SlideShare une entreprise Scribd logo
1  sur  44
BUILDING INFORMATION MODELING (BIM) WAS INTRODUCED
NEARLY TWELVE YEARS AGO TO DISTINGUISH THE INFORMATION RICH
ARCHITECTURAL 3D MODELING FROM THE TRADITIONAL 2D DRAWING. BIM IS
A BUILDING DESIGN METHODOLOGY CHARACTERIZED BY THE CREATION
AND USE OF COORDINATED, INTERNALLY CONSISTENT COMPUTABLE
INFORMATION ABOUT A BUILDING PROJECT IN DESIGN AND CONSTRUCTION.
• RELIABLE DIGITAL REPRESENTATION
• HIGH-QUALITY CONSTRUCTION DOCUMENT PRODUCTION
• CONSTRUCTION PLANNING
• PERFORMANCE PREDICTIONS
• COST ESTIMATES
WHAT IS BIM
ESSENTIAL PARAMETER IN BIM
“X”AXIS “Y”AXIS
“Z”AXIS
BIM PLATFORM USES THE THIRD
DIMENSION (ALONG “Z” AXIS) WHICH
ENHANCES OUR VISUALISATION IN 3D
AND EASES THE COORDINATION EFFORT
IN AUTOCAD TWO
DIMENSION ALONG “X” AXIS
AND “Z” AXIS ARE USED
CLIENT
DESIGN
BASIC INPUT
SCHEME/HAND SKETCH
PRESENTATION
3D MODEL
QUANTITY
CLASH
ANALYSIS
SECTIONS &
PLANS
GFC
DRAWING
 WALLS WITH THICKNESS AND HEIGHT, FIRE RATING IF REQUIRED
 ROOM DIMENSION WITH FUNCTIONAL NAMES
 CEILING TYPE, LEVEL
 VERTICAL CIRCULATION (STAIR,LIFT AND ESCALATOR) LOCATION
 EXTERIOR FAÇADE MATERIAL
 ACCESS OPENINGS IN WALL FOR DOORS,WINDOWS, LOUVER,
ROLLING SHUTTER
 WINDOW AND DOOR SCHEDULE
 SERVICE ROOMS(MECHANICAL, FIRE & PHE PUMP ROOM ) AND
SERVICE FLOORS WELL DEFINED AS PER MEP SERVICES
REQUIREMENT
 ARCITECTURAL INTENT FOR SERVICES AT CEILING LEVEL FOR
AREAS WITHOUT FALSE CEILING
 TYPE OF FIXTURES, FURNITURES
 PLANTER BODY,WATER BODIES (SPECIAL FEATURES) IF ANY
 ANY ADDITIONAL AESTHATIC REQUIREMENTS (BULK HEAD,
SKYLIGHT, COLUMN CLADDING, RAILING ETC)
 ROOF TYPE LEVELS, PARAPET HEIGHT
 FINISHING MATRIX
ARCHITECTURAL INPUT
 ARCHITECTURAL LAYOUT
 FLOOR THICK NESS & TOC.
 FOUNADTION DETAIL(ISOLATED, COMBINED, WALL FOOTING)
 COLUMN TYPE AND SIZE
 BEAM DESIGN INFORMATION(EXTRACTED FROM ANALYSIS
SOFTWARE)-
 STEPS INVOLVED:
• INNITIALLY BEAM SIZES TO BE PROVIDED
• BEAM SHOULD BE PLACED AS PER ARCHITECTURAL
LAYOUT
• SEND AGAIN TO DESGNER FOR FINAL ANALYSIS FOR
CHANGES IF ANY
 FINALLY MODEL HAS TO BE COMPLETED INCLUDING RAMP &
STAIR.
STRUCTURAL INPUT
 ARCHITECTURE & STRUCTURAL LAYOUT
 RCP LAYOUT
 EQUIPMENT CAPACITY AND LOCATION
 SHAFT LOCATION
 SCHEME AND ZONING INFORMATION
 VENDOR’S G.A. DRAWING
HVAC DESIGN INPUT
ARCHITECTURE LAYOUT SHOWING PLUMBING FIXTURE
LOCATION.
DEPTH OF SUNKEN IN WET AREAS.
PIPE MATERIAL AS PER SPEC.
PIPE DIAMETER .
PIPE TYPES (WASTE, SOIL, RAIN WATER,IRRIGATION, WATER
SUPPLY)
PIPE SLOPE.
SUPPORT SPACING WHEREVER APPLICABLE.
FLOOR SCREED.
RAIN WATER PIPE LOCATION & HARVESTING TANK..
PIPING ARRANGEMENT INSIDE THE SHAFT.
LOCATION OF VALVES AND OTHER ACCESSORIES.
LOCATION OF HOT WATER EQUIPMENTS.
EXTERNAL ROUTING OF SANITARY, STORM & WATER SUPPLY
INPUT INCLUDING GULLY TRAP, MANHOLE & RAIN WATER
CHAMBER.
LAYOUT AND DETAILS OF WTP, STP, ETC.,
PHE DESIGN INPUT
 ARCHITECTURE & STRUCTURAL LAYOUT
 RCP LAYOUT
 LIGHTING LAYOUT-NUMBER OF FIXTURES, TYPE AND
ARRANGEMENT
 POWER LAYOUT-TYPE, QUANTITY AND ARRANGEMENT
 CABLE TRAY/BUS DUCT – SIZE AND ARRANGEMENT
 SUBSTATION LAYOUT – EQUIPMENT, DIMENSIONS,
