effectively keep ground pins in
the site is square and uniformly           www.dulley.com/deck/deck01.shtml.
                                                                                      place.
pitched or level. If this is done
carefully, the frame should install        Batter boards define the corners and
                                                                                      A sledgehammer is commonly used to
easily.                                    heights of the high tunnel. They allow
                                                                                      drive in short ground posts. Most
                                           you to erect the structure with
                                                                                      companies provide a protective piece
Instead of step-by-step instructions for
constructing a high tunnel, here we
offer tips to save you time and money.
We hope these recommendations
enable you to complete your project
with less stress and more confidence.

Start with an adequate selection of
tools to make the construction process
a pleasant one. Tools to assemble
include the following:
• level, level string, chalk line, and
   transit;
• long-handled mallet or sledge
   hammer for driving ground stakes;
• post-hole digger for endwall posts;



40 – High Tunnels
to put in the pipe to protect the end     To ensure that the posts are placed at    Raising a heavy bow on a wide tunnel
from being damaged or                     the correct height, use a transit, hose   (20' or wider) is best accomplished
“doughnuting.” For a taller structure     level, or laser level. Then take down     with at least three people. One person
with extended ground posts, John          the batter boards and run a high-         stands at each leg of the bow, and a
Biernbaum (who researches and             strength nylon mason cord between         third pushes the bow up in the air with
teaches about high tunnels at             the corner ground posts. Pull the         a pike pole. This is heavy work. Each
Michigan State University) has found      string as tightly as you can to           bow will need to be picked up and
that a post or fence pounder works        minimize droop over the long              wiggled onto the spline/ground posts.
better.                                   distance. Be careful; if a tight nylon    Use one or two pike poles to keep the
                                          string breaks, it can hurt someone as     bow assembly from falling while the
The ground posts at the four corners      the end whips past.                       crew wiggles it onto the ground posts.
should be solidly cemented in. For
tunnels over 70' long, also cement in     The bows – and therefore the ground       Purlins
the intermediate ground posts in the      posts – of most high tunnels are          Purlins help stabilize the high tunnel.
middle of the long sides. Cement must     spaced on 4', 5', or 6' centers. A        They are bolted to the bows, along the
be placed below the soil freeze zone,     wooden template with notches at 4'        length of the structure. Typically a 30'
as the freezing action can force the      (or whatever the bow spacing is)          tunnel will have five purlins,
ground pin up out of the ground. You      eliminates the need for the time-         including the ridge pole.
may want to use caution when              consuming and awkward task of
employing cement as this may move         measuring from bow center to center.      The purlins can be attached once the
the structure into a ‘permanent’          Ledgewood and Rimol provide their         bows are loosely assembled and in
classification.                           greenhouse customers with these           place. A platform is much safer than
                                          spacers. They are also easy to make.      ladders and saves a tremendous
Steve Moore suggests a good way to        John Biernbaum regards them as            amount of time and energy. Use a hay
keep the ground posts in place so they    essential for construction.               wagon, truck bed, or scaffolding,
don’t pull out of the cement or slide                                               especially if you can pull it along as
down: pre-drill the ground posts          Alternatively, Steve Moore                you go!
within 2" or 3" of the bottom and         recommends measuring from the
insert a 4" to 6" piece of rebar.         same side of a post every time to         A drift punch or pipe wrench can be
                                          attain an accurate center                 used to help align bow and purlin
The ground posts need to be in the        measurement. Taping the end of the        holes. As you attach the purlins,
right location and at the right height.   measuring tape to the corner ground       tighten all bow bolts, except those that
A jig made with two old boards and        post is one simple way to do this. A      connect the bow to the ground pin.
some broccoli-type rubber bands or        level should be used to ensure the        Finally, when you are at the end bow,
thin bungee cords will align the posts    posts are vertical/plumb. A post level    with all the purlins in place, you are
with the strings between the batter       that has bubbles at 90 degree angles is   ready to “plumb” the gable end to
boards that outline the high tunnel.      useful because both directions can be     straighten the entire bow/purlin
(See diagram below.) It will also keep    seen at once.                             assembly.
the posts at the desired height. This
simple device is removed once the         Bows                                      Attach one string with a plumb bob to
cement hardens in 12 to 24 hours.         Bows typically consist of two or three    the top point of the outside edge of the
                                          shorter pieces of metal tubing.           last bow, and a second ground string
                                          Preassemble bows loosely. Do not          to the outside edge of the bottom bow.
                                          tighten the bolts. This loose bow         Allow the plumb bob string to come
                                          assembly will help in purlin              within 1/8" of the ground string.
                                          installation. (Purlins are horizontal
                                          pieces typically made of pipe that is a   A good way to adjust and hold the
                                          smaller diameter on one end               high tunnel plumb is to attach a come-
                                          (swedged) to fit inside the next pipe.)   along to a large immovable object like
                                                                                    a tree or truck and then attach a rope
                                          Historically, pike poles were used to     or chain from the come-along up to
                                          push up large sections of timber          the bow. A come-along’s ratcheting
                                          framing for barns. Pike poles also        mechanism and its steel cable allow
                                          have a place in erecting high tunnels.    for quick and precise alignment of the
                                                                                    tunnel. Now you can tighten all

41 – High Tunnels
remaining bolts and install the wind       the bow. Ted Blomgren recommends            If you use a rigid gable-end covering,
braces.                                    using a washer on the wood screw.           such as polycarbonate, the outside of
                                                                                       the baseboard will need to be flush
Baseboards                                 The frame will be complete after the        with the outside of the bow. To make
The baseboards sit on the ground           hip board (2" x 6" lumber) along with       it flush, attach an 8" piece of universal
along the sides of a high tunnel. They     “poly lock” or “wiggle wire” base is        corner (a thin-walled piece of angle
are bolted to the ground posts. Use        attached to the bows approximately 5'       iron with multiple holes for bolting)
1.5" x 8" lumber for baseboards.           or 6' off the ground. (Poly lock is the     with the same bolts that hold the side
                                           trade name for an extrusion for             baseboard.
Consider sourcing your lumber from         attaching the polyethylene film to the
local family-owned and operated            structure. It serves the same purpose       Insulation
sawmills. Often boards from these          as wiggle wire.) This will serve as the     In cold climates, insulation can make a
mills are sawn several inches longer       point of attachment for the plastic         significant difference in the
than their designated length, rather       covering.                                   performance of high tunnels. In Zone 6,
than being trimmed down to an exact,                                                   burying 1" thick by 2' wide rigid foam
even foot measure. This extra length       The hip board should be inspected at        (i.e. polystyrene) isolates frozen ground
will allow you to cut the ends at a 45     each change of polyethylene to make         from growing areas. The thickness and
degree angle for joining together at       sure it will be sound for another four      depth of insulation should be modified
the bows with a 1/4" machine bolt          or five years. Farmers should be            according to your climatic zone. This
(see diagram below).                       aware of rot and ready to replace the       foam should be buried at an angle to
                                           baseboard as necessary; the plastic         gain more benefit from the thermal
                                           need not be removed to do so.               mass of the earth. The angled placement
                                                                                       also makes installation easier and
                                           Gable Ends                                  allows space for the cement support at
                                           Doors should be large enough for            the bottom of the ground pin (see
                                           ventilation and easy access. They can       diagram below). Insulation can also be
                                           span even the full width of the high        used in pathways and along the lower
                                           tunnel. To maximize airflow and             portion of the sidewalls.
                                           accessibility, some farmers construct
                                           removable end walls. A smaller,
Use a long 1/4" bit to drill out the       personal door that opens inward
holes for the bolt through the wood        makes a convenient winter passage.
from the inside of the high tunnel.
This added length is helpful when          Unless the high tunnel will have very
attaching framing to bows.                 wide doors, some tasks such as adding
                                           compost, tilling the soil, and installing
Machine bolts are superior to carriage     utilities are best accomplished before
bolts for attaching the poly hold-down     the gable ends are closed in and
strips to the baseboard. Carriage bolts    access is restricted.
are often used for this purpose, but
they rust fast. When the baseboard         Gable end framing can be done with
needs to be replaced, sometimes the        steel or wood. If using wood, either
nuts are stuck in place and won’t turn.    select one of the rot-resistant species     Hiring Out Construction
With a wrench on either side of the        recommended for the baseboards (see         For some farmers, hiring an
nut and bolt, the machine bolts will       materials section) or be prepared to        experienced crew to do the installation
break off much faster and easier than      replace the wood as needed. Steve           may be the best option. The estimated
hack sawing carriage bolts, which          Moore uses rough sawn 2 x 4s to frame       labor cost for basic high tunnel
only turn in the wood.                     the gable end. When the wood rots           construction used to be fifty cents to
                                           right at the soil line where moisture       one dollar per square foot. However,
While bolts may be better for              and air meet, rather than take apart the    due to inflation, the labor bill for high
attaching the base boards and hip          whole assembly, he just pounds in a U-      tunnel construction in previous years
boards to the bows, galvanized pipe        shaped steel fence post and lag or          may not be relevant for estimating
straps can also do a good job, as long     machine bolts it to the post that had       costs under current conditions. Like
as the pipe strap is also tek-screwed to   rotted off. “This buys me a good many       any construction project today, expect
                                           more years service,” he says.               skilled contractors to be expensive.

