SlideShare une entreprise Scribd logo
1  sur  19
Earned	Value	
Management
Earned	Value	Management	topic	from	Control	Cost	– Cost	Management
BY	– Dilip Chaturvedi,	PMP
Email	Id	:	info@justpmp.com
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	IncConfidential	 and	Copyrighted	 material	of	JustPMP
Agenda
§ What	is	Earned	Value	Management	
§ Explained	EVM	with	examples
§ Cost	Variances	(CV	)
§ Cost	Performance	Index(CPI)
§ Schedule	Variances(SV)
§ Schedule	Performance	Index(SPI)
§ Cost	Overrun	and	Project	Slip
§ Summary	
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	IncConfidential	 and	Copyrighted	 material	of	JustPMP 2
What	is	Earned	Value	Management
§ Earned	value	management	is	the	process	of	measuring	the	performance	of	work	against	
what	was	planned	to	identify	variances,	opportunities	to	improve	the	project	or	just	check	
the	project	health’s.
§ It	is	system	of	mathematical	formulas	that	compares	work	performed	against	work	planned,	
and	measures	the	cost	of	the	work	the	project	has	performed.
§ EVM	is	an	important	part	of	cost	control,	since	it	allows	a	project	manager	to	predict	future	
variances	from	the	expenses	to	date	within	the	project.
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	IncConfidential	 and	Copyrighted	 material	of	JustPMP 3
Examples:	Project	Plan	for	Planting	
trees	
Our	team	has	been	tasked	with	Planting	the	trees	on	the	Plot	of	land	behind	 our	company’s	new	factory.
The	Plan:
- 30	Batches	of	20	trees	(	600	trees)
- 5	batches	per	day	(	100	trees	)
- Budgeted	cost	per	tree	2.90	$(	2.50	$	per	baby	tree	/	0.40	$	for	the	slow	release	fertilizer	)
- ->	total	budget	1,740	$
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	IncConfidential	 and	Copyrighted	 material	of	JustPMP 4
After	the	first	day..
1. 70	Trees	were	planted(	the	team	hit	a	patch	with	stones	that	had	to	be	removed	before	the	trees	could	
be	planted.
2. Total	cost	was	$350	(	we	had	to	rent	a	special	machine	to	help	remove	the	stones	which	cost	$147	for	
the	day	)
Simple	EVM	calculation
- Earned	value	=	70	trees	planted	*	$2.90		=	$203	
- Budgeted	cost	=	100	trees	planned	per	day	*	$2.90		=	$290	
- Actual	cost	=	70	trees	planted	*	$2.90	+	$147	for	machine	=	$350	
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	IncConfidential	 and	Copyrighted	 material	of	JustPMP 5
First	Day
0
50
100
150
200
250
300
350
400
Start 1st	Day
Cost
Duration
Actual	Cost(AC) Budgeted	Cost(BC) Earned	Value(EV)
Actual	cost(AC)- $350
Budgeted	cost(BC)-$290
Earned	value(EV)- $203
Confidential	and	Copyrighted	material	of	JustPMP
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	Inc 6
Regarding	Actual	Cost
0
50
100
150
200
250
300
350
400
Start 1st	Day
Cost
Duration
Actual	Cost Budgeted	Cost Earned	Value
Actual	cost(AC)- $350
Budgeted	cost(BC)-$290
Earned	value(EV)- $203
We	are	here
Confidential	and	Copyrighted	material	of	JustPMP
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	Inc 7
