POWER SYSTEM ANALYSIS
USING ETAP
Background:
 Power system analysis is the field of electrical study which deals with the analysis
of electrical power system and it’s behaviour during potential fault scenarios.
 System studies are usually required to be conducted during two major phases of a
project:
- The initial project design phase (Greenfield phase).
- During the modification phase of an existing system (Brown field phase).
 System study is a requisite practice in order to ensure the genuineness of the
multiple system parameters taking into practice during the system design.
 Common parameters taken into consideration during the study are short circuit,
loading, relay settings, motor parameters etc.
 The studies included within system analysis are:
- Load flow study
- Short circuit study
- Relay coordination study
- Arc flash study
- Motor starting study
Why Do We Need Protection:
As we might know an electrical system at times might get exposed to certain conditions
which causes the deviation of voltages and currents from nominal values or states. Under
normal operating conditions, power system equipment or lines carry normal voltages and
currents which results in a safer operation of the system.
But when fault occurs, it causes excessively high currents to flow in a system which causes
damage to the equipment and devices. Thus in order to protect the system from fault its is
necessary to deploy certain protection schemes.
Types of Faults in power system:
1. Symmetrical faults: These are very severe faults and occur infrequently in the power
systems. These are also called as balanced faults and are of two types namely line to
line to line to ground (L-L-L-G) and line to line to line (L-L-L). Only 2-5 percent of
system faults are symmetrical faults.
2. Unsymmetrical faults: These are very common and less severe than symmetrical
faults. There are mainly three types namely line to ground (L-G), line to line (L-L) and
double line to ground (LL-G) faults.
Methodology:
ELECTRICAL SYSTEM MODELLING
LOAD FLOW ANALYSIS
SHORT CIRCUIT ANALYSIS
RELAY COORDINATION
ARC FLASH ANALYSIS
Load Flow Study
 Load flow study is based on analysing the system’s loading scenario i.e. to ensure
whether the loading is proper or not.
 Multiple parameters taken into consideration during the study are the system’s
voltage and current ratings.
 The purpose of this study is:
- To ensure that the voltages at all the buses are maintained with in legitimate
limits.
- To determine the flows in various elements.
- To check that the losses in the system are within the reasonable limits.
- To determine the necessary tap selection for the transformer.
- To determine the active and reactive power flows in the system thereby
performing power factor compensation.
- To ensure that the generator in the system are loaded to within their real and
reactive capability limits.
Short Circuit Analysis
 The purpose of the short circuit study is to analyse the effect of three-phase
(Worst condition of Short Circuit) on the electrical system.
 The fault calculations are in compliance with IEC 60909.
 This study analysis the effect of short circuit fault on the system by taking
into account the fault current contribution of each load on the bus.
 The short circuit study is useful in:
- Determining the total fault current flowing through a bus thereby helping
in selecting the kA rating of the bus.
- Selecting the kA rating of circuit breakers through device duty SC analysis.
- Fault contribution by individual devices.
Sizing of Panels as per ETAP studies
Load Flow Study:
- Power factor of all panels and design capacitor panels as per requirement.
- Voltage drop of at all panels and size cable.
- Overload conditions of all equipment and optimise system design.
Short Circuit Study
- Short circuit current of each panel and selection of all circuit breaker, VCB,
MCCB and fuses as per short circuit current available.
- Cable withstand capacity as per short circuit current available.
Sizing of Panels as per ETAP studies – Load
flow study
Sizing of Panels as per ETAP studies – Short
Circuit Study
Relay Coordination
In order to protect an electrical system the relays and circuit breakers forms an integral part. The
nature of protection shall be such that the breaker nearest to the point of fault shall be the first
one to trip and isolate the fault section followed by the backup protection. A general scheme is