42 – High Tunnels
Bending Your Own Frames
 Rather than purchasing a hoop house kit, some farmers choose to bend their own. A good role model for this activity is
 Ed Person of Ledgewood Greenhouse. This New Hampshire farmer went from bending frames for his own use to
 developing a substantial independent business that sells and delivers high tunnel frames throughout the Northeast.
 For savvy shoppers, fabricating a high tunnel steel frame can save money. It also allows farmers to realize a better
 design idea, satisfy unique needs, or add onto an existing high tunnel.
 Ted and Jan Blomgren bent several Gothic arch high tunnel frames for their farm. Three people worked for about the
 equivalent of one week fabricating the jigs and bending and drilling the component parts for three and a half 30' x 96'
 high tunnels with trusses.
 At the time, they were able to make their own high tunnel frames for a third of the cost of a kit, thanks to a farmer
 friend’s tip about a supplier of economically priced steel. Ted cautions though that purchasing steel from a local chain
 link fence supplier might actually cost more than buying a kit with pre-bent, pre-drilled steel.
 The Blomgrens’ bows consisted of two long side pieces with a shorter, smaller diameter piece at the ridge. In all, they
 used three sizes of steel pipe—1.9", 1.6" and 1.3" diameter for bow, small ridge bow, and purlins, respectively—to
 fabricate all the high tunnel components including trusses. The only new tools they needed were a chop saw and drill
 press outfitted for cutting and drilling steel. After four years, there is no rust at the bends and the galvanized coating
 has not popped off.
 They built the two jigs needed for bending the steel for the bows by replicating a bow they had removed from their
 existing high tunnel. To bend the steel, they placed a jig, made of two-ply 3/4" plywood and lumber, on the level
 cement floor of their garage, braced against its foundation. For the easier, shallow bend, they were able to use their
 sedan with a steel cable attached to the trailer hitch. The more acute portion of the bow required the weight and
 traction of their heavy John Deere tractor. To compensate for the springback in steel, they bent it until it fit a pattern
 they had outlined on the floor.
 Bending the bows for a high tunnel can be a simpler process. For example, Thomas Christenfeld, a neighbor of the
 Blomgrens, bent the bows for his Quonset-style greenhouse using a silo as a jig. He stuck one end on one of the hoop
 bolts that holds the concrete panels of the silo together and bent the other end around the silo. Two people are needed
 to get a good enough bend in the pipe and that it probably only works for a single piece hoop. Thomas notes, “You
 cannot get any real bend in the ends of the pipe so two pieces stuck together leaves a flat part on top of the hoop house,
 which is far from ideal in a snowy climate.”

 Another Way to Bend Your Own
 Kevin Loth, who is contractor as well as a farmer, has fabricated his family’s 20' x 200' Quonset-style high tunnels
 near Lincoln, Nebraska. The Loths have two heated greenhouses and two year round high tunnels. By bending his own
 bows, he was able to get twice as much ground under cover than if he purchased kits. His calculation included what he
 paid a helper but not his own time. He said if you don’t drill the bows, you could probably bend them in a day, though
 set up might take a couple of days.
 With a borrowed pipe bender, he made bows out of the 15 gauge metal pipe used as a chain-link fence top rail. He
 saved considerably on the pipe by purchasing it by the bundle of 91 pipes. Because the pipe comes in 21' lengths, he
 had to swedge together one and a half lengths for each bow. While a swedging tool can be expensive, often when you
 buy fencing steel, one end comes already swedged.
 His finished tunnels are Quonset-shaped, 10' high at the peak. Their bows are 4' on center, and they have two purlins
 but no trusses.
 Kevin has attached the purlins and bows in several ways. Holes should be drilled prior to bending the bows. For the
 less technically adept, purlin clamp connectors (available from greenhouse suppliers) or pipe clamps (from plumbing
 supply outfits) preclude the need to drill holes for the bolts attaching the purlins. Getting these holes to line up properly
 can be difficult. Moreover, the very act of drilling holes weakens the steel.
 While the purlin connectors are aluminum, Kevin dismisses concern about mixing metals as the tunnel’s steel is
 galvanized. He thinks this is less of an issue than drilling holes as that action exposes ungalvanized steel and weakens
 the structural pieces. Also he noted that the ends of the bows are in contact with corrosive cement and soil acids.

43 – High Tunnels
Covering a High Tunnel                     stroke, bringing the plastic overhead       plastic down to the end and finish the
Farmers employ several methods for         so that it clears the peak without          gable end. The reason for the
getting the unwieldy expanse of            getting caught.                             staggered start and attachment is to
polyethylene film over the top of large                                                avoid see-sawing the plastic side to
hoop house structures and evenly           The two people walking along the            side. The lead attachers must always
attached. The size of your crew helps      sides can have an exceedingly long          keep the selvage edge the same while
determine which methods are most           way to pull the plastic. When they          the other side pulls the plastic to
feasible. The most important rule of       reach the middle of a long tunnel, two      match.
thumb is never attempt to cover a          more people standing at the original
tunnel on a windy day.                     gable end should assist pulling the         Getting all of the wrinkles out is not
                                           plastic along. These additional people      important if you are going to inflate. It
Covering a large (i.e., 30' x 96') high    also help keep the plastic from             is important not to pull the poly film
tunnel with a single layer of poly         becoming a sail if a sudden gust of         so tight that the wiggle wire in the U
should take four or five people two or     wind comes along.                           channel perforates the new plastic.
three hours. There is a learning curve
so the first few times may take longer.    After the whole tunnel has been             A variation on the pull-over-the-end
                                           covered, it’s time to even out the          method of covering a high tunnel is
Method A: Pull over the end.               plastic. The selvage edge must be           used by the Kilpatrick family. They
For this method, four or five people       even for the entire length of the tunnel    set up the plastic on scaffolding at one
and a center-folded roll of                and should be 12" or longer. You            end of the tunnel as described above.
polyethylene are required. (You can        don’t want the edge to run out!             “Make sure the scaffolding is above
order your polyethylene folded in                                                      the peak of the structure. While one
several ways.)                             If you are putting a second covering        person pulls the plastic down the
                                           on, just tack it on the first layer using   length of the high tunnel, the others
The first step is unrolling the plastic.   just a couple strategically placed poly     assist from the ground.” Philip and
To do this, set up a pair of               fasteners (i.e., wiggle wire) and repeat    Michael Kilpatrick have found that for
cinderblocks a few feet further apart      the process with the second covering.       work on the purlins, scaffolding
than the length of the roll of             Otherwise, proceed to the next step.        mounted on a cart is far more
polyethylene. For a 12' tube, set the                                                  convenient than using a ladder.
blocks about 14' apart. Then put a         Once you are satisfied that the plastic
pipe in the tube. Make cardboard           is even on the edge, temporarily            Method B: Ridge-roll.
washers about 1' square to put on the      secure the plastic in place at three or     This is one of the two ways that the
ends of the pipe. The washers serve to     four points on each side. The most          Blomgrens cover their tunnels. (The
protect the ends of the rolled up          common method for securing the              other way is described in Method C.)
polyethylene from abrasion against         plastic is wiggle wire inserted into a U    Both methods involve climbing up the
the cinderblocks when you unroll it.       channel. An alternative assembly is         high tunnel and thus entail danger.
This set up should allow the plastic to    homemade—wood attached with                 Use these methods at your own risk.
freely unroll.                             drywall screws every 6" to 8".
                                                                                       Covering a high tunnel with a lean
The next step, getting the plastic over    Now you are ready to fully secure the       crew (four people) necessitates a
the tunnel, requires five people. One      single or double layer of plastic. The      different method. Once again, make
person is stationed on a ladder at a       person on the ladder inserts wiggle         sure to obtain greenhouse plastic with
gable end of the high tunnel. Wearing      wire from the top down on one of the        its fold down the center so it will
a hooded sweatshirt is recommended         gable ends. Next the plastic film at the    unfurl properly.
to avoid plastic rubbing and to            other gable end should be pulled and
counteract the static electric generated   that plastic “tacked” down. Once one        In this technique two people carry the
by moving the plastic film over head.      gable-end plastic is permanently            entire roll of poly up to the top of the
The center of the end of the poly is       attached and the other gable end has        high tunnel. A bucket loader is handy
passed to the person on the ladder.        been “tacked” in place (with a short        for this purpose. Before climbing up,
The film unrolls as it is pulled up the    wiggle wire), one side can be attached      they insert a pipe into the cardboard
ladder. Two people on the ground           for a distance of about three bows.         tube to assist in unrolling it. With the
hold the corners and walk along side       Remember to keep a constant selvage         roll sitting on the top purlin, they
the tunnel as the plastic is unfurled.     (waste) edge. Another person (or two)       temporarily fasten it on the gable end
Meanwhile the person on the ladder         starts on the opposite side of the first    of the tunnel. Then they proceed to
does a sort of butterfly swimming          group and both groups attach side           walk it down the tunnel, making use