Expected	Cost	on	First	Day
0
50
100
150
200
250
300
350
400
Start 1st	Day
Cost
Duration
Actual	Cost Budgeted	Cost Earned	Value
Actual	cost(AC)- $350
Budgeted	cost(BC)-$290
Earned	value(EV)- $203
We	are	here
We	should	have	
been	here
Confidential	and	Copyrighted	material	of	JustPMP
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	Inc 8
Cost	Variance(CV	=	EV-AC)	on	First	Day
0
50
100
150
200
250
300
350
400
Start 1st	Day
Cost
Duration
Actual	Cost Budgeted	Cost Earned	Value
Actual	cost(AC)- $350
Budgeted	cost(BC)-$290
Earned	value(EV)- $203
We	are	here
We	should	have	
been	here
Cost	variance(CV)	=	EV	– AC
=	203	– 350	=	-147$	<	0	
Confidential	and	Copyrighted	material	of	JustPMP
9
Cost	Performance	Index(CPI	=	EV÷AC	)
on	First	Day
0
50
100
150
200
250
300
350
400
Start 1st	Day
Cost
Duration
Actual	Cost Budgeted	Cost Earned	Value
Actual	cost(AC)- $350
Budgeted	cost(BC)-$290
Earned	value(EV)- $203
We	are	here
We	should	have	
been	here
Cost	variance(CV)	=	EV	– AC
=	203	– 350	=	-147$	<	0	
CPI	=	EV	÷ AC	=	203	÷ 350
We	are	over	budget	and	have	
spent	203	÷ 350	=	58%	more	
budget	than	anticipated	(Cost	
Performance	Index	)
Confidential	and	Copyrighted	material	of	JustPMP
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	Inc 10
Regarding	Schedule	on	First	Day
0
50
100
150
200
250
300
350
400
Start 1st	Day
Cost
Duration
Actual	Cost(AC) Budgeted	Cost(BC) Earned	Value(EV)
Actual	cost(AC)- $350
Budgeted	cost(BC)-$290
Earned	value(EV)- $203
We	are	here
Confidential	and	Copyrighted	material	of	JustPMP
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	Inc 11
Regarding	Schedule	in	Duration	on	
First	Day
0
50
100
150
200
250
300
350
400
Start 1st	Day
Cost
Duration
Actual	Cost(AC) Budgeted	Cost(BC) Earned	Value(EV)
Actual	cost(AC)- $350
Budgeted	cost(BC)-$290
Earned	value(EV)- $203
We	are	here
Schedule	
variances
in	hours
Confidential	and	Copyrighted	material	of	JustPMP
Which	is	where	we	should	
have	then	been	here
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	Inc 112
Schedule	Variances(	SV	=	EV	- BC	)	on	
First	Day	
0
50
100
150
200
250
300
350
400
Start 1st	Day
Cost
Duration
Actual	Cost(AC) Budgeted	Cost(BC) Earned	Value(EV)
Actual	cost(AC)- $350
Budgeted	cost(BC)-$290
Earned	value(EV)- $203
We	are	here
Schedule	
variances
in	hours
Schedule	variance(SC)	in	dollars	=	EV	– BC
=	203	– 290	=	-87$	<	0	
Confidential	and	Copyrighted	material	of	JustPMP
Which	is	where	we	should	
have	then	been	here
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	Inc 13
Schedule	Performance	Index	
(SPI	=	EV÷ BC	)	on	First	Day
0
50
100
150
200
250
300
350
400
Start 1st	Day
Cost
Duration
Actual	Cost(AC) Budgeted	Cost(BC) Earned	Value(EV)
Actual	cost(AC)- $350
Budgeted	cost(BC)-$290
Earned	value(EV)- $203
We	are	here
Schedule	
variances
in	hours
Schedule	variance(SC)	in	dollars	=	EV	– BC
=	203	– 290	=	-87$	<	0	
Confidential	and	Copyrighted	material	of	JustPMP
Which	is	where	we	should	