shown below:
- The above figure depicts 3 levels of relays along with the power source. Here R1 would be
referred to as the primary protection and R2 and R3 will constitute to be Secondary or backup
protection.
- The point fault is nearest to the relay R1. As per the ideal protection scenario R1 must be the
first one to actuate followed by R2 and R3.
- Although if somehow R2 or R3 trips before R1 then this would case whole section to shut
down rather than just a load.
- So, in order to avoid this anomaly relay coordination study is conducted to adjust the tripping
sequence of relays.
Above figure illustrates an overcurrent protection scheme for radial distribution system of fig 15.2,
with definite time relays. Relay R1 does not have any coordination responsibility and hence it can
trip without any intentional time delay. Relay R2 has to coordinate with relay R1 and hence its time
of operation is delayed by time equal to Coordination Time Interval (CTI). Relay R3 has to back up
R2. Hence its time of operation is delayed by another CTI. Thus, we see that as we move along
towards source, the relaying action slows down. Typically, there is an upper limit on any fault
clearing time in the system and it equals approximately 1sec. This limit would be hit near the relay
close to source.
Coordination tree:
Fig 15.9 shows a coordination tree. Each node in the
tree indicates a relay. An edge exists between two
nodes of the tree if, the corresponding relays have a
primary backup coordination relationship. The source
node is also called as the "root node". The terminal
nodes except the source node are referred as leaf
nodes.
In a directed tree, nodes have parent child
relationship. Parent node of a node A refers to the
adjacent node which supplies power to node A. In a
tree, each node except source node has a unique
parent. Conversely, a node fed by the parent is
called a child. Root node has children but no parent.
Similarly, leaf nodes have parent but they do not
have any child. Note that except at leaf nodes, a
relay plays the dual role of primary and back up
protection.
Long-Time delay Setting (tr):
• Long time delay (tr) sets length of time that the circuit breaker will
carry a sustained overload before tripping.
• The delay bands are labeled in seconds of over current at six times
the ampere rating.
• Long-time delay is an inverse time characteristic in that the
tripping time decreases as the current increases.
• The long-time delay (tr) sets the length of the time that the circuit
breaker will carry an over current (below the short-time or
instantaneous pickup current level) before tripping.
• The Long time delay can be set to I2t On and I2t OFF settings.
• (A) I2t Response:I2t Out ,For coordination with other circuit
breakers with electronic trip devices and for coordination with
thermal-magnetic circuit breakers.
• (B) I2t Response: I2t In ,For coordination with fuses and upstream
transformer
Relay Settings Criteria
Short Time pickup Current Setting (Im):
• Short time protection is time-independent.
• It determines or sets the level of fault current at which the
short-time trip delay countdown is actuated.
• Short Time Pick up Value (Im) (multiplied by the ampere rating)
sets the short circuit current level at which the circuit breaker
will trip after the set time delay.
• The short-time pickup (Isd) sets current level (below
instantaneous trip level) at which circuit breaker will trip after
the preset time delay.
Standard Practice for Setting:
• No trip for a current below 80% of the short time setting
• Trip for a current equal to 120% of the short time setting
• The trip time is Less than 0.2 s for a short time protection with
no time delay and equal to the value of the time delay tsd for a
protection with time delay
Instantaneous Pickup Setting (Ii):
• Instantaneous protection is time-independent.
• It determines the level of fault current that will actuate a trip
with no time delay.
• Ii value (multiplied by the ampere rating (In)) sets the short-
circuit current level at which the circuit breaker will trip with
no intentional time delay.
• This protection trips to eliminate quickly high value currents
and its trip times cannot be set
• The instantaneous function will override the short-time
function if the instantaneous Pickup is adjusted at the same
or lower setting than the Short Time Pickup.
Thank You