ARRANGEMENT AND STATUOTORY CLEARANCE
 SCHEMATIC AND CABLE SCHEDULE.
ELECTRICAL DESIGN INPUT
 ARCHITECTURE , SHAFT LOCATION & STRUCTURAL LAYOUT
 RCP LAYOUT.
 CAR PARKING
 PIPE MATERIAL & GRADE AS PER DBR AND BOQ
 HYDRANT VALVE LOCATION AS PER RECOMMENDED INTERVAL
 PIPE TYPES (SPRINKLER, HYDRANT)
 COVERAGE OF SPRINKLER FOR CAR PARKING AND OFFICE AREA
 FIRE DETECTION AND PUBLIC ADRESSABLE SYSTEMS
 FIRE ALARM PANEL AND NUMBER OF LOOP.
 FIRE RESERVOIR.
 FIRE PUMP ROOM WITH PUMPING DETAILS AND CAPACITY.
FIRE DESIGN INPUT
CLASH REPORT IN NAVIS WORKS
CLASH REPORT DOCUMENTS
THE STEPS INVOLVED:
1. THE STRUCTURE FOUNDATION MODEL SHOULD BE FREEZED
BEFORE START OF PHE MODEL
1. IN CASE OF ANY CLASH, CAN BE RESOLVED BY CHANGING THE
PIPE ROUTE, LOWERING THE PIPE DEPTH TO BELOW
FOUNDATION ELEMENT(HUME), SLEEVES CAN ALSO BE
PROVIDED AFTER DISCUSSION WITH THE STRUCTURAL
ENGINEER
TWO ELEMENTS ARE INVOLVED HERE :
STRUCTURE
PHE
STEPS INVOLVED:
THE RCP LAYOUT IS TO BE FREEZED
THE LOCATION OF THE FOLLOWING TO BE FIXED
1.LIGHTING FIXTURE LOCATION BY ELECTRICAL
2.DIFFUSER/GRILL LAYOUT BY HVAC
3.FIRE ALARM/SPRINKLER LAYOUT BY FIRE.
ELEMENTS INVOLVED:-
ARCHITECTURE RCP
HVAC DIFFUSER
FIRE DETECTOR AND SPRINKLER
ELECTRICAL :LIGHTING FIXTURE
ELECTRICAL
ARCH-RCP
ELECTRICAL LIGHTING
LIGHTING + HVAC DIFFUSER/GRILL
DIFFUSER+LIGHTING+ SPRINKLER/FIRE ALARM
COORDINATED RCP TO ARCHITECT FOR REVIEW
(ASTHETIC/LOOK AND FILL)
COMMENTED RCP FROM ARCHITECT
HVAC FIRE
PHE PUMP ROOM PHE, HVAC, ELECTRICAL, ELV
TOILET AREA PHE, HVAC, ELECTRICAL, ELV
FIRE PUMP ROOM FIRE, HVAC, ELECTRICAL, ELV
OFFICE/ODC/CORRIDOR HVAC, PHE, FIRE, ELECTRICAL, ELV
TERRACE AREA HVAC, FIRE, PHE, ELECTRICAL, ELV
ELECTRICAL ROOM
SUB STATION
DG ROOM
HUB ROOM
BMS ROOM
SWITCH ROOM
UPS ROOM
DATA CENTER
PLAT ROOM/CHILLER PLANT/AHU ROOM HVAC, ELV
ELECTRICAL, HVAC, PHE, ELV
DAY-0 STAGE-0
A (MEP) DESIGN CAL CULATION AND REDINESS OF BASIC DRAWING INPUTS FOR THE ZONE BY THE ENGINEERS.
B (ARCH/STRUC) PREPARATION OF BASIC COORDINATED MODEL.
DAY-1 STAGE-1  
APPROX SPACE PLANNING AND BASIC ROUTING FOR INDIVIDUAL MEP DISCIPLINE BY THE ENGINEERS ON THE
ARCH. & STRUC. LAYOUT.
DAY-2
STAGE-2  
STRUCTURE & ARCHITECTURE MODEL REVIEW FOR ENABELING MEP DRAFTING PERSONS TO UDERSTAND THE
ZONE IN A 3D PLATFORM.
STAGE-3   INTER MEP DISCIPLINE COORDINATION MEETING TO FREEZ APPROX. PLAN AND ELEVATION.
DAY-3 STAGE-4   MEP DRAFTING AND MODEL DEVELOPMENT LAYOUT BASED ON INPUTS (STAGE-0 TO STAGE-3
DAY-3 & 4 STAGE-5
A CHECKING OF DRAWING BY ENGINEERS FOR TECHNICAL ADEQUECY (NOT CLASH DETECTION)
B MODEL UPDATION BY ARCH. & STRUC. AS PER MEP MODEL.
DAY-6 STAGE-6   MODEL REVIEW IN NAVIS BY ALL DISCIPLINE (MEP, STRUC, ARCH)
DAY-7 & 8 STAGE-7   CLASH COORDINATION AND RESOLVE AS PER STAGE-6
DAY-9 STAGE-8   ANNOTATION & SHEET CREATION
DAY-10 STAGE-9   QC & CORRCTION & GFC
• WALL CUT OUT LOCATION TO ARCHITECTURE.
• SLEEVE LOCATION FOR THE BEAM TO STRUC.
• DOG HOUSE LOCATION AND HEIGHT TO STRUC. & ARCH.
• LOUVERS SIZES & LOCATION TO ARCH.
• SHARE WALL OPENING TO STRUC.
• CORE CUT LOCATION & SIZE TO STRUC.
PHASE-I PHASE-II
PHASE-III
THANK YOU

