Ce diaporama a bien été signalé.
Le téléchargement de votre SlideShare est en cours. ×

Handling of Concrete

Publicité
Publicité
Publicité
Publicité
Publicité
Publicité
Publicité
Publicité
Publicité
Publicité
Publicité
Publicité
Prochain SlideShare
Underwater concrete
Underwater concrete
Chargement dans…3
×

Consultez-les par la suite

1 sur 89 Publicité

Plus De Contenu Connexe

Diaporamas pour vous (20)

Publicité

Similaire à Handling of Concrete (20)

Plus récents (20)

Publicité

Handling of Concrete

  1. 1. KAS-2012 1 CONCRETE HANDLING IN THE FIELD By K.Shah B.E.(Civil Engg) NIT Rourkela,India M.Sc. (Environment), University of Leeds, UK Ex-GM(Civil & Environment) – MNC Currently Guest faculty-College of Technology & Engineering
  2. 2. KAS-2012 2 Stages of producing concrete. (1) Batching (2) Mixing (3) Transportation (4) Placing (5) Compacting (6) Curing (7) Finishing
  3. 3. KAS-2012 3 (1) Batching (a) Volume batching (b) weight Baching
  4. 4. KAS-2012 4 Volume batching  Volume batching is not good method  Moist sand in loose condition weights less than the same volume of dry sand.  Practiced for small work.  For quality work ,weigh batching is practiced.
  5. 5. KAS-2012 5 VOLUME BATCH Gauge box  Various gauge boxes of different volumes are used. Length Width Depth Volume 33.3 cm 30 cm 20 cm 20 liters 33.3 cm 30 cm 25 cm 25 liters Grade Cement- kg Sand -lts Coarse Aggregate lts 1:11/2:3 (M 200) 50 35 70 1:2:4 (M 150) 50 70 140 1:3:6 (M100) 50 105 210
  6. 6. KAS-2012 6 Weigh Batch Machine
  7. 7. KAS-2012 7 Weigh batching  Weigh batching is correct method  Facilitates accuracy, flexibility & simplicity Different batching machine are available : (a) manual machines & (b) Automatic machines Manual machine :  Has two buckets  Buckets mounted on common spindle about which they rotate.  One is loaded while other is discharged in mixer.  Spring loaded dials indicate the weight.
  8. 8. KAS-2012 8 Automatic weigh batch  For large works  Over head hopper and discharges into mixer.  Useful in ready mix concrete plant  Recorders for weight  Calibration is required from time to time.
  9. 9. KAS-2012 9 (2) MIXING Mixing of cement,sand aggregates should ensure that:  The mass is homogeneous  Uniform in color  consistent
  10. 10. KAS-2012 10 MIXING METHODS : (1) Hand mixing (2) Machine mixing
  11. 11. KAS-2012 11 Hand mixing  Practiced for small scale work (small house, repairing of house etc)  10 % extra cement is added to compensate inferior concrete produced by this method.  Spread fine & coarse aggregate in alternate layer  Spread cement over it  Mix with shovel till uniform color is achieved
  12. 12. KAS-2012 12 Machine mixing  Medium & large scale work use machine mixing  Mixing is efficient, economical & produce quality concrete. Type of mixer: (a) Batch mixer : batch by batch with time interval (b) Continuous mixer: continuously mixed & discharged (in dam construction)
  13. 13. KAS-2012 13 CONCRETE MIXER (1) Pan type (2) drum Type: (a) tilting (b) Non –tilting (c) Reversing
  14. 14. KAS-2012 14 PAN MIXER
  15. 15. KAS-2012 15 PAN MIXER A forced movement pan mixer has blades that are fixed to an assembly that agitates the concrete throughout the pan as the vertical shaft rotates.
  16. 16. KAS-2012 16 DRUM MIXER  As per IS: 1791-1985 mixers are designated by number which shows capacity (liters) of batch: a) Tilting : 85 T, 100T, 140 T, 200T b) Non tilting : 200 NT,280 NT, 375 NT, 500 NT, 1000 R c) Reversing : 200 R, 280 R, 375 R,500 R, 1000 R T= Tilting, NT =non tilting, R=Reversing
  17. 17. KAS-2012 17 TILTING MIXER
  18. 18. KAS-2012 18 TILTING MIXER  Internal blades lift and tumble the ingredients onto itself. Two primary types exist:  horizontal (one end has and opening for charging and a different end for discharging)  single drum (materials are charged and discharged through a single opening).
  19. 19. KAS-2012 19 NON TILTING MIXER
  20. 20. KAS-2012 20 NON TILTING MIXER  Single drum rotating about a horizontal axis.  Fixed blades work the concrete towards the discharge end of the mixer, in order to provide a rapid rate of discharge.
  21. 21. KAS-2012 21 REVERSING MIXER
