From:    Brandon Valdez                    To: David Ficklin - OnGoal
                                                                             Rory O’Connor – OnGoal
                              Office: Kansas City                            Lee Turner – OnGoal
                              Date:    10.20.2010                            Andy Heitmann – Turner
                                                                             Dave Dudzik - Turner
                              Re:      Wizards Stadium Project
                                       Update – Week of
                                       10.18.2010



 Current Activities this Week:

 Foundations:
 Area 4 Field Level – Backfill of foundations for “infill”
 area between Column Lines 39-1 is complete.

 Concrete Flatwork:
 Area 3 Field Level – Concrete for base slab at Cauldron
 Club is complete.                                               Field Level Area 3 – Cauldron Club base slab
                                                                 has been placed.
 Masonry:
 Area 3 – Masonry pilaster installation at Truck Dock is
 ongoing. Area 1, 2, 3 – Masonry installation is ongoing
 at Concession Buildings.

 Steel:
 Area 1, 2, 3 – Canopy decking installation is ongoing.
 Area 2 – Concession Building steel truss and decking
 installation is nearly complete. Area 1 – Elevator
 support steel installation is ongoing for F1.
                                                                 Area 1 – Masonry and Densglas installation
                                                                 at Northwest corner of West Building.
 Roofing and Sheetmetal:
 Area 1, 3 – Canopy gutter installation is complete.
 Area 1 – Subgirt installation for metal panels is ongoing
 at West Building.

 Metal Stud Framing:
 Area 1 – Metal stud framing for Field, Concourse, Suite
 and Press Levels are ongoing. Drywall installation is
 is ongoing at Field and Mezzanine Levels

                                                                 Field Level Area 3 – Masonry pilaster
                                                                 installation at East Elevation (Truck Dock).

Building the Future
Glass:
 Area 1 - Curtainwall framing and glass installation is
 ongoing at West Building on west, south and east
 elevations. South “wing” framing is complete.

 MEP Rough-in:
 Area 4 – Underground MEP rough-in is ongoing.
 West Building - Ductwork installation on
 Concourse, Suite and Press Levels are ongoing.               Field Level Area 4 – Structural steel at infill
 Plumbing rough-in is ongoing on Suite and                    area is set and foundations are backfilled.
 Press Levels. Fire Protection rough-in is ongoing on
 Concourse, Suite and Press Levels. Electrical rough-in is
 ongoing on Concourse, Suite and Press Levels.


 Projected Activities occurring next Week:

 Concrete Flatwork:
 Area 3 Field Level – Prep for Slab-on-Grade at Stair 1
 will continue. Area 4 Field Level – Installation of on-grade
 seating risers and intermediate stairs will continue.
 Area 1 Concourse Level – Placement of topping slabs inside
 Concession Buildings will begin.                             Concourse Level Area 1 – Soffit construction
                                                              on SW Concourse Concession Buildings.
 Masonry:
 Area 3 – Field level masonry installation will continue in
 Area C and D. Area 1, 2, 3 – Concourse building
 masonry installation will continue.

 Steel:
 Field Level Area 3 – Misc steel installation that supports
 Burnished CMU will begin. Field Level Area 2 - Subroof
 installation will continue.

 Roofing and Sheetmetal:
 Area 1 – Permanent roofing installation at West
 Building will continue. Area 1 – Subgirt installation at     Mezzanine Level Area 4 – Slab prep is
 West Building will continue.                                 ongoing for Mezzanine walkway.

 Metal Stud Framing:
 Area 1 – Metal stud framing on Field Level will continue.
 Area 1 - Drywall installation will continue at Field Level


Building the Future
and Mezzanine Level. Drywall installation will begin on
 Suite Level.

 Glass:
 Area 1 – Curtain Framing and Glass installation around West
 Building will continue. Curtainwall framing on Suite and
 Press Level balconies will continue. Solar Innovations
 recessed track will deliver.
                                                               Area 1 – Shot of the Field Side of the West
 MEP Rough-in:                                                 Building looking Northwest.
 MEP Rough-in at Concourse, Suite and Press Levels will
 continue. Ductwork installation on Concourse, Suite, and
 Press Level will continue. Fire Sprinkler installation will
 continue on Concourse, Suite and Press Levels. MEP
 rough-in will continue in Main Concourse Buildings.




                                                               Area 1 – Shot of the west building showing
                                                               the progress of the exterior envelope.




Building the Future
Additional Photos:




Field Level Area 2– Swithgear is set in        Concourse Level Area 2 – Plumbing carriers
Electrical Service Room 01.20.01.              set in Restrooms 03.19.01.