Contenu connexe

Tendances

BIM Presentation
BIM PresentationBIM Presentation
BIM PresentationOmer Syed
 
Revit and Building Information Modeling (BIM) Presentation
Revit and Building Information Modeling (BIM) PresentationRevit and Building Information Modeling (BIM) Presentation
Revit and Building Information Modeling (BIM) Presentationryanabarton
 
Bim implementation
  Bim implementation   Bim implementation
Bim implementation Omar Selim
 
BIM process adoption for integrated design and constuction
BIM process adoption for integrated design and constuctionBIM process adoption for integrated design and constuction
BIM process adoption for integrated design and constuctionReshma Philip
 
Revit BIM Engineering Solutions by TrueCADD
Revit BIM Engineering Solutions by TrueCADDRevit BIM Engineering Solutions by TrueCADD
Revit BIM Engineering Solutions by TrueCADDGaurang Trivedi
 
Building information modelling
Building information modellingBuilding information modelling
Building information modellingKiran Birdi
 
Building Information Modelling Presentation
Building Information Modelling PresentationBuilding Information Modelling Presentation
Building Information Modelling PresentationMotasem Albanna
 
MTECH BIM project case study
MTECH BIM project case studyMTECH BIM project case study
MTECH BIM project case studyStephen Au
 
Digital Transformation of the Construction Industry
Digital Transformation of the Construction IndustryDigital Transformation of the Construction Industry
Digital Transformation of the Construction IndustryCCT International
 
Revit mep online training ppt
Revit mep online training pptRevit mep online training ppt
Revit mep online training pptjaymicrosoftva
 

Tendances (20)

BIM Presentation
BIM PresentationBIM Presentation
BIM Presentation
 
Revit and Building Information Modeling (BIM) Presentation
Revit and Building Information Modeling (BIM) PresentationRevit and Building Information Modeling (BIM) Presentation
Revit and Building Information Modeling (BIM) Presentation
 
BIM & Sustainability
BIM & SustainabilityBIM & Sustainability
BIM & Sustainability
 
Bim implementation
  Bim implementation   Bim implementation
Bim implementation
 
BIM Execution Plan
BIM Execution PlanBIM Execution Plan
BIM Execution Plan
 
BIM process adoption for integrated design and constuction
BIM process adoption for integrated design and constuctionBIM process adoption for integrated design and constuction
BIM process adoption for integrated design and constuction
 
Revit BIM Engineering Solutions by TrueCADD
Revit BIM Engineering Solutions by TrueCADDRevit BIM Engineering Solutions by TrueCADD
Revit BIM Engineering Solutions by TrueCADD
 
Building information modelling
Building information modellingBuilding information modelling
Building information modelling
 
Revit Mep ppt.pdf
Revit Mep ppt.pdfRevit Mep ppt.pdf
Revit Mep ppt.pdf
 
What is BIM?
What is BIM?What is BIM?
What is BIM?
 
