AKNOWLEDGEMENT:
WE EXPRESS OUR DEEP SENSE OF GRATITUDETO MR. SHAKIR SIDDIQUE
(DIRECTOR DEVELOPMENTHUMAN RESOURECE) FORENCOURAGING US TO
DO INTERNSHIP ATTHIS ORGANIZATION, PARAGONCONSTRUCTORS (PVT)
LTD.
WE ARE VERY MUCH THANKFUL TO MR. SYED HASHIM (GENERAL MANAGER)
FORHIS VALUABLEGUIDANCE, KEENINTERESTAND ENCOURAGEMENTAT
VARIOUS STAGES OF OURINTERNSHIPPERIOD.
WE EXPRESS DEEP GRATITUDETO MR. HARIS (PLANNING ENGINEER), MR.
UMAID (SITE ENGINEER), MR. FARHAN(SITESUPERVISOR) AND MR. IRSHAD-
UL-HAQ (NESPAK) FORTHEIRGUIDANCE, ENCOURAGEMENT, SUGGESTIONS
AND VERY CONSTRUCTIVECRITICISMWHICHHAVECONTRIBUTED IMMENSLY
TO OURLEARNING EXPERIENCE.
MINHAL HAIDER
ARSALAN ASHRAF
MOHAMMAD BILAL
ABDUL BASIT
STAKESHOLDER:
 Project Client : Emaar Giga karachi ltd.
 Project Contractor : Paragon constructors (pvt) ltd.
 Project Consultant : Nespak (pvt) ltd.
PARAGON:
Paragon Constructors is the leading company of PAKISTAN in the construction
field as all the mega projects going on in Pakistan, such as Lucky one shopping
mall, Bahria town icon hotel tower, Bahria opal tower, Emaar giga Coral
towers, UBL head office building,Creek view & terrace and others are heading
under their expertise. Since the company has a long history of completing
their projects within in the specified timeline, now they are heading to achieve
another historical landmark of completing the “EMMAR CORAL TOWER”
project in the upcoming year. Such a progressive attitude of the company
reflects their determination and dedication towards their profession.
EMAAR :
Emaar is a well known construction company with its origin in Dubai. Irrespective of
whether a development project is residential or commercial, it has a vast history of
creating something out of the box and jaw dropping. Burj kalifa of Dubai. It is an
apparent evidence of their determination, innovation and construction skills.
Recently, Emaar has its greatest stake in 48 towers named as Coral Towers in
Pakistan which are located at sea shore. Project is quite unique as the new
construction methods are introduced for the first time in the industry. In order to
complete the project in time, Emmar has facilitated the contractor to maximum.
NESPAK
Nespak is a prominent consultant company of Pakistan assisting and facilitating
millions by providing their services in water management, high rise construction,
transportation etc. Since its formation, NESPAK has made sure that all necessary
requirements are fulfilled regarding safety and durability. In order to prevent any
mishandlings and disorganization expert engineers are hired for the inspection
purposes.
PROJECT DETAIL:
The project comprises of 48 towers out of which two are named as CORAL TOWERS
which are in under progress. According to the direction of each tower they are
designated accordingly as North tower and South tower. Podium connects both the
towers and gives an elegant look from the distance. Both the towers are symmetrical
in shape and dimensions. Each tower consists of two basements, one mezzanine
floor and 26 ordinary floors. There are 9 columns, 9 shear walls and two cores (lift
core and stair case core). The projection is provided after every 3rd floor which
works as a shade against the scorching sunlight. A single floor is completed in 18days
as per the policy of the contractor but it may vary due the delay in the arrival of
shipments, environmental hazards or loss of material.
FORMWOR
K OF SLAB
REINFORCM
ENT OF SLAB
CONCRETEIN
G OF SLAB
REINFORCM
ENT OF
COLUMNS
AND
SHEARWALL
POST
TENSIONING
OF SLAB
FORMWORK
OF COLUMN
AND SHEAR
WALL
CONCRETING
OF
COLUMNS
AND
SHEARWALL
S
REINFORCE
MENT OF
COREWALL
CONCRETING
OF
COREWALLS
18 DAYS CYCLE OF A SINGLE FLOOR
FORMWORK OF SLAB:
The cycle begins with the placement of the scaffolding components such as
horizontal props, vertical props and main beams over which the plywood deck is
placed so that the slab reinforcements can be placed as per the drawing.
REINFORCEMENT OF SLAB:
A mesh of the slab reinforcement comprises of different types of bars. U-bars are
used to hold the reinforcement wherever the beams lie. Punching shear
reinforcement is used to provide strength against the negative moment develop at
the support. Chairs are used to provide the designed height to the tendons so that it
can balance the moments develop in the slab. A small U-shaped reinforcement is
used to hold the trumpet enclosing the strands during stressing.
CONCRETING OF SLAB:
Concreting of slab is the most critical and important part of the cycle. It takes almost
7 to 8 hours for the complete concreting of the slab, which is done through the
Reinforcement used for
holding strands on dead
end
Chairs under the re-bars Slab reinforcement mesh
Formwork of slab
placing boom being adjusted as the floor level proceeds. Mostly this activity takes
place at night to avoid the rapid setting time.
REINFORCEMENT OF COLUMNS AND SHEARWALLS:
Once the concrete is set the labors start the work on the reinforcement of columns