44 – High Tunnels
of the side purlins, walking the roll     For a big tunnel (30' x 96' or 150'), at    If you choose to use wooden batten
along as they go. By the time the pair    least eight people are needed for this      boards to fasten the plastic to the hip
has walked halfway down the tunnel,       method. Start by unrolling the plastic      board, you would be wise to use a pair
the plastic will have begun unfurling,    (without unfolding it) along the side       of batten boards one above the other
with half falling down one side and       of the high tunnel. If there is a risk of   with the plastic outside of the top one
half down the other. (This unrolling      the slightest wind, it is best to be on     and behind the bottom one. This more
procedure will go much more quickly       the windward side of the tunnel.            effectively locks the poly in place.
if the high tunnel is designed so that                                                (See diagram below.)
the ridge purlin is situated on top of    After the plastic has been unrolled,
the bow. This is an atypical purlin       people station themselves at regular
placement and is only advisable for       intervals along the tunnel. They each
tunnels that will never be covered        take hold of what will become the far
with a double, inflated layer of poly.)   edge of the poly. Pulling this edge,
                                          they climb up and over the tunnel.
Meanwhile the two other people, who       With enough people, the weight of the
are on the ground, are starting to        poly is distributed and not
tentatively connect the poly to the hip   burdensome to anyone.
board just above the roll up sides.
                                          Once the plastic is over the top of the
After the plastic has been unrolled       structure, it is squared up, and then
along the entire length of the tunnel,    temporarily fastened to the gable
the two people who have been              ends. They then proceed as in the
walking the ridge with the roll of poly   above description, with teams starting
temporarily connect the poly with         from opposite sides of one end and          After you have to undo rusty screws
wiggle wire at the top of the second      both working toward the far end.            or other failing attachments to remove
gable end. They then climb down and                                                   old poly, you will probably come to
join the two folks on the ground. With    There is an alternative to climbing up      believe that wiggle wire is a bargain at
two people on each side of the tunnel,    and over the greenhouse. Ropes may          a $1 per foot. When attaching new
they square up the plastic, and then      be attached to the plastic along its        poly with wiggle wire, don’t pull the
begin attaching the plastic along the     side. Clips available from greenhouse       poly too tight (or over inflate). The
top of the roll up sides. With the two    suppliers can be used to secure the         wiggle wire will actually cut
teams working on opposite sides of        rope to the plastic. Alternatively, wrap    perforations (corresponding to the
the tunnel, they start at one end, and    tennis balls in the plastic and use them    wiggle wire) in the new cover if there
work toward the other end.                to help fasten the rope. Toss the ropes     is too much tension. This applies to
                                          over the tunnel structure and, once on      double layers of poly, too.
They then finish the gable ends,          the other side, pull the plastic over.
taking up the slack and smoothing out                                                 When attaching plastic to battens (thin
wrinkles, before permanently                                                          boards less than 1/2" x 1-1/2"), use
attaching it there. They trim off the     Tips for Attaching the                      double headed nails—rather than
                                                                                      regular nails—for easier removal.
excess plastic at the gable ends so it    Plastic
doesn’t flap in the wind. To complete                                                 Galvanized screws are another option.
                                          Single poly can be difficult to keep on
the covering, the roll up sides must be   a structure because there is no tension
attached.                                 from an inflation fan to reduce
                                          flapping. Steve Moore has used wide
Method C: Over the side.                  poly strapping placed between every
Like the previous method, this            other bow and attached to the
covering procedure used by the            baseboard to keep the cover in place.
Blomgrens has safety and liability        This increases the longevity of the
issues. As an alternative to climbing     plastic film, and also reduces a
over the tunnel frame, Steve Moore        farmer’s worry about losing the
suggests attaching grommets to the        plastic on the tunnels (and sleep) on
plastic and using ropes to pull it over   windy nights.
the structure.



45 – High Tunnels
Getting the Right Pressure on Your Inflation
 Correct pressure ensures a balance between over and under inflation. By providing sufficient tightness of the plastic,
 flapping is minimized. If the plastic is stretched too tightly, light transmission is reduced. Simply put, correct pressure
 increases the life of the plastic and its ability to transmit light.

 A manometer is an instrument used to measure the pressure of a gas. For high tunnels with a double poly layer, it is
 useful for determining the proper inflation pressure. Steve Moore makes his own homemade manometer using this
 simple procedure.




 On the inside of the tunnel, attach a 2" x 8" (or wider) board with carriage bolts to two of the bows at a 4' to 6' height.
 (This board can be used to mount the inflation fan as well.) After covering the high tunnel with the first layer of poly, a
 4" to 6" square piece of polycarbonate is attached with drywall screws to the wood before the tunnel is covered with a
 second layer of poly.

 From the interior of the tunnel, drill a hole through the wood, the inside layer of plastic and the small piece of rigid
 material. From the inside, push a clear flexible plastic tube (available by the foot at most hardware store) into the
 wood, allowing the tube free access to the air between the layers. The tube's internal diameter can be from 3/4" to 1".
 Caulk around the tube so that it is airtight to prevent leaks.

 Let the tube form a "U" with one of the top legs of the U going through the wood. Attach the other top of the U tube to
 the board and fill the bottom of the U with a colored liquid (blue washer fluid or colored water). Mark level horizontal
 lines ¼ of an inch apart on the board next to the U portion of the clear tube. If the interior air level of the U is ¼ inch
 higher than the inflation side of the U, then the pressure is about right. The liquid level on the side of the U that is
 attached to the board should be 1/4 " lower than the side of the U that is open to the inside of the tunnel.

 Adjust the pressure by using a damper on the intake of the inflation fan. You can make a damper with a flat piece of
 metal, like an old can lid (taped to keep from cutting yourself). Insert a screw through the top edge of the metal lid.
 Attach it tightly enough to the intake of the inflation fan that it will stay in place at various degrees of opening.

 Steve has used solar power to run the inflation fan and his monitoring equipment.


46 – High Tunnels

More Related Content

What's hot

ReciproBoo Shelter
ReciproBoo ShelterReciproBoo Shelter
ReciproBoo ShelterReciproboo
 
TYPES OF SHACKLES (With Pictures)
TYPES OF SHACKLES (With Pictures)TYPES OF SHACKLES (With Pictures)
TYPES OF SHACKLES (With Pictures)Gaurav Paliwal
 
FPDC Article & FlexiDry Case Study September 2010
FPDC Article & FlexiDry Case Study September 2010FPDC Article & FlexiDry Case Study September 2010
FPDC Article & FlexiDry Case Study September 2010FlexiDry Global Ltd
 
Laxmi Udyog Cementing Aids Catalogue
Laxmi Udyog Cementing Aids CatalogueLaxmi Udyog Cementing Aids Catalogue
Laxmi Udyog Cementing Aids CatalogueEPR (Kuching) Sdn Bhd
 
Offshore lifting slings made with Dyneema®
Offshore lifting slings made with Dyneema®Offshore lifting slings made with Dyneema®
Offshore lifting slings made with Dyneema®Jac Spijkers
 
Visual Dictionary-Sandstone
Visual Dictionary-SandstoneVisual Dictionary-Sandstone
Visual Dictionary-SandstoneSandstone
 
Avalon Log Homes Construction Manual 2011
Avalon Log Homes Construction Manual 2011Avalon Log Homes Construction Manual 2011
Avalon Log Homes Construction Manual 2011Avalon Log Homes
 
Avalon Log Homes Construction Manual
Avalon Log Homes Construction Manual Avalon Log Homes Construction Manual
Avalon Log Homes Construction Manual Avalon Log Homes
 
Scaffolding
ScaffoldingScaffolding
Scaffoldingstooty s
 

What's hot (11)

ReciproBoo Shelter
ReciproBoo ShelterReciproBoo Shelter
ReciproBoo Shelter
 
TYPES OF SHACKLES (With Pictures)
TYPES OF SHACKLES (With Pictures)TYPES OF SHACKLES (With Pictures)
TYPES OF SHACKLES (With Pictures)
 
FPDC Article & FlexiDry Case Study September 2010
FPDC Article & FlexiDry Case Study September 2010FPDC Article & FlexiDry Case Study September 2010
FPDC Article & FlexiDry Case Study September 2010
 
Scaffolding
ScaffoldingScaffolding
Scaffolding
 
Laxmi Udyog Cementing Aids Catalogue
Laxmi Udyog Cementing Aids CatalogueLaxmi Udyog Cementing Aids Catalogue
Laxmi Udyog Cementing Aids Catalogue
 
Offshore lifting slings made with Dyneema®
Offshore lifting slings made with Dyneema®Offshore lifting slings made with Dyneema®
Offshore lifting slings made with Dyneema®
 
Visual Dictionary-Sandstone
Visual Dictionary-SandstoneVisual Dictionary-Sandstone
Visual Dictionary-Sandstone
 
Avalon Log Homes Construction Manual 2011
Avalon Log Homes Construction Manual 2011Avalon Log Homes Construction Manual 2011
Avalon Log Homes Construction Manual 2011
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
Avalon Log Homes Construction Manual
Avalon Log Homes Construction Manual Avalon Log Homes Construction Manual
Avalon Log Homes Construction Manual
 
Scaffolding
ScaffoldingScaffolding
Scaffolding
 

Viewers also liked

AUDI A4 B5 1.8L 1996 ELECTRICAL EQUIPMENT 01 84 multi-function steering wheel...
AUDI A4 B5 1.8L 1996 ELECTRICAL EQUIPMENT 01 84 multi-function steering wheel...AUDI A4 B5 1.8L 1996 ELECTRICAL EQUIPMENT 01 84 multi-function steering wheel...
AUDI A4 B5 1.8L 1996 ELECTRICAL EQUIPMENT 01 84 multi-function steering wheel...Gherghescu Gabriel
 