Building Information Modelling Presentation
Building Information Modelling PresentationBuilding Information Modelling Presentation
Building Information Modelling Presentation
 
BIM
BIMBIM
BIM
 
MTECH BIM project case study
MTECH BIM project case studyMTECH BIM project case study
MTECH BIM project case study
 
Building Information Modeling (BIM)
Building Information Modeling (BIM)Building Information Modeling (BIM)
Building Information Modeling (BIM)
 
MEP BIM design
MEP BIM designMEP BIM design
MEP BIM design
 
BIM
BIMBIM
BIM
 
Digital Transformation of the Construction Industry
Digital Transformation of the Construction IndustryDigital Transformation of the Construction Industry
Digital Transformation of the Construction Industry
 
BUILDING MEP SYSTEM
BUILDING MEP SYSTEMBUILDING MEP SYSTEM
BUILDING MEP SYSTEM
 
BIM Execution plan
BIM  Execution  planBIM  Execution  plan
BIM Execution plan
 
Revit mep online training ppt
Revit mep online training pptRevit mep online training ppt
Revit mep online training ppt
 

En vedette

BIM COORDINATION PORTOFOLIOOO
BIM COORDINATION PORTOFOLIOOOBIM COORDINATION PORTOFOLIOOO
BIM COORDINATION PORTOFOLIOOOMohab Magdy,PMP
 
Combined BIM & Design Coordination Workflow-r01
Combined BIM & Design Coordination Workflow-r01Combined BIM & Design Coordination Workflow-r01
Combined BIM & Design Coordination Workflow-r01saed saffarini
 
Bim Presentation
Bim PresentationBim Presentation
Bim Presentationrsalbin
 
Haram complementary projects temporary feeding proposals
Haram complementary projects temporary feeding proposalsHaram complementary projects temporary feeding proposals
Haram complementary projects temporary feeding proposalsMohamed Azzam
 
Pinnacle Infotech partaking at 2017 PCI Convention
 Pinnacle Infotech partaking at 2017 PCI Convention  Pinnacle Infotech partaking at 2017 PCI Convention
Pinnacle Infotech partaking at 2017 PCI Convention Pinnacle Infotech
 
Presentasi Sistem Tata SuryaㅡSolar System Explanation
Presentasi Sistem Tata SuryaㅡSolar System ExplanationPresentasi Sistem Tata SuryaㅡSolar System Explanation
Presentasi Sistem Tata SuryaㅡSolar System ExplanationIka
 
Au 09 Bi Mmeans Business.1.05.10
Au 09 Bi Mmeans Business.1.05.10Au 09 Bi Mmeans Business.1.05.10
Au 09 Bi Mmeans Business.1.05.10friscozephyr
 
Flevy.com - Collaborative Process Mapping
Flevy.com - Collaborative Process MappingFlevy.com - Collaborative Process Mapping
Flevy.com - Collaborative Process MappingDavid Tracy
 
Anthony N Dauginas
Anthony N DauginasAnthony N Dauginas
Anthony N Dauginasdauginas
 
Communication & Coordination on a Construction Project Through Building I...
Communication & Coordination on a Construction Project Through Building I...Communication & Coordination on a Construction Project Through Building I...
Communication & Coordination on a Construction Project Through Building I...muhammad87
 
Week 7 powerpoint reflected ceiling plans
Week 7 powerpoint   reflected ceiling plansWeek 7 powerpoint   reflected ceiling plans
Week 7 powerpoint reflected ceiling plansFreya Van Saun
 
Trusted BIM: Accurate As-Builts for Project Coordination
Trusted BIM: Accurate As-Builts for Project CoordinationTrusted BIM: Accurate As-Builts for Project Coordination
Trusted BIM: Accurate As-Builts for Project CoordinationClearEdge3D Inc
 
Bim101 Aec
Bim101 AecBim101 Aec
Bim101 Aecmarybk
 
BIM and the drywall cover up - A case for division 9
BIM and the drywall cover up - A case for division 9 BIM and the drywall cover up - A case for division 9
BIM and the drywall cover up - A case for division 9 StrucSoft Solutions
 

