P16 AIA Amaala Health & Safety Campaign
Heat Stress Management
April 2023
Sensitive
Heat Stress Management
AGENDA: HEAT STRESS MANAGEMENT CAMPAIGN
2
Strictly Private andConfidential
Week No. Date Description
Status /
Remarks
Week 15 1st April - 7th April
- Kick Off Meeting 4th April.
- Agree agenda.
Completed
Week 16
8th April - 14th
April
- Sunday 9th 10am – SLT - Focus on Heat Stress
Management (ASO and AGL Substation) Completed
- Tuesday 11th Progress Meeting Safety Moment by Egis -
Abdul Razzak Completed
- Heat stress Awareness sitewide mass TBT. Completed
- RBU Heat stress training. Completed
- Pasting of Heat Stress awareness posters in offices and on
site. Completed
Completed
Week 17
15th April - 21st
April
- Saturday 15th Heat Stress medical drill. Completed
- Sunday 16th @ 10am – SLT - Focus on Heat Stress
Management (Area not decided yet). Completed
- Tuesday 18th – Progress Meeting Safety Moment by
AMAALA - Miss Fatimah. Completed
- Construction of a sample heat stress shelter. Completed
- Collect site photos for Heat Stress Management Posters.
Completed
- Review of Heat Stress notification email list by Egis -
Abdul Razzak. Completed
Completed
Week 18
22nd April - 28th
April
- Eid break
Sensitive
Heat Stress Management
KICK OFF MEETING ON THE AGREED AGENDA
3
Strictly Private andConfidential
Sensitive
Heat Stress Management
SAFETY MOMENT by Mr. Naqash
4
Strictly Private andConfidential
Sensitive
Heat Stress Management
SITE LEADERSHIP TOUR AT IKK ASPHALT PLANT & ASO BUILDING
- Focus on Heat Stress Arrangement.
5
Strictly Private andConfidential
Sensitive
Heat Stress Management
SAFETY MOMENT by Mr. AbdulRazzak
6
Strictly Private andConfidential
Sensitive
Heat Stress Management
SITEWIDE HEAT STRESS AWARENESS & MASS TOOLBOX TALK
7
Strictly Private andConfidential
Sensitive
Heat Stress Management
SITEWIDE HEAT STRESS AWARENESS & MASS TOOLBOX TALK
8
Strictly Private andConfidential
Sensitive
Heat Stress Management
CONTRACTOR’S HEAT STRESS TRAINING
9
Strictly Private andConfidential
Sensitive
Heat Stress Management
SAFETY MOMENT by Ms. Fatimah
10
Strictly Private andConfidential
Sensitive
Heat Stress Management
HEAT STRESS EMERGENCY DRILL
11
Strictly Private andConfidential
Sensitive
Heat Stress Management
HEAT STRESS FACILITIES ON SITE
12
Strictly Private andConfidential
Sensitive
EMERGENCY CONTACT NUMBER
13
Strictly Private andConfidential
Nurse‫ممرض‬ 0555016400
NaqashYusaf(HSM) 0558319638
HeshamAlahmadi(SEM) 0550251663
IdrisAdeniran(HSE) 0530644494
ChrisBusa(Admin) 05507028425
BadwiTawk(CM) 0566083368
Abdulaziz(Security) 0553870037 POLICE ‫طة‬ ‫ر‬
‫ش‬ 999
AMAALAINTERNATIONALAIRPORT INCASEOFMEDICAL
RBUTECEMERGENCYCONTACTNUMBERS EMERGENCYCALL
GOVTAGENCIES EMERGENCYNUMBERS
CIVILDEFENSE ‫ي‬‫المدن‬‫الدفاع‬ 998
MOHAMBULANCE 997
All workers at the site will receive Emergency Contact Number cards, which they can use to call for
assistance during any emergency situations.
Heat Stress Management
Sensitive
Heat Stress Management
HEAT STRESS AWARENESS POSTERS IN OFFICES & ON SITE
14
Strictly Private andConfidential
Sensitive
Heat Stress Management
CONTINUOUS HEAT STRESS AWARENESS
15
Strictly Private andConfidential
Sensitive
HEAT STRESS MANAGEMENT PLAN
16
Strictly Private andConfidential
Before the commencement of the mid-day break, a revised Heat Stress Management Plan, which
incorporates specific work-rest regimens for different levels of work intensity (light, moderate, and
heavy), will be resubmitted for approval.
Heat Stress Management
Thank You

More Related Content

Recently uploaded

Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...
Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...
Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...Sebastiano Panichella
 