have	then	been	here
SPI	=	EV	÷ BC	=	203	÷ 290
We	are	late	and	have	only	
performed		203	÷ 290	=	70%	of	
the	work	planned	(	Our Schedule	
Performance	Index	)
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	Inc 14
The	Consequences..	Cost	Overrun
0
500
1000
1500
2000
2500
3000
3500
Start 1st	Day 2nd	Day 3rd	Day 4th	Day 5th	Day 6th	Day 7th	Day 8th	Day 9th	Day
Cost
Duration
Actual	Cost(AC) Budgeted	Cost(BC) Earned	Value(EV)
Actual	cost(AC)- $350
Budgeted	cost(BC)-$290
Earned	value(EV)- $203
Confidential	and	Copyrighted	material	of	JustPMP
Estimate	at	
completion(EAC)	=	
$	3000	
Budget	at	completion
BAC	=		$	1740		
Cost	Overrun
Planned	end	date
=	6	days
Estimate	at	completion	
=	8.57	days
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	Inc 15
The	Consequences..	Project	Slip
0
500
1000
1500
2000
2500
3000
3500
Start 1st	Day 2nd	Day 3rd	Day 4th	Day 5th	Day 6th	Day 7th	Day 8th	Day 9th	Day
Cost
Duration
Actual	Cost(AC) Budgeted	Cost(BC) Earned	Value(EV)
Actual	cost(AC)- $350
Budgeted	cost(BC)-$290
Earned	value(EV)- $203
Project	Slip
Confidential	and	Copyrighted	material	of	JustPMP
Estimate	at	
completion(EAC)	=	
3000	$
Budget	at	completion
BAC	=		1740	$	
Cost	Overrun
Planned	end	date
=	6	days
Estimate	at	completion	
=	8.57	days
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	Inc 16
Summary	of	the	Consequences
1. If	we	continue	at	this	rate,	we	will	need:	1740	÷ 58	=	$	3,000(Cost	Estimate	at	Completion)
and	6	days	÷ 70%	=	8.57	days	(Schedule	Estimate	at	Completion)to	finish	the	work
2. If	you	want	to	finish	on	budget,	we	need	to	work	at	(Planned	remaining	budget)	÷ (actual	
remaining	budget)	(	1740	– 290	)	÷ (	1740	– 350	)	=	104.3%	of	the	originally	performance	
3. If	we	want	to	finish	on	time,	we	need	to	work	at	(actual	remaining	work)	÷ (planned	
remaining	work)	(600	– 70)	÷ (600	- 100)	=	106%	of	the	originally	planned	performance
Confidential	and	Copyrighted	material	of	JustPMP
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	Inc 17
In	technical	terms…
1. In	real	life,	the	elements	we	calculated	have	slightly	different	names:
2. The	Actual	Cost	is	usually	referred	to	as	Actual	Cost	of	Works	Performed(ACWP)
3. The	Planned	Cost	=	Budgeted	Cost	for	Work	Schedules(BCWS)
4. The	Earned	Value	=	Budgeted	Cost	for	Work	Performed	(BCWP)		
Confidential	and	Copyrighted	material	of	JustPMP
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	Inc 18
Thank	you
Please	contact	us	for	PMP	Exam	Prep	Training,FREE	PMP	Notes,	FREE	Mock	PMP	Online	
test,	FREE	PMP	Application	assistance
Email	Id	:	info@justpmp.com
Website	:	www.justpmp.com
Follow	us	on	Twitter	for	latest	update:	https://twitter.com/just_pmp
Like	us	on	Facebook:	https://facebook.com/justpmp
Click	on	Subscribe	button	on	Our	Youtube	Channel	for	FREE	Videos	of	
PMP
PMI,	PMP,	PMBOK	and	PMI-ACP	are	registered	 marks	of	Project	 Management	Institute,	IncConfidential	 and	Copyrighted	 material	of	JustPMP 19