En vedette (20)

BIM COORDINATION PORTOFOLIOOO
BIM COORDINATION PORTOFOLIOOOBIM COORDINATION PORTOFOLIOOO
BIM COORDINATION PORTOFOLIOOO
 
Combined BIM & Design Coordination Workflow-r01
Combined BIM & Design Coordination Workflow-r01Combined BIM & Design Coordination Workflow-r01
Combined BIM & Design Coordination Workflow-r01
 
Bim Presentation
Bim PresentationBim Presentation
Bim Presentation
 
Sidz
SidzSidz
Sidz
 
STAINES AP-PLANS PHDD C2-A0 HVAC MECH
STAINES AP-PLANS PHDD C2-A0 HVAC  MECHSTAINES AP-PLANS PHDD C2-A0 HVAC  MECH
STAINES AP-PLANS PHDD C2-A0 HVAC MECH
 
Haram complementary projects temporary feeding proposals
Haram complementary projects temporary feeding proposalsHaram complementary projects temporary feeding proposals
Haram complementary projects temporary feeding proposals
 
1 Generral Layout
1 Generral Layout1 Generral Layout
1 Generral Layout
 
EMCI Presentation
EMCI PresentationEMCI Presentation
EMCI Presentation
 
Pinnacle Infotech partaking at 2017 PCI Convention
 Pinnacle Infotech partaking at 2017 PCI Convention  Pinnacle Infotech partaking at 2017 PCI Convention
Pinnacle Infotech partaking at 2017 PCI Convention
 
Presentasi Sistem Tata SuryaㅡSolar System Explanation
Presentasi Sistem Tata SuryaㅡSolar System ExplanationPresentasi Sistem Tata SuryaㅡSolar System Explanation
Presentasi Sistem Tata SuryaㅡSolar System Explanation
 
Bim Facades.Final
Bim Facades.FinalBim Facades.Final
Bim Facades.Final
 
Au 09 Bi Mmeans Business.1.05.10
Au 09 Bi Mmeans Business.1.05.10Au 09 Bi Mmeans Business.1.05.10
Au 09 Bi Mmeans Business.1.05.10
 
Flevy.com - Collaborative Process Mapping
Flevy.com - Collaborative Process MappingFlevy.com - Collaborative Process Mapping
Flevy.com - Collaborative Process Mapping
 
Anthony N Dauginas
Anthony N DauginasAnthony N Dauginas
Anthony N Dauginas
 
Communication & Coordination on a Construction Project Through Building I...
Communication & Coordination on a Construction Project Through Building I...Communication & Coordination on a Construction Project Through Building I...
Communication & Coordination on a Construction Project Through Building I...
 
Reducing Risk with BIM
Reducing Risk with BIMReducing Risk with BIM
Reducing Risk with BIM
 
Week 7 powerpoint reflected ceiling plans
Week 7 powerpoint   reflected ceiling plansWeek 7 powerpoint   reflected ceiling plans
Week 7 powerpoint reflected ceiling plans
 
Trusted BIM: Accurate As-Builts for Project Coordination
Trusted BIM: Accurate As-Builts for Project CoordinationTrusted BIM: Accurate As-Builts for Project Coordination
Trusted BIM: Accurate As-Builts for Project Coordination
 
Bim101 Aec
Bim101 AecBim101 Aec
Bim101 Aec
 
BIM and the drywall cover up - A case for division 9
BIM and the drywall cover up - A case for division 9 BIM and the drywall cover up - A case for division 9
BIM and the drywall cover up - A case for division 9
 

Similaire à BIM & Coordination Work Process Presentation

Similaire à BIM & Coordination Work Process Presentation (20)

C.v mep engineer draftsman
C.v mep engineer draftsmanC.v mep engineer draftsman
C.v mep engineer draftsman
 
RESUME 2016
RESUME 2016RESUME 2016
RESUME 2016
 
Pasinaya-Townhomes-Thickened-Slab-1.pdf
Pasinaya-Townhomes-Thickened-Slab-1.pdfPasinaya-Townhomes-Thickened-Slab-1.pdf
Pasinaya-Townhomes-Thickened-Slab-1.pdf
 
Presentation- HVAC & PLUMBING DESIGN
Presentation- HVAC & PLUMBING DESIGNPresentation- HVAC & PLUMBING DESIGN
Presentation- HVAC & PLUMBING DESIGN
 