and shear walls. Proper lap distances between bars, placement of stirrups and
placement of vertical bars are laid as per the drawing so that the consultants gives
the positive IR and work may proceed further.
o SHEAR WALL:
The primary purpose of the shear wall is to resist the lateral forces being developed
below or above the ground surface. These lateral forces include seismic force, which
is maximum at the ground surface and wind pressure, which is maximum at the
higher altitude. Shear wall distributes the load developed by these forces and saves
the structure from any significant failure.
POST TENSION SLAB:
The important thing about this project is post tensioning slab which is introduced for
the first time in the Pakistan. The function of post tension slab is to reduce the
thickness of slab, reduction in self weight of the building, reduction in steel uses in
Reinforcement of column Reinforcement of shear wall
slab, since all of the tensile forces develop in the structure is taken by the tendons. It
reduces or eliminates shrinkage cracking-therefore no joints, or fewer joints, are
needed.
Post tensioning wires has two ends:
 Live end wires
 Dead end wires
Live end wires are those which are free on both sides of the slab therefore stressing
can be done from both ends. Dead end wires are those which are free from one end
and discontinued at mid span of slab near the supports where onion of the wires is
made to prevent the slippage of the stands during stressing.
The procedure of post tensioning begins with the replacement of temporary blocks
with the shear blocks in the trumpet. Shear blocks are designed according to the
number of strands in the tendon. Threaded wedges are provided in the holes of the
block so that during the stressing, strands do not move back and stay elongated. The
stressing of tendon is done through the hydraulic jack attached with the hydraulic
pump. In the beginning the 50% of the designed pressure is applied then in the
second round of stressing the pressure is increased up to 100%. During the stressing
procedure if the wire breaks then the threaded coupler is used. The strands are
threaded and fixed on both ends of the coupler for the continuity.
Shear block with wedges
FORMWORK OF COLUMNS AND SHEAR WALLS:
Although the formwork of the slab and shear wall is carried out side by side with the
post tensioning of the slab but special attention is laid on the alignment of the
formwork for which heavy objects are tied and hanged. The measurement is taken
from the face of the form work to the string to check the alignment.
CONCRETING OF COLUMNS AND SHEARWALLS:
Columns and shear walls are concreted through the buckets lifted up by the cranes.
Special attention is paid during the concreting in order to avoid the danger of
breaking of formwork due to the weight of the concrete.
Formworkof column
Live end of tendon Dead end of tendon
REINFORCEMNT OF COREWALLS:
Since the reinforcement of the core is quite heavy and complicated therefore special
attention is paid during the placement and the alignment of steel. Here on site there
are two core pits, one is for the stairs and other one is for the elevators.
CONCRETING OF CORE:
In a high rise building majority of the load is taken by the core therefore, its strength
and durability for the entire structure is very crucial. Once the consultant give the
positive IR to the core reinforcement and formwork alignment then it starts the
concreting of the core which is done through the placing boom.
OTHER ACTIVITIES DURING CONSTRUCTION:
Reinforcement of core walls
Concreting through bucket
GROUTING:
It is a mixture of cement, water and FOSPAK 337 chemical, used as a bonding agent
between the tendon wires and corrugated sheet. It prevents the danger of corrosion
in the strands and develops the homogeneity between the tendon and the concrete.
BLOCK MASONARY
Here in this project hollow blocks are used instead of solid concrete blocks. The
reasons for selecting hollow blocks over solid concrete blocks are:
 It reduces the building cost
 Economically friendly and cheap rates
 The acoustic system of the rooms becomes good
 It maintains the thermal balance
 It reduces the labor cost
The blocks are prepared on site. The materials used to make the blocks are:
 ½ cement bag
 3 trolleys of aggregates and sand
 Water
The material is mixed in a mixing machine and transported through the wheelbarrow
to the block making machine. Once the block is put into its size curing is done. These
blocks are later on supplied to the site where they were used in making partition
walls. During the placements of the blocks alignments is checked through the bob to
maintain the uniformity of the blocks.
PLASTERING
Plastering is done over the block masonry for the uniform and plain surface. The
thickness of plaster varies at some walls and ceilings due to uneven surface level. The
Block masonry Block masonry
minimum thickness of plaster is 0.75in and maximum is 2in. The material used in