AUDI A4 B5 1.8L 1996 BADY ODB 01 108 interior monitor
AUDI A4 B5 1.8L 1996 BADY ODB 01 108 interior monitorAUDI A4 B5 1.8L 1996 BADY ODB 01 108 interior monitor
AUDI A4 B5 1.8L 1996 BADY ODB 01 108 interior monitorGherghescu Gabriel
 
AUDI A4 B5 1.8L 1996 BADY 66 5 lower trim strip rear door
AUDI A4 B5 1.8L 1996 BADY 66 5 lower trim strip rear doorAUDI A4 B5 1.8L 1996 BADY 66 5 lower trim strip rear door
AUDI A4 B5 1.8L 1996 BADY 66 5 lower trim strip rear doorGherghescu Gabriel
 
Kennelly tomatofruitdiseasesdisorders
Kennelly tomatofruitdiseasesdisordersKennelly tomatofruitdiseasesdisorders
Kennelly tomatofruitdiseasesdisordersGherghescu Gabriel
 
Www.referat.ro infiintareauneiplantatiidemarinsistemintensivpeosuprafatade25h...
Www.referat.ro infiintareauneiplantatiidemarinsistemintensivpeosuprafatade25h...Www.referat.ro infiintareauneiplantatiidemarinsistemintensivpeosuprafatade25h...
Www.referat.ro infiintareauneiplantatiidemarinsistemintensivpeosuprafatade25h...Gherghescu Gabriel
 
Sistem irigare legume naandanjain in sighisoara
Sistem irigare legume naandanjain in sighisoaraSistem irigare legume naandanjain in sighisoara
Sistem irigare legume naandanjain in sighisoaraGherghescu Gabriel
 
Infiintarea plantatiilor pomicole
Infiintarea plantatiilor pomicoleInfiintarea plantatiilor pomicole
Infiintarea plantatiilor pomicoleGherghescu Gabriel
 

Viewers also liked (20)

Expresii algebrice-rezolvate
Expresii algebrice-rezolvateExpresii algebrice-rezolvate
Expresii algebrice-rezolvate
 
41713312 reteta-urzici
41713312 reteta-urzici41713312 reteta-urzici
41713312 reteta-urzici
 
Bolile la varza conopida etc
Bolile la varza conopida etcBolile la varza conopida etc
Bolile la varza conopida etc
 
0 fraza 8 romana
0 fraza 8 romana0 fraza 8 romana
0 fraza 8 romana
 
AUDI A4 B5 1.8L 1996 ELECTRICAL EQUIPMENT 01 84 multi-function steering wheel...
AUDI A4 B5 1.8L 1996 ELECTRICAL EQUIPMENT 01 84 multi-function steering wheel...AUDI A4 B5 1.8L 1996 ELECTRICAL EQUIPMENT 01 84 multi-function steering wheel...
AUDI A4 B5 1.8L 1996 ELECTRICAL EQUIPMENT 01 84 multi-function steering wheel...
 
AUDI A4 B5 1.8L 1996 BADY ODB 01 108 interior monitor
AUDI A4 B5 1.8L 1996 BADY ODB 01 108 interior monitorAUDI A4 B5 1.8L 1996 BADY ODB 01 108 interior monitor
AUDI A4 B5 1.8L 1996 BADY ODB 01 108 interior monitor
 
AUDI A4 B5 1.8L 1996 BADY 66 5 lower trim strip rear door
AUDI A4 B5 1.8L 1996 BADY 66 5 lower trim strip rear doorAUDI A4 B5 1.8L 1996 BADY 66 5 lower trim strip rear door
AUDI A4 B5 1.8L 1996 BADY 66 5 lower trim strip rear door
 
Revista dulgher-09
Revista dulgher-09Revista dulgher-09
Revista dulgher-09
 
Agrochimie
AgrochimieAgrochimie
Agrochimie
 
Caracteristici tehnice sere
Caracteristici tehnice sereCaracteristici tehnice sere
Caracteristici tehnice sere
 
Kennelly tomatofruitdiseasesdisorders
Kennelly tomatofruitdiseasesdisordersKennelly tomatofruitdiseasesdisorders
Kennelly tomatofruitdiseasesdisorders
 
Gh high tunnels_2008-01pr
Gh high tunnels_2008-01prGh high tunnels_2008-01pr
Gh high tunnels_2008-01pr
 
Cresterea prepelitelor
Cresterea prepelitelorCresterea prepelitelor
Cresterea prepelitelor
 
Catalog salata 2009 s&g
Catalog salata 2009  s&gCatalog salata 2009  s&g
Catalog salata 2009 s&g
 
14 varza-de-bruxelles
14 varza-de-bruxelles14 varza-de-bruxelles
14 varza-de-bruxelles
 
Ardei blondy f1,_barbie_f1
Ardei blondy f1,_barbie_f1Ardei blondy f1,_barbie_f1
Ardei blondy f1,_barbie_f1
 
Caracteristici tehnice sere 1
Caracteristici tehnice sere 1Caracteristici tehnice sere 1
Caracteristici tehnice sere 1
 
Www.referat.ro infiintareauneiplantatiidemarinsistemintensivpeosuprafatade25h...
Www.referat.ro infiintareauneiplantatiidemarinsistemintensivpeosuprafatade25h...Www.referat.ro infiintareauneiplantatiidemarinsistemintensivpeosuprafatade25h...
Www.referat.ro infiintareauneiplantatiidemarinsistemintensivpeosuprafatade25h...
 
Sistem irigare legume naandanjain in sighisoara
Sistem irigare legume naandanjain in sighisoaraSistem irigare legume naandanjain in sighisoara
Sistem irigare legume naandanjain in sighisoara
 
Infiintarea plantatiilor pomicole
Infiintarea plantatiilor pomicoleInfiintarea plantatiilor pomicole
Infiintarea plantatiilor pomicole
 

Similar to High tunnels constructiontips

AquaTerra User Guide
AquaTerra User GuideAquaTerra User Guide
AquaTerra User Guidejeffmmoreau
 
Site Report for CT! MEASUREMENT AND BM
Site Report for CT! MEASUREMENT AND BMSite Report for CT! MEASUREMENT AND BM
Site Report for CT! MEASUREMENT AND BMcheeweishan
 
Estimating Systems for Homes1
Estimating Systems for Homes1Estimating Systems for Homes1
Estimating Systems for Homes1Keith Daggett
 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresShivananda Roy
 
Flat Grid / Waffle Slab
Flat Grid / Waffle SlabFlat Grid / Waffle Slab
Flat Grid / Waffle SlabAkshay Gawade
 
Underground cabling installation
Underground cabling installationUnderground cabling installation
Underground cabling installationAmit Kumar
 
Ground Engineering Datasheets
Ground Engineering DatasheetsGround Engineering Datasheets
Ground Engineering Datasheetskavdavid
 
Tubular Rivet Foundation (Part 1) .pdf
Tubular Rivet Foundation (Part 1) .pdfTubular Rivet Foundation (Part 1) .pdf
Tubular Rivet Foundation (Part 1) .pdfDongyuanWang1
 
CABLE ANCHORING AND GROUTING / Diaphragm Walls
CABLE ANCHORING AND GROUTING / Diaphragm Walls CABLE ANCHORING AND GROUTING / Diaphragm Walls
CABLE ANCHORING AND GROUTING / Diaphragm Walls Manvinder Kingra
 
Cable anchoring and grouting for cable tensioning
Cable anchoring and grouting for cable tensioningCable anchoring and grouting for cable tensioning
Cable anchoring and grouting for cable tensioningChinnuNinan
 
Shoring system and Dewatering
Shoring system and DewateringShoring system and Dewatering
Shoring system and DewateringSALEM MOHAMMED
 
CONSTRUCTION METHODS BASICS BTCE-503-18
CONSTRUCTION METHODS BASICSBTCE-503-18CONSTRUCTION METHODS BASICSBTCE-503-18
CONSTRUCTION METHODS BASICS BTCE-503-18SANJEEV Wazir
 
Pile foundation -sunil kumar mohapatra
Pile foundation -sunil kumar mohapatraPile foundation -sunil kumar mohapatra
Pile foundation -sunil kumar mohapatraSUNIL KUMAR MOHAPATRA
 
Slipform construction
Slipform constructionSlipform construction
Slipform constructionErankajKumar
 
6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTUVATSAL PATEL
 

Similar to High tunnels constructiontips (20)

AquaTerra User Guide
AquaTerra User GuideAquaTerra User Guide
AquaTerra User Guide
 
Site Report for CT! MEASUREMENT AND BM
Site Report for CT! MEASUREMENT AND BMSite Report for CT! MEASUREMENT AND BM
Site Report for CT! MEASUREMENT AND BM
 
Estimating Systems for Homes1
Estimating Systems for Homes1Estimating Systems for Homes1
Estimating Systems for Homes1
 
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining StructuresEXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
EXCAVATION FOR FOUNDATION - Methods & Temporary Earth Retaining Structures
 
Flat Grid / Waffle Slab
Flat Grid / Waffle SlabFlat Grid / Waffle Slab
Flat Grid / Waffle Slab
 
Underground cabling installation
Underground cabling installationUnderground cabling installation
Underground cabling installation
 
UNderpinning.pptx.pdf
UNderpinning.pptx.pdfUNderpinning.pptx.pdf
UNderpinning.pptx.pdf
 