  22. 22. KAS-2012 22 REVERSING MIXER  The entire drum rotates around its axis as materials are loaded through a charge chute at one end of the drum and exit through a discharge chute at the opposite end of the drum.  Mixing blades are mounted on the inside surface of the drum and as the drum rotates the blades mix by lifting and dropping the materials during each rotation.  Once the materials are sufficiently mixed the rotation of the drum is reversed and the blade arrangement pushes the concrete through to the discharge end of the mixer.
  23. 23. KAS-2012 23 Sequence of charging drum  First half quantity of coarse aggregate is placed in skip  Over it half quantity of sand  On that full quantity of cement  Over it balance quantity of coarse & fine aggregates is place.  This prevents spillage of cement in air while discharging in drum
  24. 24. KAS-2012 24  25 % Water is placed in drum and then mix from skip is discharged in the drum  This prevents sticking of cement on blades  75 water is immediately poured after placing mix material (cement sand etc) in drum.
  25. 25. KAS-2012 25 Mixing time  In small machine, mixing time varies between 1-2 minutes  In Ready Mix Cement mixer – 15-30 seconds  RPM of drum : 15-20  Compressive strength of concrete increases with increase in mixing time but after 2 minutes increase in compressive strength is not significant.
  26. 26. KAS-2012 26  If concrete is not used after mixing it may set  But when concrete is agitated on time to time in drum setting time rule does not follow.
  27. 27. KAS-2012 27 Retempering of concrete :  Some time concrete from RMC plant is not delivered to site due to traffic congestion  Concrete becomes stiff and becomes unworkable  Site engineers can reject the concrete if delay is more  If it can be of used then small volume of water is added and again agitated in the drum. This is called RETEMPERING OF CONCRETE.
  28. 28. KAS-2012 28 MANUFACTURING OF CONCRETE  With same material if care is not taken, resulting concrete will be bad concrete  What are good rules to make good quality concrete.
  29. 29. KAS-2012 29 TRANSPORTATION OF CONCRETE Precaution in concrete transportation:  Homogeneity of conc. Mass is maintained  Movement of hand trolly or truck on rough road surface makes vibrations  This results in deposition of heavy aggregates at bottom of truck  Water & cement slurry comes on top.
  30. 30. KAS-2012 30 METHODS OF TRANSPORTATION 1. Mortar Pan 2. Wheel barrow 3. Truck Mixer & dumpers 4. Crane, Bucket & rope way 5. Belt conveyors 6. Chutes 7. Skip & hoist 8. Transit Mixer 9. Pump & pipeline 10. Helicopter
  31. 31. KAS-2012 31 MORTAR PAN  Common method in India  More labour required  Segregation of concrete is less  Greater surface area of concrete is exposed to sun, concrete dries.
  32. 32. KAS-2012 32 WHEEL BARROW  When transportation of concrete is at ground level.  Movement of wheel on rough road surface, segregates concrete.  Some wheel barrows have pneumatic wheel to reduce vibration
  33. 33. KAS-2012 33 CRANE  Used for transporting concrete above ground level.  For high rise buildings.  Cranes are fast  Can move horizontally & vertically  Concrete in skip discharge from bottom  In bucket concrete is discharged by tilting.
  34. 34. KAS-2012 34 BUCKET & ROPEWAY Use for construction in:  Valley  Bridge pier in river  Dam Advantage: Concrete is not exposed to sun or air & no loss of water.
  35. 35. KAS-2012 35 Truck Mixer & dumpers  Used for large concrete works.  Can travel any part of site.  Dumpers - 2-3 M3 Capacity  Trucks – 4 M3 Capacity  Bottom surface of truck is kept wet  Top of truck is covered to prevent evaporation
  36. 36. KAS-2012 36 BELT CONVEYORS  Limited use in construction Advantages:  Can transport large volume  Very quick  Can go where access is limited Disadvantages :  On steep slope concrete segregates.  Exposed to sun for long time.
  37. 37. KAS-2012 37 CHUTE  For transporting from ground level to lower level. (basement etc).  Used where labour can not reach due to less space in trench etc.  Made of metal  Slope should not be < 1 vertical : 2.5 horizontal.