making a durable plaster is cement and sand mixed in the ratio of 1:4. A layout for
the plaster is made on the wall and on the ceiling so that the uniformity in the
thickness is maintained. Plastering at the joints is discontinued so that the cracks
develop on the ceiling do not transfer at the plastering layer of the wall.
CURING OF CONCRETE:
Curing is done so that the temperature and the moisture content of the newly placed
concrete remain stable. Generally curing is done for 7 days but here early strength
concrete is used therefore the curing period is reduced up to 3 days.
chippingisdone forplastering
Layout of plastering
Discontinuityatthe topand
bottomplastering
BATCHING OF CONCRETE:
Batching of concrete is a process whereby cement is mixed with the coarse aggregate
and fine aggregate as well as with the water. Concrete batch plants are devices used
to mix the various ingredients to form concrete. Here on site the plant used for
batching is Central Mixed Plant.
The concrete batch plant can be categorizes into 4 parts:
1- Aggregate feeding
2- Cement feeding
3- Water and admixture for mixing the material
4- Conveyance and storage
The process begins with the mixture of aggregate of size 10mm and 20mm along
with the sand which is pushed forward by the operator into the bucket having a
capacity of 1m3. The bucket is lifted up by the conveyor belt and drop the mixture
into mixing machine where it get mixed with the water supplied through the pipe
and cement supplied through the silos of capacity 100, 110 and 130 tons. The TM
underneath the mixing machine hopper receives the mixture into the rotating drum
mounted on a transit mixture. It takes just 17 seconds in this entire process.
The concrete prepared in the plant is of the following strength:
Lean concrete 2000psi
Pile 5000psi
Curing of slab
Columns 5000psi
Shear walls 5000psi
PT slab 5000psi
The admixture used for the slab concrete is R-850 which works as an accelerator i.e.
increases the setting time of concrete.
PILE LOAD TEST:
Piles are used where the bearing capacity of the soil is too weak to carry the
structural load. Generally piles are of two types, the one is friction pile which is used
where hard strata is not available at sufficient depth so the pile uses the friction of
the surrounding soil and get stuck within it. The other is end bearing pile which is
used when the hard strata is available at required depth. The pile rests on that hard
strata and transfers the structural load. Since the strata of the soil under the pile
sometimes varies which results in the differential settlement. In order to avoid the
danger of differential settlement some tests are conducted to ensure the safety of
the future structure.
REACTION PILE METHOD:
In this method design load of 590 tons and maximum working load of 890 tons is
applied on the index pile. The load is applied through the hydraulic pump attached
with the heavy girders supported by the two supporting piles. Criteria can be carried
out by loading and unloading process. If the rate of settlement is greater than
0.25mm/hr then test will go for 24 hours.
Load is applied in a cyclic manner i.e. 25%, 50%, 75% and 100% of design load which
is 590 tons; this cycle is reversed on an unloading condition. A same criterion is
applied at max load which is 890 tons.
Pile load test Gauges measuring the settlement
EQUIPMENTS USED IN CONSTRUCTION:
SELF ERECTING TOWER CRANE:
Self erecting tower crane is used for transferring of materials such as steel, plywood
deck, hydraulic pump at high floors. The bucket used for concreting the shear wall
and columns is also carried by such crane. Its maximum load carrying capacity is 4 to
5 tons and has a jib length of 40 m.
TRANSIT MIXTURE:
Transit mixture is used for transferring concrete from the batching plant to the
construction site. Its carrying capacity varies according to the demand on site. Here
the TM. Of 9m3 is used.
PLACING BOOM
Placing boom is used for concreting the slabs and the corewalls. It is a combination
of large pipes operated hydraulically. The main pipe goes down to the last floor
Tower crane
Transit mixture
where it is attached with the static pump. When the TM pours the concrete it is
pushed forward by the static pump.
STATIC PUMP
A static pump is a machine used for transferring concrete at higher floors by applying
a high pressure on it. This pump is used in large construction projects where high
volume of concrete is required constantly. It applies the hydraulic pressure of 10 to
20 MPA while pushing forward the concrete through the pipe line. The maximum
voltage of the pump is 380volts and current is 100 ampere.
HYDRAULIC JACK AND HYDRAULIC PUMP:
Placing boom
Static pump
It is a device used for stressing the wires. It consists of the meter which shows the
applied pressure value on application. The meter is filled with fluid so that needles
do not get disturbed due the air pressure.
Hydraulic jack

