SlideShare a Scribd company logo
1 of 13
May 22, 2013
S- Curve
Agenda
Agenda
1. Introduction
2. Basis of S-Curve and Set-up
3. Interpretation
4. Questions
Introduction
What is S - Curve:
 Value Vs project time:
 Planning Value – Planning progress value
 Earned Value -- Actual progress value
 Actual Value -- Actual Spent value
Why we use S-curve:
 As a tool for project helthy check (status)
 As a tool for control of schedule and cost
 Forcast of completion ETC and EAC
What it is not:
 Not only for the PM (but also for company level of schedule and cost
monitoring)
 Not the only project control tool (shall together with schedule
control, cost control as well as man power plan etc.)
Set-up and use
Basis of S-curve
 Basis of Data:
 Cost baseline– Budget (BOQ with levels of WBS)
 Input Data:
 Progress data as percentage
 TBD Standard Tool:
 Already set as EPCM Tool :10.161.34.1PublicProject Tools MatrixEPCM
Project Tools_02Project MangementPM01 Project Plan
Set-up and use
How to Set- up
 Line 1- Planning Value Intial setup
 Distribute budget Vs Time and consist with master schedule
 Update of budget (only possible through approved DCN)
 Line 2- Earned Value timely update
 Earned Value or Actual progress, udpated as percentage.
 Line 3 – Actual Value
 Expenditure accumulated value ( invesigation cash flow)
 Forecast of completion
 Estimate to completion (ETC )
 Estimate at completion ( EAC)
Set-up and use
How to Set – up - sample
TASK
PLAN
BUDGET
%
COMPLETE
EV PV AV
Task A 1,000 100% 1,000 1,000 900
Task B 3,500 80% 2,800 2,500 2,200
Task C 2,500 60% 1,500 1,200 1,400
Task D 1,800 30% 540 400 200
Task E 700 5% 35 0 20
Task F 500 0% 0 0 0
TOTALS 10,000 5,875 5,100 4,720
0
650
1500
3000
5100
7200
8600
9400
10000
$0
$1,000
$2,000
$3,000
$4,000
$5,000
$6,000
$7,000
$8,000
$9,000
$10,000
1/1 1/16 1/31 2/15 3/2 3/17 4/1 4/16 5/1
Plan = BCWS Earned Value - BCWP ACWP
 How to use for analysis - sample
Set-up and use
Time
Status Point
Schedule Variance
EV - PV
$5875 - $5100
Ahead of Schedule
Earned Value
Schedule Status:
EV is higher than plan, the project is ahead of schedule
 How to use for analysis - sample
Set-up and use
Actual Cost :
- ahead of schedule ;
- under budget;
- is it a problem if AV>PV?
No! if EV>AV, it is may not be a problem.
Status Point
Cost Variance
EV - AV
$5875 - $4720
Time
Below Budget
0
5,000,000
10,000,000
15,000,000
20,000,000
25,000,000
30,000,000
ProgressValue
Sample Construction Progress Analysis - XXXX Yangzhou Recycling Plant
Planning value($)
Earned Value($)
Actual Value(Cash Flow).($)
Project Controls - Construction
Progress Curve Sample
0
5,000,000
10,000,000
15,000,000
20,000,000
25,000,000
30,000,000
ProgressValue
S-curve - Metallkraft Yangzhou Recycling Plant
施工进程——麦拓卡夫特扬州回收工厂
Planning value($)
Earned Value($)
Actual Value(Cash Flow).($)
Sample Case of
S-curve
Explanation
Axis
 X-axis time line
 Y-axis Progress --- RMB or $
3 Lines
 Planning Value (PV) - Planned progress
 Earned Value (EV) - Actual progress
 Actual Value (AV) - Spent progress
Manpower plan
Other Highlights
 The S – Curve is currently majorly as tools used for
monitoring the schedule status in construction stage.
• For cost status including ETC,EAC etc., it is included in Detailed
Cost Report ( which is already as TBD standard EPCM document
)
• For schedule control, it will be detailed in schedule control process.
Questions

More Related Content

What's hot

Managing Project Resources
Managing Project ResourcesManaging Project Resources
Managing Project ResourcesToyin Osunlaja
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement ignitetribes
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1adeelmunir158
 
Network analysis by PERT and CPM
Network analysis by PERT and CPMNetwork analysis by PERT and CPM
Network analysis by PERT and CPMRajendrakumar Kadi
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project managementKabilan Kabi
 
7.4 Earned Value Analysis
7.4 Earned Value Analysis7.4 Earned Value Analysis
7.4 Earned Value AnalysisDavidMcLachlan1
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Schedulingsslovepk
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource SchedulingNicola2903
 
Role of project engineering in project management
Role of project engineering in project managementRole of project engineering in project management
Role of project engineering in project managementDr. Pramod Deshpande
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management FundamentalsOxfordCambridge
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of schedulingjmd2011
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baronignitetribes
 
Project Management and Process
Project Management and ProcessProject Management and Process
Project Management and ProcessMuhammad Rehman
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo
 

What's hot (20)