Contenu connexe

Tendances

ETAP - Coordination and protecion 2
ETAP -  Coordination and protecion 2ETAP -  Coordination and protecion 2
ETAP - Coordination and protecion 2Himmelstern
 
ETAP - Transformer mva sizing
ETAP - Transformer mva sizingETAP - Transformer mva sizing
ETAP - Transformer mva sizingHimmelstern
 
ETAP - device coordination
ETAP - device coordinationETAP - device coordination
ETAP - device coordinationHimmelstern
 
Ipsa mv relay co-ordiantion shaik adam
Ipsa  mv relay  co-ordiantion shaik adamIpsa  mv relay  co-ordiantion shaik adam
Ipsa mv relay co-ordiantion shaik adamShaik Abdullah Adam
 
Over current Relays
Over current RelaysOver current Relays
Over current RelaysASWANTH6270
 
Relay coordination
Relay coordinationRelay coordination
Relay coordinationD Målîk
 
ETAP - Coordination and protecion
ETAP -  Coordination and protecionETAP -  Coordination and protecion
ETAP - Coordination and protecionHimmelstern
 
Transformer protection
Transformer protectionTransformer protection
Transformer protectionjawaharramaya
 
Synchronous machines
Synchronous machinesSynchronous machines
Synchronous machinesmichaeljmack
 
ETAP - Arcflash analysis & mitigation methods
ETAP - Arcflash analysis &  mitigation  methodsETAP - Arcflash analysis &  mitigation  methods
ETAP - Arcflash analysis & mitigation methodsHimmelstern
 
RELAY CO-ORDINATION WITH FAULT CALCULATION
RELAY CO-ORDINATION WITH FAULT CALCULATIONRELAY CO-ORDINATION WITH FAULT CALCULATION
RELAY CO-ORDINATION WITH FAULT CALCULATIONMd Sarowar Alam
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1Md Irshad Ahmad
 
Blackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load SheddingBlackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load Sheddingmichaeljmack
 
DigSILENT PF - 06 (es) short circuit theory
DigSILENT PF - 06 (es) short circuit theoryDigSILENT PF - 06 (es) short circuit theory
DigSILENT PF - 06 (es) short circuit theoryHimmelstern
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level CalculationDinesh Sarda
 
ETAP - optimal power flow (OPF)
ETAP - optimal power flow (OPF)ETAP - optimal power flow (OPF)
ETAP - optimal power flow (OPF)Himmelstern
 
ETAP - Load flow and panel rev2014-1
ETAP - Load flow and panel   rev2014-1ETAP - Load flow and panel   rev2014-1
ETAP - Load flow and panel rev2014-1Himmelstern
 
Ppt on protection of power transformers
Ppt on protection of power transformersPpt on protection of power transformers
Ppt on protection of power transformerssiddharam kantoli
 
Protection Relays Numbering (ANSI)
Protection Relays Numbering (ANSI)Protection Relays Numbering (ANSI)
Protection Relays Numbering (ANSI)AHMED MOHAMED HEGAB
 

Tendances (20)

ETAP - Coordination and protecion 2
ETAP -  Coordination and protecion 2ETAP -  Coordination and protecion 2
ETAP - Coordination and protecion 2
 
Out of step
Out of stepOut of step
Out of step
 
ETAP - Transformer mva sizing
ETAP - Transformer mva sizingETAP - Transformer mva sizing
ETAP - Transformer mva sizing
 
ETAP - device coordination
ETAP - device coordinationETAP - device coordination
ETAP - device coordination
 
Ipsa mv relay co-ordiantion shaik adam
Ipsa  mv relay  co-ordiantion shaik adamIpsa  mv relay  co-ordiantion shaik adam
Ipsa mv relay co-ordiantion shaik adam
 
Over current Relays
Over current RelaysOver current Relays
Over current Relays
 
Relay coordination
Relay coordinationRelay coordination
Relay coordination
 
ETAP - Coordination and protecion
ETAP -  Coordination and protecionETAP -  Coordination and protecion
ETAP - Coordination and protecion
 
Transformer protection
Transformer protectionTransformer protection
Transformer protection
 
Synchronous machines
Synchronous machinesSynchronous machines
Synchronous machines
 
ETAP - Arcflash analysis & mitigation methods
ETAP - Arcflash analysis &  mitigation  methodsETAP - Arcflash analysis &  mitigation  methods
ETAP - Arcflash analysis & mitigation methods
 
RELAY CO-ORDINATION WITH FAULT CALCULATION
RELAY CO-ORDINATION WITH FAULT CALCULATIONRELAY CO-ORDINATION WITH FAULT CALCULATION
RELAY CO-ORDINATION WITH FAULT CALCULATION
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1
 
Blackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load SheddingBlackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load Shedding
 
DigSILENT PF - 06 (es) short circuit theory
DigSILENT PF - 06 (es) short circuit theoryDigSILENT PF - 06 (es) short circuit theory
DigSILENT PF - 06 (es) short circuit theory
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level Calculation
 
ETAP - optimal power flow (OPF)
ETAP - optimal power flow (OPF)ETAP - optimal power flow (OPF)
ETAP - optimal power flow (OPF)
 
ETAP - Load flow and panel rev2014-1
ETAP - Load flow and panel   rev2014-1ETAP - Load flow and panel   rev2014-1
ETAP - Load flow and panel rev2014-1
 
Ppt on protection of power transformers
Ppt on protection of power transformersPpt on protection of power transformers
Ppt on protection of power transformers
 