Mohd_Anwarulla
Mohd_AnwarullaMohd_Anwarulla
Mohd_Anwarulla
 
POWER SYSTEM.pdf
POWER SYSTEM.pdfPOWER SYSTEM.pdf
POWER SYSTEM.pdf
 
Citizens Tower Presentation July 28, 2016
Citizens Tower Presentation July 28, 2016Citizens Tower Presentation July 28, 2016
Citizens Tower Presentation July 28, 2016
 
PDMS
PDMSPDMS
PDMS
 
Recycled water project draft plans and specifications
Recycled water project draft plans and specificationsRecycled water project draft plans and specifications
Recycled water project draft plans and specifications
 
LA FLORESTA
LA FLORESTALA FLORESTA
LA FLORESTA
 
KFC - Surprise, AZ
KFC - Surprise, AZKFC - Surprise, AZ
KFC - Surprise, AZ
 
Farmers PDC Chino CA
Farmers PDC Chino CAFarmers PDC Chino CA
Farmers PDC Chino CA
 
D48073646
D48073646D48073646
D48073646
 
Introduction OF NR BIM CONSULTANT
Introduction OF NR BIM CONSULTANTIntroduction OF NR BIM CONSULTANT
Introduction OF NR BIM CONSULTANT
 
Introduction of nr bim consultant
Introduction of nr bim consultantIntroduction of nr bim consultant
Introduction of nr bim consultant
 
Introduction OF NR BIM CONSULTANT
Introduction OF NR BIM CONSULTANTIntroduction OF NR BIM CONSULTANT
Introduction OF NR BIM CONSULTANT
 
Graduation Project (DESIGN AND ANALYSIS OF MULTI-TOWER STRUCTURE USING ETABS).
Graduation Project (DESIGN AND ANALYSIS OF MULTI-TOWER STRUCTURE USING ETABS).Graduation Project (DESIGN AND ANALYSIS OF MULTI-TOWER STRUCTURE USING ETABS).
Graduation Project (DESIGN AND ANALYSIS OF MULTI-TOWER STRUCTURE USING ETABS).
 
Pdf soummmm
Pdf soummmmPdf soummmm
Pdf soummmm
 
Pdf soummmm
Pdf soummmmPdf soummmm
Pdf soummmm
 
Resume (Expanded) - Christopher C. Love
Resume (Expanded) - Christopher C. LoveResume (Expanded) - Christopher C. Love
Resume (Expanded) - Christopher C. Love
 