Managing Project Resources
Managing Project ResourcesManaging Project Resources
Managing Project Resources
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
 
Cpm n pert lecture 1
Cpm n pert lecture 1Cpm n pert lecture 1
Cpm n pert lecture 1
 
Network analysis by PERT and CPM
Network analysis by PERT and CPMNetwork analysis by PERT and CPM
Network analysis by PERT and CPM
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 
Project Schedule - Level IV Schedule
Project Schedule - Level IV ScheduleProject Schedule - Level IV Schedule
Project Schedule - Level IV Schedule
 
50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
 
Primavera Training P6
Primavera Training P6Primavera Training P6
Primavera Training P6
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
7.4 Earned Value Analysis
7.4 Earned Value Analysis7.4 Earned Value Analysis
7.4 Earned Value Analysis
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 
Resource Scheduling
Resource SchedulingResource Scheduling
Resource Scheduling
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Role of project engineering in project management
Role of project engineering in project managementRole of project engineering in project management
Role of project engineering in project management
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
 
Assignment project scheduling
Assignment project schedulingAssignment project scheduling
Assignment project scheduling
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baron
 
Project Management and Process
Project Management and ProcessProject Management and Process
Project Management and Process
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
 

Viewers also liked

S-curve analysis for development of hydrographs
S-curve analysis for development of hydrographsS-curve analysis for development of hydrographs
S-curve analysis for development of hydrographsWaleed Liaqat
 
Technology s curves-in_renewable_energies
Technology s curves-in_renewable_energiesTechnology s curves-in_renewable_energies
Technology s curves-in_renewable_energiesMuhammad Sadiq Aftab
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysisNikhil Raj
 
Wk 4 technology life cycle
Wk 4   technology life cycleWk 4   technology life cycle
Wk 4 technology life cycleSaddan Juhari
 
Earned Value Analysis - EVA
Earned Value Analysis - EVAEarned Value Analysis - EVA
Earned Value Analysis - EVAAhmed Bamasdoos
 
Technology Life Cycle With Mobile Generation Example
Technology Life Cycle With Mobile Generation ExampleTechnology Life Cycle With Mobile Generation Example
Technology Life Cycle With Mobile Generation ExampleRahul Kumar
 
S curve innovation #BBTwisnu
S curve innovation #BBTwisnuS curve innovation #BBTwisnu
S curve innovation #BBTwisnuWisnu Dewobroto
 
Human aspect of project management
Human aspect of project managementHuman aspect of project management
Human aspect of project managementKinshook Chaturvedi
 
Technology life cycle
Technology life cycleTechnology life cycle
Technology life cycleMBAMithlesh
 
Innovation and the S-Curve
Innovation and the S-CurveInnovation and the S-Curve
Innovation and the S-Curvewright4
 

Viewers also liked (12)

S-curve analysis for development of hydrographs
S-curve analysis for development of hydrographsS-curve analysis for development of hydrographs
S-curve analysis for development of hydrographs
 
Technology s curves-in_renewable_energies
Technology s curves-in_renewable_energiesTechnology s curves-in_renewable_energies
Technology s curves-in_renewable_energies
 
Earned value analysis
Earned value analysisEarned value analysis
Earned value analysis
 
Wk 4 technology life cycle
Wk 4   technology life cycleWk 4   technology life cycle
Wk 4 technology life cycle
 
Earned Value Analysis - EVA
Earned Value Analysis - EVAEarned Value Analysis - EVA
Earned Value Analysis - EVA
 
Technology Life Cycle With Mobile Generation Example
Technology Life Cycle With Mobile Generation ExampleTechnology Life Cycle With Mobile Generation Example
Technology Life Cycle With Mobile Generation Example
 
S curve innovation #BBTwisnu
S curve innovation #BBTwisnuS curve innovation #BBTwisnu
S curve innovation #BBTwisnu
 
Human aspect of project management
Human aspect of project managementHuman aspect of project management
Human aspect of project management
 
Technology life cycle
Technology life cycleTechnology life cycle
Technology life cycle
 
Innovation and the S-Curve
Innovation and the S-CurveInnovation and the S-Curve
Innovation and the S-Curve
 
Product life cycle
Product life cycleProduct life cycle
Product life cycle
 
Technology S-curves
Technology S-curvesTechnology S-curves
Technology S-curves
 

Similar to S-Curve Presentation- 20130529

Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance ManagementCraig Brown
 
L06 cost management
L06 cost managementL06 cost management
L06 cost managementAsa Chan
 
CostManagementSlides.pdf
CostManagementSlides.pdfCostManagementSlides.pdf
CostManagementSlides.pdfAmrishTyagi8
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptRedhaElhuni
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagementDhamo daran
 
Pppl evms training_02
Pppl evms training_02Pppl evms training_02
Pppl evms training_02apocalypto1
 
Develop a network schedule for your project using either the arrow.docx
Develop a network schedule for your project using either the arrow.docxDevelop a network schedule for your project using either the arrow.docx
Develop a network schedule for your project using either the arrow.docxkhenry4
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control CostAnand Bobade
 
