HOW TO IMPROVE TIME TO MARKET
WITH EXISTING RESOURCES
The Product Development View of the
Resource Management and Capacity Planning
Benchmark Study
Commissioned by Planview®

conducted by
Appleseed Partners and OpenSky Research

©2013 Planview, Inc.
RESEARCH REPORT

HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES

Product development organizations face specific challenges when it comes to resource management and capacity
planning. What’s at stake? In short, time to market targets and revenue. If product teams choose to embrace the
status quo, they will not reap the benefits of change – optimized resources, stronger company bottom lines, better
market share and brand awareness equity.
Key findings of this Product Development View of the Resource Management and Capacity Planning Study include:
•	 Pain: Lacking visibility into both capacity and incoming demand and the impact of constant change.
•	 Business risk: Lost revenue and market share due to missed market windows, remaining in crisis mode, and
resources wasted on the wrong projects and products.
•	 Opportunity: Improve processes to increase resource management and capacity planning maturity; this can
support goals such as reducing total cost of development, filling the pipeline with profitable products, and speeding
time to market.
This research report is an extension of the Resource Management and Capacity Planning Benchmark Study 2013,
available at Planview.com/RMCPBenchmarkStudy. Containing product development specific charts and analysis not
presented in the original benchmark report, this focused view speaks explicitly to product development organizations.

Executive Summary
This report reveals the state of resource management and capacity planning in product development organizations. It shows that within
these groups, there is considerable room for growth – and many of them are very aware of the need, as well of the potential benefits.
What stymies product development organizations is the how and the where: how to do it, where to start.
More than 280 globally-based product development executives participated in the benchmark study1, sharing their top pain points,
business risks, pain causes, software impacts, and process improvements relative to resource management and capacity planning.
These executives were aware of what was at risk and spoke to their goals of improving time to market, reducing the total cost of
development, and improving their ability to effectively prioritize winning ideas. They understood that not addressing resource management
issues leads directly to problems, including a lack of visibility into demand and capacity resulting in ongoing chaos among their teams,
missing market windows, and the inability to optimize both people and financial investments.
It should not be construed, however, that the groups participating
were homogeneous. Their problems varied, as indicated by their

Resource Management and Capacity Planning
Maturity Spectrum

position on the Resource Management and Capacity Planning
Maturity Spectrum (Figure 1). This spectrum allowed participants
to identify their groups’ maturity on a five-tier grading system from
1-Basic (having very limited understanding of resources, capacity,
and demand) to 5-Optimized (having up-to-date data). Reference
section IX. Maturity Matrix for complete details.
Roughly two-thirds of product organizations identified as low- to midlevel maturity; only a third labeled their organizations with a higher
state of maturity, at which point they break through to a certain level
of management control and optimization, and thus greater visibility.

Figure 1. Maturity Spectrum
1

Carlson, M. (2013). Resource Management and Capacity Planning Benchmark Study.

©2013 Planview, Inc.

2
HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES

RESEARCH REPORT

Key Findings
The report shows several common threads of challenges such as
constant change, inaccurate project estimation, and the inability to

Capacity Planning Maturity Levels for
Product Development

complete projects on time. Slightly more organizations identified as
more mature when it came to resource management than capacity
planning (38% vs. 31%); there is significant opportunity for growth in
the latter, which could help organizations prioritize more effectively and
alleviate many of their pains (Figures 2 and 3).
Improvements in resource management and capacity planning come
down to three things:
•	 Improved, consistently used processes
•	 Commitment, follow-through, and executive support
•	 The right enterprise software for the job

Figure 2: Capacity Planning Maturity Levels

Addressing these areas allows organizations to better align and connect products with their strategy; enables management to run critical
what-if scenarios in the face of constant change; and ensures that scarce resources are leveraged wisely for the most competitive
offerings and high value returns.

The Six Characteristics of Mature Organizations
As determined in the Resource Management and Capacity Planning
Benchmark Study 2013, those organizations that excel at resource

Resource Management Maturity Levels for
Product Development

management and capacity planning performance tend to:
1.	 Have insight into what people are working on, can identify
bottlenecks, and run scenarios on-demand, to adapt to change
2.	 Meld top-down with bottom-up approaches to capacity planning
and resource management
3.	 Have a dedicated function to lead resource management and
capacity planning activities
4.	 Agree on these top three best practices: prioritization; what-if
analysis; executive buy-in
5.	 Estimate projects well and have good supporting processes in
place
6.	 Use Product Portfolio Management (PPM) software to optimize

Figure 3: Resource Management Maturity Levels

their resources

©2013 Planview, Inc.

3
HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES

RESEARCH REPORT

Summary
Product organizations face unique pressures, both from the outside and within. One of those internal pressures comes from the
nonconformist view that process is the enemy of creativity and innovation, rather than its support structure.
For those surveyed, no matter how mature their resource management and capacity planning performance, all said that their processes
needed bolstering. Improving processes is in every product organizations’ best interest: it derisks the entire portfolio, helps drive
down costs, builds efficiencies into projects, encourages innovation by enabling the prioritization of products and resources in line with
strategy, and creates an environment that gets products to market faster.
When the external world continues to make its presence known – more, now, better, faster – not hitting market windows is not an option,
nor is not delivering quality products or hiring more resources to make it all happen. Something has to give.
External pressures are going to continue to build. Resources are going to continue to be finite and scarce. Product groups must find
better ways of dealing with these pressures, and a foundation based on consistent, enforced process is an excellent place to start.
Embrace change: allow process and software to support the team and the company goals.

Key Report Statistics
Of those organizations surveyed:
•	 More than 50% of lower maturity organizations perceive their greatest business risk is delayed time to market resulting in
losses of revenue, savings, user/customer satisfaction, and/or market share; this reduces by more than 10% for higher maturity
organizations
•	 Nearly 70% of all organizations want streamlined and accurate resource and forecasting and planning to be the main result of
improving resource management and capacity planning processes and using enterprise software
•	 The top best practices recommended by higher maturity organizations are better prioritization and performing what-if analysis
on capacity plans to determine the best use of resources and for risk mitigation

©2013 Planview, Inc.

4
RESEARCH REPORT

HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES

Table of Contents
Executive Summary

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

I. Product Development Maturity: Resource Management vs. Capacity Planning
II. Organizational Plan

. . . . . . . . . . . . . . . . . . . .

6

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

7

A. Pain Points Before and After Software
B. Pain Causes

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

7

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

8

C. Pain Point Shifts by Maturity Level
III. Expected Business Benefits

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

10

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

10

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

11

VI. Recommendations

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

A. What Are Your Priorities? Get Your Process House In Order
B. Change the Future with Historical Actuals

11

. . . . . . . . . . . . . . . . . . . . . . . . . . . .

11

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

11

C. Look at the Proof and Make the Business Investment in the Right Software
VII. Next Steps

9

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

IV. Business Risks
V. Best Practices

2

. . . . . . . . . . . . . .

12

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

12

VIII. About the Product Development View of the Resource Management Capacity Planning Study . 13
A. About the Report

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

13

B. Use of the Report

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

13

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

13

C. Study Objectives

D. Study Participants and Methodology
IX. The Maturity Matrix

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

14

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

14

X. About the Chief Researcher
XI. About Planview

©2013 Planview, Inc.

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

15

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

15

5
RESEARCH REPORT

HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES

I. Product Development Maturity: Resource Management vs. Capacity Planning
In the benchmark study, participants were asked to identify their organizations’ maturity levels against a specially designed, objective
matrix that allowed for the benchmarking of resource management and capacity planning performance. Please reference Section IX of
this report to review this maturity spectrum in depth.
While maturity levels in both capacity planning and resource
management broke down fairly evenly into thirds, overall organizations

Capacity Planning Maturity Levels for
Product Development

indicated a slightly higher maturity level in terms of resource
management (Figure 2 and 3).
The higher resource management maturity level is unsurprising. In
product development organizations, there is essential ongoing or inflight tactical assignment of personnel to planned and unscheduled
activities. The nature of capacity planning is more proactive and
forward-looking. Capacity planning addresses the need to take
human and non-human (e.g., production lines, patient beds) resource
constraints into account in the sequencing and prioritization of
products and projects during both the annual planning process and for
gate approvals. Longer range capacity planning ensures the company
has the facility to take on new ideas at the right time.

Figure 2: Capacity Planning Maturity Levels

Given the aforementioned continual interaction with resource management activity, it is surprising to note that nearly one third of survey
respondents say that they are still at a Level 1-Basic or Level 2-Ad-Hoc stage of maturity in this area. Lower maturity here is characterized
as chaotic, with virtually no visibility into demand or insight into what their resources are working on. The mid-tier Level 3-Limited maturity
organizations gain visibility, but with that new insight, they ironically uncover or become more aware of a host of challenges to address
for optimizing the productivity of their resources.
Encouragingly, a third of organizations are breaking through to higher
maturity. Level 4-Managed and Level 5-Optimized environments

Resource Management Maturity Levels for
Product Development

benefit from greater control and true productivity optimization (but
even these organizations said there’s room for improvement).
When asked to identify best practices to help enable a breakthrough
to higher maturity levels, these more mature product development
organizations pointed to several that, for the more complex
organization, are challenging if not impossible to achieve without a
strong foundation of software, process, and executive support. With
this foundation, however, mid- or lower-level maturity organizations
can begin to build on the best practices to achieve a more complete
picture of capacity and demand.

Figure 3: Resource Management Maturity Levels

“We’re good on the demand side but not the capacity side. Right now our project managers can’t
see the availability, skill set, or number of weeks of effort; and the assumptions are not right. If the
resource managers are not using the system to give the product managers visibility, even the best
project plan can’t be properly resourced.”
Senior Manager PMO, Large Insurance Company

©2013 Planview, Inc.

6
RESEARCH REPORT

HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES

II. Organizational Plan
A. Pain Points Before and After Software
Before implementing enterprise software
for resource management and capacity

Pain Points Before and After Enterprise Software
for Product Development

planning, the top two pains points are clear:
lack of visibility into capacity, followed
swiftly by its twin, poor insight into demand.
Equally apparent is the cascade of pain
that follows from those two problems
(Figure 4).
Once supporting enterprise software is
properly
picture

implemented,
takes

shape.

an

interesting

As

might

be

expected, several areas show significant
improvement.

Capacity

and

demand

visibility are enhanced, as is reporting
on demand, and the 6% improvement of
resources completing projects on time can

Figure 4. Pain Points Before and After Enterprise Software

make a substantial difference in margins.
How then to explain increased pains, post-implementation of software, in items such as constant change affecting assignments, ineffective
demand prioritization, and challenges managing shared resources across projects (which affects a reported 80% of organizations
surveyed)? While a few of the pain points appear to be more problematic after software adoption, there are a few factors to consider:
•	

As referenced earlier in the Executive Summary of this report, while implementation of enterprise software is a key characteristic of
mature companies, as indicated by the best practices they recommend, it’s not a silver bullet. Without the supporting processes and
management mandate to ensure its consistent use by product, project, and resource managers, the software will not succeed in its
goals.

•	

It is often a case of “ignorance is bliss.” When software and process are leveraged effectively, an organization’s eyes are opened:
the more it can see into incoming demand and the true state of its capacity, the more opportunities for improvement are revealed.

•	

All enterprise software is not created equal. Are product organizations using the right software for the needs of resource management
and capacity planning? Refer to section VI. Recommendations for more on this topic.

