Objective of this presentation: 
– 
The purpose of this presentation is to provide a 10 minute storyboard type walkthrough of how to assess a group of risks on a project, for the purpose of decision making 
– 
which is easy to follow and understand  
• 
What it is not designed to do 
• 
It is not designed to give you guidance on: 
– 
Risk identification 
• 
Or 
– 
The management of risk 
• 
Those are dealt with in separate presentations 
Project Risk Assessment: Worked Example 
pmis-consulting.com
© PMIS Consulting Limited: all rights reserved 
• 
This presentation assumes you and your team have identified a series of risks, and now you need to assess them, and use this process and the information it produces to help you make decisions, such as: 
– 
Which risks require action 
– 
How to use Assessment to help prioritise actions 
Project Risk Assessment: Worked Example 
pmis-consulting.com 
H 
M 
L 
Probability 
20% 
40% 
Impact 
H 
M 
L 
1 
9 
4 
3 level schema: (Low = 1, Med = 2, High = 3) also 5 level schema.
© PMIS Consulting Limited: all rights reserved 
• 
It examines and assesses both the probability of occurrence of each risk, together with the impact of each risk if it occurs. 
• 
Using common values (e.g. H/M/L) (or thresholds) can provide each risk a score, allowing a comparative analysis of risks across a whole project. 
Project Risk Assessment: Worked Example 
pmis-consulting.com 
H 
M 
L 
Probability 
20% 
40% 
Impact 
H 
M 
L 
1 
9 
4 
3 level schema: (Low = 1, Med = 2, High = 3) also 5 level schema.
© PMIS Consulting Limited: all rights reserved 
• 
Before we can assess the risks we must: 
– 
Decide if we are going to assess just overall impact or assess impact on cost, schedule and performance (of our end product, aka Technical) separately 
– 
If we are doing the latter, we must define values for L/M/H for each of these, e.g. for schedule 
• 
E.g. L=<1 week, M=< 1 month, and H=>1 month 
– 
Then we do the same for cost etc. 
Project Risk Assessment: Worked Example 
pmis-consulting.com 
H 
M 
L 
Probability 
20% 
40% 
Impact 
H 
M 
L 
1 
9 
4 
So, what do we have to do? 
3 level schema: 
(Low = 1, Med = 2, High = 3) 
also 5 level schema.
© PMIS Consulting Limited: all rights reserved 
• 
N.B: Impact Values 
– 
Despite it seeming logical, percentages do not work for cost impact – actual ‘threshold’ values must be agreed per project, sometimes even with the key stakeholders 
– 
For probabilities, people often start out with percentages way to high for probability, e.g. high > 80% - this is far too high - a probability of greater than 1 in 2 (50%) chance of occurring is a high risk item 
Project Risk Assessment: Worked Example 
pmis-consulting.com 
H 
M 
L 
Probability 
20% 
40% 
Impact 
H 
M 
L 
1 
9 
4 
Tips on Impact Values / Ranges 
3 level schema: (Low = 1, Med = 2, High = 3) also 5 level schema.
© PMIS Consulting Limited: all rights reserved 
Example Thresholds: 
pmis-consulting.com 
Impact 
1 
2 
3 
4 
5 
Very Low 
Low 
Moderate 
High 
Very High 
Objective 
Time 
Thresholds 
Less than 1 week 
Up to 2 weeks 
Up to 4 weeks 
5-10 weeks 
11 weeks and above 
Cost 
Thresholds 
$ up to 100K (in 000s) 
$ up to 200K 
(in 000s) 
$ up to 500K 
(in 000s) 
$ up to 1M 
$ >1M 
Quality 
No safety issues, C, O, M deficiencies approved by project team 
No safety issues, C, O, M deficiencies require District management approval 
Quality may be made acceptable through mitigation or agreement (i.e. Fact Sheet) 
Quality does not meet one or all of the following Safety, C, O, & M 
Probability of occurrence 
1-9 % 
10-19% 
20-39% 
40-59% 
60-99%
© PMIS Consulting Limited: all rights reserved 
• 
Risk Score 
– 
When we go through the assessment of individual risks and allocate them a value for probability and impact, we can translate this at the same time into a risk score, e.g.: 
• 
Low = 1 
• 
Med = 2 
• 
High = 3 
– 
Therefore: 
• 
H/H = 3 * 3 =9 
• 
H/L = 3 * 1 = 3, etc. 
– 
If we use C/S & T impact values, we multiply their average by the probability 
Project Risk Assessment: Worked Example 
pmis-consulting.com 
H 
M 
L 
Probability 
20% 
40% 
Impact 
H 
M 
L 
1 
9 
4 
Producing the risk ‘score’ 
3 level schema: (Low = 1, Med = 2, High = 3) also 5 level schema.
© PMIS Consulting Limited: all rights reserved 
• 
Risk Score 
– 
The risk score is useful, but must never be used on its own as an absolute driver of the need for actions etc. following assessment – in other words it is simply wrong to write a process that says ‘accept’ all risks with a risk score less than ….. this is taking process driven management far to far and will result in important risks being ignored 
Project Risk Assessment: Worked Example 
pmis-consulting.com 
H 
M 
L 
Probability 
20% 
40% 
Impact 
H 
M 
L 
1 
9 
4 
How not to use the risk ‘score’ 
3 level schema: 
(Low = 1, Med = 2, High = 3) 
also 5 level schema.
© PMIS Consulting Limited: all rights reserved 
• 
Risk Score 
– 
Developing the risk score itself should be a team task – no one person can do this. 
– 
Developing the score allows the team to better understand risk, which is a challenging task in itself 
– 
This then allows much better informed, structured and successful decision making and actions to follow this phase of the overall project risk management process 
Project Risk Assessment: Worked Example 
pmis-consulting.com 
H 
M 
L 
Probability 
20% 
40% 
Impact 
H 
M 
L 
1 
9 
4 
How to use the risk ‘score’ 
3 level schema: 
(Low = 1, Med = 2, High = 3) 
also 5 level schema.
© PMIS Consulting Limited: all rights reserved 
• 
Please feel free to share this presentation or embed this presentation in your website and respect our Copyright at all times. 
• 
Thank you ! 
• 
Please click on the link below for more information or training on this topic. 
Thank you 
http://pmis-consulting.com/articles/project-risk-management/ 
H 
M 
L 
Probability 
20% 
40% 
Impact 
H 
M 
L 
1 
9 
4 
3 level schema: (Low = 1, Med = 2, High = 3) also 5 level schema.