Field Level Area 3 – Emergency Generator is    Concourse Level Area 1 – Stair 4 installation
set.                                           is ongoing.




Concourse Level Area 4 – Installation of
metal decking is nearly complete at “infill”   Field Level Area 1 – Metal stud framing is
area.                                          ongoing in Wizards Locker room.




Building the Future

Contenu connexe

Memo wizards 10-20-2010

  • 1. From: Brandon Valdez To: David Ficklin - OnGoal Rory O’Connor – OnGoal Office: Kansas City Lee Turner – OnGoal Date: 10.20.2010 Andy Heitmann – Turner Dave Dudzik - Turner Re: Wizards Stadium Project Update – Week of 10.18.2010 Current Activities this Week: Foundations: Area 4 Field Level – Backfill of foundations for “infill” area between Column Lines 39-1 is complete. Concrete Flatwork: Area 3 Field Level – Concrete for base slab at Cauldron Club is complete. Field Level Area 3 – Cauldron Club base slab has been placed. Masonry: Area 3 – Masonry pilaster installation at Truck Dock is ongoing. Area 1, 2, 3 – Masonry installation is ongoing at Concession Buildings. Steel: Area 1, 2, 3 – Canopy decking installation is ongoing. Area 2 – Concession Building steel truss and decking installation is nearly complete. Area 1 – Elevator support steel installation is ongoing for F1. Area 1 – Masonry and Densglas installation at Northwest corner of West Building. Roofing and Sheetmetal: Area 1, 3 – Canopy gutter installation is complete. Area 1 – Subgirt installation for metal panels is ongoing at West Building. Metal Stud Framing: Area 1 – Metal stud framing for Field, Concourse, Suite and Press Levels are ongoing. Drywall installation is is ongoing at Field and Mezzanine Levels Field Level Area 3 – Masonry pilaster installation at East Elevation (Truck Dock). Building the Future
  • 2. Glass: Area 1 - Curtainwall framing and glass installation is ongoing at West Building on west, south and east elevations. South “wing” framing is complete. MEP Rough-in: Area 4 – Underground MEP rough-in is ongoing. West Building - Ductwork installation on Concourse, Suite and Press Levels are ongoing. Field Level Area 4 – Structural steel at infill Plumbing rough-in is ongoing on Suite and area is set and foundations are backfilled. Press Levels. Fire Protection rough-in is ongoing on Concourse, Suite and Press Levels. Electrical rough-in is ongoing on Concourse, Suite and Press Levels. Projected Activities occurring next Week: Concrete Flatwork: Area 3 Field Level – Prep for Slab-on-Grade at Stair 1 will continue. Area 4 Field Level – Installation of on-grade seating risers and intermediate stairs will continue. Area 1 Concourse Level – Placement of topping slabs inside Concession Buildings will begin. Concourse Level Area 1 – Soffit construction on SW Concourse Concession Buildings. Masonry: Area 3 – Field level masonry installation will continue in Area C and D. Area 1, 2, 3 – Concourse building masonry installation will continue. Steel: Field Level Area 3 – Misc steel installation that supports Burnished CMU will begin. Field Level Area 2 - Subroof installation will continue. Roofing and Sheetmetal: Area 1 – Permanent roofing installation at West Building will continue. Area 1 – Subgirt installation at Mezzanine Level Area 4 – Slab prep is West Building will continue. ongoing for Mezzanine walkway. Metal Stud Framing: Area 1 – Metal stud framing on Field Level will continue. Area 1 - Drywall installation will continue at Field Level Building the Future
  • 3. and Mezzanine Level. Drywall installation will begin on Suite Level. Glass: Area 1 – Curtain Framing and Glass installation around West Building will continue. Curtainwall framing on Suite and Press Level balconies will continue. Solar Innovations recessed track will deliver. Area 1 – Shot of the Field Side of the West MEP Rough-in: Building looking Northwest. MEP Rough-in at Concourse, Suite and Press Levels will continue. Ductwork installation on Concourse, Suite, and Press Level will continue. Fire Sprinkler installation will continue on Concourse, Suite and Press Levels. MEP rough-in will continue in Main Concourse Buildings. Area 1 – Shot of the west building showing the progress of the exterior envelope. Building the Future
  • 4. Additional Photos: Field Level Area 2– Swithgear is set in Concourse Level Area 2 – Plumbing carriers Electrical Service Room 01.20.01. set in Restrooms 03.19.01. Field Level Area 3 – Emergency Generator is Concourse Level Area 1 – Stair 4 installation set. is ongoing. Concourse Level Area 4 – Installation of metal decking is nearly complete at “infill” Field Level Area 1 – Metal stud framing is area. ongoing in Wizards Locker room. Building the Future