Earned value
Earned valueEarned value
Earned valueOliver
 
Program Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureProgram Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureJohn Carter
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.pptProfDrAnbalaganChinn
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 

Similar to S-Curve Presentation- 20130529 (20)

Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
CostManagementSlides.pdf
CostManagementSlides.pdfCostManagementSlides.pdf
CostManagementSlides.pdf
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
Pppl evms training_02
Pppl evms training_02Pppl evms training_02
Pppl evms training_02
 
Develop a network schedule for your project using either the arrow.docx
Develop a network schedule for your project using either the arrow.docxDevelop a network schedule for your project using either the arrow.docx
Develop a network schedule for your project using either the arrow.docx
 
Chap 7.4 Control Cost
Chap 7.4   Control CostChap 7.4   Control Cost
Chap 7.4 Control Cost
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
 
COST MANAGEMENT REPORT
COST MANAGEMENT REPORT COST MANAGEMENT REPORT
COST MANAGEMENT REPORT
 
Earned value
Earned valueEarned value
Earned value
 
Program Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown StructureProgram Management 2.0: Work Breakdown Structure
Program Management 2.0: Work Breakdown Structure
 
Schulte
SchulteSchulte
Schulte
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 

S-Curve Presentation- 20130529

  • 2. Agenda Agenda 1. Introduction 2. Basis of S-Curve and Set-up 3. Interpretation 4. Questions
  • 3. Introduction What is S - Curve:  Value Vs project time:  Planning Value – Planning progress value  Earned Value -- Actual progress value  Actual Value -- Actual Spent value Why we use S-curve:  As a tool for project helthy check (status)  As a tool for control of schedule and cost  Forcast of completion ETC and EAC What it is not:  Not only for the PM (but also for company level of schedule and cost monitoring)  Not the only project control tool (shall together with schedule control, cost control as well as man power plan etc.)
  • 4. Set-up and use Basis of S-curve  Basis of Data:  Cost baseline– Budget (BOQ with levels of WBS)  Input Data:  Progress data as percentage  TBD Standard Tool:  Already set as EPCM Tool :10.161.34.1PublicProject Tools MatrixEPCM Project Tools_02Project MangementPM01 Project Plan
  • 5. Set-up and use How to Set- up  Line 1- Planning Value Intial setup  Distribute budget Vs Time and consist with master schedule  Update of budget (only possible through approved DCN)  Line 2- Earned Value timely update  Earned Value or Actual progress, udpated as percentage.  Line 3 – Actual Value  Expenditure accumulated value ( invesigation cash flow)  Forecast of completion  Estimate to completion (ETC )  Estimate at completion ( EAC)
  • 6. Set-up and use How to Set – up - sample TASK PLAN BUDGET % COMPLETE EV PV AV Task A 1,000 100% 1,000 1,000 900 Task B 3,500 80% 2,800 2,500 2,200 Task C 2,500 60% 1,500 1,200 1,400 Task D 1,800 30% 540 400 200 Task E 700 5% 35 0 20 Task F 500 0% 0 0 0 TOTALS 10,000 5,875 5,100 4,720 0 650 1500 3000 5100 7200 8600 9400 10000 $0 $1,000 $2,000 $3,000 $4,000 $5,000 $6,000 $7,000 $8,000 $9,000 $10,000 1/1 1/16 1/31 2/15 3/2 3/17 4/1 4/16 5/1 Plan = BCWS Earned Value - BCWP ACWP
  • 7.  How to use for analysis - sample Set-up and use Time Status Point Schedule Variance EV - PV $5875 - $5100 Ahead of Schedule Earned Value Schedule Status: EV is higher than plan, the project is ahead of schedule
  • 8.  How to use for analysis - sample Set-up and use Actual Cost : - ahead of schedule ; - under budget; - is it a problem if AV>PV? No! if EV>AV, it is may not be a problem. Status Point Cost Variance EV - AV $5875 - $4720 Time Below Budget
  • 9. 0 5,000,000 10,000,000 15,000,000 20,000,000 25,000,000 30,000,000 ProgressValue Sample Construction Progress Analysis - XXXX Yangzhou Recycling Plant Planning value($) Earned Value($) Actual Value(Cash Flow).($) Project Controls - Construction Progress Curve Sample
  • 10. 0 5,000,000 10,000,000 15,000,000 20,000,000 25,000,000 30,000,000 ProgressValue S-curve - Metallkraft Yangzhou Recycling Plant 施工进程——麦拓卡夫特扬州回收工厂 Planning value($) Earned Value($) Actual Value(Cash Flow).($) Sample Case of S-curve
  • 11. Explanation Axis  X-axis time line  Y-axis Progress --- RMB or $ 3 Lines  Planning Value (PV) - Planned progress  Earned Value (EV) - Actual progress  Actual Value (AV) - Spent progress Manpower plan
  • 12. Other Highlights  The S – Curve is currently majorly as tools used for monitoring the schedule status in construction stage. • For cost status including ETC,EAC etc., it is included in Detailed Cost Report ( which is already as TBD standard EPCM document ) • For schedule control, it will be detailed in schedule control process.

Editor's Notes

  1. 2016年3月8日星期二