5. Scale of the task
The solution:
Split into ≈20 separate projects
Spread over 4 years
Common design
Common delivery
Avoid doing it again for at least 7-10 years!
16. Design – Buy – Build – Transition
Delivery of fibre
Delivery of circuits
Delivery of PoPs
Installation of equipment
Plumbing it all together
Testing
Ready For Service
This is business as usual
18. Design – Buy – Build – Transition
New regional infrastructure
New access circuit(s)
New Ethernet device(s)
Same (or enhanced) set of services
Migrate from old to new
at a time that suits you
This is business as usual
19. Design – Buy – Build – Transition
Continual improvement – trying to be more efficient
Migration within 30 days is normal
Last year migration delays cost Jisc (and therefore the community)
over £80,000
We appreciate your support in this area
21. Design – Buy – Build – Transition – Operate
Fibre/circuit support arrangements
same as usual
Equipment support arrangements
at PoP sites ‘4hr + engineer’
at customer sites ‘4hr parts only’
slightly different process
test fault calls planned
we’ll be monitoring this
24. How are we getting on?
2 regions in build
South
South West
Lots of regions in design
Midlands
London
East (Anglia)
North West
Scotland
Thinking about the rest