Publicité

Presentation for Final Year Students about Solar.pptx

10 Aug 2022
Publicité

Contenu connexe

Publicité

Presentation for Final Year Students about Solar.pptx

  1. Solar System Installation By: AMS Green Energies (Pvt. LTD)
  2. Component of Solar Pv system.
  3. SOLAR PANELS Solar Panels or PV modules are the most commonly known component in a photovoltaic array. Made up of mostly solar cells, framing, and glass; solar panels work by collecting and harnessing photovoltaic energy from the sun, and delivering that energy as ‘direct current’. The DC power generated by a solar module is an electric current that flows in a constant direction. This type of power is generally not readily useable for standard electric demands, and must be translated into ‘alternating current’ (AC) power before it can be used for standard electric devices inside a home or building. Solar Panels consist of two most well-known types of solar cells, Polycrystalline and Monocrystalline. The difference consists of how silicon crystals in the ingots or wafers are harvested, developed and formed, each creating a different look and color to their appearance. Both types of PV cells are known to be effective in their general ability to produce solar electricity. EVA(ethyl vinyl acetate) is a layer used to encapsulate the photovoltaic cells.
  4. INVERTERS Inverters (or Converters) intake DC power generated by a solar panel and process that energy by converting it into AC power, the resulting power can then be sent to a breaker or balance of system component and is available for standard use. Inverters come in different types of sizes and use various technologies to enable efficiency in the function to produce AC power. The most common inverters are; String Inverters, Central Inverters, Microinverters, and Battery- based Inverters. Each will carry different mechanical and technical characteristics.
  5. Mounting/Racking Structure Most racking systems will use a combination of: Rails, Flashings, Lugs, Mounting Brackets, Wire Clips, Splice Kits, Braces, End Caps, Attachments, Tilt Legs - and other components to complete a full racking and mounting system. Ground mount systems will require concrete and steel piping in addition to a complete racking kit to be placed onto land. Two types of structure are Used for Panel installation. 1 Ground Mounting Structure. 2 Customized structure.
  6. Ground Mounting Structure Ground mount systems will require concrete and steel piping in addition to a complete racking kit to be placed onto land.
  7. LOCATION: Plaspack Factory PROJECT SIZE: 50Kw Costumized Structure
  8. Types of PV system Hybrid Grid-connected solar system with battery storage. On- grid On Grid with Batteries This system includes both batteries as well as grid. also known as a grid-tie or grid-feed solar system 1. Benefit of both Batteries as well as Grid feeding. 1. Grid feeding which results in lower bill costs. 1. Allows you to store excess solar or low cost (off-peak) electricity. 2. Reduces power consumption from the grid (reduced demand) 3. Higher cost. Mainly due to the high cost of batteries.
  9. Hybrid System Modern hybrid systems combine solar and battery storage in one and are now available in many different forms and configurations. The battery bank. In a hybrid system once the solar power is used by the appliances in your property, any excess power will be sent to the battery bank. Once the battery bank is fully charged, it will stop receiving power from the solar system. The energy from the battery can then be discharged and used to power your home, usually during the peak evening period when the cost of electricity is typically at it’s highest. The meter and electricity grid. Depending on how your hybrid system is set up and whether your utility allows it, once your batteries are fully charged excess solar power not required by your appliances can be exported to the grid via your meter. When your solar system is not in use, and if you have drained the usable power in your batteries your appliances will then start drawing power from the grid.
  10. HYBRID SOLAR SYSTEM
  11. On-grid These systems do not need batteries and use either solar inverters or micro-inverters and are connected to the public electricity grid. Any excess solar power that you generate is exported to the electricity grid and you usually get paid a feed-in-tariff (FiT) or credits for the energy you export. The meter. Excess solar energy runs through the meter, which calculates how much power you are either exporting or importing (purchasing). The electricity grid. Electricity that is sent to the grid from your solar system can then be used by other consumers on the grid (your neighbors). When your solar system is not operating, or you are using more electricity than your system is producing, you will start importing or consuming electricity from the grid.
  12. On-Grid SOLAR SYSTEM
  13. Advantages of On-Grid System 1. Huge reduction in electricity bills With net-metering in place, the consumer has to pay only for the surplus electricity he consumes, ensuring the bill generated every month is reduced drastically. Many of our customers have been able to reduce their monthly bills by 90%. 2. Easy maintenance The elimination of batteries in the on-grid system makes the maintenance quite easy. It also eliminates the cost of upkeep of the batteries 3. Synchronize with other sources of power These systems can also synchronize with a diesel generator on site. This is important in case grid power is not available. (We should add a link here to connect with another blog or technical article to learn more about this) 4. Better ROI Cost of a On-grid solar system is lower than other types of solar systems because there are no batteries. It also generates the highest amount of power compared to other types of solar systems. The minimal maintenance and reduction in monthly power bills ensure the customer gets an ROI of 25 – 30%. This means the customer earns Rs.25,000 for every 1,00,000 they invest in solar.
  14. On Grid with Batteries In this system, the customer enjoys the benefit of both Hybrid as well as On Grid system. The excess energy is stored in batteries as well as fed back to the grid resulting in dual benefit for the end user.
  15. Efficient and Effective Energy Solution through 15 Year Experienced Technical team Reduce your Electricity bills to Zero. REDUCE YOUR BILLS SELLING FEATURES Online Monitoring Up to Mark Which will Convert your Solar system More Profitable App Based Monitoring Efficient and Effective Energy Solution through 15 Year Experienced Technical team Payback Time: 2-3 Years.
  16. Scope of Work Site Survey with costumer Electrical/Mechanical Design of project/site. BOQ and Quotation Costumer approval/purchase/work order with advance payment. Procurement of Material/vendor. Material delivery at site. Civil/Mechanical and Electrical Installation at site. Testing and Commissioning. Inspection report of project/site. Plant monitoring through apps.
