Earned Value Management topic from Control Cost – Cost Management
What is Earned Value Management
Explained EVM with examples
Cost Variances (CV )
Cost Performance Index(CPI)
Schedule Variances(SV)
Schedule Performance Index(SPI)
Cost Overrun and Project Slip
PMP Training in USA,PMP Training in California,PMP Training in Qatar,PMP training in Saudi Arabia,PMP training in India,PMP training in Mumbai,PMP Training in Hyderbad,
PMP Training in Chennai,PMP Training in Canada
2. Agenda
§ What is Earned Value Management
§ Explained EVM with examples
§ Cost Variances (CV )
§ Cost Performance Index(CPI)
§ Schedule Variances(SV)
§ Schedule Performance Index(SPI)
§ Cost Overrun and Project Slip
§ Summary
PMI, PMP, PMBOK and PMI-ACP are registered marks of Project Management Institute, IncConfidential and Copyrighted material of JustPMP 2
10. Cost Performance Index(CPI = EV÷AC )
on First Day
0
50
100
150
200
250
300
350
400
Start 1st Day
Cost
Duration
Actual Cost Budgeted Cost Earned Value
Actual cost(AC)- $350
Budgeted cost(BC)-$290
Earned value(EV)- $203
We are here
We should have
been here
Cost variance(CV) = EV – AC
= 203 – 350 = -147$ < 0
CPI = EV ÷ AC = 203 ÷ 350
We are over budget and have
spent 203 ÷ 350 = 58% more
budget than anticipated (Cost
Performance Index )
Confidential and Copyrighted material of JustPMP
PMI, PMP, PMBOK and PMI-ACP are registered marks of Project Management Institute, Inc 10
13. Schedule Variances( SV = EV - BC ) on
First Day
0
50
100
150
200
250
300
350
400
Start 1st Day
Cost
Duration
Actual Cost(AC) Budgeted Cost(BC) Earned Value(EV)
Actual cost(AC)- $350
Budgeted cost(BC)-$290
Earned value(EV)- $203
We are here
Schedule
variances
in hours
Schedule variance(SC) in dollars = EV – BC
= 203 – 290 = -87$ < 0
Confidential and Copyrighted material of JustPMP
Which is where we should
have then been here
PMI, PMP, PMBOK and PMI-ACP are registered marks of Project Management Institute, Inc 13
14. Schedule Performance Index
(SPI = EV÷ BC ) on First Day
0
50
100
150
200
250
300
350
400
Start 1st Day
Cost
Duration
Actual Cost(AC) Budgeted Cost(BC) Earned Value(EV)
Actual cost(AC)- $350
Budgeted cost(BC)-$290
Earned value(EV)- $203
We are here
Schedule
variances
in hours
Schedule variance(SC) in dollars = EV – BC
= 203 – 290 = -87$ < 0
Confidential and Copyrighted material of JustPMP
Which is where we should
have then been here
SPI = EV ÷ BC = 203 ÷ 290
We are late and have only
performed 203 ÷ 290 = 70% of
the work planned ( Our Schedule
Performance Index )
PMI, PMP, PMBOK and PMI-ACP are registered marks of Project Management Institute, Inc 14
15. The Consequences.. Cost Overrun
0
500
1000
1500
2000
2500
3000
3500
Start 1st Day 2nd Day 3rd Day 4th Day 5th Day 6th Day 7th Day 8th Day 9th Day
Cost
Duration
Actual Cost(AC) Budgeted Cost(BC) Earned Value(EV)
Actual cost(AC)- $350
Budgeted cost(BC)-$290
Earned value(EV)- $203
Confidential and Copyrighted material of JustPMP
Estimate at
completion(EAC) =
$ 3000
Budget at completion
BAC = $ 1740
Cost Overrun
Planned end date
= 6 days
Estimate at completion
= 8.57 days
PMI, PMP, PMBOK and PMI-ACP are registered marks of Project Management Institute, Inc 15
16. The Consequences.. Project Slip
0
500
1000
1500
2000
2500
3000
3500
Start 1st Day 2nd Day 3rd Day 4th Day 5th Day 6th Day 7th Day 8th Day 9th Day
Cost
Duration
Actual Cost(AC) Budgeted Cost(BC) Earned Value(EV)
Actual cost(AC)- $350
Budgeted cost(BC)-$290
Earned value(EV)- $203
Project Slip
Confidential and Copyrighted material of JustPMP
Estimate at
completion(EAC) =
3000 $
Budget at completion
BAC = 1740 $
Cost Overrun
Planned end date
= 6 days
Estimate at completion
= 8.57 days
PMI, PMP, PMBOK and PMI-ACP are registered marks of Project Management Institute, Inc 16
17. Summary of the Consequences
1. If we continue at this rate, we will need: 1740 ÷ 58 = $ 3,000(Cost Estimate at Completion)
and 6 days ÷ 70% = 8.57 days (Schedule Estimate at Completion)to finish the work
2. If you want to finish on budget, we need to work at (Planned remaining budget) ÷ (actual
remaining budget) ( 1740 – 290 ) ÷ ( 1740 – 350 ) = 104.3% of the originally performance
3. If we want to finish on time, we need to work at (actual remaining work) ÷ (planned
remaining work) (600 – 70) ÷ (600 - 100) = 106% of the originally planned performance
Confidential and Copyrighted material of JustPMP
PMI, PMP, PMBOK and PMI-ACP are registered marks of Project Management Institute, Inc 17