  38. 38. KAS-2012 38 SKIP & HOIST  Labour can go upto 3rd or 4th floors.  So skip is used for transport vertically up (in multistory building).  Skip travels on vertical rail.  Skip can discharge manually or automatically.
  39. 39. KAS-2012 39 TRANSIT MIXER
  40. 40. KAS-2012 40 TRANSIT MIXER  Used for long distance travel in RMC plant.  Concrete is continuously agitated in truck drum (2 – 6 rpm).  Also transported mix in dry condition and water is added on reaching the destination.  Wet Mix in truck must reach site in 1- 1.5 hours.  Pumps are also fitted on truck mixer to discharge concrete.
  41. 41. KAS-2012 41 PUMPS & PIPELINE  Most popular method  Reliable & good quality pumps are used.  Mostly operated by diesel.  Concrete is placed in collecting hopper.  Rotating blades in hopper pushes concrete towards pipe.  Vacume in hose pipe (600 mm Hg)  Rotating rollers in pump chambers squeeze the concrete in pipe and flow of concrete is started.  Concrete is discharged from other end of hose pipe.  Concrete can be pumped upto 400 m height and 2000 m distance.
  42. 42. KAS-2012 42 SECTION OF PUMP
  43. 43. KAS-2012 43 PIPELINE Pipeline should :  Have correct diameter as per pump pressure. (generally 125 mm)  Have sufficient thickness  Good couplings  Poor pipeline can cause blockage.
  44. 44. KAS-2012 44 PIPELINE  Thumb rule : For 30 M3 /hr concrete and 200 m length, dia should be 100 mm.  Length > 500 m then dia = 150 mm.  Dia = 3 to 4 times the size of aggregate  Leaky pipe & coupling result in escape of water /air & finally block the concrete.  Vertical pipe should good otherwise difficult to change at height.  Pump is kept at distance from building about 15 % of vertical length.
  45. 45. KAS-2012 45 PUMPABLE CONCRETE  Concrete which can be pushed through a pipeline is called pumpable concrete.  Friction between pipe wall and concrete is less.  Concrete flows in the form of plug which is separated from pipe wall by a thin layer of lubricating cement paste.  Flow resistant must be < pump pressure.  If the concrete is more wet then water comes out of mix which makes more resistance to flow.  Stiff and also very wet concrete is not pumpable.
  46. 46. KAS-2012 46 Design of pumpable concrete  Concrete Mix is so designed that all material remain together.  Mix must make redial movement of grout to maintain lubricating paste.  Mix should be deformed at bends  Cement & fine particles (0.25 mm size) are important for good flow.  350 to 400 Kg/ M3 of fine particles are necessary for flow.  Slump of pumpable concrete is above 75 mm.
  47. 47. KAS-2012 47 PROBLEMS IN PUMPING  Blockage in pipe  Pipe should be cleaned after each day operation  Blockage can be cleaned by forward- backward pumping.  Tapping pipe with hammer  Clean pipe with rod or sponge ball pushed by compressed air.
  48. 48. KAS-2012 48 PLACING CONCRETE  Must be placed in systematic manner. Can be placed with following methods:  Within earth mould : Foundation  In timber plank formwork : Road, airport slab.  Steel shuttering : Dam  Under water
  49. 49. KAS-2012 49 Concrete in Foundation  In foundation, ground is made wet.  Plastic sheet are laid between ground & slab  Concrete is dumped not poured.  No heap and dragging  Placed in layers of 35 – 40 cm in mass concrete  Avoid cold joints between 2 layers  Surface of previous layer is cleaned with wire brush  Sometime, cement slurry is placed on old surface  Top of previous layer kept rough for good bond.
  50. 50. KAS-2012 50 Concrete on Road, airport, floor slabs  Placed in alternate bays (allow shrinkage) with contraction joints : contraction joints Bays
  51. 51. KAS-2012 51 Concrete in Beams & Column  Reinforcement correctly placed.  Correct cover required  Joints of shuttering to be plugged.  Mould releasing agent inside formwork
  52. 52. KAS-2012 52 STRIPPING TIME  Form work should not removed until good strength has come. Type of form work Time Vertical wall, columns 16-24 hrs Soffit of slab (Prop should be refixed immediately) 3 days Soffit of beam (Prop should be refixed immediately) 7 days Props to slab Span < 4.5 m 7 days Props to slab Span > 4.5 m 14 days Props of beam (Span < 6 m) 14 days Props of beam (Span > 6 m) 21 days
  53. 53. KAS-2012 53 UNDER WATER CONCRETE