“We are transitioning from having our own resources to sharing pooled resources. Our challenge is
that some of the organization is doing resource management and capacity well, while other parts of the
organization are just getting started. In a shared resource arrangement, more of the organization needs
to be on board. Our biggest risk of not addressing resource management and capacity planning is time
to market for our seasonal products.”
Project Management Director, Large Consumer Products Company

©2013 Planview, Inc.

7
RESEARCH REPORT

HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES

B. Pain Causes
Process is the name of the game – and

Product Development - Pain Causes by Maturity Level

across the board, organizations appear
to believe it’s the solution.
For the more mature organizations, the
top causes of pain points are challenges
estimating for projects and lack of
process maturity, closely followed by
ineffective use of historical data (Figure
5).
These

causes

are

related.

When

process matures and is repeatable, and
experiences, best practices, and lessons
learned are stored in a centralized,
accessible

system,

managers

can

acquire information from historical data

Figure 5: Pain Causes by Maturity Level

and improve high-level and detailed project estimates and deliver them more quickly and painlessly. Unfortunately for most, this information
is siloed, residing in the heads of product and development managers or in desktop files. This is often the result of resources being so
overloaded that they’re rushing to the next project, a lack of process adoption, or reliance on information that is non-standard without
the right technology to store, search, and apply it. A minimally invasive process that is enforced and enabled across the organization can
make a significant difference to improve vitally important data for resource and project estimation.
Level 3-Limited maturity organizations, with their newfound visibility, have pinpointed some specific top issues to address – they also want
to start with process, and then tackle project-estimating issues. Just like the most mature, they will greatly benefit from the efficiencies
they gain, as well as project derisking.
Lower-level maturity organizations, those in the Level 1 and Level 2 segments, have identified a good place to start addressing their
problems: process and executive buy-in (their top pain causes). Best practices indicate that it is a powerful first step to leverage executive
mandate to ensure that processes be improved and adopted across the enterprise to begin to resolve resource management and
capacity planning issues.

“Our recommendation is to understand the body of work and do time tracking on the work. To
do estimates, you need a baseline. Try to do it without a tool and then show others how a tool
can be beneficial. Then you need to figure out how to capture your demand. It doesn’t have to
be perfect, just start somewhere.”
Program Manager, Consumer Goods Product Company

©2013 Planview, Inc.

8
RESEARCH REPORT

HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES

C. Pain Point Shifts by Maturity Level
The most mature product development
organizations (Level 4-Managed and

Product Development Top Five Pain Points (after
software) by Maturity Level

Level 5-Optimized) place ineffective
demand prioritization and constant
change and its impact atop their list
of top pains (Figure 6). Pains one
and two are separated by two small
percentage points. From there, it is
quite a jump to the next smaller pain,
that of underutilizing resources. Not to
minimize this third concern, but with
a difference of 15% between pains
two and three, it is clear that these
organizations have identified where it
hurts – and on what they need to focus.
Level 3-Limited organizations have
identified the same pains as their
higher-level brethren, although their
emphasis on them is reversed. And the
difference doesn’t end there. For these

Figure 6. Top 5 Pain Points (after software) by Maturity Level

teams, the pain of constant change that
affects assignments and availability comes in at 49%, in and of itself a whopper, and a rather tremendous 19% ahead of its next closest
competitor in the race for biggest pain (Figure 6). What to make of this lead, and why do nearly 50% of these organizations identify so
fiercely with this challenge? One explanation is that they have some awareness of the demand in the product pipeline, understand to a
fairly significant extent where their commitments already lie, and can essentially see where their resources are already allocated. The
constant change of their environments becomes all the more unreasonable as they comprehend just how much opportunity is falling by
the wayside, and how much room for improvement is still open to them.
Those at maturity levels 1 and 2 are most challenged by an inability to see into their companies’ strategic goals, making prioritization
challenging (Figure 6). Given that they operate in a highly chaotic, tactical state, this is unsurprising – as is their second-highest pain,
which echoes from the other two groups, that of constant change and its impact. This group, however, sees its pains as more evenly
distributed; all pains also bear higher percentage points across the board. For these organizations, everything hurts.

“Our biggest risk is having different versions of the truth and schedule.”
Senior Project Manager, Semiconductor Products Company

©2013 Planview, Inc.

9
HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES

RESEARCH REPORT

III. Expected Business Benefits
Study participants were asked what
business benefits they believed their
organizations
addressing

would

recognize

resource

by

What are the expected Business Benefits of addressing Resource
Management and Capacity Planning with an improved process and
enterprise software? (select 3)

management

and capacity planning with improved
processes and the use of enterprise
software. All participants, regardless of
their organization’s maturity level, shared
two key expectations:
1.	 Streamlined and accurate resource
forecasting and planning
2.	 Improved project success and time to
market
Depending on their maturity level, they
also wanted to improve visibility into
what resources are working on; optimize
the productivity of resources; or improve

Figure 7. Expected Business Benefits with Improved Process and Enterprise Software

visibility into capacity respectively as they
move up the matrix (Figure 7).

IV. Business Risks
Connecting the dots between business
risks and the impact they have is key for
organizations looking to improve resource
management

and

capacity

What are the greatest Business Risks of not addressing Resource Management
and Capacity Planning with an improved process and the use of enterpise
software? (select all that apply)

planning

performance. What is the bottom line?
Study participants indicated that by leveraging
software and process correctly, they believed
they would decrease the business risks of
time to market, decision-making, alignment
of resources, and reporting (Figure 8).
Participants further felt that risk would decline
by significant percentages (8–10%) in each
of these key areas. What would it mean to
reduce risk by 10% in time to market? What
is the impact of inaction?
Figure 8. Business Risks with no Improved Process and Enterprise Software

©2013 Planview, Inc.

10
HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES

RESEARCH REPORT

V. Best Practices
As alluded to earlier, when asked the top best practices for improving resource management and capacity planning, the most mature
organizations recommended:
•	 Better prioritization
•	 Performing what-if analysis on capacity plans to determine the best use of resources and for risk mitigation
•	 Establishing and communicating processes
Organizations were also asked what type of approach they use for resource management and capacity planning: 1) bottom-up resource
management on projects; 2) top-down capacity or full time equivalent (FTE) planning; or 3) a combination of the two. The most mature
companies indicated they used a combined approach that gave everyone in the organization a shared responsibility for resource
management and capacity planning, making this a strongly recommended best practice.
The implementation of these practices could go a long way toward addressing the pain points identified by respondents. However,
attempting to implement these practices without the right software, processes, and management support, especially in a resourcestrapped and/or project-heavy environment can be a thankless challenge that ends poorly or simply subsides. The organization seeking
to use best practices to migrate up the maturity model matrix might well consider if it is not worth the time and money to put a stronger
foundation in place to achieve the breakthrough it seeks.

VI. Recommendations
A. What Are Your Priorities? Get Your Process House In Order
As has been seen throughout this report, organizations at all levels of maturity can benefit from improving their resource management and
capacity planning process performance.
Organizations at maturity levels 1–3 have a tremendous opportunity to move up the maturity scale when it comes to capacity planning
in support of proper prioritization. It’s important to consider the capacity plan in context with demand. Everything is a top priority if it’s
assumed there are enough resources to handle the work. Addressing capacity planning has a tremendous payoff, both for project
prioritization and for good resource utilization practices.
Those at maturity levels 4 and 5 still struggle with pain points such as an ineffective demand prioritization and governance process. To
focus on continuous improvement and mature standard processes, use this report to benchmark where your product development team
lies, and put a measureable, specific plan in place for both resource management (to address in-flight challenges) and capacity planning.
This will help the executive team to prioritize, help product development to focus efforts on the most impactful products, and grow planning
from a reactive 3–6 months to a proactive 1–2 years out. Think forward – this is where real strategic competitive differentiation, time to
market improvements, and margin maximization take place.

B. Change the Future with Historical Actuals
Best practice dictates that your product portfolio should be a balance between breakthrough innovation and incremental innovation.
Unfortunately, for many companies, line extension and product updates take as long as those breakthroughs. Luckily there are ample
opportunities to deliver these small product changes to market faster, using less money and less people, and direct more resources toward
game changers – and this is where leveraging historical actuals to estimate for the future can come to the rescue. How? Implement the
capability to track historical actuals in terms of money, duration, and effort, and have a place to store it for future reference (that requires
process and the right software). If it means more time reporting, then do it. When a project ends, ensure the data is correct and captured.
Hold an honest post mortem. All these moments of data capture, small and large, turn into an incredible opportunity for cost savings and
time to market improvement down the road, along with enabling future, accurate, and efficient project and resource estimation and better
capacity planning. There is a reason many of the key pain causes – such as challenges estimating for projects; lack of process maturity;
ineffective use of historical data – resonated across maturity levels. Not enough people take the time to capture how long things really take
and what resources were really required because they are already on to the next thing. Start capturing the data and stop feeling the pain.

©2013 Planview, Inc.

11
HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES

RESEARCH REPORT

C. Look at the Proof and Make the Business Investment in the Right Software
In this report, organizations that invested in enterprise software are 27% better off in their visibility into capacity and 22% better off in
visibility into demand. And the inability of resources to consistently complete products on time gets better by 6%, and that’s significant.
Enterprise software is providing great dividends but there are still great prospects for improvement and a move up the maturity ladder to
realize even greater business gains.
Think about software from two perspectives:
1.	 Is it the right software? According to the study, many organizations are reporting that they use different types of enterprise software
including Product Lifecycle Management (PLM) or Enterprise Resource Planning (ERP) and expect it to address resource management
and capacity planning. Not so. While Product Portfolio Management (PPM) software can relieve the pain points identified in the survey,
PLM and ERP are not going to effectively prioritize demand and improve the governance process; will not help to address the lack of
visibility into a company’s strategic goals; nor will they help with capacity or demand. Not all enterprise software is designed to address
the same problems.
2.	 Is it being used the right way? Many survey respondents check the box (“Yes, we have a PPM solution”) but they don’t use the full
breadth of the software they purchased. PPM is not just about the application itself; it’s also about fostering the supporting processes.
Organizations leveraging enterprise software to improve resource management and capacity planning performance should take the
time to develop a big picture plan; maintain the stamina needed to execute; follow through; and ensure that leadership support is in
place. They should not underestimate how much a strong, pragmatic leader is needed to see the plan through end-to-end so that the
company can realize the business benefits that come from enterprise PPM software including reducing time to market, increasing
revenue, and launching differentiated products.

VII. Next Steps
If you would like to learn more about more improving resource management and capacity planning, take advantage of the following
resources:
•	 Download the whitepaper Ten Proven Military Strategies for Better Resource Planning: Avoiding Custer’s Last Stand. Nowhere is there
a richer source of strategies and tactics for how to apply limited human resources than in military history. With that in mind, we invite
you to read this whitepaper from top-selling author Jerry Manas, which explores 10 timeless military strategies – tried and tested over
thousands of years – that can be effectively applied toward modern day resource planning.
Download the paper at Planview.com/TenProvenMilitaryStrategies.
•	 View this On-Demand Webcast: How Technology-Enabled Visibility Lets You Prioritize Products and Optimize Resources to discover
how you can deliver the visibility needed to make effective, informed, and timely decisions with confidence regarding your product
pipeline. Through the use of PPM technology, organizations can optimize their limited people and financial resources to achieve their
product delivery objectives. Featuring Frost & Sullivan, Isabel SA, and Planview.
Access the webcast on demand at Planview.com/PrioritizeProductsandOptimizeResourcesWebcast.
•	 Read Issue in Focus: Meeting Fixed Product Launch Windows, Managing Portfolios When Time to Market is Non-Negotiable. In this
research report, Jim Brown, president of Tech-Clarity, addresses the critical nature of hitting launch windows and provides insight from
successful companies as well as tips for improving the odds of success. Gain vision into:
◦◦ Challenges impeding time to market
◦◦ Starting with the right ideas
◦◦ Ways to derisk your process
◦◦ Effective execution with a PPM solution
Download your copy at Planview.com/LaunchWindowsWhitepaper.