Protection Relays Numbering (ANSI)
Protection Relays Numbering (ANSI)Protection Relays Numbering (ANSI)
Protection Relays Numbering (ANSI)
 

Similaire à POWER SYSTEM ANALYSIS USING ETAP

Relay operation principles
Relay operation principlesRelay operation principles
Relay operation principlesAmmar Al Hakeim
 
Switch gear and protection
Switch gear and protectionSwitch gear and protection
Switch gear and protectionDinesh Sharma
 
DigSILENT PF - 05 short circuit theory
DigSILENT PF - 05 short circuit theoryDigSILENT PF - 05 short circuit theory
DigSILENT PF - 05 short circuit theoryHimmelstern
 
Presentation1.pptx power system
Presentation1.pptx power systemPresentation1.pptx power system
Presentation1.pptx power systemArvind Nathan
 
Unit 03 Protective relays
Unit  03 Protective relaysUnit  03 Protective relays
Unit 03 Protective relaysPremanandDesai
 
SHORT CIRCUIT ANALYSIS OF ELECTRICAL DISTRIBUTION SYSTEM FOR INDUSTRY APPLICA...
SHORT CIRCUIT ANALYSIS OF ELECTRICAL DISTRIBUTION SYSTEM FOR INDUSTRY APPLICA...SHORT CIRCUIT ANALYSIS OF ELECTRICAL DISTRIBUTION SYSTEM FOR INDUSTRY APPLICA...
SHORT CIRCUIT ANALYSIS OF ELECTRICAL DISTRIBUTION SYSTEM FOR INDUSTRY APPLICA...IRJET Journal
 
Short circuit current calculations
Short circuit current calculationsShort circuit current calculations
Short circuit current calculationsRonald Santos
 
Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)ingcortez
 
A simple approach to short circuit calculations
A simple approach to short circuit calculationsA simple approach to short circuit calculations
A simple approach to short circuit calculationsSouvik Dutta
 
Analisis de corto circuito edp01 cálculo de cc
Analisis de corto circuito edp01 cálculo de ccAnalisis de corto circuito edp01 cálculo de cc
Analisis de corto circuito edp01 cálculo de ccWaldemar Campuzano
 
FEEDER AND BUS BAR PROTECTION
FEEDER AND BUS BAR PROTECTIONFEEDER AND BUS BAR PROTECTION
FEEDER AND BUS BAR PROTECTIONDr. Rohit Babu
 
17648889-Introduction-to-Power-System-Protection-Relays.pdf
17648889-Introduction-to-Power-System-Protection-Relays.pdf17648889-Introduction-to-Power-System-Protection-Relays.pdf
17648889-Introduction-to-Power-System-Protection-Relays.pdfThien Phan Bản
 
Unit 05 Protection of feeders and bus-bars
Unit  05 Protection of feeders and bus-bars Unit  05 Protection of feeders and bus-bars
Unit 05 Protection of feeders and bus-bars PremanandDesai
 
Lecture no 1 switchgears bt255 converted
Lecture no 1 switchgears bt255 convertedLecture no 1 switchgears bt255 converted
Lecture no 1 switchgears bt255 convertedFazal Ur Rehman
 
IRJET- Study Over Current Relay (MCGG53) Response using Matlab Model
IRJET- Study Over Current Relay (MCGG53) Response using Matlab ModelIRJET- Study Over Current Relay (MCGG53) Response using Matlab Model
IRJET- Study Over Current Relay (MCGG53) Response using Matlab ModelIRJET Journal
 
A Simple Approach To Short-Circuit Calculations by Cooper Bussmann (Ellis Pat...
A Simple Approach To Short-Circuit Calculations by Cooper Bussmann (Ellis Pat...A Simple Approach To Short-Circuit Calculations by Cooper Bussmann (Ellis Pat...
A Simple Approach To Short-Circuit Calculations by Cooper Bussmann (Ellis Pat...Thorne & Derrick International
 

Similaire à POWER SYSTEM ANALYSIS USING ETAP (20)

D04522631
D04522631D04522631
D04522631
 
Relay operation principles
Relay operation principlesRelay operation principles
Relay operation principles
 
Protective relay.pptx
Protective relay.pptxProtective relay.pptx
Protective relay.pptx
 
Switch gear and protection
Switch gear and protectionSwitch gear and protection
Switch gear and protection
 