Understanding Post Production changes (PPC) in Clinical Data Management (CDM)...
Understanding Post Production changes (PPC) in Clinical Data Management (CDM)...Understanding Post Production changes (PPC) in Clinical Data Management (CDM)...
Understanding Post Production changes (PPC) in Clinical Data Management (CDM)...soumyapottola
 
cse-csp batch4 review-1.1.pptx cyber security
cse-csp batch4 review-1.1.pptx cyber securitycse-csp batch4 review-1.1.pptx cyber security
cse-csp batch4 review-1.1.pptx cyber securitysandeepnani2260
 
05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx
05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx
05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptxerickamwana1
 
Scootsy Overview Deck - Pan City Delivery
Scootsy Overview Deck - Pan City DeliveryScootsy Overview Deck - Pan City Delivery
Scootsy Overview Deck - Pan City Deliveryrishi338139
 
General Elections Final Press Noteas per M
General Elections Final Press Noteas per MGeneral Elections Final Press Noteas per M
General Elections Final Press Noteas per MVidyaAdsule1
 
Application of GIS in Landslide Disaster Response.pptx
Application of GIS in Landslide Disaster Response.pptxApplication of GIS in Landslide Disaster Response.pptx
Application of GIS in Landslide Disaster Response.pptxRoquia Salam
 
GESCO SE Press and Analyst Conference on Financial Results 2024
GESCO SE Press and Analyst Conference on Financial Results 2024GESCO SE Press and Analyst Conference on Financial Results 2024
GESCO SE Press and Analyst Conference on Financial Results 2024GESCO SE
 
Sunlight Spectacle 2024 Practical Action Launch Event 2024-04-08
Sunlight Spectacle 2024 Practical Action Launch Event 2024-04-08Sunlight Spectacle 2024 Practical Action Launch Event 2024-04-08
Sunlight Spectacle 2024 Practical Action Launch Event 2024-04-08LloydHelferty
 
Don't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunity
Don't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunityDon't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunity
Don't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunityApp Ethena
 
Testing with Fewer Resources: Toward Adaptive Approaches for Cost-effective ...
Testing with Fewer Resources:  Toward Adaptive Approaches for Cost-effective ...Testing with Fewer Resources:  Toward Adaptive Approaches for Cost-effective ...
Testing with Fewer Resources: Toward Adaptive Approaches for Cost-effective ...Sebastiano Panichella
 

Recently uploaded (11)

Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...
Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...
Testing and Development Challenges for Complex Cyber-Physical Systems: Insigh...
 
Understanding Post Production changes (PPC) in Clinical Data Management (CDM)...
Understanding Post Production changes (PPC) in Clinical Data Management (CDM)...Understanding Post Production changes (PPC) in Clinical Data Management (CDM)...
Understanding Post Production changes (PPC) in Clinical Data Management (CDM)...
 
cse-csp batch4 review-1.1.pptx cyber security
cse-csp batch4 review-1.1.pptx cyber securitycse-csp batch4 review-1.1.pptx cyber security
cse-csp batch4 review-1.1.pptx cyber security
 
05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx
05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx
05.02 MMC - Assignment 4 - Image Attribution Lovepreet.pptx
 
Scootsy Overview Deck - Pan City Delivery
Scootsy Overview Deck - Pan City DeliveryScootsy Overview Deck - Pan City Delivery
Scootsy Overview Deck - Pan City Delivery
 
General Elections Final Press Noteas per M
General Elections Final Press Noteas per MGeneral Elections Final Press Noteas per M
General Elections Final Press Noteas per M
 
Application of GIS in Landslide Disaster Response.pptx
Application of GIS in Landslide Disaster Response.pptxApplication of GIS in Landslide Disaster Response.pptx
Application of GIS in Landslide Disaster Response.pptx
 
GESCO SE Press and Analyst Conference on Financial Results 2024
GESCO SE Press and Analyst Conference on Financial Results 2024GESCO SE Press and Analyst Conference on Financial Results 2024
GESCO SE Press and Analyst Conference on Financial Results 2024
 
Sunlight Spectacle 2024 Practical Action Launch Event 2024-04-08
Sunlight Spectacle 2024 Practical Action Launch Event 2024-04-08Sunlight Spectacle 2024 Practical Action Launch Event 2024-04-08
Sunlight Spectacle 2024 Practical Action Launch Event 2024-04-08
 
Don't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunity
Don't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunityDon't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunity
Don't Miss Out: Strategies for Making the Most of the Ethena DigitalOpportunity
 
Testing with Fewer Resources: Toward Adaptive Approaches for Cost-effective ...
Testing with Fewer Resources:  Toward Adaptive Approaches for Cost-effective ...Testing with Fewer Resources:  Toward Adaptive Approaches for Cost-effective ...
Testing with Fewer Resources: Toward Adaptive Approaches for Cost-effective ...
 