©2013 Planview, Inc.

12
HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES

RESEARCH REPORT

•	 Access The 3rd Product Portfolio Management Benchmark Study. In 2012, 320 product development executives and managers
participated in the online survey on the state of product portfolio management, conducted by Appleseed Partners and OpenSky
Research, and sponsored by Planview. Here are just a few of the many illuminating stats gathered from respondents:
◦◦ 68% indicate they have too many projects for their resources
◦◦ 90% rely on informal ways to integrate the customer voice into the product development process
◦◦ 55% indicate they are not able to measure the cost of a product launch delay
While the report reveals trends across the past three surveys, an overriding theme of this study is the need to innovate smarter
and harder. In addition to insightful statistics and informative data on the state of product portfolio management, the report provides
thought-provoking recommendations for all product development organizations.
Download the full report at Planview.com/ThirdPPMBenchmarkStudy.

VIII. About the Product Development View of the Resource Management Capacity Planning Study
A. About the Report
This report is an extension of the Resource Management and Capacity Planning Benchmark Study 2013, available at
Planview.com/RMCPBenchmarkStudy. Containing product development specific charts and analysis not presented in the original report,
this report speaks explicitly to product development organizations.
To develop the research on which both the original study and this report are based, Appleseed Partners and OpenSky Research,
commissioned by Planview, conducted the first in-depth benchmark study on the state of resource management and capacity planning
at project-based organizations. The survey, run during November and December 2012, garnered participation from more than 600 global
executives and managers responsible for the planning and utilization of human resources to deliver services, projects, and/or products
for their organizations.

B. Use of the Report
Please contact market@planview.com for all inquiries, comments, and permissions to use portions of the report in the public domain.

C. Study Objectives
The study was conducted to deepen the understanding of the state of resource management and capacity planning at large, complex,
project-based companies and organizations. Executives at these organizations have expressed, through a variety of adjacent surveys
and studies that “having too many projects for their resources” is their number one pain point, leading to concerns about maximizing the
productivity of their most scarce resource: people.
To date, there has not been a study this comprehensive on the subject – one that covers global organizations and spans various facets
of business. The objective of this survey was to delve into the disciplines of resource management and capacity planning and identify the
maturity level of these organizations; the top pain points specifically for these areas; causes, risks, and other aspects of people, process,
and technology. An additional goal was to understand the characteristics of the most mature, best performers in these areas and the best
practices that they recommend.

©2013 Planview, Inc.

13
HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES

RESEARCH REPORT

D. Study Participants and Methodology
The study started by conducting phone interviews with executives and managers of large, project-based organizations. This served to
develop the online survey conducted by Appleseed Partners and OpenSky Research. Participants were qualified as being part of their
organization’s resource management or capacity planning process.
Participants were asked which groups their resource management and capacity planning process covered; 281 participants from Product
Development were included in the more than 600 total participants. This Product Development View includes only those answers provided
by these 281 product development participants.
Note that not all questions were required and that respondent numbers are provided for all graphs. Because of this, the total number of
responses for any given question varies from the total number of survey respondents.
Participants shared their company or organization size by annual USD revenue. The breakdown is:
•	 > $5.1B: 24%
•	 $1.1B-$5B: 16%
•	 $500M-$1B: 16%
•	 < $500M: 25%
•	 Remainder do not know or do not report revenues
For full demographics, please download the Resource Management and Capacity Planning Benchmark Study 2013 at
Planview.com/RMCPBenchmarkStudy.

IX. The Maturity Matrix
This matrix was designed as an objective benchmarking tool for the survey; it can, however, be leveraged by any organization to identify
where it lies today, and uncover and address specific opportunities that can result in tangible benefits.

Capacity Planning Maturity Levels
Level 1-Basic

•	 Very limited understanding of capacity or demand
•	 No process for visibility

Level 2-Ad-hoc

•	 Visibility is limited and relies on ad-hoc processes
•	 Not feasible to consolidate resource visibility across the groups/projects

Level 3-Limited

•	 High-level visibility of how staff and contract resources align with demand
•	 Not a complete or repeatable process

Level 4-Managed

•	 Effective planning process with visibility of role-level demand before work is committed
•	 Can balance organization-wide capacity against prioritized pipeline
•	 Still difficult to adapt to changes and reprioritize

Level 5-Optimized

•	 Planning is continually monitored based on up-to-date capacity and demand data
•	 Can run scenarios to manage change and prioritization
•	 Can apply most valuable resources to the highest-value projects

©2013 Planview, Inc.

14
HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES

RESEARCH REPORT

Resource Management Maturity Levels
Level 1-Basic

•	 Unable to view workload and activities from a resource perspective
•	 Basic understanding of how resources are grouped by role (i.e., engineer, analyst)
•	 Assignments are made verbally, and resources are often overbooked or idle. No data to show
resources’ start/end dates, committed, etc.

Level 2-Ad-hoc

•	 Track high-level deliverables or key milestones against a project
•	 Informally coordinate availability and assignment mostly by generic role, process is manual

Level 3-Limited

•	 Project- or phase-level named resource assignment and simple role-based planning
•	 Visibility into the projects each person is working on/percent time allocated, no roll-off dates
•	 Actual time completed captured, little on upcoming assignments

Level 4-Managed

•	 Detailed project schedules with short-term named resource assignments
•	 Resource requests are at the role level
•	 Resource assignments are made at a task level for better visibility
•	 Global resource visibility, but difficult to adapt to changes and reprioritize
•	 Ability to select from low-cost resource pools/offshore resources

Level 5-Optimized

•	 Mature work and activity planning process. Detailed, task-level schedules, cost information
•	 Formal process to request and approve resources by role and skill, short/long term
•	 Adapt to change and iterate effectively
•	 Project managers ensure that resource assignments on projects are current and accurate,
resources can provide feedback

X. About the Chief Researcher
Maureen Carlson is a partner at Appleseed Partners, an independent marketing consulting and research firm. Maureen has 20 years
of experience in high technology, business-to-business marketing, research, and consulting. She has focused on product marketing for
hardware, software, and professional services and has deep experience across various market segments including Manufacturing and
Healthcare. She is the researcher and author of three benchmark studies with Planview focused on Product Portfolio Management.
Follow Maureen on Twitter: @mocarlson.

XI. About Planview
This report was sponsored by Planview, a maker and provider of product and resource portfolio management software with hundreds
of global enterprise customers. Known for its singular focus on portfolio management and its customer-centric culture, the company’s
comprehensive solutions successfully manage a wide range of portfolios spanning product development, IT, services, and corporate
finance. The result is an enterprise-wide view of resources against demand. Learn more about Planview at Planview.com.
Carlson, M. (2013). Resource Management and Capacity Planning Benchmark Study.
For more than 20 years, Planview has been advancing the discipline of portfolio management, helping our customers change the way they manage people and money to make better
business decisions. With a singular focus on portfolio management, Planview is the only company that combines customer-driven software, unmatched domain expertise, and proven best
practices to solve each customer’s unique business problems. For more information, visit www.planview.com.
© 2013 Planview, Inc. All rights reserved. All trademarks acknowledged.

WWW.PLANVIEW.COM | MARKET@PLANVIEW.COM | 800.856.8600 | +1.512.346.8600 |

Contenu connexe

Tendances

PrinciplesBasedApprochtoCPM
PrinciplesBasedApprochtoCPMPrinciplesBasedApprochtoCPM
PrinciplesBasedApprochtoCPMJoseph Alenchery
 
Scenario planning: addressing a capability gap affecting industry competitive...
Scenario planning: addressing a capability gap affecting industry competitive...Scenario planning: addressing a capability gap affecting industry competitive...
Scenario planning: addressing a capability gap affecting industry competitive...Charles Edwards
 
Strategy as Transformation
Strategy as TransformationStrategy as Transformation
Strategy as TransformationSharon Johnson
 
Pan europa foods - Project Management
Pan europa foods - Project ManagementPan europa foods - Project Management
Pan europa foods - Project ManagementRobbi Palacios
 
Mc kinsey the eight essentials of innovation
Mc kinsey the eight essentials of innovationMc kinsey the eight essentials of innovation
Mc kinsey the eight essentials of innovationChien Do Van
 
Data Leadership talk for CIIA March 2022.pdf
Data Leadership talk for CIIA March 2022.pdfData Leadership talk for CIIA March 2022.pdf
Data Leadership talk for CIIA March 2022.pdfPaul Laughlin
 
Quiz1 otherQUIZ strategic management concepts &cases 11th edition by Fred R. ...
Quiz1 otherQUIZ strategic management concepts &cases 11th edition by Fred R. ...Quiz1 otherQUIZ strategic management concepts &cases 11th edition by Fred R. ...
Quiz1 otherQUIZ strategic management concepts &cases 11th edition by Fred R. ...حمد بوجرادة
 
Strategic review (Sample)
Strategic review (Sample)Strategic review (Sample)
Strategic review (Sample)guestbbb20c4
 
Effective Turnaround Strategy For Business Restructuring PowerPoint Presentat...
Effective Turnaround Strategy For Business Restructuring PowerPoint Presentat...Effective Turnaround Strategy For Business Restructuring PowerPoint Presentat...
Effective Turnaround Strategy For Business Restructuring PowerPoint Presentat...SlideTeam
 
EffectiveFinancialForecasting
EffectiveFinancialForecastingEffectiveFinancialForecasting
EffectiveFinancialForecastingNeerajSinghal
 
The Alignment Health Check™ Value Proposition (V.2)
The Alignment  Health Check™   Value Proposition (V.2)The Alignment  Health Check™   Value Proposition (V.2)
The Alignment Health Check™ Value Proposition (V.2)Dragica Grbavac
 
Gaining Competitive advantage through Knowledge process outsourcing
Gaining Competitive advantage through Knowledge process outsourcing Gaining Competitive advantage through Knowledge process outsourcing
Gaining Competitive advantage through Knowledge process outsourcing WNS Global Services
 
How to Write a SWOT Analysis Report
How to Write a SWOT Analysis ReportHow to Write a SWOT Analysis Report
How to Write a SWOT Analysis Reportcfdmaster
 

Tendances (20)

Trn 02
Trn 02Trn 02
Trn 02
 
PrinciplesBasedApprochtoCPM
PrinciplesBasedApprochtoCPMPrinciplesBasedApprochtoCPM
PrinciplesBasedApprochtoCPM
 
Change management white paper
Change management white paperChange management white paper
Change management white paper
 
Is Strategy
Is StrategyIs Strategy
Is Strategy
 
Scenario planning: addressing a capability gap affecting industry competitive...
Scenario planning: addressing a capability gap affecting industry competitive...Scenario planning: addressing a capability gap affecting industry competitive...
Scenario planning: addressing a capability gap affecting industry competitive...
 