DigSILENT PF - 05 short circuit theory
DigSILENT PF - 05 short circuit theoryDigSILENT PF - 05 short circuit theory
DigSILENT PF - 05 short circuit theory
 
Presentation1.pptx power system
Presentation1.pptx power systemPresentation1.pptx power system
Presentation1.pptx power system
 
Unit 03 Protective relays
Unit  03 Protective relaysUnit  03 Protective relays
Unit 03 Protective relays
 
SHORT CIRCUIT ANALYSIS OF ELECTRICAL DISTRIBUTION SYSTEM FOR INDUSTRY APPLICA...
SHORT CIRCUIT ANALYSIS OF ELECTRICAL DISTRIBUTION SYSTEM FOR INDUSTRY APPLICA...SHORT CIRCUIT ANALYSIS OF ELECTRICAL DISTRIBUTION SYSTEM FOR INDUSTRY APPLICA...
SHORT CIRCUIT ANALYSIS OF ELECTRICAL DISTRIBUTION SYSTEM FOR INDUSTRY APPLICA...
 
What's short circuit level
What's short circuit levelWhat's short circuit level
What's short circuit level
 
Short circuit current calculations
Short circuit current calculationsShort circuit current calculations
Short circuit current calculations
 
Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)Bus ele tech_lib_short_circuit_current_calculations (1)
Bus ele tech_lib_short_circuit_current_calculations (1)
 
A simple approach to short circuit calculations
A simple approach to short circuit calculationsA simple approach to short circuit calculations
A simple approach to short circuit calculations
 
Analisis de corto circuito edp01 cálculo de cc
Analisis de corto circuito edp01 cálculo de ccAnalisis de corto circuito edp01 cálculo de cc
Analisis de corto circuito edp01 cálculo de cc
 
FEEDER AND BUS BAR PROTECTION
FEEDER AND BUS BAR PROTECTIONFEEDER AND BUS BAR PROTECTION
FEEDER AND BUS BAR PROTECTION
 
17648889-Introduction-to-Power-System-Protection-Relays.pdf
17648889-Introduction-to-Power-System-Protection-Relays.pdf17648889-Introduction-to-Power-System-Protection-Relays.pdf
17648889-Introduction-to-Power-System-Protection-Relays.pdf
 
Unit 05 Protection of feeders and bus-bars
Unit  05 Protection of feeders and bus-bars Unit  05 Protection of feeders and bus-bars
Unit 05 Protection of feeders and bus-bars
 
Lecture no 1 switchgears bt255 converted
Lecture no 1 switchgears bt255 convertedLecture no 1 switchgears bt255 converted
Lecture no 1 switchgears bt255 converted
 
Relays
RelaysRelays
Relays
 
IRJET- Study Over Current Relay (MCGG53) Response using Matlab Model
IRJET- Study Over Current Relay (MCGG53) Response using Matlab ModelIRJET- Study Over Current Relay (MCGG53) Response using Matlab Model
IRJET- Study Over Current Relay (MCGG53) Response using Matlab Model
 
A Simple Approach To Short-Circuit Calculations by Cooper Bussmann (Ellis Pat...
A Simple Approach To Short-Circuit Calculations by Cooper Bussmann (Ellis Pat...A Simple Approach To Short-Circuit Calculations by Cooper Bussmann (Ellis Pat...
A Simple Approach To Short-Circuit Calculations by Cooper Bussmann (Ellis Pat...
 

Dernier

Uk-NO1 kala jadu karne wale ka contact number kala jadu karne wale baba kala ...
Uk-NO1 kala jadu karne wale ka contact number kala jadu karne wale baba kala ...Uk-NO1 kala jadu karne wale ka contact number kala jadu karne wale baba kala ...
Uk-NO1 kala jadu karne wale ka contact number kala jadu karne wale baba kala ...Amil baba
 
Robotics Group 10 (Control Schemes) cse.pdf
Robotics Group 10  (Control Schemes) cse.pdfRobotics Group 10  (Control Schemes) cse.pdf
Robotics Group 10 (Control Schemes) cse.pdfsahilsajad201
 
Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________Romil Mishra
 
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTFUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTSneha Padhiar
 
Secure Key Crypto - Tech Paper JET Tech Labs
Secure Key Crypto - Tech Paper JET Tech LabsSecure Key Crypto - Tech Paper JET Tech Labs
Secure Key Crypto - Tech Paper JET Tech Labsamber724300
 