Contenu connexe

Tendances

Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)Harshit Mahajan
 
Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners Shenin Hassan
 
Chap 5.4 Create WBS
Chap 5.4 Create WBSChap 5.4 Create WBS
Chap 5.4 Create WBSAnand Bobade
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost ManagementAnand Bobade
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 waleed hamdy
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedulesHatem Hegazi
 
Project Time Management - PMBOK 5th Edition
Project  Time Management - PMBOK 5th EditionProject  Time Management - PMBOK 5th Edition
Project Time Management - PMBOK 5th Editionpankajsh10
 
Project cost management PMBOK 5th Edition
Project cost management PMBOK 5th EditionProject cost management PMBOK 5th Edition
Project cost management PMBOK 5th Editionpankajsh10
 
construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
Project life cycle
Project life cycleProject life cycle
Project life cycleMaryam Juma
 
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...Anand Bobade
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1Anand Bobade
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsAcumen
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 
Construction Management (1st Lecture)
Construction Management (1st Lecture) Construction Management (1st Lecture)
Construction Management (1st Lecture) Muhammad Aljalali
 
PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2Anand Bobade
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimationReetesh Gupta
 

Tendances (20)

Earned value analysis (1)
Earned value analysis (1)Earned value analysis (1)
Earned value analysis (1)
 
Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners
 
Chap 5.4 Create WBS
Chap 5.4 Create WBSChap 5.4 Create WBS
Chap 5.4 Create WBS
 
Chap 7.1 Plan Cost Management
Chap 7.1  Plan Cost ManagementChap 7.1  Plan Cost Management
Chap 7.1 Plan Cost Management
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedules
 
Project Management Steps
Project Management StepsProject Management Steps
Project Management Steps
 
Project Time Management - PMBOK 5th Edition
Project  Time Management - PMBOK 5th EditionProject  Time Management - PMBOK 5th Edition
Project Time Management - PMBOK 5th Edition
 
Project cost management PMBOK 5th Edition
Project cost management PMBOK 5th EditionProject cost management PMBOK 5th Edition
Project cost management PMBOK 5th Edition
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
 
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
PMP - Download 49 Processes Chart | PMBOK6 | Links to all Slides | Link to Yo...
 
PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1PMP Chap 6 - Project Time management - Part1
PMP Chap 6 - Project Time management - Part1
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Construction Management (1st Lecture)
Construction Management (1st Lecture) Construction Management (1st Lecture)
Construction Management (1st Lecture)
 
PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2PMP Chap 7 - Project Cost Management - Part 2
PMP Chap 7 - Project Cost Management - Part 2
 
project planning-estimation
project planning-estimationproject planning-estimation
project planning-estimation
 
Project Monitoring and Control
Project Monitoring and ControlProject Monitoring and Control
Project Monitoring and Control
 

En vedette

Earned value management
Earned value managementEarned value management
Earned value managementAshif AR
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic ConceptsRicardo Viana Vargas
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionPlanisware
 
Earned Value Reporting
Earned Value ReportingEarned Value Reporting
Earned Value Reportingcfreema7
 
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation trainingProject Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation trainingJustAcademy
 
Probability Distribution Fitting of Cost Overrun Profiles
Probability Distribution Fitting of Cost Overrun ProfilesProbability Distribution Fitting of Cost Overrun Profiles
Probability Distribution Fitting of Cost Overrun Profilespedlove
 
Evaluating Earned Value Management
Evaluating Earned Value ManagementEvaluating Earned Value Management
Evaluating Earned Value ManagementKristine Hejna
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)Ejaz Bhatti
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementBaroness PM
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value ManagementMansoor Shoaib
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)Glen Alleman
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value ManagementGlen Alleman
 
TBx Consulting Ltd
TBx Consulting LtdTBx Consulting Ltd
TBx Consulting Ltdbontoux
 
RIW-09 Presentations: Vimpelcom
RIW-09 Presentations: VimpelcomRIW-09 Presentations: Vimpelcom
RIW-09 Presentations: VimpelcomAlyona Podboronova
 

En vedette (20)

Earned value management
Earned value managementEarned value management
Earned value management
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic Concepts
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Earned Value Reporting
Earned Value ReportingEarned Value Reporting
Earned Value Reporting
 
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation trainingProject Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
Project Scope Management,PMP Chapter 5,PMBOK,PMP Exam Preparation training
 
Probability Distribution Fitting of Cost Overrun Profiles
Probability Distribution Fitting of Cost Overrun ProfilesProbability Distribution Fitting of Cost Overrun Profiles
Probability Distribution Fitting of Cost Overrun Profiles
 
Evaluating Earned Value Management
Evaluating Earned Value ManagementEvaluating Earned Value Management
Evaluating Earned Value Management
 