Planning budgeting forecasting
Planning budgeting forecastingPlanning budgeting forecasting
Planning budgeting forecasting
 
Strategy as Transformation
Strategy as TransformationStrategy as Transformation
Strategy as Transformation
 
Pan europa foods - Project Management
Pan europa foods - Project ManagementPan europa foods - Project Management
Pan europa foods - Project Management
 
Mc kinsey the eight essentials of innovation
Mc kinsey the eight essentials of innovationMc kinsey the eight essentials of innovation
Mc kinsey the eight essentials of innovation
 
What your FP&A set up reveals
What your FP&A set up revealsWhat your FP&A set up reveals
What your FP&A set up reveals
 
Data Leadership talk for CIIA March 2022.pdf
Data Leadership talk for CIIA March 2022.pdfData Leadership talk for CIIA March 2022.pdf
Data Leadership talk for CIIA March 2022.pdf
 
Moving On Up
Moving On UpMoving On Up
Moving On Up
 
Quiz1 otherQUIZ strategic management concepts &cases 11th edition by Fred R. ...
Quiz1 otherQUIZ strategic management concepts &cases 11th edition by Fred R. ...Quiz1 otherQUIZ strategic management concepts &cases 11th edition by Fred R. ...
Quiz1 otherQUIZ strategic management concepts &cases 11th edition by Fred R. ...
 
Strategic review (Sample)
Strategic review (Sample)Strategic review (Sample)
Strategic review (Sample)
 
Effective Turnaround Strategy For Business Restructuring PowerPoint Presentat...
Effective Turnaround Strategy For Business Restructuring PowerPoint Presentat...Effective Turnaround Strategy For Business Restructuring PowerPoint Presentat...
Effective Turnaround Strategy For Business Restructuring PowerPoint Presentat...
 
EffectiveFinancialForecasting
EffectiveFinancialForecastingEffectiveFinancialForecasting
EffectiveFinancialForecasting
 
Strategy planning for small digital companies
Strategy planning for small digital companiesStrategy planning for small digital companies
Strategy planning for small digital companies
 
The Alignment Health Check™ Value Proposition (V.2)
The Alignment  Health Check™   Value Proposition (V.2)The Alignment  Health Check™   Value Proposition (V.2)
The Alignment Health Check™ Value Proposition (V.2)
 
Gaining Competitive advantage through Knowledge process outsourcing
Gaining Competitive advantage through Knowledge process outsourcing Gaining Competitive advantage through Knowledge process outsourcing
Gaining Competitive advantage through Knowledge process outsourcing
 
How to Write a SWOT Analysis Report
How to Write a SWOT Analysis ReportHow to Write a SWOT Analysis Report
How to Write a SWOT Analysis Report
 

En vedette

Silicon scanners cambridge report
Silicon scanners cambridge reportSilicon scanners cambridge report
Silicon scanners cambridge reportLiberteks
 
Sharingeconomyforslideshare 130428073944-phpapp02
Sharingeconomyforslideshare 130428073944-phpapp02Sharingeconomyforslideshare 130428073944-phpapp02
Sharingeconomyforslideshare 130428073944-phpapp02Liberteks
 
Facebook marketing seminar 45
Facebook marketing seminar 45Facebook marketing seminar 45
Facebook marketing seminar 45Liberteks
 
Kco resource management smalbany
Kco resource management   smalbanyKco resource management   smalbany
Kco resource management smalbanyLiberteks
 
Dk 45 presentation seo soc 2012
Dk 45 presentation seo soc 2012Dk 45 presentation seo soc 2012
Dk 45 presentation seo soc 2012Liberteks
 
smAlbany july 17 2014 work life balance b4b innovation suny cnse suny it
smAlbany july 17 2014 work life balance b4b innovation suny cnse suny itsmAlbany july 17 2014 work life balance b4b innovation suny cnse suny it
smAlbany july 17 2014 work life balance b4b innovation suny cnse suny itLiberteks
 
Digital-skills-gap-whitepaper
Digital-skills-gap-whitepaperDigital-skills-gap-whitepaper
Digital-skills-gap-whitepaperLiberteks
 
Cit, p&s, sm albany you are your brand - 071712
Cit, p&s, sm albany   you are your brand - 071712Cit, p&s, sm albany   you are your brand - 071712
Cit, p&s, sm albany you are your brand - 071712Liberteks
 

En vedette (8)

Silicon scanners cambridge report
Silicon scanners cambridge reportSilicon scanners cambridge report
Silicon scanners cambridge report
 
Sharingeconomyforslideshare 130428073944-phpapp02
Sharingeconomyforslideshare 130428073944-phpapp02Sharingeconomyforslideshare 130428073944-phpapp02
Sharingeconomyforslideshare 130428073944-phpapp02
 
Facebook marketing seminar 45
Facebook marketing seminar 45Facebook marketing seminar 45
Facebook marketing seminar 45
 
Kco resource management smalbany
Kco resource management   smalbanyKco resource management   smalbany
Kco resource management smalbany
 
Dk 45 presentation seo soc 2012
Dk 45 presentation seo soc 2012Dk 45 presentation seo soc 2012
Dk 45 presentation seo soc 2012
 
smAlbany july 17 2014 work life balance b4b innovation suny cnse suny it
smAlbany july 17 2014 work life balance b4b innovation suny cnse suny itsmAlbany july 17 2014 work life balance b4b innovation suny cnse suny it
smAlbany july 17 2014 work life balance b4b innovation suny cnse suny it
 
Digital-skills-gap-whitepaper
Digital-skills-gap-whitepaperDigital-skills-gap-whitepaper
Digital-skills-gap-whitepaper
 
Cit, p&s, sm albany you are your brand - 071712
Cit, p&s, sm albany   you are your brand - 071712Cit, p&s, sm albany   you are your brand - 071712
Cit, p&s, sm albany you are your brand - 071712
 

Similaire à How to Improve Time to Market w Existing Resources

Insights and Trends: Current Portfolio, Programme, and Project Management ...
Insights and Trends:  Current Portfolio,  Programme, and Project  Management ...Insights and Trends:  Current Portfolio,  Programme, and Project  Management ...
Insights and Trends: Current Portfolio, Programme, and Project Management ...CollectiveKnowledge
 
Corporate Sustainability Strategy Plan
Corporate Sustainability Strategy PlanCorporate Sustainability Strategy Plan
Corporate Sustainability Strategy PlanJOSE ANTONIO CHAVES
 
Vardarajan 20sethuraman-131008015800-phpapp02
Vardarajan 20sethuraman-131008015800-phpapp02Vardarajan 20sethuraman-131008015800-phpapp02
Vardarajan 20sethuraman-131008015800-phpapp02PMI_IREP_TP
 
Vardarajan sethuraman
Vardarajan sethuramanVardarajan sethuraman
Vardarajan sethuramanPMI2011
 
Productivity improvement through right governance
Productivity improvement through right governanceProductivity improvement through right governance
Productivity improvement through right governanceChandan Patary
 
Ikea Management Analysis
Ikea Management AnalysisIkea Management Analysis
Ikea Management AnalysisJen Cloud
 
S-OP 5 Steps to Success Logility.pdf
S-OP 5 Steps to Success Logility.pdfS-OP 5 Steps to Success Logility.pdf
S-OP 5 Steps to Success Logility.pdfintern9
 
Hackathon report final
Hackathon report finalHackathon report final
Hackathon report finalSheel Majumdar
 
Advanced Sourcing Maximizing Savings Identification
Advanced Sourcing Maximizing Savings IdentificationAdvanced Sourcing Maximizing Savings Identification
Advanced Sourcing Maximizing Savings IdentificationConstantine Limberakis
 
Mastering Finance in Business
Mastering Finance in BusinessMastering Finance in Business
Mastering Finance in BusinessMelih ÖZCANLI
 
T-Lessons_from_the_Trenches-_quality_digest_article
T-Lessons_from_the_Trenches-_quality_digest_articleT-Lessons_from_the_Trenches-_quality_digest_article
T-Lessons_from_the_Trenches-_quality_digest_articleDerrell James
 
The Business Strategy Of Mazzella Companies
The Business Strategy Of Mazzella CompaniesThe Business Strategy Of Mazzella Companies
The Business Strategy Of Mazzella CompaniesAshley Davis
 
MIS 04 Management of Business
MIS 04  Management of BusinessMIS 04  Management of Business
MIS 04 Management of BusinessTushar B Kute
 
Achieving business agility_by_restructuring_the_organization
Achieving business agility_by_restructuring_the_organizationAchieving business agility_by_restructuring_the_organization
Achieving business agility_by_restructuring_the_organizationChandan Patary
 
Effective New Product Development
Effective New Product DevelopmentEffective New Product Development
Effective New Product DevelopmentHeather Rice
 
8 Ways a Quick Assessment Can Propel Your Company's Growth | The Enterprise ...
8 Ways a Quick Assessment Can Propel Your Company's Growth |  The Enterprise ...8 Ways a Quick Assessment Can Propel Your Company's Growth |  The Enterprise ...
8 Ways a Quick Assessment Can Propel Your Company's Growth | The Enterprise ...TEWMAGAZINE
 
Apply Strategic Plan EvaluationRefer back to the Week 2 compa.docx
Apply Strategic Plan EvaluationRefer back to the Week 2 compa.docxApply Strategic Plan EvaluationRefer back to the Week 2 compa.docx
Apply Strategic Plan EvaluationRefer back to the Week 2 compa.docxjewisonantone
 
Web-Project-Management-Best-Practice-Guidelines
Web-Project-Management-Best-Practice-GuidelinesWeb-Project-Management-Best-Practice-Guidelines
Web-Project-Management-Best-Practice-GuidelinesVu Nam Hung
 

Similaire à How to Improve Time to Market w Existing Resources (20)

Insights and Trends: Current Portfolio, Programme, and Project Management ...
Insights and Trends:  Current Portfolio,  Programme, and Project  Management ...Insights and Trends:  Current Portfolio,  Programme, and Project  Management ...
Insights and Trends: Current Portfolio, Programme, and Project Management ...
 
Corporate Sustainability Strategy Plan
Corporate Sustainability Strategy PlanCorporate Sustainability Strategy Plan
Corporate Sustainability Strategy Plan
 
Business architecture case studies
Business architecture case studiesBusiness architecture case studies
Business architecture case studies
 
Vardarajan 20sethuraman-131008015800-phpapp02
Vardarajan 20sethuraman-131008015800-phpapp02Vardarajan 20sethuraman-131008015800-phpapp02
Vardarajan 20sethuraman-131008015800-phpapp02
 
Vardarajan sethuraman
Vardarajan sethuramanVardarajan sethuraman
Vardarajan sethuraman
 
Productivity improvement through right governance
Productivity improvement through right governanceProductivity improvement through right governance
Productivity improvement through right governance
 
Ikea Management Analysis
Ikea Management AnalysisIkea Management Analysis
Ikea Management Analysis
 
S-OP 5 Steps to Success Logility.pdf
S-OP 5 Steps to Success Logility.pdfS-OP 5 Steps to Success Logility.pdf
S-OP 5 Steps to Success Logility.pdf
 
ETCA_7
ETCA_7ETCA_7
ETCA_7
 
Hackathon report final
Hackathon report finalHackathon report final
Hackathon report final
 
Advanced Sourcing Maximizing Savings Identification
Advanced Sourcing Maximizing Savings IdentificationAdvanced Sourcing Maximizing Savings Identification
Advanced Sourcing Maximizing Savings Identification
 
Mastering Finance in Business
Mastering Finance in BusinessMastering Finance in Business
Mastering Finance in Business
 
T-Lessons_from_the_Trenches-_quality_digest_article
T-Lessons_from_the_Trenches-_quality_digest_articleT-Lessons_from_the_Trenches-_quality_digest_article
T-Lessons_from_the_Trenches-_quality_digest_article
 
The Business Strategy Of Mazzella Companies
The Business Strategy Of Mazzella CompaniesThe Business Strategy Of Mazzella Companies
The Business Strategy Of Mazzella Companies
 
MIS 04 Management of Business
MIS 04  Management of BusinessMIS 04  Management of Business
MIS 04 Management of Business
 
Achieving business agility_by_restructuring_the_organization
Achieving business agility_by_restructuring_the_organizationAchieving business agility_by_restructuring_the_organization
Achieving business agility_by_restructuring_the_organization
 
Effective New Product Development
Effective New Product DevelopmentEffective New Product Development
Effective New Product Development
 
8 Ways a Quick Assessment Can Propel Your Company's Growth | The Enterprise ...
8 Ways a Quick Assessment Can Propel Your Company's Growth |  The Enterprise ...8 Ways a Quick Assessment Can Propel Your Company's Growth |  The Enterprise ...
8 Ways a Quick Assessment Can Propel Your Company's Growth | The Enterprise ...
 