Curve setting (Basic Mine Surveying)_MI10412MI.pptx
Curve setting (Basic Mine Surveying)_MI10412MI.pptxCurve setting (Basic Mine Surveying)_MI10412MI.pptx
Curve setting (Basic Mine Surveying)_MI10412MI.pptxRomil Mishra
 
70 POWER PLANT IAE V2500 technical training
70 POWER PLANT IAE V2500 technical training70 POWER PLANT IAE V2500 technical training
70 POWER PLANT IAE V2500 technical trainingGladiatorsKasper
 
Theory of Machine Notes / Lecture Material .pdf
Theory of Machine Notes / Lecture Material .pdfTheory of Machine Notes / Lecture Material .pdf
Theory of Machine Notes / Lecture Material .pdfShreyas Pandit
 
"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...Erbil Polytechnic University
 
Indian Tradition, Culture & Societies.pdf
Indian Tradition, Culture & Societies.pdfIndian Tradition, Culture & Societies.pdf
Indian Tradition, Culture & Societies.pdfalokitpathak01
 
Artificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewArtificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewsandhya757531
 
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.elesangwon
 
A brief look at visionOS - How to develop app on Apple's Vision Pro
A brief look at visionOS - How to develop app on Apple's Vision ProA brief look at visionOS - How to develop app on Apple's Vision Pro
A brief look at visionOS - How to develop app on Apple's Vision ProRay Yuan Liu
 
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfComprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfalene1
 
tourism-management-srs_compress-software-engineering.pdf
tourism-management-srs_compress-software-engineering.pdftourism-management-srs_compress-software-engineering.pdf
tourism-management-srs_compress-software-engineering.pdfchess188chess188
 
STATE TRANSITION DIAGRAM in psoc subject
STATE TRANSITION DIAGRAM in psoc subjectSTATE TRANSITION DIAGRAM in psoc subject
STATE TRANSITION DIAGRAM in psoc subjectGayathriM270621
 
Javier_Fernandez_CARS_workshop_presentation.pptx
Javier_Fernandez_CARS_workshop_presentation.pptxJavier_Fernandez_CARS_workshop_presentation.pptx
Javier_Fernandez_CARS_workshop_presentation.pptxJavier Fernández Muñoz
 

Dernier (20)

Uk-NO1 kala jadu karne wale ka contact number kala jadu karne wale baba kala ...
Uk-NO1 kala jadu karne wale ka contact number kala jadu karne wale baba kala ...Uk-NO1 kala jadu karne wale ka contact number kala jadu karne wale baba kala ...
Uk-NO1 kala jadu karne wale ka contact number kala jadu karne wale baba kala ...
 
Robotics Group 10 (Control Schemes) cse.pdf
Robotics Group 10  (Control Schemes) cse.pdfRobotics Group 10  (Control Schemes) cse.pdf
Robotics Group 10 (Control Schemes) cse.pdf
 
Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________
 
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTFUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
 
Secure Key Crypto - Tech Paper JET Tech Labs
Secure Key Crypto - Tech Paper JET Tech LabsSecure Key Crypto - Tech Paper JET Tech Labs
Secure Key Crypto - Tech Paper JET Tech Labs
 
Curve setting (Basic Mine Surveying)_MI10412MI.pptx
Curve setting (Basic Mine Surveying)_MI10412MI.pptxCurve setting (Basic Mine Surveying)_MI10412MI.pptx
Curve setting (Basic Mine Surveying)_MI10412MI.pptx
 
70 POWER PLANT IAE V2500 technical training
70 POWER PLANT IAE V2500 technical training70 POWER PLANT IAE V2500 technical training
70 POWER PLANT IAE V2500 technical training
 
Theory of Machine Notes / Lecture Material .pdf
Theory of Machine Notes / Lecture Material .pdfTheory of Machine Notes / Lecture Material .pdf
Theory of Machine Notes / Lecture Material .pdf
 
"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...
 