Earned Value fundamentals
Earned Value fundamentalsEarned Value fundamentals
Earned Value fundamentals
 
Earned value Project Management (evpm)
Earned value Project Management (evpm)Earned value Project Management (evpm)
Earned value Project Management (evpm)
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)A gentle introduction to earned value management systems (neutral)
A gentle introduction to earned value management systems (neutral)
 
Earning Value from Earned Value Management
Earning Value from Earned Value ManagementEarning Value from Earned Value Management
Earning Value from Earned Value Management
 
Lost in transition
Lost in transitionLost in transition
Lost in transition
 
Tfs 2008 Overview
Tfs 2008 OverviewTfs 2008 Overview
Tfs 2008 Overview
 
TBx Consulting Ltd
TBx Consulting LtdTBx Consulting Ltd
TBx Consulting Ltd
 
RIW-09 Presentations: Vimpelcom
RIW-09 Presentations: VimpelcomRIW-09 Presentations: Vimpelcom
RIW-09 Presentations: Vimpelcom
 

Similaire à Earned value management with Examples | Control Cost | PMBOK | PMP

Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Glen Alleman
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project managementselinasimpson1601
 
iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...IRJET Journal
 
Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018Roger H. Mandel
 
Using Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project PerformanceUsing Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project PerformanceLewisFowlerLLC
 
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaOnline PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaGlobalSkillup
 
Chap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdfChap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdfVarunSubramanyam
 
Sharath's Resume-Project Manager-V5 30th May'15
Sharath's Resume-Project Manager-V5 30th May'15Sharath's Resume-Project Manager-V5 30th May'15
Sharath's Resume-Project Manager-V5 30th May'15Sharath Sri Karan
 
2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.pptAlfredoArturoGranado
 
L4_Cost Management.ppt
L4_Cost Management.pptL4_Cost Management.ppt
L4_Cost Management.pptMUST
 
CostManagementSlides.pdf
CostManagementSlides.pdfCostManagementSlides.pdf
CostManagementSlides.pdfAmrishTyagi8
 
Notional cam interview questions (update)
Notional cam interview questions (update)Notional cam interview questions (update)
Notional cam interview questions (update)Glen Alleman
 
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...JustAcademy
 
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...JustAcademy
 
Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Glen Alleman
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagementDhamo daran
 
Managing service projects in a B2B environment
Managing service projects in a B2B environmentManaging service projects in a B2B environment
Managing service projects in a B2B environmentGideon Cohen
 

Similaire à Earned value management with Examples | Control Cost | PMBOK | PMP (20)

Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)Chapter 0 of Performance Based Project Management (sm)
Chapter 0 of Performance Based Project Management (sm)
 
Webinar on PMS
Webinar on PMSWebinar on PMS
Webinar on PMS
 
Quality metrics in project management
Quality metrics in project managementQuality metrics in project management
Quality metrics in project management
 
iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...iEVM (Integrated Earned Value Management) An approach for integrating quality...
iEVM (Integrated Earned Value Management) An approach for integrating quality...
 
Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018Evm intro. slide deck 13 may 2018
Evm intro. slide deck 13 may 2018
 
Using Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project PerformanceUsing Earned Value Management Concepts to Improve Commercial Project Performance
Using Earned Value Management Concepts to Improve Commercial Project Performance
 
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaOnline PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
 
Chap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdfChap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdf
 
Project Quality Management
Project Quality ManagementProject Quality Management
Project Quality Management
 
Sharath's Resume-Project Manager-V5 30th May'15
Sharath's Resume-Project Manager-V5 30th May'15Sharath's Resume-Project Manager-V5 30th May'15
Sharath's Resume-Project Manager-V5 30th May'15
 
2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt2.11 Milestone Review - Phase 1.ppt
2.11 Milestone Review - Phase 1.ppt
 
L4_Cost Management.ppt
L4_Cost Management.pptL4_Cost Management.ppt
L4_Cost Management.ppt
 
CostManagementSlides.pdf
CostManagementSlides.pdfCostManagementSlides.pdf
CostManagementSlides.pdf
 
7.4 Control Costs
7.4 Control Costs7.4 Control Costs
7.4 Control Costs
 
Notional cam interview questions (update)
Notional cam interview questions (update)Notional cam interview questions (update)
Notional cam interview questions (update)
 
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
PMP NOTES Based on PMBOK Guide 5th Edition and updated PMP syllabus after 11 ...
 