Apply Strategic Plan EvaluationRefer back to the Week 2 compa.docx
Apply Strategic Plan EvaluationRefer back to the Week 2 compa.docxApply Strategic Plan EvaluationRefer back to the Week 2 compa.docx
Apply Strategic Plan EvaluationRefer back to the Week 2 compa.docx
 
Web-Project-Management-Best-Practice-Guidelines
Web-Project-Management-Best-Practice-GuidelinesWeb-Project-Management-Best-Practice-Guidelines
Web-Project-Management-Best-Practice-Guidelines
 

Plus de Liberteks

Testing SAP Solutions for Dummies
Testing SAP Solutions for DummiesTesting SAP Solutions for Dummies
Testing SAP Solutions for DummiesLiberteks
 
System Engineering for Dummies
System Engineering for DummiesSystem Engineering for Dummies
System Engineering for DummiesLiberteks
 
Sales and use tax compliance for dummies
Sales and use tax compliance for dummiesSales and use tax compliance for dummies
Sales and use tax compliance for dummiesLiberteks
 
QuestionPro for dummies
QuestionPro for dummiesQuestionPro for dummies
QuestionPro for dummiesLiberteks
 
IT Policy Compliance for Dummies
IT Policy Compliance for DummiesIT Policy Compliance for Dummies
IT Policy Compliance for DummiesLiberteks
 
Point -of-Sale Security for Dummies
Point -of-Sale Security for DummiesPoint -of-Sale Security for Dummies
Point -of-Sale Security for DummiesLiberteks
 
Midmarket Collaboration for Dummies
Midmarket Collaboration for DummiesMidmarket Collaboration for Dummies
Midmarket Collaboration for DummiesLiberteks
 
Email Signatures for Dummies
Email Signatures for DummiesEmail Signatures for Dummies
Email Signatures for DummiesLiberteks
 
Custom Publishing for Dummies
Custom Publishing for DummiesCustom Publishing for Dummies
Custom Publishing for DummiesLiberteks
 
Cloud Service for Dummies
Cloud Service for DummiesCloud Service for Dummies
Cloud Service for DummiesLiberteks
 
B2B Online Display Advertising for Dummies
B2B Online Display Advertising for DummiesB2B Online Display Advertising for Dummies
B2B Online Display Advertising for DummiesLiberteks
 
APIs for dummies
APIs for dummiesAPIs for dummies
APIs for dummiesLiberteks
 
Website Threats for Dummies
Website Threats for DummiesWebsite Threats for Dummies
Website Threats for DummiesLiberteks
 
Software-Defined WAM for Dummies
Software-Defined WAM for DummiesSoftware-Defined WAM for Dummies
Software-Defined WAM for DummiesLiberteks
 
Vulnerability Management for Dummies
Vulnerability Management for DummiesVulnerability Management for Dummies
Vulnerability Management for DummiesLiberteks
 
Integrated Marketing For Dummies
Integrated Marketing For DummiesIntegrated Marketing For Dummies
Integrated Marketing For DummiesLiberteks
 
Hyper-Converged Appliances for Dummies
Hyper-Converged Appliances for DummiesHyper-Converged Appliances for Dummies
Hyper-Converged Appliances for DummiesLiberteks
 
Flash Array Deployment for Dummies
Flash Array Deployment for DummiesFlash Array Deployment for Dummies
Flash Array Deployment for DummiesLiberteks
 
Container Storage for Dummies
Container Storage for DummiesContainer Storage for Dummies
Container Storage for DummiesLiberteks
 
Cloud Security for Dumies
Cloud Security for DumiesCloud Security for Dumies
Cloud Security for DumiesLiberteks
 

Plus de Liberteks (20)

Testing SAP Solutions for Dummies
Testing SAP Solutions for DummiesTesting SAP Solutions for Dummies
Testing SAP Solutions for Dummies
 
System Engineering for Dummies
System Engineering for DummiesSystem Engineering for Dummies
System Engineering for Dummies
 
Sales and use tax compliance for dummies
Sales and use tax compliance for dummiesSales and use tax compliance for dummies
Sales and use tax compliance for dummies
 
QuestionPro for dummies
QuestionPro for dummiesQuestionPro for dummies
QuestionPro for dummies
 
IT Policy Compliance for Dummies
IT Policy Compliance for DummiesIT Policy Compliance for Dummies
IT Policy Compliance for Dummies
 
Point -of-Sale Security for Dummies
Point -of-Sale Security for DummiesPoint -of-Sale Security for Dummies
Point -of-Sale Security for Dummies
 
Midmarket Collaboration for Dummies
Midmarket Collaboration for DummiesMidmarket Collaboration for Dummies
Midmarket Collaboration for Dummies
 
Email Signatures for Dummies
Email Signatures for DummiesEmail Signatures for Dummies
Email Signatures for Dummies
 
Custom Publishing for Dummies
Custom Publishing for DummiesCustom Publishing for Dummies
Custom Publishing for Dummies
 
Cloud Service for Dummies
Cloud Service for DummiesCloud Service for Dummies
Cloud Service for Dummies
 
B2B Online Display Advertising for Dummies
B2B Online Display Advertising for DummiesB2B Online Display Advertising for Dummies
B2B Online Display Advertising for Dummies
 
APIs for dummies
APIs for dummiesAPIs for dummies
APIs for dummies
 
Website Threats for Dummies
Website Threats for DummiesWebsite Threats for Dummies
Website Threats for Dummies
 
Software-Defined WAM for Dummies
Software-Defined WAM for DummiesSoftware-Defined WAM for Dummies
Software-Defined WAM for Dummies
 
Vulnerability Management for Dummies
Vulnerability Management for DummiesVulnerability Management for Dummies
Vulnerability Management for Dummies
 
Integrated Marketing For Dummies
Integrated Marketing For DummiesIntegrated Marketing For Dummies
Integrated Marketing For Dummies
 
Hyper-Converged Appliances for Dummies
Hyper-Converged Appliances for DummiesHyper-Converged Appliances for Dummies
Hyper-Converged Appliances for Dummies
 
Flash Array Deployment for Dummies
Flash Array Deployment for DummiesFlash Array Deployment for Dummies
Flash Array Deployment for Dummies
 
Container Storage for Dummies
Container Storage for DummiesContainer Storage for Dummies
Container Storage for Dummies
 
Cloud Security for Dumies
Cloud Security for DumiesCloud Security for Dumies
Cloud Security for Dumies
 

Dernier

PDT 88 - 4 million seed - Seed - Protecto.pdf
PDT 88 - 4 million seed - Seed - Protecto.pdfPDT 88 - 4 million seed - Seed - Protecto.pdf
PDT 88 - 4 million seed - Seed - Protecto.pdfHajeJanKamps
 
Plano de marketing- inglês em formato ppt
Plano de marketing- inglês  em formato pptPlano de marketing- inglês  em formato ppt
Plano de marketing- inglês em formato pptElizangelaSoaresdaCo
 
UNLEASHING THE POWER OF PROGRAMMATIC ADVERTISING
UNLEASHING THE POWER OF PROGRAMMATIC ADVERTISINGUNLEASHING THE POWER OF PROGRAMMATIC ADVERTISING
UNLEASHING THE POWER OF PROGRAMMATIC ADVERTISINGlokeshwarmaha
 
Fabric RFID Wristbands in Ireland for Events and Festivals
Fabric RFID Wristbands in Ireland for Events and FestivalsFabric RFID Wristbands in Ireland for Events and Festivals
Fabric RFID Wristbands in Ireland for Events and FestivalsWristbands Ireland
 
To Create Your Own Wig Online To Create Your Own Wig Online
To Create Your Own Wig Online  To Create Your Own Wig OnlineTo Create Your Own Wig Online  To Create Your Own Wig Online
To Create Your Own Wig Online To Create Your Own Wig Onlinelng ths
 
BCE24 | Virtual Brand Ambassadors: Making Brands Personal - John Meulemans
BCE24 | Virtual Brand Ambassadors: Making Brands Personal - John MeulemansBCE24 | Virtual Brand Ambassadors: Making Brands Personal - John Meulemans
BCE24 | Virtual Brand Ambassadors: Making Brands Personal - John MeulemansBBPMedia1
 
Building Your Personal Brand on LinkedIn - Expert Planet- 2024
 Building Your Personal Brand on LinkedIn - Expert Planet-  2024 Building Your Personal Brand on LinkedIn - Expert Planet-  2024
Building Your Personal Brand on LinkedIn - Expert Planet- 2024Stephan Koning
 
Borderless Access - Global Panel book-unlock 2024
Borderless Access - Global Panel book-unlock 2024Borderless Access - Global Panel book-unlock 2024
Borderless Access - Global Panel book-unlock 2024Borderless Access
 
A flour, rice and Suji company in Jhang.
A flour, rice and Suji company in Jhang.A flour, rice and Suji company in Jhang.
A flour, rice and Suji company in Jhang.mcshagufta46
 
Project Brief & Information Architecture Report
Project Brief & Information Architecture ReportProject Brief & Information Architecture Report
Project Brief & Information Architecture Reportamberjiles31
 
Lecture_6.pptx English speaking easyb to
Lecture_6.pptx English speaking easyb toLecture_6.pptx English speaking easyb to
Lecture_6.pptx English speaking easyb toumarfarooquejamali32
 
Data skills for Agile Teams- Killing story points
Data skills for Agile Teams- Killing story pointsData skills for Agile Teams- Killing story points
Data skills for Agile Teams- Killing story pointsyasinnathani
 
Personal Brand Exploration Presentation Eric Bonilla
Personal Brand Exploration Presentation Eric BonillaPersonal Brand Exploration Presentation Eric Bonilla
Personal Brand Exploration Presentation Eric BonillaEricBonilla13
 
Introduction to The overview of GAAP LO 1-5.pptx
Introduction to The overview of GAAP LO 1-5.pptxIntroduction to The overview of GAAP LO 1-5.pptx
Introduction to The overview of GAAP LO 1-5.pptxJemalSeid25
 
Developing Coaching Skills: Mine, Yours, Ours
Developing Coaching Skills: Mine, Yours, OursDeveloping Coaching Skills: Mine, Yours, Ours
Developing Coaching Skills: Mine, Yours, OursKaiNexus
 
Borderless Access - Global B2B Panel book-unlock 2024
Borderless Access - Global B2B Panel book-unlock 2024Borderless Access - Global B2B Panel book-unlock 2024
Borderless Access - Global B2B Panel book-unlock 2024Borderless Access
 