Ground Engineering Datasheets
Ground Engineering DatasheetsGround Engineering Datasheets
Ground Engineering Datasheets
 
Tubular Rivet Foundation (Part 1) .pdf
Tubular Rivet Foundation (Part 1) .pdfTubular Rivet Foundation (Part 1) .pdf
Tubular Rivet Foundation (Part 1) .pdf
 
CABLE ANCHORING AND GROUTING / Diaphragm Walls
CABLE ANCHORING AND GROUTING / Diaphragm Walls CABLE ANCHORING AND GROUTING / Diaphragm Walls
CABLE ANCHORING AND GROUTING / Diaphragm Walls
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 
Cable anchoring and grouting for cable tensioning
Cable anchoring and grouting for cable tensioningCable anchoring and grouting for cable tensioning
Cable anchoring and grouting for cable tensioning
 
Shoring system and Dewatering
Shoring system and DewateringShoring system and Dewatering
Shoring system and Dewatering
 
CONSTRUCTION METHODS BASICS BTCE-503-18
CONSTRUCTION METHODS BASICSBTCE-503-18CONSTRUCTION METHODS BASICSBTCE-503-18
CONSTRUCTION METHODS BASICS BTCE-503-18
 
Construções
ConstruçõesConstruções
Construções
 
Pile foundation -sunil kumar mohapatra
Pile foundation -sunil kumar mohapatraPile foundation -sunil kumar mohapatra
Pile foundation -sunil kumar mohapatra
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU
 
Industrial buildings
Industrial buildingsIndustrial buildings
Industrial buildings
 
Pile foundation
Pile foundationPile foundation
Pile foundation
 

More from Gherghescu Gabriel

Modele si variante bac matematica m1 2010 (model oficial)
Modele si variante bac matematica m1   2010 (model oficial)Modele si variante bac matematica m1   2010 (model oficial)
Modele si variante bac matematica m1 2010 (model oficial)Gherghescu Gabriel
 
9 varianta oficiala bac matematica m1 2010 (prima sesiune)
9 varianta oficiala bac matematica m1   2010 (prima sesiune)9 varianta oficiala bac matematica m1   2010 (prima sesiune)
9 varianta oficiala bac matematica m1 2010 (prima sesiune)Gherghescu Gabriel
 
9 barem varianta oficiala bac matematica m1 2010 (prima sesiune)
9 barem varianta oficiala bac matematica m1   2010 (prima sesiune)9 barem varianta oficiala bac matematica m1   2010 (prima sesiune)
9 barem varianta oficiala bac matematica m1 2010 (prima sesiune)Gherghescu Gabriel
 
6 varianta oficiala bac matematica m1 2010 (sesiune august)
6 varianta oficiala bac matematica m1   2010 (sesiune august)6 varianta oficiala bac matematica m1   2010 (sesiune august)
6 varianta oficiala bac matematica m1 2010 (sesiune august)Gherghescu Gabriel
 
6 barem varianta oficiala bac matematica m1 2010 (sesiune august)
6 barem varianta oficiala bac matematica m1   2010 (sesiune august)6 barem varianta oficiala bac matematica m1   2010 (sesiune august)
6 barem varianta oficiala bac matematica m1 2010 (sesiune august)Gherghescu Gabriel
 
Algebra clasa a 9a si a 10 a teorie cu teste si nrezolvari in detaliu
Algebra clasa a 9a si a 10 a teorie cu teste si nrezolvari in detaliuAlgebra clasa a 9a si a 10 a teorie cu teste si nrezolvari in detaliu
Algebra clasa a 9a si a 10 a teorie cu teste si nrezolvari in detaliuGherghescu Gabriel
 
Algebra clasa a 9a si a 10 a cu teorie si teste cu rezolvari in detaliu
Algebra clasa a 9a si a 10 a cu teorie si  teste cu rezolvari in detaliuAlgebra clasa a 9a si a 10 a cu teorie si  teste cu rezolvari in detaliu
Algebra clasa a 9a si a 10 a cu teorie si teste cu rezolvari in detaliuGherghescu Gabriel
 
AUDI Siguranţe fuzibile incepand cu an 1996
AUDI Siguranţe fuzibile incepand cu an 1996AUDI Siguranţe fuzibile incepand cu an 1996
AUDI Siguranţe fuzibile incepand cu an 1996Gherghescu Gabriel
 
Pionier deh 2000 mp ownersmanual1019 audi
Pionier deh 2000 mp ownersmanual1019 audi Pionier deh 2000 mp ownersmanual1019 audi
Pionier deh 2000 mp ownersmanual1019 audi Gherghescu Gabriel
 
Montare carlig remorcare audi a4 b5
Montare carlig remorcare audi a4 b5Montare carlig remorcare audi a4 b5
Montare carlig remorcare audi a4 b5Gherghescu Gabriel
 
A3 electrical AUDI A3 1997 2000 1.8 20V 4ADR
A3 electrical AUDI A3  1997 2000 1.8 20V 4ADRA3 electrical AUDI A3  1997 2000 1.8 20V 4ADR
A3 electrical AUDI A3 1997 2000 1.8 20V 4ADRGherghescu Gabriel
 
Siguranţe fuzibile şi relee AUDI A4 B5 1996 2000 1.8 20V 4ADR
Siguranţe fuzibile şi relee AUDI A4 B5 1996 2000 1.8 20V 4ADRSiguranţe fuzibile şi relee AUDI A4 B5 1996 2000 1.8 20V 4ADR
Siguranţe fuzibile şi relee AUDI A4 B5 1996 2000 1.8 20V 4ADRGherghescu Gabriel
 
Siguranţe fuzibile pana in anul 1996 AUDI
Siguranţe fuzibile pana in anul 1996 AUDISiguranţe fuzibile pana in anul 1996 AUDI
Siguranţe fuzibile pana in anul 1996 AUDIGherghescu Gabriel
 
Motor AUDI A4 B5 1996 2000 1.8 20V 4ADR
Motor AUDI A4 B5 1996 2000 1.8 20V 4ADRMotor AUDI A4 B5 1996 2000 1.8 20V 4ADR
Motor AUDI A4 B5 1996 2000 1.8 20V 4ADRGherghescu Gabriel
 
General AUDI A4 B5 1996 2000 1.8 20V 4ADR
General AUDI A4 B5 1996 2000 1.8 20V 4ADRGeneral AUDI A4 B5 1996 2000 1.8 20V 4ADR
General AUDI A4 B5 1996 2000 1.8 20V 4ADRGherghescu Gabriel
 
Compart 3 AUDI A4 B5 1996 2000 1.8 20V 4ADR
Compart 3 AUDI A4 B5 1996 2000 1.8 20V 4ADRCompart 3 AUDI A4 B5 1996 2000 1.8 20V 4ADR
Compart 3 AUDI A4 B5 1996 2000 1.8 20V 4ADRGherghescu Gabriel
 
Air flow sensors AUDI A4 B5 1996 2000 1.8 20V 4ADR
Air flow sensors AUDI A4 B5 1996 2000 1.8 20V 4ADRAir flow sensors AUDI A4 B5 1996 2000 1.8 20V 4ADR
Air flow sensors AUDI A4 B5 1996 2000 1.8 20V 4ADRGherghescu Gabriel
 

More from Gherghescu Gabriel (20)

Modele si variante bac matematica m1 2010 (model oficial)
Modele si variante bac matematica m1   2010 (model oficial)Modele si variante bac matematica m1   2010 (model oficial)
Modele si variante bac matematica m1 2010 (model oficial)
 
9 varianta oficiala bac matematica m1 2010 (prima sesiune)
9 varianta oficiala bac matematica m1   2010 (prima sesiune)9 varianta oficiala bac matematica m1   2010 (prima sesiune)
9 varianta oficiala bac matematica m1 2010 (prima sesiune)
 
9 barem varianta oficiala bac matematica m1 2010 (prima sesiune)
9 barem varianta oficiala bac matematica m1   2010 (prima sesiune)9 barem varianta oficiala bac matematica m1   2010 (prima sesiune)
9 barem varianta oficiala bac matematica m1 2010 (prima sesiune)
 
6 varianta oficiala bac matematica m1 2010 (sesiune august)
6 varianta oficiala bac matematica m1   2010 (sesiune august)6 varianta oficiala bac matematica m1   2010 (sesiune august)
6 varianta oficiala bac matematica m1 2010 (sesiune august)
 
6 barem varianta oficiala bac matematica m1 2010 (sesiune august)
6 barem varianta oficiala bac matematica m1   2010 (sesiune august)6 barem varianta oficiala bac matematica m1   2010 (sesiune august)
6 barem varianta oficiala bac matematica m1 2010 (sesiune august)
 
Algebra clasa a 9a si a 10 a teorie cu teste si nrezolvari in detaliu
Algebra clasa a 9a si a 10 a teorie cu teste si nrezolvari in detaliuAlgebra clasa a 9a si a 10 a teorie cu teste si nrezolvari in detaliu
Algebra clasa a 9a si a 10 a teorie cu teste si nrezolvari in detaliu
 
Algebra clasa a 9a si a 10 a cu teorie si teste cu rezolvari in detaliu
Algebra clasa a 9a si a 10 a cu teorie si  teste cu rezolvari in detaliuAlgebra clasa a 9a si a 10 a cu teorie si  teste cu rezolvari in detaliu
Algebra clasa a 9a si a 10 a cu teorie si teste cu rezolvari in detaliu
 