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...
Free PMP Notes based on PMBOK guide and covers latest PMP changes after 11 Ja...
 
Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
Managing service projects in a B2B environment
Managing service projects in a B2B environmentManaging service projects in a B2B environment
Managing service projects in a B2B environment
 

Dernier

ClimART Action | eTwinning Project
ClimART Action    |    eTwinning ProjectClimART Action    |    eTwinning Project
ClimART Action | eTwinning Projectjordimapav
 
Grade Three -ELLNA-REVIEWER-ENGLISH.pptx
Grade Three -ELLNA-REVIEWER-ENGLISH.pptxGrade Three -ELLNA-REVIEWER-ENGLISH.pptx
Grade Three -ELLNA-REVIEWER-ENGLISH.pptxkarenfajardo43
 
CLASSIFICATION OF ANTI - CANCER DRUGS.pptx
CLASSIFICATION OF ANTI - CANCER DRUGS.pptxCLASSIFICATION OF ANTI - CANCER DRUGS.pptx
CLASSIFICATION OF ANTI - CANCER DRUGS.pptxAnupam32727
 
How to Make a Duplicate of Your Odoo 17 Database
How to Make a Duplicate of Your Odoo 17 DatabaseHow to Make a Duplicate of Your Odoo 17 Database
How to Make a Duplicate of Your Odoo 17 DatabaseCeline George
 
4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptx4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptxmary850239
 
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...DhatriParmar
 
Indexing Structures in Database Management system.pdf
Indexing Structures in Database Management system.pdfIndexing Structures in Database Management system.pdf
Indexing Structures in Database Management system.pdfChristalin Nelson
 
Oppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmOppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmStan Meyer
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfPatidar M
 
How to Fix XML SyntaxError in Odoo the 17
How to Fix XML SyntaxError in Odoo the 17How to Fix XML SyntaxError in Odoo the 17
How to Fix XML SyntaxError in Odoo the 17Celine George
 
Q-Factor General Quiz-7th April 2024, Quiz Club NITW
Q-Factor General Quiz-7th April 2024, Quiz Club NITWQ-Factor General Quiz-7th April 2024, Quiz Club NITW
Q-Factor General Quiz-7th April 2024, Quiz Club NITWQuiz Club NITW
 
Unraveling Hypertext_ Analyzing Postmodern Elements in Literature.pptx
Unraveling Hypertext_ Analyzing  Postmodern Elements in  Literature.pptxUnraveling Hypertext_ Analyzing  Postmodern Elements in  Literature.pptx
Unraveling Hypertext_ Analyzing Postmodern Elements in Literature.pptxDhatriParmar
 
How to Manage Buy 3 Get 1 Free in Odoo 17
How to Manage Buy 3 Get 1 Free in Odoo 17How to Manage Buy 3 Get 1 Free in Odoo 17
How to Manage Buy 3 Get 1 Free in Odoo 17Celine George
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4JOYLYNSAMANIEGO
 
Congestive Cardiac Failure..presentation
Congestive Cardiac Failure..presentationCongestive Cardiac Failure..presentation
Congestive Cardiac Failure..presentationdeepaannamalai16
 
Tree View Decoration Attribute in the Odoo 17
Tree View Decoration Attribute in the Odoo 17Tree View Decoration Attribute in the Odoo 17
Tree View Decoration Attribute in the Odoo 17Celine George
 
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptxDecoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptxDhatriParmar
 
4.11.24 Poverty and Inequality in America.pptx
4.11.24 Poverty and Inequality in America.pptx4.11.24 Poverty and Inequality in America.pptx
4.11.24 Poverty and Inequality in America.pptxmary850239
 