Michael Vidyakin: Introduction to PMO (UA)
Michael Vidyakin: Introduction to PMO (UA)Michael Vidyakin: Introduction to PMO (UA)
Michael Vidyakin: Introduction to PMO (UA)Lviv Startup Club
 
ISONIKE Ltd Accreditation for the Conformity Assessment and Certification of ...
ISONIKE Ltd Accreditation for the Conformity Assessment and Certification of ...ISONIKE Ltd Accreditation for the Conformity Assessment and Certification of ...
ISONIKE Ltd Accreditation for the Conformity Assessment and Certification of ...ISONIKELtd
 
Amazon ppt.pptx Amazon about the company
Amazon ppt.pptx Amazon about the companyAmazon ppt.pptx Amazon about the company
Amazon ppt.pptx Amazon about the companyfashionfound007
 
7movierulz.uk
7movierulz.uk7movierulz.uk
7movierulz.ukaroemirsr
 

Dernier (20)

PDT 88 - 4 million seed - Seed - Protecto.pdf
PDT 88 - 4 million seed - Seed - Protecto.pdfPDT 88 - 4 million seed - Seed - Protecto.pdf
PDT 88 - 4 million seed - Seed - Protecto.pdf
 
Plano de marketing- inglês em formato ppt
Plano de marketing- inglês  em formato pptPlano de marketing- inglês  em formato ppt
Plano de marketing- inglês em formato ppt
 
UNLEASHING THE POWER OF PROGRAMMATIC ADVERTISING
UNLEASHING THE POWER OF PROGRAMMATIC ADVERTISINGUNLEASHING THE POWER OF PROGRAMMATIC ADVERTISING
UNLEASHING THE POWER OF PROGRAMMATIC ADVERTISING
 
Fabric RFID Wristbands in Ireland for Events and Festivals
Fabric RFID Wristbands in Ireland for Events and FestivalsFabric RFID Wristbands in Ireland for Events and Festivals
Fabric RFID Wristbands in Ireland for Events and Festivals
 
To Create Your Own Wig Online To Create Your Own Wig Online
To Create Your Own Wig Online  To Create Your Own Wig OnlineTo Create Your Own Wig Online  To Create Your Own Wig Online
To Create Your Own Wig Online To Create Your Own Wig Online
 
BCE24 | Virtual Brand Ambassadors: Making Brands Personal - John Meulemans
BCE24 | Virtual Brand Ambassadors: Making Brands Personal - John MeulemansBCE24 | Virtual Brand Ambassadors: Making Brands Personal - John Meulemans
BCE24 | Virtual Brand Ambassadors: Making Brands Personal - John Meulemans
 
Building Your Personal Brand on LinkedIn - Expert Planet- 2024
 Building Your Personal Brand on LinkedIn - Expert Planet-  2024 Building Your Personal Brand on LinkedIn - Expert Planet-  2024
Building Your Personal Brand on LinkedIn - Expert Planet- 2024
 
Borderless Access - Global Panel book-unlock 2024
Borderless Access - Global Panel book-unlock 2024Borderless Access - Global Panel book-unlock 2024
Borderless Access - Global Panel book-unlock 2024
 
A flour, rice and Suji company in Jhang.
A flour, rice and Suji company in Jhang.A flour, rice and Suji company in Jhang.
A flour, rice and Suji company in Jhang.
 
Project Brief & Information Architecture Report
Project Brief & Information Architecture ReportProject Brief & Information Architecture Report
Project Brief & Information Architecture Report
 
Lecture_6.pptx English speaking easyb to
Lecture_6.pptx English speaking easyb toLecture_6.pptx English speaking easyb to
Lecture_6.pptx English speaking easyb to
 
Data skills for Agile Teams- Killing story points
Data skills for Agile Teams- Killing story pointsData skills for Agile Teams- Killing story points
Data skills for Agile Teams- Killing story points
 
Personal Brand Exploration Presentation Eric Bonilla
Personal Brand Exploration Presentation Eric BonillaPersonal Brand Exploration Presentation Eric Bonilla
Personal Brand Exploration Presentation Eric Bonilla
 
Introduction to The overview of GAAP LO 1-5.pptx
Introduction to The overview of GAAP LO 1-5.pptxIntroduction to The overview of GAAP LO 1-5.pptx
Introduction to The overview of GAAP LO 1-5.pptx
 
Developing Coaching Skills: Mine, Yours, Ours
Developing Coaching Skills: Mine, Yours, OursDeveloping Coaching Skills: Mine, Yours, Ours
Developing Coaching Skills: Mine, Yours, Ours
 
Borderless Access - Global B2B Panel book-unlock 2024
Borderless Access - Global B2B Panel book-unlock 2024Borderless Access - Global B2B Panel book-unlock 2024
Borderless Access - Global B2B Panel book-unlock 2024
 
Michael Vidyakin: Introduction to PMO (UA)
Michael Vidyakin: Introduction to PMO (UA)Michael Vidyakin: Introduction to PMO (UA)
Michael Vidyakin: Introduction to PMO (UA)
 
ISONIKE Ltd Accreditation for the Conformity Assessment and Certification of ...
ISONIKE Ltd Accreditation for the Conformity Assessment and Certification of ...ISONIKE Ltd Accreditation for the Conformity Assessment and Certification of ...
ISONIKE Ltd Accreditation for the Conformity Assessment and Certification of ...
 
Amazon ppt.pptx Amazon about the company
Amazon ppt.pptx Amazon about the companyAmazon ppt.pptx Amazon about the company
Amazon ppt.pptx Amazon about the company
 