AUDI Siguranţe fuzibile incepand cu an 1996
AUDI Siguranţe fuzibile incepand cu an 1996AUDI Siguranţe fuzibile incepand cu an 1996
AUDI Siguranţe fuzibile incepand cu an 1996
 
Pionier deh 2000 mp ownersmanual1019 audi
Pionier deh 2000 mp ownersmanual1019 audi Pionier deh 2000 mp ownersmanual1019 audi
Pionier deh 2000 mp ownersmanual1019 audi
 
Montare carlig remorcare audi a4 b5
Montare carlig remorcare audi a4 b5Montare carlig remorcare audi a4 b5
Montare carlig remorcare audi a4 b5
 
Cutie sigurante audi
Cutie sigurante audiCutie sigurante audi
Cutie sigurante audi
 
A3 1997 AUDI maintenance
A3 1997 AUDI maintenanceA3 1997 AUDI maintenance
A3 1997 AUDI maintenance
 
A3 electrical AUDI A3 1997 2000 1.8 20V 4ADR
A3 electrical AUDI A3  1997 2000 1.8 20V 4ADRA3 electrical AUDI A3  1997 2000 1.8 20V 4ADR
A3 electrical AUDI A3 1997 2000 1.8 20V 4ADR
 
Siguranţe fuzibile şi relee AUDI A4 B5 1996 2000 1.8 20V 4ADR
Siguranţe fuzibile şi relee AUDI A4 B5 1996 2000 1.8 20V 4ADRSiguranţe fuzibile şi relee AUDI A4 B5 1996 2000 1.8 20V 4ADR
Siguranţe fuzibile şi relee AUDI A4 B5 1996 2000 1.8 20V 4ADR
 
Siguranţe fuzibile pana in anul 1996 AUDI
Siguranţe fuzibile pana in anul 1996 AUDISiguranţe fuzibile pana in anul 1996 AUDI
Siguranţe fuzibile pana in anul 1996 AUDI
 
Motor AUDI A4 B5 1996 2000 1.8 20V 4ADR
Motor AUDI A4 B5 1996 2000 1.8 20V 4ADRMotor AUDI A4 B5 1996 2000 1.8 20V 4ADR
Motor AUDI A4 B5 1996 2000 1.8 20V 4ADR
 
General AUDI A4 B5 1996 2000 1.8 20V 4ADR
General AUDI A4 B5 1996 2000 1.8 20V 4ADRGeneral AUDI A4 B5 1996 2000 1.8 20V 4ADR
General AUDI A4 B5 1996 2000 1.8 20V 4ADR
 
Compart 3 AUDI A4 B5 1996 2000 1.8 20V 4ADR
Compart 3 AUDI A4 B5 1996 2000 1.8 20V 4ADRCompart 3 AUDI A4 B5 1996 2000 1.8 20V 4ADR
Compart 3 AUDI A4 B5 1996 2000 1.8 20V 4ADR
 
Audi a6 adr
Audi a6 adrAudi a6 adr
Audi a6 adr
 
Air flow sensors AUDI A4 B5 1996 2000 1.8 20V 4ADR
Air flow sensors AUDI A4 B5 1996 2000 1.8 20V 4ADRAir flow sensors AUDI A4 B5 1996 2000 1.8 20V 4ADR
Air flow sensors AUDI A4 B5 1996 2000 1.8 20V 4ADR
 

Recently uploaded

MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Doge Mining Website
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environmentelijahj01012
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
Call Girls Contact Number Andheri 9920874524
Call Girls Contact Number Andheri 9920874524Call Girls Contact Number Andheri 9920874524
Call Girls Contact Number Andheri 9920874524najka9823
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in PhilippinesDavidSamuel525586
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFChandresh Chudasama
 

Recently uploaded (20)

MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
Unlocking the Future: Explore Web 3.0 Workshop to Start Earning Today!
 
Call Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North GoaCall Us ➥9319373153▻Call Girls In North Goa
Call Us ➥9319373153▻Call Girls In North Goa
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environment
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
Call Girls Contact Number Andheri 9920874524
Call Girls Contact Number Andheri 9920874524Call Girls Contact Number Andheri 9920874524
Call Girls Contact Number Andheri 9920874524
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in Philippines
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDF
 