  54. 54. KAS-2012 54 UNDER WATER CONCRETE  Tremie (means hopper) is used.  Funnel on top  Pipe of 200 mm size  Pipe bottom is plugged  Fill pipe with concrete  Lift pipe or jerk to release the plug  Keep bottom of pipe inside concrete
  55. 55. KAS-2012 55 Underwater Concrete  No compaction required as hydrostatic pr of water compacts concrete.  Concrete of 0.3 W/C ratio can be placed with Tremie.  Used for Pile or well foundation
  56. 56. KAS-2012 56 SLIP FORM TECHNIQUE  In this method, concrete is continuously placed, compacted & form work is pulled up for next layer of concrete.  Vertical slip form for Tall structure like silo, chimney  Horizontal slip form paver machine (HSFP) for road construction.  Concrete is dumped in front of HSFP machine by dumpers.  Compaction by vibrator installed inside HSFP machines.  Finishing of surface by HSF paver.  Operation of road alignment, gradient, curve are controlled by Computerized Laser Control system.  Speed of construction is 1 mt /min.  1 km of concrete road of 3.75 mt width is built in one day (16 hrs work).  Mumbai-Pune Expressway was constructed by this machine.
  57. 57. KAS-2012 57 VERTICAL SLIP FORM
  58. 58. KAS-2012 58 HORIZONTAL SLIP FORM ROAD PAVER
  59. 59. KAS-2012 59 COMPACTION OF CONCRETE  Compaction is a process of expelling the entrapped air inside concrete mass.  During mixing, transporting & placing the concrete, air gets trapped in concrete mass.  If this air is not removed, concrete will not get strength.  5 % of air voids reduces strength by 30 %  10 % of air voids reduces strength by 50 %  Durability of concrete is also reduces with air voids.  Insufficient compaction increases permeability of concrete.  Results in entry of aggressive chemicals in solution.  Chemicals attack concrete & reinforcement and life of concrete is reduced.
  60. 60. KAS-2012 60 METHODS OF COMPACTION 1. Hand compaction 2. Compaction by vibration 3. Compaction by pressure & jolting 4. Compaction by spinning
  61. 61. KAS-2012 61 (2) COMPACTION BY VIBRATION a) Internal Vibrator b) Formwork Vibrator c) Table Vibrator d) Platform Vibrator e) Surface Vibrator
  62. 62. KAS-2012 62 (1) HAND COMPACTION  Hand Rodding Poking inside concrete with 1-2 mt long steel rod  Ramming Unreinforced foundation & ground floor work  Tamping Wooden beam is used to beat concrete (low thickness slab, road slab)
  63. 63. KAS-2012 63 COMPACTION BY VIBRATION  In hand compaction w/c ratio is more so we get less strength in concrete.  In mechanical vibrator w/c can be kept low so we get good strength.
  64. 64. KAS-2012 64 INTERNAL VIBRATOR
  65. 65. KAS-2012 65 (a) INTERNAL VIBRATOR  Most common in use  Called, Needle Vibrator or Immersion vibrator or Poker vibrator.  Consists : electrical/diesel power supply, Needle and shaft.  Frequency of vibrations can be 12000 cycles vibration per minute.  Needle diameter 20 to 75 mm  Length 25 to 90 cm.  Portable.
  66. 66. KAS-2012 66 FORMWORK VIBRATOR  Used for columns, walls, precast slab  Vibrator is clamped to formwork  Vibration is given to formwork  Vibration is transferred from formwork to concrete  Useful in thin wall where reinforcement obstruct the needle type vibrator.  Efficiency is lower then needle vibrator
  67. 67. KAS-2012 67 TABLE VIBRATOR  Vibrator is clamped to table  Used for concrete test cubes  Cubes are kept on table to get vibrations  Also used for small prefabricated slab
  68. 68. KAS-2012 68 TABLE VIBRATOR
  69. 69. KAS-2012 69 PLATFORM VIBRATOR  Similar to table vibrator but of large size  Used for long concrete electrical pole, railway sleeper,prefabricated roofing element
  70. 70. KAS-2012 70 PLATEFORM VIBRATOR
  71. 71. KAS-2012 71 SURFACE VIBRATOR  Known as Screed Board Vibrator  Used for thin roof slab where needle vibrator can not be used  Not effective if slab thickness is more then 15 cm.
  72. 72. KAS-2012 72 SURFACE VIBRATOR
  73. 73. KAS-2012 73 COMPACTION BY PRESSURE & JOLTING  Used for hollow blocks, solid concrete blocks  Stiff concrete is vibrated, pressed & given jolts  Stiff concrete is compacted to get dense form & good strength is achived.
  74. 74. KAS-2012 74 VIBRATION BY SPINNING  New method  Used for concrete pipes  Concrete when spun at high speed gets compaction by centrifugal force