7movierulz.uk
7movierulz.uk7movierulz.uk
7movierulz.uk
 

How to Improve Time to Market w Existing Resources

  • 1. HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES The Product Development View of the Resource Management and Capacity Planning Benchmark Study Commissioned by Planview® conducted by Appleseed Partners and OpenSky Research ©2013 Planview, Inc.
  • 2. RESEARCH REPORT HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES Product development organizations face specific challenges when it comes to resource management and capacity planning. What’s at stake? In short, time to market targets and revenue. If product teams choose to embrace the status quo, they will not reap the benefits of change – optimized resources, stronger company bottom lines, better market share and brand awareness equity. Key findings of this Product Development View of the Resource Management and Capacity Planning Study include: • Pain: Lacking visibility into both capacity and incoming demand and the impact of constant change. • Business risk: Lost revenue and market share due to missed market windows, remaining in crisis mode, and resources wasted on the wrong projects and products. • Opportunity: Improve processes to increase resource management and capacity planning maturity; this can support goals such as reducing total cost of development, filling the pipeline with profitable products, and speeding time to market. This research report is an extension of the Resource Management and Capacity Planning Benchmark Study 2013, available at Planview.com/RMCPBenchmarkStudy. Containing product development specific charts and analysis not presented in the original benchmark report, this focused view speaks explicitly to product development organizations. Executive Summary This report reveals the state of resource management and capacity planning in product development organizations. It shows that within these groups, there is considerable room for growth – and many of them are very aware of the need, as well of the potential benefits. What stymies product development organizations is the how and the where: how to do it, where to start. More than 280 globally-based product development executives participated in the benchmark study1, sharing their top pain points, business risks, pain causes, software impacts, and process improvements relative to resource management and capacity planning. These executives were aware of what was at risk and spoke to their goals of improving time to market, reducing the total cost of development, and improving their ability to effectively prioritize winning ideas. They understood that not addressing resource management issues leads directly to problems, including a lack of visibility into demand and capacity resulting in ongoing chaos among their teams, missing market windows, and the inability to optimize both people and financial investments. It should not be construed, however, that the groups participating were homogeneous. Their problems varied, as indicated by their Resource Management and Capacity Planning Maturity Spectrum position on the Resource Management and Capacity Planning Maturity Spectrum (Figure 1). This spectrum allowed participants to identify their groups’ maturity on a five-tier grading system from 1-Basic (having very limited understanding of resources, capacity, and demand) to 5-Optimized (having up-to-date data). Reference section IX. Maturity Matrix for complete details. Roughly two-thirds of product organizations identified as low- to midlevel maturity; only a third labeled their organizations with a higher state of maturity, at which point they break through to a certain level of management control and optimization, and thus greater visibility. Figure 1. Maturity Spectrum 1 Carlson, M. (2013). Resource Management and Capacity Planning Benchmark Study. ©2013 Planview, Inc. 2
  • 3. HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES RESEARCH REPORT Key Findings The report shows several common threads of challenges such as constant change, inaccurate project estimation, and the inability to Capacity Planning Maturity Levels for Product Development complete projects on time. Slightly more organizations identified as more mature when it came to resource management than capacity planning (38% vs. 31%); there is significant opportunity for growth in the latter, which could help organizations prioritize more effectively and alleviate many of their pains (Figures 2 and 3). Improvements in resource management and capacity planning come down to three things: • Improved, consistently used processes • Commitment, follow-through, and executive support • The right enterprise software for the job Figure 2: Capacity Planning Maturity Levels Addressing these areas allows organizations to better align and connect products with their strategy; enables management to run critical what-if scenarios in the face of constant change; and ensures that scarce resources are leveraged wisely for the most competitive offerings and high value returns. The Six Characteristics of Mature Organizations As determined in the Resource Management and Capacity Planning Benchmark Study 2013, those organizations that excel at resource Resource Management Maturity Levels for Product Development management and capacity planning performance tend to: 1. Have insight into what people are working on, can identify bottlenecks, and run scenarios on-demand, to adapt to change 2. Meld top-down with bottom-up approaches to capacity planning and resource management 3. Have a dedicated function to lead resource management and capacity planning activities 4. Agree on these top three best practices: prioritization; what-if analysis; executive buy-in 5. Estimate projects well and have good supporting processes in place 6. Use Product Portfolio Management (PPM) software to optimize Figure 3: Resource Management Maturity Levels their resources ©2013 Planview, Inc. 3
  • 4. HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES RESEARCH REPORT Summary Product organizations face unique pressures, both from the outside and within. One of those internal pressures comes from the nonconformist view that process is the enemy of creativity and innovation, rather than its support structure. For those surveyed, no matter how mature their resource management and capacity planning performance, all said that their processes needed bolstering. Improving processes is in every product organizations’ best interest: it derisks the entire portfolio, helps drive down costs, builds efficiencies into projects, encourages innovation by enabling the prioritization of products and resources in line with strategy, and creates an environment that gets products to market faster. When the external world continues to make its presence known – more, now, better, faster – not hitting market windows is not an option, nor is not delivering quality products or hiring more resources to make it all happen. Something has to give. External pressures are going to continue to build. Resources are going to continue to be finite and scarce. Product groups must find better ways of dealing with these pressures, and a foundation based on consistent, enforced process is an excellent place to start. Embrace change: allow process and software to support the team and the company goals. Key Report Statistics Of those organizations surveyed: • More than 50% of lower maturity organizations perceive their greatest business risk is delayed time to market resulting in losses of revenue, savings, user/customer satisfaction, and/or market share; this reduces by more than 10% for higher maturity organizations • Nearly 70% of all organizations want streamlined and accurate resource and forecasting and planning to be the main result of improving resource management and capacity planning processes and using enterprise software • The top best practices recommended by higher maturity organizations are better prioritization and performing what-if analysis on capacity plans to determine the best use of resources and for risk mitigation ©2013 Planview, Inc. 4
  • 5. RESEARCH REPORT HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES Table of Contents Executive Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I. Product Development Maturity: Resource Management vs. Capacity Planning II. Organizational Plan . . . . . . . . . . . . . . . . . . . . 6 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 A. Pain Points Before and After Software B. Pain Causes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8 C. Pain Point Shifts by Maturity Level III. Expected Business Benefits . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 VI. Recommendations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . A. What Are Your Priorities? Get Your Process House In Order B. Change the Future with Historical Actuals 11 . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 C. Look at the Proof and Make the Business Investment in the Right Software VII. Next Steps 9 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . IV. Business Risks V. Best Practices 2 . . . . . . . . . . . . . . 12 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12 VIII. About the Product Development View of the Resource Management Capacity Planning Study . 13 A. About the Report . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13 B. Use of the Report . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13 C. Study Objectives D. Study Participants and Methodology IX. The Maturity Matrix . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14 X. About the Chief Researcher XI. About Planview ©2013 Planview, Inc. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15 5
  • 6. RESEARCH REPORT HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES I. Product Development Maturity: Resource Management vs. Capacity Planning In the benchmark study, participants were asked to identify their organizations’ maturity levels against a specially designed, objective matrix that allowed for the benchmarking of resource management and capacity planning performance. Please reference Section IX of this report to review this maturity spectrum in depth. While maturity levels in both capacity planning and resource management broke down fairly evenly into thirds, overall organizations Capacity Planning Maturity Levels for Product Development indicated a slightly higher maturity level in terms of resource management (Figure 2 and 3). The higher resource management maturity level is unsurprising. In product development organizations, there is essential ongoing or inflight tactical assignment of personnel to planned and unscheduled activities. The nature of capacity planning is more proactive and forward-looking. Capacity planning addresses the need to take human and non-human (e.g., production lines, patient beds) resource constraints into account in the sequencing and prioritization of products and projects during both the annual planning process and for gate approvals. Longer range capacity planning ensures the company has the facility to take on new ideas at the right time. Figure 2: Capacity Planning Maturity Levels Given the aforementioned continual interaction with resource management activity, it is surprising to note that nearly one third of survey respondents say that they are still at a Level 1-Basic or Level 2-Ad-Hoc stage of maturity in this area. Lower maturity here is characterized as chaotic, with virtually no visibility into demand or insight into what their resources are working on. The mid-tier Level 3-Limited maturity organizations gain visibility, but with that new insight, they ironically uncover or become more aware of a host of challenges to address for optimizing the productivity of their resources. Encouragingly, a third of organizations are breaking through to higher maturity. Level 4-Managed and Level 5-Optimized environments Resource Management Maturity Levels for Product Development benefit from greater control and true productivity optimization (but even these organizations said there’s room for improvement). When asked to identify best practices to help enable a breakthrough to higher maturity levels, these more mature product development organizations pointed to several that, for the more complex organization, are challenging if not impossible to achieve without a strong foundation of software, process, and executive support. With this foundation, however, mid- or lower-level maturity organizations can begin to build on the best practices to achieve a more complete picture of capacity and demand. Figure 3: Resource Management Maturity Levels “We’re good on the demand side but not the capacity side. Right now our project managers can’t see the availability, skill set, or number of weeks of effort; and the assumptions are not right. If the resource managers are not using the system to give the product managers visibility, even the best project plan can’t be properly resourced.” Senior Manager PMO, Large Insurance Company ©2013 Planview, Inc. 6
  • 7. RESEARCH REPORT HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES II. Organizational Plan A. Pain Points Before and After Software Before implementing enterprise software for resource management and capacity Pain Points Before and After Enterprise Software for Product Development planning, the top two pains points are clear: lack of visibility into capacity, followed swiftly by its twin, poor insight into demand. Equally apparent is the cascade of pain that follows from those two problems (Figure 4). Once supporting enterprise software is properly picture implemented, takes shape. an interesting As might be expected, several areas show significant improvement. Capacity and demand visibility are enhanced, as is reporting on demand, and the 6% improvement of resources completing projects on time can Figure 4. Pain Points Before and After Enterprise Software make a substantial difference in margins. How then to explain increased pains, post-implementation of software, in items such as constant change affecting assignments, ineffective demand prioritization, and challenges managing shared resources across projects (which affects a reported 80% of organizations surveyed)? While a few of the pain points appear to be more problematic after software adoption, there are a few factors to consider: • As referenced earlier in the Executive Summary of this report, while implementation of enterprise software is a key characteristic of mature companies, as indicated by the best practices they recommend, it’s not a silver bullet. Without the supporting processes and management mandate to ensure its consistent use by product, project, and resource managers, the software will not succeed in its goals. • It is often a case of “ignorance is bliss.” When software and process are leveraged effectively, an organization’s eyes are opened: the more it can see into incoming demand and the true state of its capacity, the more opportunities for improvement are revealed. • All enterprise software is not created equal. Are product organizations using the right software for the needs of resource management and capacity planning? Refer to section VI. Recommendations for more on this topic. “We are transitioning from having our own resources to sharing pooled resources. Our challenge is that some of the organization is doing resource management and capacity well, while other parts of the organization are just getting started. In a shared resource arrangement, more of the organization needs to be on board. Our biggest risk of not addressing resource management and capacity planning is time to market for our seasonal products.” Project Management Director, Large Consumer Products Company ©2013 Planview, Inc. 7
  • 8. RESEARCH REPORT HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES B. Pain Causes Process is the name of the game – and Product Development - Pain Causes by Maturity Level across the board, organizations appear to believe it’s the solution. For the more mature organizations, the top causes of pain points are challenges estimating for projects and lack of process maturity, closely followed by ineffective use of historical data (Figure 5). These causes are related. When process matures and is repeatable, and experiences, best practices, and lessons learned are stored in a centralized, accessible system, managers can acquire information from historical data Figure 5: Pain Causes by Maturity Level and improve high-level and detailed project estimates and deliver them more quickly and painlessly. Unfortunately for most, this information is siloed, residing in the heads of product and development managers or in desktop files. This is often the result of resources being so overloaded that they’re rushing to the next project, a lack of process adoption, or reliance on information that is non-standard without the right technology to store, search, and apply it. A minimally invasive process that is enforced and enabled across the organization can make a significant difference to improve vitally important data for resource and project estimation. Level 3-Limited maturity organizations, with their newfound visibility, have pinpointed some specific top issues to address – they also want to start with process, and then tackle project-estimating issues. Just like the most mature, they will greatly benefit from the efficiencies they gain, as well as project derisking. Lower-level maturity organizations, those in the Level 1 and Level 2 segments, have identified a good place to start addressing their problems: process and executive buy-in (their top pain causes). Best practices indicate that it is a powerful first step to leverage executive mandate to ensure that processes be improved and adopted across the enterprise to begin to resolve resource management and capacity planning issues. “Our recommendation is to understand the body of work and do time tracking on the work. To do estimates, you need a baseline. Try to do it without a tool and then show others how a tool can be beneficial. Then you need to figure out how to capture your demand. It doesn’t have to be perfect, just start somewhere.” Program Manager, Consumer Goods Product Company ©2013 Planview, Inc. 8
  • 9. RESEARCH REPORT HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES C. Pain Point Shifts by Maturity Level The most mature product development organizations (Level 4-Managed and Product Development Top Five Pain Points (after software) by Maturity Level Level 5-Optimized) place ineffective demand prioritization and constant change and its impact atop their list of top pains (Figure 6). Pains one and two are separated by two small percentage points. From there, it is quite a jump to the next smaller pain, that of underutilizing resources. Not to minimize this third concern, but with a difference of 15% between pains two and three, it is clear that these organizations have identified where it hurts – and on what they need to focus. Level 3-Limited organizations have identified the same pains as their higher-level brethren, although their emphasis on them is reversed. And the difference doesn’t end there. For these Figure 6. Top 5 Pain Points (after software) by Maturity Level teams, the pain of constant change that affects assignments and availability comes in at 49%, in and of itself a whopper, and a rather tremendous 19% ahead of its next closest competitor in the race for biggest pain (Figure 6). What to make of this lead, and why do nearly 50% of these organizations identify so fiercely with this challenge? One explanation is that they have some awareness of the demand in the product pipeline, understand to a fairly significant extent where their commitments already lie, and can essentially see where their resources are already allocated. The constant change of their environments becomes all the more unreasonable as they comprehend just how much opportunity is falling by the wayside, and how much room for improvement is still open to them. Those at maturity levels 1 and 2 are most challenged by an inability to see into their companies’ strategic goals, making prioritization challenging (Figure 6). Given that they operate in a highly chaotic, tactical state, this is unsurprising – as is their second-highest pain, which echoes from the other two groups, that of constant change and its impact. This group, however, sees its pains as more evenly distributed; all pains also bear higher percentage points across the board. For these organizations, everything hurts. “Our biggest risk is having different versions of the truth and schedule.” Senior Project Manager, Semiconductor Products Company ©2013 Planview, Inc. 9