BIM & Coordination Work Process Presentation

  • 1.
  • 2. BUILDING INFORMATION MODELING (BIM) WAS INTRODUCED NEARLY TWELVE YEARS AGO TO DISTINGUISH THE INFORMATION RICH ARCHITECTURAL 3D MODELING FROM THE TRADITIONAL 2D DRAWING. BIM IS A BUILDING DESIGN METHODOLOGY CHARACTERIZED BY THE CREATION AND USE OF COORDINATED, INTERNALLY CONSISTENT COMPUTABLE INFORMATION ABOUT A BUILDING PROJECT IN DESIGN AND CONSTRUCTION. • RELIABLE DIGITAL REPRESENTATION • HIGH-QUALITY CONSTRUCTION DOCUMENT PRODUCTION • CONSTRUCTION PLANNING • PERFORMANCE PREDICTIONS • COST ESTIMATES WHAT IS BIM
  • 3. ESSENTIAL PARAMETER IN BIM “X”AXIS “Y”AXIS “Z”AXIS BIM PLATFORM USES THE THIRD DIMENSION (ALONG “Z” AXIS) WHICH ENHANCES OUR VISUALISATION IN 3D AND EASES THE COORDINATION EFFORT IN AUTOCAD TWO DIMENSION ALONG “X” AXIS AND “Z” AXIS ARE USED
  • 5.
  • 6.
  • 7.
  • 8.
  • 9. DESIGN BASIC INPUT SCHEME/HAND SKETCH PRESENTATION 3D MODEL QUANTITY CLASH ANALYSIS SECTIONS & PLANS GFC DRAWING
  • 10.
  • 11.
  • 12.
  • 13.
  • 14.
  • 15.
  • 16.
  • 17.
  • 18.
  • 19.  WALLS WITH THICKNESS AND HEIGHT, FIRE RATING IF REQUIRED  ROOM DIMENSION WITH FUNCTIONAL NAMES  CEILING TYPE, LEVEL  VERTICAL CIRCULATION (STAIR,LIFT AND ESCALATOR) LOCATION  EXTERIOR FAÇADE MATERIAL  ACCESS OPENINGS IN WALL FOR DOORS,WINDOWS, LOUVER, ROLLING SHUTTER  WINDOW AND DOOR SCHEDULE  SERVICE ROOMS(MECHANICAL, FIRE & PHE PUMP ROOM ) AND SERVICE FLOORS WELL DEFINED AS PER MEP SERVICES REQUIREMENT  ARCITECTURAL INTENT FOR SERVICES AT CEILING LEVEL FOR AREAS WITHOUT FALSE CEILING  TYPE OF FIXTURES, FURNITURES  PLANTER BODY,WATER BODIES (SPECIAL FEATURES) IF ANY  ANY ADDITIONAL AESTHATIC REQUIREMENTS (BULK HEAD, SKYLIGHT, COLUMN CLADDING, RAILING ETC)  ROOF TYPE LEVELS, PARAPET HEIGHT  FINISHING MATRIX ARCHITECTURAL INPUT
  • 20.  ARCHITECTURAL LAYOUT  FLOOR THICK NESS & TOC.  FOUNADTION DETAIL(ISOLATED, COMBINED, WALL FOOTING)  COLUMN TYPE AND SIZE  BEAM DESIGN INFORMATION(EXTRACTED FROM ANALYSIS SOFTWARE)-  STEPS INVOLVED: • INNITIALLY BEAM SIZES TO BE PROVIDED • BEAM SHOULD BE PLACED AS PER ARCHITECTURAL LAYOUT • SEND AGAIN TO DESGNER FOR FINAL ANALYSIS FOR CHANGES IF ANY  FINALLY MODEL HAS TO BE COMPLETED INCLUDING RAMP & STAIR. STRUCTURAL INPUT
  • 21.  ARCHITECTURE & STRUCTURAL LAYOUT  RCP LAYOUT  EQUIPMENT CAPACITY AND LOCATION  SHAFT LOCATION  SCHEME AND ZONING INFORMATION  VENDOR’S G.A. DRAWING HVAC DESIGN INPUT
  • 22. ARCHITECTURE LAYOUT SHOWING PLUMBING FIXTURE LOCATION. DEPTH OF SUNKEN IN WET AREAS. PIPE MATERIAL AS PER SPEC. PIPE DIAMETER . PIPE TYPES (WASTE, SOIL, RAIN WATER,IRRIGATION, WATER SUPPLY) PIPE SLOPE. SUPPORT SPACING WHEREVER APPLICABLE. FLOOR SCREED. RAIN WATER PIPE LOCATION & HARVESTING TANK.. PIPING ARRANGEMENT INSIDE THE SHAFT. LOCATION OF VALVES AND OTHER ACCESSORIES. LOCATION OF HOT WATER EQUIPMENTS. EXTERNAL ROUTING OF SANITARY, STORM & WATER SUPPLY INPUT INCLUDING GULLY TRAP, MANHOLE & RAIN WATER CHAMBER. LAYOUT AND DETAILS OF WTP, STP, ETC., PHE DESIGN INPUT
  • 23.  ARCHITECTURE & STRUCTURAL LAYOUT  RCP LAYOUT  LIGHTING LAYOUT-NUMBER OF FIXTURES, TYPE AND ARRANGEMENT  POWER LAYOUT-TYPE, QUANTITY AND ARRANGEMENT  CABLE TRAY/BUS DUCT – SIZE AND ARRANGEMENT  SUBSTATION LAYOUT – EQUIPMENT, DIMENSIONS, ARRANGEMENT AND STATUOTORY CLEARANCE  SCHEMATIC AND CABLE SCHEDULE. ELECTRICAL DESIGN INPUT