More Related Content

Recently uploaded

Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
alinstan901
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Riyadh +966572737505 get cytotec
 

Recently uploaded (20)

Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
situational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Ssituational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima S
 
Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 99 Noida Escorts >༒8448380779 Escort Service
 
Discover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdfDiscover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdf
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdfImagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
 
Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024
 
LoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner CircleLoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner Circle
 
Continuous Improvement Posters for Learning
Continuous Improvement Posters for LearningContinuous Improvement Posters for Learning
Continuous Improvement Posters for Learning
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdfImagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 
Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 

Featured

Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
Kurio // The Social Media Age(ncy)
 

Featured (20)

PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024PEPSICO Presentation to CAGNY Conference Feb 2024
PEPSICO Presentation to CAGNY Conference Feb 2024
 
Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)Content Methodology: A Best Practices Report (Webinar)
Content Methodology: A Best Practices Report (Webinar)
 
How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024How to Prepare For a Successful Job Search for 2024
How to Prepare For a Successful Job Search for 2024
 
Social Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie InsightsSocial Media Marketing Trends 2024 // The Global Indie Insights
Social Media Marketing Trends 2024 // The Global Indie Insights
 
Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024Trends In Paid Search: Navigating The Digital Landscape In 2024
Trends In Paid Search: Navigating The Digital Landscape In 2024
 
5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary5 Public speaking tips from TED - Visualized summary
5 Public speaking tips from TED - Visualized summary
 
ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd ChatGPT and the Future of Work - Clark Boyd
ChatGPT and the Future of Work - Clark Boyd
 
Getting into the tech field. what next
Getting into the tech field. what next Getting into the tech field. what next
Getting into the tech field. what next
 
Google's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search IntentGoogle's Just Not That Into You: Understanding Core Updates & Search Intent
Google's Just Not That Into You: Understanding Core Updates & Search Intent
 
How to have difficult conversations
How to have difficult conversations How to have difficult conversations
How to have difficult conversations
 
Introduction to Data Science
Introduction to Data ScienceIntroduction to Data Science
Introduction to Data Science
 
Time Management & Productivity - Best Practices
Time Management & Productivity -  Best PracticesTime Management & Productivity -  Best Practices
Time Management & Productivity - Best Practices
 
The six step guide to practical project management
The six step guide to practical project managementThe six step guide to practical project management
The six step guide to practical project management
 
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
Beginners Guide to TikTok for Search - Rachel Pearson - We are Tilt __ Bright...
 
Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...
Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...
Unlocking the Power of ChatGPT and AI in Testing - A Real-World Look, present...
 
12 Ways to Increase Your Influence at Work
12 Ways to Increase Your Influence at Work12 Ways to Increase Your Influence at Work
12 Ways to Increase Your Influence at Work
 
ChatGPT webinar slides
ChatGPT webinar slidesChatGPT webinar slides
ChatGPT webinar slides
 
More than Just Lines on a Map: Best Practices for U.S Bike Routes
More than Just Lines on a Map: Best Practices for U.S Bike RoutesMore than Just Lines on a Map: Best Practices for U.S Bike Routes
More than Just Lines on a Map: Best Practices for U.S Bike Routes
 
Ride the Storm: Navigating Through Unstable Periods / Katerina Rudko (Belka G...
Ride the Storm: Navigating Through Unstable Periods / Katerina Rudko (Belka G...Ride the Storm: Navigating Through Unstable Periods / Katerina Rudko (Belka G...
Ride the Storm: Navigating Through Unstable Periods / Katerina Rudko (Belka G...
 
Barbie - Brand Strategy Presentation
Barbie - Brand Strategy PresentationBarbie - Brand Strategy Presentation
Barbie - Brand Strategy Presentation
 

