Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Construction Update 09-15-2010
1. From: Brandon Valdez To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Office: Kansas City Lee Turner – OnGoal
Date: 9.15.2010 Andy Heitmann – Turner
Dave Dudzik - Turner
Re: Wizards Stadium Project
Update – Week of
9.13.2010
Current Activities this Week:
Underground Utilities:
Area 3 - Deep underground Plumbing continues.
Foundations:
Area 2 Concourse Level – Excavation for remaining D-Line
footing has started.
Area 3 – Underground plumbing installation
Concrete Flatwork: is nearly complete at the lower dock area.
Area 4 Field Level – Prep work for lower dock slab on
grade has started.
Structural Steel Erection:
Area 3 – Main Canopy Truss Erection are set to Column
Line 1. Area 4 – Metal decking installation in Sequence
3-3 has started. Field Level Area 1 – Subroof decking
installation is ongoing
MEP Rough-in:
Area 3 – Shallow electrical and plumbing rough-in is Area 2 – CMU perimeter wall installation at
ongoing. West Building - Ductwork installation on Stage are nearly topped out.
Concourse, Suite and Press Levels are ongoing.
Plumbing rough-in is ongoing on Suite and
Press Levels. Fire Protection rough-in is ongoing on
Concourse, Suite and Press Levels. Electrical rough-in is
ongoing on Concourse, Suite and Press Levels.
Metal Stud Framing:
Area 1 – Metal stud framing for Field, Concourse, Suite
and Press Levels are ongoing. Exterior metal stud framing
and sheathing installation is ongoing at Field, Suite, and
Area 4 – Decking being installed at North
Elevation.
Building the Future
2. Press Levels.
Masonry:
Area 1 Field Level – Masonry wall installation is ongoing
in Areas E, F, G and H.
Area 1, 2, 3 Concourse Level – Masonry wall installation at
Main Concourse Buildings are ongoing.
Area 3 – Canopy Truss erection is nearly
Curtainwall:
complete in Sequence 3-5.
Area 1 – Curtainwall framing installation will continue
at West Elevation. Installation of Curtainwall glass is
ongoing.
Projected Activities occurring next Week:
Underground Utilities:
Deep Plumbing installation will continue in Area 3, moving
to the north.
Foundations:
Area 4 Field Level – Foundation wall installation for Main
Stair will begin. Field Level Area 3 – Formwork for Stairs to
Cauldron Club is set.
Concrete Flatwork:
Area 3 Field Level – Concrete placement for Slab-on
Grade at lower dock area will begin. Prep work for slab-
on-grade for lower dock area will continue.
Area 3 and 4 Field Level – Installation of on-grade seating
risers and intermediate stairs will continue.
Structural Steel Erection:
Area 2 – Canopy truss installation at North side of Stadium
will continue. Area 1/2 – Filled and polished CMU Block
walls at the Southwest and South Concourse
MEP Rough-in: Buildings.
MEP Rough-in at Concourse, Suite and Press Levels will
continue. Ductwork installation on Concourse, Suite, and
Press Level will continue. Fire Sprinkler installation will
continue on Concourse, Suite and Press Levels.
Building the Future
3. Metal Stud Framing:
Area 1 – Metal stud framing for Field, Concourse, Suite
and Press Levels will continue. Exterior Framing and
sheathing installation will continue.
Curtainwall:
Area 1 – Curtain Framing and Glass installation will
continue.
Area 1 – Installation of curtainwall framing
at Stair 4.
Area 1 – Shot of the west building showing
the progress of the canopy decking on
trusses.
Building the Future
4. Additional Photos:
Concourse Level Area 3 – Exterior CMU walls
started northeast Concession and Men’s Field Level Area 3 – Upper Dock concrete is
Restroom Buildings. placed.
Bowl – Shot of the bowl from the roof of the
Field Level Area 1 – Subroof decking Stadium Suite, showing the elevation
installation is ongoing. change of the canopy trusses.
Area 3 – 300 Ton Crane lifting Column Line 1 Suite Level Area 1 – Metal stud framing and
Truss into place. in wall MEP rough-in is ongoing.
Building the Future