  • 24.  ARCHITECTURE , SHAFT LOCATION & STRUCTURAL LAYOUT  RCP LAYOUT.  CAR PARKING  PIPE MATERIAL & GRADE AS PER DBR AND BOQ  HYDRANT VALVE LOCATION AS PER RECOMMENDED INTERVAL  PIPE TYPES (SPRINKLER, HYDRANT)  COVERAGE OF SPRINKLER FOR CAR PARKING AND OFFICE AREA  FIRE DETECTION AND PUBLIC ADRESSABLE SYSTEMS  FIRE ALARM PANEL AND NUMBER OF LOOP.  FIRE RESERVOIR.  FIRE PUMP ROOM WITH PUMPING DETAILS AND CAPACITY. FIRE DESIGN INPUT
  • 25.
  • 26. CLASH REPORT IN NAVIS WORKS
  • 28. THE STEPS INVOLVED: 1. THE STRUCTURE FOUNDATION MODEL SHOULD BE FREEZED BEFORE START OF PHE MODEL 1. IN CASE OF ANY CLASH, CAN BE RESOLVED BY CHANGING THE PIPE ROUTE, LOWERING THE PIPE DEPTH TO BELOW FOUNDATION ELEMENT(HUME), SLEEVES CAN ALSO BE PROVIDED AFTER DISCUSSION WITH THE STRUCTURAL ENGINEER TWO ELEMENTS ARE INVOLVED HERE : STRUCTURE PHE
  • 29. STEPS INVOLVED: THE RCP LAYOUT IS TO BE FREEZED THE LOCATION OF THE FOLLOWING TO BE FIXED 1.LIGHTING FIXTURE LOCATION BY ELECTRICAL 2.DIFFUSER/GRILL LAYOUT BY HVAC 3.FIRE ALARM/SPRINKLER LAYOUT BY FIRE. ELEMENTS INVOLVED:- ARCHITECTURE RCP HVAC DIFFUSER FIRE DETECTOR AND SPRINKLER ELECTRICAL :LIGHTING FIXTURE
  • 30. ELECTRICAL ARCH-RCP ELECTRICAL LIGHTING LIGHTING + HVAC DIFFUSER/GRILL DIFFUSER+LIGHTING+ SPRINKLER/FIRE ALARM COORDINATED RCP TO ARCHITECT FOR REVIEW (ASTHETIC/LOOK AND FILL) COMMENTED RCP FROM ARCHITECT HVAC FIRE
  • 31.
  • 32.
  • 33. PHE PUMP ROOM PHE, HVAC, ELECTRICAL, ELV TOILET AREA PHE, HVAC, ELECTRICAL, ELV FIRE PUMP ROOM FIRE, HVAC, ELECTRICAL, ELV OFFICE/ODC/CORRIDOR HVAC, PHE, FIRE, ELECTRICAL, ELV TERRACE AREA HVAC, FIRE, PHE, ELECTRICAL, ELV ELECTRICAL ROOM SUB STATION DG ROOM HUB ROOM BMS ROOM SWITCH ROOM UPS ROOM DATA CENTER PLAT ROOM/CHILLER PLANT/AHU ROOM HVAC, ELV ELECTRICAL, HVAC, PHE, ELV
  • 34. DAY-0 STAGE-0 A (MEP) DESIGN CAL CULATION AND REDINESS OF BASIC DRAWING INPUTS FOR THE ZONE BY THE ENGINEERS. B (ARCH/STRUC) PREPARATION OF BASIC COORDINATED MODEL. DAY-1 STAGE-1   APPROX SPACE PLANNING AND BASIC ROUTING FOR INDIVIDUAL MEP DISCIPLINE BY THE ENGINEERS ON THE ARCH. & STRUC. LAYOUT. DAY-2 STAGE-2   STRUCTURE & ARCHITECTURE MODEL REVIEW FOR ENABELING MEP DRAFTING PERSONS TO UDERSTAND THE ZONE IN A 3D PLATFORM. STAGE-3   INTER MEP DISCIPLINE COORDINATION MEETING TO FREEZ APPROX. PLAN AND ELEVATION. DAY-3 STAGE-4   MEP DRAFTING AND MODEL DEVELOPMENT LAYOUT BASED ON INPUTS (STAGE-0 TO STAGE-3 DAY-3 & 4 STAGE-5 A CHECKING OF DRAWING BY ENGINEERS FOR TECHNICAL ADEQUECY (NOT CLASH DETECTION) B MODEL UPDATION BY ARCH. & STRUC. AS PER MEP MODEL. DAY-6 STAGE-6   MODEL REVIEW IN NAVIS BY ALL DISCIPLINE (MEP, STRUC, ARCH) DAY-7 & 8 STAGE-7   CLASH COORDINATION AND RESOLVE AS PER STAGE-6 DAY-9 STAGE-8   ANNOTATION & SHEET CREATION DAY-10 STAGE-9   QC & CORRCTION & GFC
  • 35. • WALL CUT OUT LOCATION TO ARCHITECTURE. • SLEEVE LOCATION FOR THE BEAM TO STRUC. • DOG HOUSE LOCATION AND HEIGHT TO STRUC. & ARCH. • LOUVERS SIZES & LOCATION TO ARCH. • SHARE WALL OPENING TO STRUC. • CORE CUT LOCATION & SIZE TO STRUC.
  • 37.
  • 38.
  • 39.
  • 40.
  • 41.
  • 42.
  • 43.