Project Risk Assessment Worked Example

  • 1. © PMIS Consulting Limited: all rights reserved • Objective of this presentation: – The purpose of this presentation is to provide a 10 minute storyboard type walkthrough of how to assess a group of risks on a project, for the purpose of decision making – which is easy to follow and understand  • What it is not designed to do • It is not designed to give you guidance on: – Risk identification • Or – The management of risk • Those are dealt with in separate presentations Project Risk Assessment: Worked Example pmis-consulting.com
  • 2. © PMIS Consulting Limited: all rights reserved • This presentation assumes you and your team have identified a series of risks, and now you need to assess them, and use this process and the information it produces to help you make decisions, such as: – Which risks require action – How to use Assessment to help prioritise actions Project Risk Assessment: Worked Example pmis-consulting.com H M L Probability 20% 40% Impact H M L 1 9 4 3 level schema: (Low = 1, Med = 2, High = 3) also 5 level schema.
  • 3. © PMIS Consulting Limited: all rights reserved • It examines and assesses both the probability of occurrence of each risk, together with the impact of each risk if it occurs. • Using common values (e.g. H/M/L) (or thresholds) can provide each risk a score, allowing a comparative analysis of risks across a whole project. Project Risk Assessment: Worked Example pmis-consulting.com H M L Probability 20% 40% Impact H M L 1 9 4 3 level schema: (Low = 1, Med = 2, High = 3) also 5 level schema.
  • 4. © PMIS Consulting Limited: all rights reserved • Before we can assess the risks we must: – Decide if we are going to assess just overall impact or assess impact on cost, schedule and performance (of our end product, aka Technical) separately – If we are doing the latter, we must define values for L/M/H for each of these, e.g. for schedule • E.g. L=<1 week, M=< 1 month, and H=>1 month – Then we do the same for cost etc. Project Risk Assessment: Worked Example pmis-consulting.com H M L Probability 20% 40% Impact H M L 1 9 4 So, what do we have to do? 3 level schema: (Low = 1, Med = 2, High = 3) also 5 level schema.
  • 5. © PMIS Consulting Limited: all rights reserved • N.B: Impact Values – Despite it seeming logical, percentages do not work for cost impact – actual ‘threshold’ values must be agreed per project, sometimes even with the key stakeholders – For probabilities, people often start out with percentages way to high for probability, e.g. high > 80% - this is far too high - a probability of greater than 1 in 2 (50%) chance of occurring is a high risk item Project Risk Assessment: Worked Example pmis-consulting.com H M L Probability 20% 40% Impact H M L 1 9 4 Tips on Impact Values / Ranges 3 level schema: (Low = 1, Med = 2, High = 3) also 5 level schema.
  • 6. © PMIS Consulting Limited: all rights reserved Example Thresholds: pmis-consulting.com Impact 1 2 3 4 5 Very Low Low Moderate High Very High Objective Time Thresholds Less than 1 week Up to 2 weeks Up to 4 weeks 5-10 weeks 11 weeks and above Cost Thresholds $ up to 100K (in 000s) $ up to 200K (in 000s) $ up to 500K (in 000s) $ up to 1M $ >1M Quality No safety issues, C, O, M deficiencies approved by project team No safety issues, C, O, M deficiencies require District management approval Quality may be made acceptable through mitigation or agreement (i.e. Fact Sheet) Quality does not meet one or all of the following Safety, C, O, & M Probability of occurrence 1-9 % 10-19% 20-39% 40-59% 60-99%
  • 7. © PMIS Consulting Limited: all rights reserved • Risk Score – When we go through the assessment of individual risks and allocate them a value for probability and impact, we can translate this at the same time into a risk score, e.g.: • Low = 1 • Med = 2 • High = 3 – Therefore: • H/H = 3 * 3 =9 • H/L = 3 * 1 = 3, etc. – If we use C/S & T impact values, we multiply their average by the probability Project Risk Assessment: Worked Example pmis-consulting.com H M L Probability 20% 40% Impact H M L 1 9 4 Producing the risk ‘score’ 3 level schema: (Low = 1, Med = 2, High = 3) also 5 level schema.
  • 8. © PMIS Consulting Limited: all rights reserved • Risk Score – The risk score is useful, but must never be used on its own as an absolute driver of the need for actions etc. following assessment – in other words it is simply wrong to write a process that says ‘accept’ all risks with a risk score less than ….. this is taking process driven management far to far and will result in important risks being ignored Project Risk Assessment: Worked Example pmis-consulting.com H M L Probability 20% 40% Impact H M L 1 9 4 How not to use the risk ‘score’ 3 level schema: (Low = 1, Med = 2, High = 3) also 5 level schema.
  • 9. © PMIS Consulting Limited: all rights reserved • Risk Score – Developing the risk score itself should be a team task – no one person can do this. – Developing the score allows the team to better understand risk, which is a challenging task in itself – This then allows much better informed, structured and successful decision making and actions to follow this phase of the overall project risk management process Project Risk Assessment: Worked Example pmis-consulting.com H M L Probability 20% 40% Impact H M L 1 9 4 How to use the risk ‘score’ 3 level schema: (Low = 1, Med = 2, High = 3) also 5 level schema.
  • 10. © PMIS Consulting Limited: all rights reserved • Please feel free to share this presentation or embed this presentation in your website and respect our Copyright at all times. • Thank you ! • Please click on the link below for more information or training on this topic. Thank you http://pmis-consulting.com/articles/project-risk-management/ H M L Probability 20% 40% Impact H M L 1 9 4 3 level schema: (Low = 1, Med = 2, High = 3) also 5 level schema.