Indian Tradition, Culture & Societies.pdf
Indian Tradition, Culture & Societies.pdfIndian Tradition, Culture & Societies.pdf
Indian Tradition, Culture & Societies.pdf
 
Artificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewArtificial Intelligence in Power System overview
Artificial Intelligence in Power System overview
 
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
 
A brief look at visionOS - How to develop app on Apple's Vision Pro
A brief look at visionOS - How to develop app on Apple's Vision ProA brief look at visionOS - How to develop app on Apple's Vision Pro
A brief look at visionOS - How to develop app on Apple's Vision Pro
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfComprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
 
tourism-management-srs_compress-software-engineering.pdf
tourism-management-srs_compress-software-engineering.pdftourism-management-srs_compress-software-engineering.pdf
tourism-management-srs_compress-software-engineering.pdf
 
ASME-B31.4-2019-estandar para diseño de ductos
ASME-B31.4-2019-estandar para diseño de ductosASME-B31.4-2019-estandar para diseño de ductos
ASME-B31.4-2019-estandar para diseño de ductos
 
Versatile Engineering Construction Firms
Versatile Engineering Construction FirmsVersatile Engineering Construction Firms
Versatile Engineering Construction Firms
 
STATE TRANSITION DIAGRAM in psoc subject
STATE TRANSITION DIAGRAM in psoc subjectSTATE TRANSITION DIAGRAM in psoc subject
STATE TRANSITION DIAGRAM in psoc subject
 
Javier_Fernandez_CARS_workshop_presentation.pptx
Javier_Fernandez_CARS_workshop_presentation.pptxJavier_Fernandez_CARS_workshop_presentation.pptx
Javier_Fernandez_CARS_workshop_presentation.pptx
 