Heat Stress Management.pptx

  • 1. P16 AIA Amaala Health & Safety Campaign Heat Stress Management April 2023
  • 2. Sensitive Heat Stress Management AGENDA: HEAT STRESS MANAGEMENT CAMPAIGN 2 Strictly Private andConfidential Week No. Date Description Status / Remarks Week 15 1st April - 7th April - Kick Off Meeting 4th April. - Agree agenda. Completed Week 16 8th April - 14th April - Sunday 9th 10am – SLT - Focus on Heat Stress Management (ASO and AGL Substation) Completed - Tuesday 11th Progress Meeting Safety Moment by Egis - Abdul Razzak Completed - Heat stress Awareness sitewide mass TBT. Completed - RBU Heat stress training. Completed - Pasting of Heat Stress awareness posters in offices and on site. Completed Completed Week 17 15th April - 21st April - Saturday 15th Heat Stress medical drill. Completed - Sunday 16th @ 10am – SLT - Focus on Heat Stress Management (Area not decided yet). Completed - Tuesday 18th – Progress Meeting Safety Moment by AMAALA - Miss Fatimah. Completed - Construction of a sample heat stress shelter. Completed - Collect site photos for Heat Stress Management Posters. Completed - Review of Heat Stress notification email list by Egis - Abdul Razzak. Completed Completed Week 18 22nd April - 28th April - Eid break
  • 3. Sensitive Heat Stress Management KICK OFF MEETING ON THE AGREED AGENDA 3 Strictly Private andConfidential
  • 4. Sensitive Heat Stress Management SAFETY MOMENT by Mr. Naqash 4 Strictly Private andConfidential
  • 5. Sensitive Heat Stress Management SITE LEADERSHIP TOUR AT IKK ASPHALT PLANT & ASO BUILDING - Focus on Heat Stress Arrangement. 5 Strictly Private andConfidential
  • 6. Sensitive Heat Stress Management SAFETY MOMENT by Mr. AbdulRazzak 6 Strictly Private andConfidential
  • 7. Sensitive Heat Stress Management SITEWIDE HEAT STRESS AWARENESS & MASS TOOLBOX TALK 7 Strictly Private andConfidential
  • 8. Sensitive Heat Stress Management SITEWIDE HEAT STRESS AWARENESS & MASS TOOLBOX TALK 8 Strictly Private andConfidential
  • 9. Sensitive Heat Stress Management CONTRACTOR’S HEAT STRESS TRAINING 9 Strictly Private andConfidential
  • 10. Sensitive Heat Stress Management SAFETY MOMENT by Ms. Fatimah 10 Strictly Private andConfidential
  • 11. Sensitive Heat Stress Management HEAT STRESS EMERGENCY DRILL 11 Strictly Private andConfidential
  • 12. Sensitive Heat Stress Management HEAT STRESS FACILITIES ON SITE 12 Strictly Private andConfidential
  • 13. Sensitive EMERGENCY CONTACT NUMBER 13 Strictly Private andConfidential Nurse‫ممرض‬ 0555016400 NaqashYusaf(HSM) 0558319638 HeshamAlahmadi(SEM) 0550251663 IdrisAdeniran(HSE) 0530644494 ChrisBusa(Admin) 05507028425 BadwiTawk(CM) 0566083368 Abdulaziz(Security) 0553870037 POLICE ‫طة‬ ‫ر‬ ‫ش‬ 999 AMAALAINTERNATIONALAIRPORT INCASEOFMEDICAL RBUTECEMERGENCYCONTACTNUMBERS EMERGENCYCALL GOVTAGENCIES EMERGENCYNUMBERS CIVILDEFENSE ‫ي‬‫المدن‬‫الدفاع‬ 998 MOHAMBULANCE 997 All workers at the site will receive Emergency Contact Number cards, which they can use to call for assistance during any emergency situations. Heat Stress Management
  • 14. Sensitive Heat Stress Management HEAT STRESS AWARENESS POSTERS IN OFFICES & ON SITE 14 Strictly Private andConfidential
  • 15. Sensitive Heat Stress Management CONTINUOUS HEAT STRESS AWARENESS 15 Strictly Private andConfidential
  • 16. Sensitive HEAT STRESS MANAGEMENT PLAN 16 Strictly Private andConfidential Before the commencement of the mid-day break, a revised Heat Stress Management Plan, which incorporates specific work-rest regimens for different levels of work intensity (light, moderate, and heavy), will be resubmitted for approval. Heat Stress Management