High tunnels constructiontips

  • 1. Construction Tips • cordless drill and drill bits (plus H oop house construction can be as exacting or casual as you like. However, not paying attention to initial details can cost spares) for the various size fasteners you plan to use; • good step ladder; confidence whenever you are ready. There is nothing worse than grabbing an hour here or there to work on a high tunnel only to find that someone extra time in the long run, and the • socket set; bumped the stake and all your work is resulting structure may not look as • drift punch or pipe wrench; now out of line. nice or stand as long. • miter saw or circular saw; • speed square; Ground Posts Two people with good construction As farmers, we are striving for a • hacksaw or saws-all; skills can erect a 30' x 96' high tunnel loose, well-structured soil in which to • power cord; and in about a week. The 75 to 100 hour grow our plants. But we need a • tape measures (12', 25', and 100'). estimated completion time assumes medium with the opposite that all materials are on site. Setting characteristics to support a building. An experienced high tunnel builder up the metal frame, installing (If you have concerns about your site advises: “a cordless drill (preferably baseboards and hipboards, roll-up and its ability to support a high tunnel, one with ample batteries) will be your sides, and building endwalls are check with a qualified professional.) best friend for fastening those millions included. Additional time will be of quarter inch bolts and nuts.” required for site preparation, utility A high tunnel’s foundation is installation and covering the tunnel provided by ground posts, which are with polyethylene film. Batter Boards steel pipes partially buried in the It is important to set up batter boards ground. On rocky ground, in high Most manufacturers provide at the start of high tunnel construction wind areas, or where significant instruction manuals with the frame (see Diagram 4 below). The small ground disturbance occurred during and technical support if needed. amount of extra time involved will be site preparation, a little additional Some, however, are less helpful than well-rewarded by the increased ease support may be warranted. In these others in their support so inquire of construction. The use of these specific situations or for extra before selecting a company. The most semi-permanent building markers is stability, a couple shovels of cement important step is to make certain that described at will effectively keep ground pins in the site is square and uniformly www.dulley.com/deck/deck01.shtml. place. pitched or level. If this is done carefully, the frame should install Batter boards define the corners and A sledgehammer is commonly used to easily. heights of the high tunnel. They allow drive in short ground posts. Most you to erect the structure with companies provide a protective piece Instead of step-by-step instructions for constructing a high tunnel, here we offer tips to save you time and money. We hope these recommendations enable you to complete your project with less stress and more confidence. Start with an adequate selection of tools to make the construction process a pleasant one. Tools to assemble include the following: • level, level string, chalk line, and transit; • long-handled mallet or sledge hammer for driving ground stakes; • post-hole digger for endwall posts; 40 – High Tunnels
  • 2. to put in the pipe to protect the end To ensure that the posts are placed at Raising a heavy bow on a wide tunnel from being damaged or the correct height, use a transit, hose (20' or wider) is best accomplished “doughnuting.” For a taller structure level, or laser level. Then take down with at least three people. One person with extended ground posts, John the batter boards and run a high- stands at each leg of the bow, and a Biernbaum (who researches and strength nylon mason cord between third pushes the bow up in the air with teaches about high tunnels at the corner ground posts. Pull the a pike pole. This is heavy work. Each Michigan State University) has found string as tightly as you can to bow will need to be picked up and that a post or fence pounder works minimize droop over the long wiggled onto the spline/ground posts. better. distance. Be careful; if a tight nylon Use one or two pike poles to keep the string breaks, it can hurt someone as bow assembly from falling while the The ground posts at the four corners the end whips past. crew wiggles it onto the ground posts. should be solidly cemented in. For tunnels over 70' long, also cement in The bows – and therefore the ground Purlins the intermediate ground posts in the posts – of most high tunnels are Purlins help stabilize the high tunnel. middle of the long sides. Cement must spaced on 4', 5', or 6' centers. A They are bolted to the bows, along the be placed below the soil freeze zone, wooden template with notches at 4' length of the structure. Typically a 30' as the freezing action can force the (or whatever the bow spacing is) tunnel will have five purlins, ground pin up out of the ground. You eliminates the need for the time- including the ridge pole. may want to use caution when consuming and awkward task of employing cement as this may move measuring from bow center to center. The purlins can be attached once the the structure into a ‘permanent’ Ledgewood and Rimol provide their bows are loosely assembled and in classification. greenhouse customers with these place. A platform is much safer than spacers. They are also easy to make. ladders and saves a tremendous Steve Moore suggests a good way to John Biernbaum regards them as amount of time and energy. Use a hay keep the ground posts in place so they essential for construction. wagon, truck bed, or scaffolding, don’t pull out of the cement or slide especially if you can pull it along as down: pre-drill the ground posts Alternatively, Steve Moore you go! within 2" or 3" of the bottom and recommends measuring from the insert a 4" to 6" piece of rebar. same side of a post every time to A drift punch or pipe wrench can be attain an accurate center used to help align bow and purlin The ground posts need to be in the measurement. Taping the end of the holes. As you attach the purlins, right location and at the right height. measuring tape to the corner ground tighten all bow bolts, except those that A jig made with two old boards and post is one simple way to do this. A connect the bow to the ground pin. some broccoli-type rubber bands or level should be used to ensure the Finally, when you are at the end bow, thin bungee cords will align the posts posts are vertical/plumb. A post level with all the purlins in place, you are with the strings between the batter that has bubbles at 90 degree angles is ready to “plumb” the gable end to boards that outline the high tunnel. useful because both directions can be straighten the entire bow/purlin (See diagram below.) It will also keep seen at once. assembly. the posts at the desired height. This simple device is removed once the Bows Attach one string with a plumb bob to cement hardens in 12 to 24 hours. Bows typically consist of two or three the top point of the outside edge of the shorter pieces of metal tubing. last bow, and a second ground string Preassemble bows loosely. Do not to the outside edge of the bottom bow. tighten the bolts. This loose bow Allow the plumb bob string to come assembly will help in purlin within 1/8" of the ground string. installation. (Purlins are horizontal pieces typically made of pipe that is a A good way to adjust and hold the smaller diameter on one end high tunnel plumb is to attach a come- (swedged) to fit inside the next pipe.) along to a large immovable object like a tree or truck and then attach a rope Historically, pike poles were used to or chain from the come-along up to push up large sections of timber the bow. A come-along’s ratcheting framing for barns. Pike poles also mechanism and its steel cable allow have a place in erecting high tunnels. for quick and precise alignment of the tunnel. Now you can tighten all 41 – High Tunnels
  • 3. remaining bolts and install the wind the bow. Ted Blomgren recommends If you use a rigid gable-end covering, braces. using a washer on the wood screw. such as polycarbonate, the outside of the baseboard will need to be flush Baseboards The frame will be complete after the with the outside of the bow. To make The baseboards sit on the ground hip board (2" x 6" lumber) along with it flush, attach an 8" piece of universal along the sides of a high tunnel. They “poly lock” or “wiggle wire” base is corner (a thin-walled piece of angle are bolted to the ground posts. Use attached to the bows approximately 5' iron with multiple holes for bolting) 1.5" x 8" lumber for baseboards. or 6' off the ground. (Poly lock is the with the same bolts that hold the side trade name for an extrusion for baseboard. Consider sourcing your lumber from attaching the polyethylene film to the local family-owned and operated structure. It serves the same purpose Insulation sawmills. Often boards from these as wiggle wire.) This will serve as the In cold climates, insulation can make a mills are sawn several inches longer point of attachment for the plastic significant difference in the than their designated length, rather covering. performance of high tunnels. In Zone 6, than being trimmed down to an exact, burying 1" thick by 2' wide rigid foam even foot measure. This extra length The hip board should be inspected at (i.e. polystyrene) isolates frozen ground will allow you to cut the ends at a 45 each change of polyethylene to make from growing areas. The thickness and degree angle for joining together at sure it will be sound for another four depth of insulation should be modified the bows with a 1/4" machine bolt or five years. Farmers should be according to your climatic zone. This (see diagram below). aware of rot and ready to replace the foam should be buried at an angle to baseboard as necessary; the plastic gain more benefit from the thermal need not be removed to do so. mass of the earth. The angled placement also makes installation easier and Gable Ends allows space for the cement support at Doors should be large enough for the bottom of the ground pin (see ventilation and easy access. They can diagram below). Insulation can also be span even the full width of the high used in pathways and along the lower tunnel. To maximize airflow and portion of the sidewalls. accessibility, some farmers construct removable end walls. A smaller, Use a long 1/4" bit to drill out the personal door that opens inward holes for the bolt through the wood makes a convenient winter passage. from the inside of the high tunnel. This added length is helpful when Unless the high tunnel will have very attaching framing to bows. wide doors, some tasks such as adding compost, tilling the soil, and installing Machine bolts are superior to carriage utilities are best accomplished before bolts for attaching the poly hold-down the gable ends are closed in and strips to the baseboard. Carriage bolts access is restricted. are often used for this purpose, but they rust fast. When the baseboard Gable end framing can be done with needs to be replaced, sometimes the steel or wood. If using wood, either nuts are stuck in place and won’t turn. select one of the rot-resistant species Hiring Out Construction With a wrench on either side of the recommended for the baseboards (see For some farmers, hiring an nut and bolt, the machine bolts will materials section) or be prepared to experienced crew to do the installation break off much faster and easier than replace the wood as needed. Steve may be the best option. The estimated hack sawing carriage bolts, which Moore uses rough sawn 2 x 4s to frame labor cost for basic high tunnel only turn in the wood. the gable end. When the wood rots construction used to be fifty cents to right at the soil line where moisture one dollar per square foot. However, While bolts may be better for and air meet, rather than take apart the due to inflation, the labor bill for high attaching the base boards and hip whole assembly, he just pounds in a U- tunnel construction in previous years boards to the bows, galvanized pipe shaped steel fence post and lag or may not be relevant for estimating straps can also do a good job, as long machine bolts it to the post that had costs under current conditions. Like as the pipe strap is also tek-screwed to rotted off. “This buys me a good many any construction project today, expect more years service,” he says. skilled contractors to be expensive. 42 – High Tunnels