  • 10. HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES RESEARCH REPORT III. Expected Business Benefits Study participants were asked what business benefits they believed their organizations addressing would recognize resource by What are the expected Business Benefits of addressing Resource Management and Capacity Planning with an improved process and enterprise software? (select 3) management and capacity planning with improved processes and the use of enterprise software. All participants, regardless of their organization’s maturity level, shared two key expectations: 1. Streamlined and accurate resource forecasting and planning 2. Improved project success and time to market Depending on their maturity level, they also wanted to improve visibility into what resources are working on; optimize the productivity of resources; or improve Figure 7. Expected Business Benefits with Improved Process and Enterprise Software visibility into capacity respectively as they move up the matrix (Figure 7). IV. Business Risks Connecting the dots between business risks and the impact they have is key for organizations looking to improve resource management and capacity What are the greatest Business Risks of not addressing Resource Management and Capacity Planning with an improved process and the use of enterpise software? (select all that apply) planning performance. What is the bottom line? Study participants indicated that by leveraging software and process correctly, they believed they would decrease the business risks of time to market, decision-making, alignment of resources, and reporting (Figure 8). Participants further felt that risk would decline by significant percentages (8–10%) in each of these key areas. What would it mean to reduce risk by 10% in time to market? What is the impact of inaction? Figure 8. Business Risks with no Improved Process and Enterprise Software ©2013 Planview, Inc. 10
  • 11. HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES RESEARCH REPORT V. Best Practices As alluded to earlier, when asked the top best practices for improving resource management and capacity planning, the most mature organizations recommended: • Better prioritization • Performing what-if analysis on capacity plans to determine the best use of resources and for risk mitigation • Establishing and communicating processes Organizations were also asked what type of approach they use for resource management and capacity planning: 1) bottom-up resource management on projects; 2) top-down capacity or full time equivalent (FTE) planning; or 3) a combination of the two. The most mature companies indicated they used a combined approach that gave everyone in the organization a shared responsibility for resource management and capacity planning, making this a strongly recommended best practice. The implementation of these practices could go a long way toward addressing the pain points identified by respondents. However, attempting to implement these practices without the right software, processes, and management support, especially in a resourcestrapped and/or project-heavy environment can be a thankless challenge that ends poorly or simply subsides. The organization seeking to use best practices to migrate up the maturity model matrix might well consider if it is not worth the time and money to put a stronger foundation in place to achieve the breakthrough it seeks. VI. Recommendations A. What Are Your Priorities? Get Your Process House In Order As has been seen throughout this report, organizations at all levels of maturity can benefit from improving their resource management and capacity planning process performance. Organizations at maturity levels 1–3 have a tremendous opportunity to move up the maturity scale when it comes to capacity planning in support of proper prioritization. It’s important to consider the capacity plan in context with demand. Everything is a top priority if it’s assumed there are enough resources to handle the work. Addressing capacity planning has a tremendous payoff, both for project prioritization and for good resource utilization practices. Those at maturity levels 4 and 5 still struggle with pain points such as an ineffective demand prioritization and governance process. To focus on continuous improvement and mature standard processes, use this report to benchmark where your product development team lies, and put a measureable, specific plan in place for both resource management (to address in-flight challenges) and capacity planning. This will help the executive team to prioritize, help product development to focus efforts on the most impactful products, and grow planning from a reactive 3–6 months to a proactive 1–2 years out. Think forward – this is where real strategic competitive differentiation, time to market improvements, and margin maximization take place. B. Change the Future with Historical Actuals Best practice dictates that your product portfolio should be a balance between breakthrough innovation and incremental innovation. Unfortunately, for many companies, line extension and product updates take as long as those breakthroughs. Luckily there are ample opportunities to deliver these small product changes to market faster, using less money and less people, and direct more resources toward game changers – and this is where leveraging historical actuals to estimate for the future can come to the rescue. How? Implement the capability to track historical actuals in terms of money, duration, and effort, and have a place to store it for future reference (that requires process and the right software). If it means more time reporting, then do it. When a project ends, ensure the data is correct and captured. Hold an honest post mortem. All these moments of data capture, small and large, turn into an incredible opportunity for cost savings and time to market improvement down the road, along with enabling future, accurate, and efficient project and resource estimation and better capacity planning. There is a reason many of the key pain causes – such as challenges estimating for projects; lack of process maturity; ineffective use of historical data – resonated across maturity levels. Not enough people take the time to capture how long things really take and what resources were really required because they are already on to the next thing. Start capturing the data and stop feeling the pain. ©2013 Planview, Inc. 11
  • 12. HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES RESEARCH REPORT C. Look at the Proof and Make the Business Investment in the Right Software In this report, organizations that invested in enterprise software are 27% better off in their visibility into capacity and 22% better off in visibility into demand. And the inability of resources to consistently complete products on time gets better by 6%, and that’s significant. Enterprise software is providing great dividends but there are still great prospects for improvement and a move up the maturity ladder to realize even greater business gains. Think about software from two perspectives: 1. Is it the right software? According to the study, many organizations are reporting that they use different types of enterprise software including Product Lifecycle Management (PLM) or Enterprise Resource Planning (ERP) and expect it to address resource management and capacity planning. Not so. While Product Portfolio Management (PPM) software can relieve the pain points identified in the survey, PLM and ERP are not going to effectively prioritize demand and improve the governance process; will not help to address the lack of visibility into a company’s strategic goals; nor will they help with capacity or demand. Not all enterprise software is designed to address the same problems. 2. Is it being used the right way? Many survey respondents check the box (“Yes, we have a PPM solution”) but they don’t use the full breadth of the software they purchased. PPM is not just about the application itself; it’s also about fostering the supporting processes. Organizations leveraging enterprise software to improve resource management and capacity planning performance should take the time to develop a big picture plan; maintain the stamina needed to execute; follow through; and ensure that leadership support is in place. They should not underestimate how much a strong, pragmatic leader is needed to see the plan through end-to-end so that the company can realize the business benefits that come from enterprise PPM software including reducing time to market, increasing revenue, and launching differentiated products. VII. Next Steps If you would like to learn more about more improving resource management and capacity planning, take advantage of the following resources: • Download the whitepaper Ten Proven Military Strategies for Better Resource Planning: Avoiding Custer’s Last Stand. Nowhere is there a richer source of strategies and tactics for how to apply limited human resources than in military history. With that in mind, we invite you to read this whitepaper from top-selling author Jerry Manas, which explores 10 timeless military strategies – tried and tested over thousands of years – that can be effectively applied toward modern day resource planning. Download the paper at Planview.com/TenProvenMilitaryStrategies. • View this On-Demand Webcast: How Technology-Enabled Visibility Lets You Prioritize Products and Optimize Resources to discover how you can deliver the visibility needed to make effective, informed, and timely decisions with confidence regarding your product pipeline. Through the use of PPM technology, organizations can optimize their limited people and financial resources to achieve their product delivery objectives. Featuring Frost & Sullivan, Isabel SA, and Planview. Access the webcast on demand at Planview.com/PrioritizeProductsandOptimizeResourcesWebcast. • Read Issue in Focus: Meeting Fixed Product Launch Windows, Managing Portfolios When Time to Market is Non-Negotiable. In this research report, Jim Brown, president of Tech-Clarity, addresses the critical nature of hitting launch windows and provides insight from successful companies as well as tips for improving the odds of success. Gain vision into: ◦◦ Challenges impeding time to market ◦◦ Starting with the right ideas ◦◦ Ways to derisk your process ◦◦ Effective execution with a PPM solution Download your copy at Planview.com/LaunchWindowsWhitepaper. ©2013 Planview, Inc. 12
  • 13. HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES RESEARCH REPORT • Access The 3rd Product Portfolio Management Benchmark Study. In 2012, 320 product development executives and managers participated in the online survey on the state of product portfolio management, conducted by Appleseed Partners and OpenSky Research, and sponsored by Planview. Here are just a few of the many illuminating stats gathered from respondents: ◦◦ 68% indicate they have too many projects for their resources ◦◦ 90% rely on informal ways to integrate the customer voice into the product development process ◦◦ 55% indicate they are not able to measure the cost of a product launch delay While the report reveals trends across the past three surveys, an overriding theme of this study is the need to innovate smarter and harder. In addition to insightful statistics and informative data on the state of product portfolio management, the report provides thought-provoking recommendations for all product development organizations. Download the full report at Planview.com/ThirdPPMBenchmarkStudy. VIII. About the Product Development View of the Resource Management Capacity Planning Study A. About the Report This report is an extension of the Resource Management and Capacity Planning Benchmark Study 2013, available at Planview.com/RMCPBenchmarkStudy. Containing product development specific charts and analysis not presented in the original report, this report speaks explicitly to product development organizations. To develop the research on which both the original study and this report are based, Appleseed Partners and OpenSky Research, commissioned by Planview, conducted the first in-depth benchmark study on the state of resource management and capacity planning at project-based organizations. The survey, run during November and December 2012, garnered participation from more than 600 global executives and managers responsible for the planning and utilization of human resources to deliver services, projects, and/or products for their organizations. B. Use of the Report Please contact market@planview.com for all inquiries, comments, and permissions to use portions of the report in the public domain. C. Study Objectives The study was conducted to deepen the understanding of the state of resource management and capacity planning at large, complex, project-based companies and organizations. Executives at these organizations have expressed, through a variety of adjacent surveys and studies that “having too many projects for their resources” is their number one pain point, leading to concerns about maximizing the productivity of their most scarce resource: people. To date, there has not been a study this comprehensive on the subject – one that covers global organizations and spans various facets of business. The objective of this survey was to delve into the disciplines of resource management and capacity planning and identify the maturity level of these organizations; the top pain points specifically for these areas; causes, risks, and other aspects of people, process, and technology. An additional goal was to understand the characteristics of the most mature, best performers in these areas and the best practices that they recommend. ©2013 Planview, Inc. 13
  • 14. HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES RESEARCH REPORT D. Study Participants and Methodology The study started by conducting phone interviews with executives and managers of large, project-based organizations. This served to develop the online survey conducted by Appleseed Partners and OpenSky Research. Participants were qualified as being part of their organization’s resource management or capacity planning process. Participants were asked which groups their resource management and capacity planning process covered; 281 participants from Product Development were included in the more than 600 total participants. This Product Development View includes only those answers provided by these 281 product development participants. Note that not all questions were required and that respondent numbers are provided for all graphs. Because of this, the total number of responses for any given question varies from the total number of survey respondents. Participants shared their company or organization size by annual USD revenue. The breakdown is: • > $5.1B: 24% • $1.1B-$5B: 16% • $500M-$1B: 16% • < $500M: 25% • Remainder do not know or do not report revenues For full demographics, please download the Resource Management and Capacity Planning Benchmark Study 2013 at Planview.com/RMCPBenchmarkStudy. IX. The Maturity Matrix This matrix was designed as an objective benchmarking tool for the survey; it can, however, be leveraged by any organization to identify where it lies today, and uncover and address specific opportunities that can result in tangible benefits. Capacity Planning Maturity Levels Level 1-Basic • Very limited understanding of capacity or demand • No process for visibility Level 2-Ad-hoc • Visibility is limited and relies on ad-hoc processes • Not feasible to consolidate resource visibility across the groups/projects Level 3-Limited • High-level visibility of how staff and contract resources align with demand • Not a complete or repeatable process Level 4-Managed • Effective planning process with visibility of role-level demand before work is committed • Can balance organization-wide capacity against prioritized pipeline • Still difficult to adapt to changes and reprioritize Level 5-Optimized • Planning is continually monitored based on up-to-date capacity and demand data • Can run scenarios to manage change and prioritization • Can apply most valuable resources to the highest-value projects ©2013 Planview, Inc. 14
  • 15. HOW TO IMPROVE TIME TO MARKET WITH EXISTING RESOURCES RESEARCH REPORT Resource Management Maturity Levels Level 1-Basic • Unable to view workload and activities from a resource perspective • Basic understanding of how resources are grouped by role (i.e., engineer, analyst) • Assignments are made verbally, and resources are often overbooked or idle. No data to show resources’ start/end dates, committed, etc. Level 2-Ad-hoc • Track high-level deliverables or key milestones against a project • Informally coordinate availability and assignment mostly by generic role, process is manual Level 3-Limited • Project- or phase-level named resource assignment and simple role-based planning • Visibility into the projects each person is working on/percent time allocated, no roll-off dates • Actual time completed captured, little on upcoming assignments Level 4-Managed • Detailed project schedules with short-term named resource assignments • Resource requests are at the role level • Resource assignments are made at a task level for better visibility • Global resource visibility, but difficult to adapt to changes and reprioritize • Ability to select from low-cost resource pools/offshore resources Level 5-Optimized • Mature work and activity planning process. Detailed, task-level schedules, cost information • Formal process to request and approve resources by role and skill, short/long term • Adapt to change and iterate effectively • Project managers ensure that resource assignments on projects are current and accurate, resources can provide feedback X. About the Chief Researcher Maureen Carlson is a partner at Appleseed Partners, an independent marketing consulting and research firm. Maureen has 20 years of experience in high technology, business-to-business marketing, research, and consulting. She has focused on product marketing for hardware, software, and professional services and has deep experience across various market segments including Manufacturing and Healthcare. She is the researcher and author of three benchmark studies with Planview focused on Product Portfolio Management. Follow Maureen on Twitter: @mocarlson. XI. About Planview This report was sponsored by Planview, a maker and provider of product and resource portfolio management software with hundreds of global enterprise customers. Known for its singular focus on portfolio management and its customer-centric culture, the company’s comprehensive solutions successfully manage a wide range of portfolios spanning product development, IT, services, and corporate finance. The result is an enterprise-wide view of resources against demand. Learn more about Planview at Planview.com. Carlson, M. (2013). Resource Management and Capacity Planning Benchmark Study. For more than 20 years, Planview has been advancing the discipline of portfolio management, helping our customers change the way they manage people and money to make better business decisions. With a singular focus on portfolio management, Planview is the only company that combines customer-driven software, unmatched domain expertise, and proven best practices to solve each customer’s unique business problems. For more information, visit www.planview.com. © 2013 Planview, Inc. All rights reserved. All trademarks acknowledged. WWW.PLANVIEW.COM | MARKET@PLANVIEW.COM | 800.856.8600 | +1.512.346.8600 |