  75. 75. KAS-2012 75 VIBRATORY ROLLER  Road rollers has vibrating system  Roller while moving on raod slab gives vibrations  Used for Lean concrete (M10) for road base 
  76. 76. KAS-2012 76 ROLLER VIBRATOR
  77. 77. KAS-2012 77 PRECAUTIONS IN VIBRATING CONCRETE  Vibrator gets damaged if comes in contact with hard object (Formwork, hard concrete)  Switch on when needle is inside fresh concrete mass  Should conform to IS 2505-1963  Degree of compaction can be recognized from rising air bubbles & formation of thin film on top
  78. 78. KAS-2012 78 HYDRATION OF CEMENT  Cement is made by Cao, SiO2, Al2O3, Fe2O3, MgO, K2O, SO3  After burning in Kiln following products are made: 3Cao. SiO2 (C3S) - Tri calcium silicate 2Cao. SiO2(C2S) – Di cacium silicate 3Cao. Al2O3 (C3A) – Tri cacium aluminate 4Cao. Al2O3. Fe2O3(C3AF) -Tricalcium alumino ferrite. On addition of water in cement reaction of C3S, C2S, C3A & C3AF liberate heat. Heat is suside by addition of water.
  79. 79. KAS-2012 79 CURING OF CONCRETE  Curing is defined as “ making satisfactory moisture content & favourable temperature” in concrete after placing the concrete. So that hydration may continue until the strength is developed.  Curing is required immediately after placing concrete.  During hydration, heat of hydration is released.
  80. 80. KAS-2012 80 CURING OF CONCRETE  Concrete delivers its strength by the hydration of cement particles.  Hydration is continuous & long time process.  Rate of hydration is fast immediately after making the concrete  Theoretically 0.23 w/c ratio required for hydration  0.15 w/c ratio required for filling the voids in gel.  Total 0.38 w/c ratio is optimum  In field condition, water evaporates & available water quantity reduced for hydration  Extra water is given by curing
  81. 81. KAS-2012 81 METHODS OF CURING a) Water curing b) Membrane curing c) Application of heat d) Other methods
  82. 82. KAS-2012 82 WATER CURING a) Immersion : Slab is kept in water tank b) Ponding: Roof slab is filled with water c) Spraying : water spary on concrete wall is d) Wet covering : Wet gunny bags on wall
  83. 83. KAS-2012 83 MEMBRANE CURING  Concrete surface is covered by plastic membrane  It is used where water availability is less.  Plastic sheet reduces evaporation in concrete  Membrane is applied after 2 days of water curing
  84. 84. KAS-2012 84 APPLICATION OF HEAT  Spraying of steam on concrete provides heat & moisture.  Higher temperature accelerates hydration rate & strength of concrete is attended  Early strength of structure is obtained  Steam application possible at precast factory only.  Precast prestressed concrete girders of bridge are cured with steam  Fast construction of bridge
  85. 85. KAS-2012 85 HIGH PRESSURE STEAM CURING  Superheated steam at high pressure (8.5 kg/cm2) & high temperature(175 deg C) is applied on concrete.  This process is called “Autoclaving”  28 days strength of concrete is achieved in one day  Concrete becomes sulphate resistant  Low shrinkage in concrete  Used in production of Cellular concrete products( Siporex, Celcrete)
  86. 86. FINISHING OF CONCRETE  Finishing is last operation of concrete making.  Finishing of top surface is required in roads, airport strip, home floor Methods of Finishing: a) Form work Finish b) Surface Treatment c) Applied Finishes SHAH K.A. 86
  87. 87. FORMWORK FINISH  Concrete obeys the shape of formwork  Grooves & lining on formwork plate gives makes grooves & lining on concrete  Prefabricated tiles can be made of any design
  88. 88. SURFACE TREATMENT  Domestic floor should be smooth, wear resistant, crack free.  Mix should have good proportion without excess “Matrix”  Exposed aggregate finish : Colored pebbles on top layer of wall  Bush Hammering : Electrically operated Brush with teeth when applied on concrete removes top cement layer, exposes aggregates and makes shining aggregates. KAS-2012 88
  89. 89. APPLIED FINISH  Rough cast finish : mixture of cement, sand, round gravel is applied on wall  Non slip finish: Railway platform & walkway around pool are given non slippery finish by mixing large size sand particles in floor concrete.

×