3. Introduction
What is S - Curve:
Value Vs project time:
Planning Value – Planning progress value
Earned Value -- Actual progress value
Actual Value -- Actual Spent value
Why we use S-curve:
As a tool for project helthy check (status)
As a tool for control of schedule and cost
Forcast of completion ETC and EAC
What it is not:
Not only for the PM (but also for company level of schedule and cost
monitoring)
Not the only project control tool (shall together with schedule
control, cost control as well as man power plan etc.)
4. Set-up and use
Basis of S-curve
Basis of Data:
Cost baseline– Budget (BOQ with levels of WBS)
Input Data:
Progress data as percentage
TBD Standard Tool:
Already set as EPCM Tool :10.161.34.1PublicProject Tools MatrixEPCM
Project Tools_02Project MangementPM01 Project Plan
5. Set-up and use
How to Set- up
Line 1- Planning Value Intial setup
Distribute budget Vs Time and consist with master schedule
Update of budget (only possible through approved DCN)
Line 2- Earned Value timely update
Earned Value or Actual progress, udpated as percentage.
Line 3 – Actual Value
Expenditure accumulated value ( invesigation cash flow)
Forecast of completion
Estimate to completion (ETC )
Estimate at completion ( EAC)
6. Set-up and use
How to Set – up - sample
TASK
PLAN
BUDGET
%
COMPLETE
EV PV AV
Task A 1,000 100% 1,000 1,000 900
Task B 3,500 80% 2,800 2,500 2,200
Task C 2,500 60% 1,500 1,200 1,400
Task D 1,800 30% 540 400 200
Task E 700 5% 35 0 20
Task F 500 0% 0 0 0
TOTALS 10,000 5,875 5,100 4,720
0
650
1500
3000
5100
7200
8600
9400
10000
$0
$1,000
$2,000
$3,000
$4,000
$5,000
$6,000
$7,000
$8,000
$9,000
$10,000
1/1 1/16 1/31 2/15 3/2 3/17 4/1 4/16 5/1
Plan = BCWS Earned Value - BCWP ACWP
7. How to use for analysis - sample
Set-up and use
Time
Status Point
Schedule Variance
EV - PV
$5875 - $5100
Ahead of Schedule
Earned Value
Schedule Status:
EV is higher than plan, the project is ahead of schedule
8. How to use for analysis - sample
Set-up and use
Actual Cost :
- ahead of schedule ;
- under budget;
- is it a problem if AV>PV?
No! if EV>AV, it is may not be a problem.
Status Point
Cost Variance
EV - AV
$5875 - $4720
Time
Below Budget
11. Explanation
Axis
X-axis time line
Y-axis Progress --- RMB or $
3 Lines
Planning Value (PV) - Planned progress
Earned Value (EV) - Actual progress
Actual Value (AV) - Spent progress
Manpower plan
12. Other Highlights
The S – Curve is currently majorly as tools used for
monitoring the schedule status in construction stage.
• For cost status including ETC,EAC etc., it is included in Detailed
Cost Report ( which is already as TBD standard EPCM document
)
• For schedule control, it will be detailed in schedule control process.