Dernier (20)

ClimART Action | eTwinning Project
ClimART Action    |    eTwinning ProjectClimART Action    |    eTwinning Project
ClimART Action | eTwinning Project
 
Grade Three -ELLNA-REVIEWER-ENGLISH.pptx
Grade Three -ELLNA-REVIEWER-ENGLISH.pptxGrade Three -ELLNA-REVIEWER-ENGLISH.pptx
Grade Three -ELLNA-REVIEWER-ENGLISH.pptx
 
CLASSIFICATION OF ANTI - CANCER DRUGS.pptx
CLASSIFICATION OF ANTI - CANCER DRUGS.pptxCLASSIFICATION OF ANTI - CANCER DRUGS.pptx
CLASSIFICATION OF ANTI - CANCER DRUGS.pptx
 
Mattingly "AI & Prompt Design: Large Language Models"
Mattingly "AI & Prompt Design: Large Language Models"Mattingly "AI & Prompt Design: Large Language Models"
Mattingly "AI & Prompt Design: Large Language Models"
 
How to Make a Duplicate of Your Odoo 17 Database
How to Make a Duplicate of Your Odoo 17 DatabaseHow to Make a Duplicate of Your Odoo 17 Database
How to Make a Duplicate of Your Odoo 17 Database
 
4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptx4.11.24 Mass Incarceration and the New Jim Crow.pptx
4.11.24 Mass Incarceration and the New Jim Crow.pptx
 
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
 
Indexing Structures in Database Management system.pdf
Indexing Structures in Database Management system.pdfIndexing Structures in Database Management system.pdf
Indexing Structures in Database Management system.pdf
 
Oppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmOppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and Film
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdf
 
How to Fix XML SyntaxError in Odoo the 17
How to Fix XML SyntaxError in Odoo the 17How to Fix XML SyntaxError in Odoo the 17
How to Fix XML SyntaxError in Odoo the 17
 
Q-Factor General Quiz-7th April 2024, Quiz Club NITW
Q-Factor General Quiz-7th April 2024, Quiz Club NITWQ-Factor General Quiz-7th April 2024, Quiz Club NITW
Q-Factor General Quiz-7th April 2024, Quiz Club NITW
 
Unraveling Hypertext_ Analyzing Postmodern Elements in Literature.pptx
Unraveling Hypertext_ Analyzing  Postmodern Elements in  Literature.pptxUnraveling Hypertext_ Analyzing  Postmodern Elements in  Literature.pptx
Unraveling Hypertext_ Analyzing Postmodern Elements in Literature.pptx
 
How to Manage Buy 3 Get 1 Free in Odoo 17
How to Manage Buy 3 Get 1 Free in Odoo 17How to Manage Buy 3 Get 1 Free in Odoo 17
How to Manage Buy 3 Get 1 Free in Odoo 17
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4
 
Congestive Cardiac Failure..presentation
Congestive Cardiac Failure..presentationCongestive Cardiac Failure..presentation
Congestive Cardiac Failure..presentation
 
Faculty Profile prashantha K EEE dept Sri Sairam college of Engineering
Faculty Profile prashantha K EEE dept Sri Sairam college of EngineeringFaculty Profile prashantha K EEE dept Sri Sairam college of Engineering
Faculty Profile prashantha K EEE dept Sri Sairam college of Engineering
 
Tree View Decoration Attribute in the Odoo 17
Tree View Decoration Attribute in the Odoo 17Tree View Decoration Attribute in the Odoo 17
Tree View Decoration Attribute in the Odoo 17
 
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptxDecoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
Decoding the Tweet _ Practical Criticism in the Age of Hashtag.pptx
 
4.11.24 Poverty and Inequality in America.pptx
4.11.24 Poverty and Inequality in America.pptx4.11.24 Poverty and Inequality in America.pptx
4.11.24 Poverty and Inequality in America.pptx
 

Earned value management with Examples | Control Cost | PMBOK | PMP