  • 4. Bending Your Own Frames Rather than purchasing a hoop house kit, some farmers choose to bend their own. A good role model for this activity is Ed Person of Ledgewood Greenhouse. This New Hampshire farmer went from bending frames for his own use to developing a substantial independent business that sells and delivers high tunnel frames throughout the Northeast. For savvy shoppers, fabricating a high tunnel steel frame can save money. It also allows farmers to realize a better design idea, satisfy unique needs, or add onto an existing high tunnel. Ted and Jan Blomgren bent several Gothic arch high tunnel frames for their farm. Three people worked for about the equivalent of one week fabricating the jigs and bending and drilling the component parts for three and a half 30' x 96' high tunnels with trusses. At the time, they were able to make their own high tunnel frames for a third of the cost of a kit, thanks to a farmer friend’s tip about a supplier of economically priced steel. Ted cautions though that purchasing steel from a local chain link fence supplier might actually cost more than buying a kit with pre-bent, pre-drilled steel. The Blomgrens’ bows consisted of two long side pieces with a shorter, smaller diameter piece at the ridge. In all, they used three sizes of steel pipe—1.9", 1.6" and 1.3" diameter for bow, small ridge bow, and purlins, respectively—to fabricate all the high tunnel components including trusses. The only new tools they needed were a chop saw and drill press outfitted for cutting and drilling steel. After four years, there is no rust at the bends and the galvanized coating has not popped off. They built the two jigs needed for bending the steel for the bows by replicating a bow they had removed from their existing high tunnel. To bend the steel, they placed a jig, made of two-ply 3/4" plywood and lumber, on the level cement floor of their garage, braced against its foundation. For the easier, shallow bend, they were able to use their sedan with a steel cable attached to the trailer hitch. The more acute portion of the bow required the weight and traction of their heavy John Deere tractor. To compensate for the springback in steel, they bent it until it fit a pattern they had outlined on the floor. Bending the bows for a high tunnel can be a simpler process. For example, Thomas Christenfeld, a neighbor of the Blomgrens, bent the bows for his Quonset-style greenhouse using a silo as a jig. He stuck one end on one of the hoop bolts that holds the concrete panels of the silo together and bent the other end around the silo. Two people are needed to get a good enough bend in the pipe and that it probably only works for a single piece hoop. Thomas notes, “You cannot get any real bend in the ends of the pipe so two pieces stuck together leaves a flat part on top of the hoop house, which is far from ideal in a snowy climate.” Another Way to Bend Your Own Kevin Loth, who is contractor as well as a farmer, has fabricated his family’s 20' x 200' Quonset-style high tunnels near Lincoln, Nebraska. The Loths have two heated greenhouses and two year round high tunnels. By bending his own bows, he was able to get twice as much ground under cover than if he purchased kits. His calculation included what he paid a helper but not his own time. He said if you don’t drill the bows, you could probably bend them in a day, though set up might take a couple of days. With a borrowed pipe bender, he made bows out of the 15 gauge metal pipe used as a chain-link fence top rail. He saved considerably on the pipe by purchasing it by the bundle of 91 pipes. Because the pipe comes in 21' lengths, he had to swedge together one and a half lengths for each bow. While a swedging tool can be expensive, often when you buy fencing steel, one end comes already swedged. His finished tunnels are Quonset-shaped, 10' high at the peak. Their bows are 4' on center, and they have two purlins but no trusses. Kevin has attached the purlins and bows in several ways. Holes should be drilled prior to bending the bows. For the less technically adept, purlin clamp connectors (available from greenhouse suppliers) or pipe clamps (from plumbing supply outfits) preclude the need to drill holes for the bolts attaching the purlins. Getting these holes to line up properly can be difficult. Moreover, the very act of drilling holes weakens the steel. While the purlin connectors are aluminum, Kevin dismisses concern about mixing metals as the tunnel’s steel is galvanized. He thinks this is less of an issue than drilling holes as that action exposes ungalvanized steel and weakens the structural pieces. Also he noted that the ends of the bows are in contact with corrosive cement and soil acids. 43 – High Tunnels
  • 5. Covering a High Tunnel stroke, bringing the plastic overhead plastic down to the end and finish the Farmers employ several methods for so that it clears the peak without gable end. The reason for the getting the unwieldy expanse of getting caught. staggered start and attachment is to polyethylene film over the top of large avoid see-sawing the plastic side to hoop house structures and evenly The two people walking along the side. The lead attachers must always attached. The size of your crew helps sides can have an exceedingly long keep the selvage edge the same while determine which methods are most way to pull the plastic. When they the other side pulls the plastic to feasible. The most important rule of reach the middle of a long tunnel, two match. thumb is never attempt to cover a more people standing at the original tunnel on a windy day. gable end should assist pulling the Getting all of the wrinkles out is not plastic along. These additional people important if you are going to inflate. It Covering a large (i.e., 30' x 96') high also help keep the plastic from is important not to pull the poly film tunnel with a single layer of poly becoming a sail if a sudden gust of so tight that the wiggle wire in the U should take four or five people two or wind comes along. channel perforates the new plastic. three hours. There is a learning curve so the first few times may take longer. After the whole tunnel has been A variation on the pull-over-the-end covered, it’s time to even out the method of covering a high tunnel is Method A: Pull over the end. plastic. The selvage edge must be used by the Kilpatrick family. They For this method, four or five people even for the entire length of the tunnel set up the plastic on scaffolding at one and a center-folded roll of and should be 12" or longer. You end of the tunnel as described above. polyethylene are required. (You can don’t want the edge to run out! “Make sure the scaffolding is above order your polyethylene folded in the peak of the structure. While one several ways.) If you are putting a second covering person pulls the plastic down the on, just tack it on the first layer using length of the high tunnel, the others The first step is unrolling the plastic. just a couple strategically placed poly assist from the ground.” Philip and To do this, set up a pair of fasteners (i.e., wiggle wire) and repeat Michael Kilpatrick have found that for cinderblocks a few feet further apart the process with the second covering. work on the purlins, scaffolding than the length of the roll of Otherwise, proceed to the next step. mounted on a cart is far more polyethylene. For a 12' tube, set the convenient than using a ladder. blocks about 14' apart. Then put a Once you are satisfied that the plastic pipe in the tube. Make cardboard is even on the edge, temporarily Method B: Ridge-roll. washers about 1' square to put on the secure the plastic in place at three or This is one of the two ways that the ends of the pipe. The washers serve to four points on each side. The most Blomgrens cover their tunnels. (The protect the ends of the rolled up common method for securing the other way is described in Method C.) polyethylene from abrasion against plastic is wiggle wire inserted into a U Both methods involve climbing up the the cinderblocks when you unroll it. channel. An alternative assembly is high tunnel and thus entail danger. This set up should allow the plastic to homemade—wood attached with Use these methods at your own risk. freely unroll. drywall screws every 6" to 8". Covering a high tunnel with a lean The next step, getting the plastic over Now you are ready to fully secure the crew (four people) necessitates a the tunnel, requires five people. One single or double layer of plastic. The different method. Once again, make person is stationed on a ladder at a person on the ladder inserts wiggle sure to obtain greenhouse plastic with gable end of the high tunnel. Wearing wire from the top down on one of the its fold down the center so it will a hooded sweatshirt is recommended gable ends. Next the plastic film at the unfurl properly. to avoid plastic rubbing and to other gable end should be pulled and counteract the static electric generated that plastic “tacked” down. Once one In this technique two people carry the by moving the plastic film over head. gable-end plastic is permanently entire roll of poly up to the top of the The center of the end of the poly is attached and the other gable end has high tunnel. A bucket loader is handy passed to the person on the ladder. been “tacked” in place (with a short for this purpose. Before climbing up, The film unrolls as it is pulled up the wiggle wire), one side can be attached they insert a pipe into the cardboard ladder. Two people on the ground for a distance of about three bows. tube to assist in unrolling it. With the hold the corners and walk along side Remember to keep a constant selvage roll sitting on the top purlin, they the tunnel as the plastic is unfurled. (waste) edge. Another person (or two) temporarily fasten it on the gable end Meanwhile the person on the ladder starts on the opposite side of the first of the tunnel. Then they proceed to does a sort of butterfly swimming group and both groups attach side walk it down the tunnel, making use 44 – High Tunnels
  • 6. of the side purlins, walking the roll For a big tunnel (30' x 96' or 150'), at If you choose to use wooden batten along as they go. By the time the pair least eight people are needed for this boards to fasten the plastic to the hip has walked halfway down the tunnel, method. Start by unrolling the plastic board, you would be wise to use a pair the plastic will have begun unfurling, (without unfolding it) along the side of batten boards one above the other with half falling down one side and of the high tunnel. If there is a risk of with the plastic outside of the top one half down the other. (This unrolling the slightest wind, it is best to be on and behind the bottom one. This more procedure will go much more quickly the windward side of the tunnel. effectively locks the poly in place. if the high tunnel is designed so that (See diagram below.) the ridge purlin is situated on top of After the plastic has been unrolled, the bow. This is an atypical purlin people station themselves at regular placement and is only advisable for intervals along the tunnel. They each tunnels that will never be covered take hold of what will become the far with a double, inflated layer of poly.) edge of the poly. Pulling this edge, they climb up and over the tunnel. Meanwhile the two other people, who With enough people, the weight of the are on the ground, are starting to poly is distributed and not tentatively connect the poly to the hip burdensome to anyone. board just above the roll up sides. Once the plastic is over the top of the After the plastic has been unrolled structure, it is squared up, and then along the entire length of the tunnel, temporarily fastened to the gable the two people who have been ends. They then proceed as in the walking the ridge with the roll of poly above description, with teams starting temporarily connect the poly with from opposite sides of one end and After you have to undo rusty screws wiggle wire at the top of the second both working toward the far end. or other failing attachments to remove gable end. They then climb down and old poly, you will probably come to join the two folks on the ground. With There is an alternative to climbing up believe that wiggle wire is a bargain at two people on each side of the tunnel, and over the greenhouse. Ropes may a $1 per foot. When attaching new they square up the plastic, and then be attached to the plastic along its poly with wiggle wire, don’t pull the begin attaching the plastic along the side. Clips available from greenhouse poly too tight (or over inflate). The top of the roll up sides. With the two suppliers can be used to secure the wiggle wire will actually cut teams working on opposite sides of rope to the plastic. Alternatively, wrap perforations (corresponding to the the tunnel, they start at one end, and tennis balls in the plastic and use them wiggle wire) in the new cover if there work toward the other end. to help fasten the rope. Toss the ropes is too much tension. This applies to over the tunnel structure and, once on double layers of poly, too. They then finish the gable ends, the other side, pull the plastic over. taking up the slack and smoothing out When attaching plastic to battens (thin wrinkles, before permanently boards less than 1/2" x 1-1/2"), use attaching it there. They trim off the Tips for Attaching the double headed nails—rather than regular nails—for easier removal. excess plastic at the gable ends so it Plastic doesn’t flap in the wind. To complete Galvanized screws are another option. Single poly can be difficult to keep on the covering, the roll up sides must be a structure because there is no tension attached. from an inflation fan to reduce flapping. Steve Moore has used wide Method C: Over the side. poly strapping placed between every Like the previous method, this other bow and attached to the covering procedure used by the baseboard to keep the cover in place. Blomgrens has safety and liability This increases the longevity of the issues. As an alternative to climbing plastic film, and also reduces a over the tunnel frame, Steve Moore farmer’s worry about losing the suggests attaching grommets to the plastic on the tunnels (and sleep) on plastic and using ropes to pull it over windy nights. the structure. 45 – High Tunnels
  • 7. Getting the Right Pressure on Your Inflation Correct pressure ensures a balance between over and under inflation. By providing sufficient tightness of the plastic, flapping is minimized. If the plastic is stretched too tightly, light transmission is reduced. Simply put, correct pressure increases the life of the plastic and its ability to transmit light. A manometer is an instrument used to measure the pressure of a gas. For high tunnels with a double poly layer, it is useful for determining the proper inflation pressure. Steve Moore makes his own homemade manometer using this simple procedure. On the inside of the tunnel, attach a 2" x 8" (or wider) board with carriage bolts to two of the bows at a 4' to 6' height. (This board can be used to mount the inflation fan as well.) After covering the high tunnel with the first layer of poly, a 4" to 6" square piece of polycarbonate is attached with drywall screws to the wood before the tunnel is covered with a second layer of poly. From the interior of the tunnel, drill a hole through the wood, the inside layer of plastic and the small piece of rigid material. From the inside, push a clear flexible plastic tube (available by the foot at most hardware store) into the wood, allowing the tube free access to the air between the layers. The tube's internal diameter can be from 3/4" to 1". Caulk around the tube so that it is airtight to prevent leaks. Let the tube form a "U" with one of the top legs of the U going through the wood. Attach the other top of the U tube to the board and fill the bottom of the U with a colored liquid (blue washer fluid or colored water). Mark level horizontal lines ¼ of an inch apart on the board next to the U portion of the clear tube. If the interior air level of the U is ¼ inch higher than the inflation side of the U, then the pressure is about right. The liquid level on the side of the U that is attached to the board should be 1/4 " lower than the side of the U that is open to the inside of the tunnel. Adjust the pressure by using a damper on the intake of the inflation fan. You can make a damper with a flat piece of metal, like an old can lid (taped to keep from cutting yourself). Insert a screw through the top edge of the metal lid. Attach it tightly enough to the intake of the inflation fan that it will stay in place at various degrees of opening. Steve has used solar power to run the inflation fan and his monitoring equipment. 46 – High Tunnels