POWER SYSTEM ANALYSIS USING ETAP

  • 2. Background:  Power system analysis is the field of electrical study which deals with the analysis of electrical power system and it’s behaviour during potential fault scenarios.  System studies are usually required to be conducted during two major phases of a project: - The initial project design phase (Greenfield phase). - During the modification phase of an existing system (Brown field phase).  System study is a requisite practice in order to ensure the genuineness of the multiple system parameters taking into practice during the system design.  Common parameters taken into consideration during the study are short circuit, loading, relay settings, motor parameters etc.  The studies included within system analysis are: - Load flow study - Short circuit study - Relay coordination study - Arc flash study - Motor starting study
  • 3. Why Do We Need Protection: As we might know an electrical system at times might get exposed to certain conditions which causes the deviation of voltages and currents from nominal values or states. Under normal operating conditions, power system equipment or lines carry normal voltages and currents which results in a safer operation of the system. But when fault occurs, it causes excessively high currents to flow in a system which causes damage to the equipment and devices. Thus in order to protect the system from fault its is necessary to deploy certain protection schemes. Types of Faults in power system: 1. Symmetrical faults: These are very severe faults and occur infrequently in the power systems. These are also called as balanced faults and are of two types namely line to line to line to ground (L-L-L-G) and line to line to line (L-L-L). Only 2-5 percent of system faults are symmetrical faults. 2. Unsymmetrical faults: These are very common and less severe than symmetrical faults. There are mainly three types namely line to ground (L-G), line to line (L-L) and double line to ground (LL-G) faults.
  • 4. Methodology: ELECTRICAL SYSTEM MODELLING LOAD FLOW ANALYSIS SHORT CIRCUIT ANALYSIS RELAY COORDINATION ARC FLASH ANALYSIS
  • 5. Load Flow Study  Load flow study is based on analysing the system’s loading scenario i.e. to ensure whether the loading is proper or not.  Multiple parameters taken into consideration during the study are the system’s voltage and current ratings.  The purpose of this study is: - To ensure that the voltages at all the buses are maintained with in legitimate limits. - To determine the flows in various elements. - To check that the losses in the system are within the reasonable limits. - To determine the necessary tap selection for the transformer. - To determine the active and reactive power flows in the system thereby performing power factor compensation. - To ensure that the generator in the system are loaded to within their real and reactive capability limits.
  • 6. Short Circuit Analysis  The purpose of the short circuit study is to analyse the effect of three-phase (Worst condition of Short Circuit) on the electrical system.  The fault calculations are in compliance with IEC 60909.  This study analysis the effect of short circuit fault on the system by taking into account the fault current contribution of each load on the bus.  The short circuit study is useful in: - Determining the total fault current flowing through a bus thereby helping in selecting the kA rating of the bus. - Selecting the kA rating of circuit breakers through device duty SC analysis. - Fault contribution by individual devices.
  • 7. Sizing of Panels as per ETAP studies Load Flow Study: - Power factor of all panels and design capacitor panels as per requirement. - Voltage drop of at all panels and size cable. - Overload conditions of all equipment and optimise system design. Short Circuit Study - Short circuit current of each panel and selection of all circuit breaker, VCB, MCCB and fuses as per short circuit current available. - Cable withstand capacity as per short circuit current available.
  • 8. Sizing of Panels as per ETAP studies – Load flow study
  • 9. Sizing of Panels as per ETAP studies – Short Circuit Study
  • 10. Relay Coordination In order to protect an electrical system the relays and circuit breakers forms an integral part. The nature of protection shall be such that the breaker nearest to the point of fault shall be the first one to trip and isolate the fault section followed by the backup protection. A general scheme is shown below: - The above figure depicts 3 levels of relays along with the power source. Here R1 would be referred to as the primary protection and R2 and R3 will constitute to be Secondary or backup protection. - The point fault is nearest to the relay R1. As per the ideal protection scenario R1 must be the first one to actuate followed by R2 and R3. - Although if somehow R2 or R3 trips before R1 then this would case whole section to shut down rather than just a load. - So, in order to avoid this anomaly relay coordination study is conducted to adjust the tripping sequence of relays.
  • 11. Above figure illustrates an overcurrent protection scheme for radial distribution system of fig 15.2, with definite time relays. Relay R1 does not have any coordination responsibility and hence it can trip without any intentional time delay. Relay R2 has to coordinate with relay R1 and hence its time of operation is delayed by time equal to Coordination Time Interval (CTI). Relay R3 has to back up R2. Hence its time of operation is delayed by another CTI. Thus, we see that as we move along towards source, the relaying action slows down. Typically, there is an upper limit on any fault clearing time in the system and it equals approximately 1sec. This limit would be hit near the relay close to source.
  • 12. Coordination tree: Fig 15.9 shows a coordination tree. Each node in the tree indicates a relay. An edge exists between two nodes of the tree if, the corresponding relays have a primary backup coordination relationship. The source node is also called as the "root node". The terminal nodes except the source node are referred as leaf nodes. In a directed tree, nodes have parent child relationship. Parent node of a node A refers to the adjacent node which supplies power to node A. In a tree, each node except source node has a unique parent. Conversely, a node fed by the parent is called a child. Root node has children but no parent. Similarly, leaf nodes have parent but they do not have any child. Note that except at leaf nodes, a relay plays the dual role of primary and back up protection.
  • 13.
  • 14.
  • 15. Long-Time delay Setting (tr): • Long time delay (tr) sets length of time that the circuit breaker will carry a sustained overload before tripping. • The delay bands are labeled in seconds of over current at six times the ampere rating. • Long-time delay is an inverse time characteristic in that the tripping time decreases as the current increases. • The long-time delay (tr) sets the length of the time that the circuit breaker will carry an over current (below the short-time or instantaneous pickup current level) before tripping. • The Long time delay can be set to I2t On and I2t OFF settings. • (A) I2t Response:I2t Out ,For coordination with other circuit breakers with electronic trip devices and for coordination with thermal-magnetic circuit breakers. • (B) I2t Response: I2t In ,For coordination with fuses and upstream transformer Relay Settings Criteria
  • 16. Short Time pickup Current Setting (Im): • Short time protection is time-independent. • It determines or sets the level of fault current at which the short-time trip delay countdown is actuated. • Short Time Pick up Value (Im) (multiplied by the ampere rating) sets the short circuit current level at which the circuit breaker will trip after the set time delay. • The short-time pickup (Isd) sets current level (below instantaneous trip level) at which circuit breaker will trip after the preset time delay. Standard Practice for Setting: • No trip for a current below 80% of the short time setting • Trip for a current equal to 120% of the short time setting • The trip time is Less than 0.2 s for a short time protection with no time delay and equal to the value of the time delay tsd for a protection with time delay
  • 17. Instantaneous Pickup Setting (Ii): • Instantaneous protection is time-independent. • It determines the level of fault current that will actuate a trip with no time delay. • Ii value (multiplied by the ampere rating (In)) sets the short- circuit current level at which the circuit breaker will trip with no intentional time delay. • This protection trips to eliminate quickly high value currents and its trip times cannot be set • The instantaneous function will override the short-time function if the instantaneous Pickup is adjusted at the same or lower setting than the Short Time Pickup.