  17. SOLAR SITE SURVEY Solar project site survey should answer following questions Is there enough space for solar PV installation? What is the shadow free area? What is the average sunlight there? What is the orientation of the building? What would be the azimuth angle? Current state of electrical infrastructure – sanctioned load, current connection etc. The average and peak requirements for the customer
  18. BOQ and Quotation
  19. DESIGNING OF PROJECT A solar PV system design can be done in four steps: 1. Load estimation 2. Estimation of number of PV panels 3. Selection of Suitable equipment 4. Cost estimation of the system.
  20. LOAD ESTIMATION Furthermore you can also look at the electricity bill and see the peak load used by the customer. By a thumb rule, 1 KW of Solar System approximately produces 4 kWh Units per day. In this case, the solar requirement will be = Maximum Peak Units in month (kWh)/4 To calculate for units per day, we divide it with 30: For doing load estimation, you multiply the power utilized by every machine times the hours of the day that you use it. This gives you the absolute number of kWh every day for that apparatus.
  21. LOAD ESTIMATION(CONTD.)  Example, consider the following bill in which peak units are 1200 kWh units/per month We divide it by 30 to get units required per day i.e; 1200/30=40 units per month Furthermore, we divide it by 4 to get the system in kW required for that system: System in kW Required: 40/4= 10kW System required.
  22. LOAD ESTIMATION(CONTD.)  Another way to do load estimation is to multiply the wattage of the fan, lights to the number of hours used per day. For Example, if a light of 12W is lit for 7 hours per day for Solar, then the total Watt hour will be: Energy consumed by bulbs = 12W x 7h = 84 Wh Similarly we add the Watt Hour for all the appliances to get the required Wh for the system.
  23. ESTIMATING NO. OF PANELS  The next step is estimation of Solar Panels required for the system. The roof top area which we measure from Site Survey will come in handy for designing of solar panels for that site. After taking the complete dimensions, we simulate it in different design softwares such as SketchUp, AUTOCAD, Helioscope etc.
  24. Design of Projects Software: Helio Scope  Energy yield simulator.  Detailed financial calculator.  Proposal editor. Electrical Design Software: SketchUp Design: Mechanical 3D Structure Design
  25. 3D Design (SketchUp)
  26. Electrical Design (SLD)
  27. Project Installation After complete procurement of material, the next phase of project is installation. Following is the sequence of work flow in installation phase: 1) Construction of Civil Blocks 2) Curing of Civil Blocks 3) Assembling and installation of Solar Panel Structure 4) Installation of Panels on Solar Structure 5) Stringing of Solar Panels (Attaching Solar Panels in Series) 6) Installation of Cable Duct and Inverter 7) Connection of Cables with Inverter and Earth Bore. 8) Commissioning of the Inverter
  28. Construction of civil blocks Civil Blocks are the first component which is constructed at site before installation. They are important because they serve as a protection for solar panels and structure which are to be installed on the rooftop. The dimension of these civil blocks we use is: 10” Length 10” Width 8” Height One of the main process of civil work is cement curing.
  29. Curing Methods of Curing Maintain the presence of water in the concrete during the early hardening period, Reduce the loss of water from the surface of the concrete, and Accelerate concrete strength gain by supplying heat and additional moisture. It takes 2-3 days in this process. We have to shower it with water regularly for strengthening. GCC-31S water-base concrete curing compound is formulated from hydrocarbon resins and may be used on interior, exterior, vertical and horizontal concrete surfaces.
  30. Solar Panel Installation Process Nevertheless, if installation on the roof is not applicable or desired, the solar panels could also be mounted on the ground. You just need to make sure that there are no objects blocking access to the sun. The following steps explain solar panel installation on a roof: The most common location for the installation of solar PV panels is the roof. Most roofs typically have the desired specifications for the installation, so that panels get the maximum sunlight.
  31.  Assembling and installation of Solar Panel Structure Then, the solar panel mounting system has to be set up. This will support the base of the solar panels. The whole mounting structure must be tilted and have an angle between 10 to 25 degrees to have maximum sunlight exposure.  Install the Solar Panels When the mounts are set up, the solar panel itself has to be installed on the mounting structure. Make sure to tighten up all the bolts and nuts so that it stays stable.  Stringing of Solar Panels The next step in the installation process is to install the electrical wiring. In most cases, MC4 connectors are used because they are suited for all types of solar panels. Make sure to shut off the household’s electricity supply during the wiring installation. Panels are firstly connected in series in order to make an array of panels.
  32. Install Solar Inverter After that, the solar inverter must be connected to the system. It is typically installed near the main panel and it could be both indoors and outdoors. Inverters are more efficient if kept in a cooler place. If the inverter is outdoors, it should be kept out from the afternoon sun. If it is installed indoors, the garage or utility room are usually the best places, since they stay cool for most of the year and have ventilation. Bond Solar Inverter and Solar Battery In Hybrid Systems solar inverter has to be connected to the solar battery. The solar battery storage can save you from worrying about the lack of usable energy during cloudy times, it can also lower the solar battery storage system cost during installation. Connect the Inverter to the Consumer Unit The inverter should be connected to the consumer unit to generate electricity. A generation meter should also be connected to monitor the amount of electricity the solar panels actually produce. You can use your computer or other device to check your solar system’s performance. For example, you can check how much electricity you generate at different times and decide what time is suitable for using your washing machine or other utilities.
  33. Testing and Commissioning and Monitoring of Solar system The final step is to switch the power on and test the newly installed solar panel system. After that, the solar panel installation process is completed.
  34. Superior Multan Road Campus Superior Hospital 1
Publicité