More Related Content

What's hot

pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentationRahul bhatnagar
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing TechniqueSeminar Links
 
Construction Technology II (Seminar) - Deep excavation
Construction Technology II (Seminar) - Deep excavationConstruction Technology II (Seminar) - Deep excavation
Construction Technology II (Seminar) - Deep excavationYee Len Wan
 
Earthquake resistant structure
Earthquake resistant structureEarthquake resistant structure
Earthquake resistant structurevikskyn
 
Raza presentation
Raza presentationRaza presentation
Raza presentationQadir Raza
 
Indian Standard
Indian StandardIndian Standard
Indian Standardaman kumar
 
Ppt supersstructure
Ppt supersstructurePpt supersstructure
Ppt supersstructureShrafatBalti
 
Top down construction by Sai Towers P Ltd.
Top down construction by Sai Towers P Ltd.Top down construction by Sai Towers P Ltd.
Top down construction by Sai Towers P Ltd.Sai Towers P Ltd.
 
Earthquake resistant confined masonry structure with concrete beams and columns
Earthquake resistant confined masonry structure with concrete beams and columnsEarthquake resistant confined masonry structure with concrete beams and columns
Earthquake resistant confined masonry structure with concrete beams and columnsSajjad Ahmad
 
Ct 1 assignment
Ct 1 assignmentCt 1 assignment
Ct 1 assignmentJamesMoy7
 
high rise seismic resistant buildings
 high rise seismic resistant buildings high rise seismic resistant buildings
high rise seismic resistant buildingsAr.Farooqh A
 
Lec01 Design of RC Structures under lateral load (Earthquake Engineering هندس...
Lec01 Design of RC Structures under lateral load (Earthquake Engineering هندس...Lec01 Design of RC Structures under lateral load (Earthquake Engineering هندس...
Lec01 Design of RC Structures under lateral load (Earthquake Engineering هندس...Hossam Shafiq II
 

What's hot (20)

pile foundation and pile cap presentation
pile foundation and pile cap presentationpile foundation and pile cap presentation
pile foundation and pile cap presentation
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
 
Construction Technology II (Seminar) - Deep excavation
Construction Technology II (Seminar) - Deep excavationConstruction Technology II (Seminar) - Deep excavation
Construction Technology II (Seminar) - Deep excavation
 
Earthquake resistant structure
Earthquake resistant structureEarthquake resistant structure
Earthquake resistant structure
 
Shoring and underpinning
Shoring and underpinningShoring and underpinning
Shoring and underpinning
 
Raza presentation
Raza presentationRaza presentation
Raza presentation
 
Indian Standard
Indian StandardIndian Standard
Indian Standard
 
Top Down Construction Presentation.
Top Down Construction Presentation.Top Down Construction Presentation.
Top Down Construction Presentation.
 
Ct report
Ct reportCt report
Ct report
 
Ajmal
AjmalAjmal
Ajmal
 
PPT ON BURJ AL ARAB
PPT ON BURJ AL ARABPPT ON BURJ AL ARAB
PPT ON BURJ AL ARAB
 
Ppt supersstructure
Ppt supersstructurePpt supersstructure
Ppt supersstructure
 
Shear wall
Shear wallShear wall
Shear wall
 
CT assignment
CT assignmentCT assignment
CT assignment
 
Top down construction by Sai Towers P Ltd.
Top down construction by Sai Towers P Ltd.Top down construction by Sai Towers P Ltd.
Top down construction by Sai Towers P Ltd.
 
Earthquake resistant confined masonry structure with concrete beams and columns
Earthquake resistant confined masonry structure with concrete beams and columnsEarthquake resistant confined masonry structure with concrete beams and columns
Earthquake resistant confined masonry structure with concrete beams and columns
 
Ct 1 assignment
Ct 1 assignmentCt 1 assignment
Ct 1 assignment
 
high rise seismic resistant buildings
 high rise seismic resistant buildings high rise seismic resistant buildings
high rise seismic resistant buildings
 
Top down construction presentation
Top down construction presentationTop down construction presentation
Top down construction presentation
 
Lec01 Design of RC Structures under lateral load (Earthquake Engineering هندس...
Lec01 Design of RC Structures under lateral load (Earthquake Engineering هندس...Lec01 Design of RC Structures under lateral load (Earthquake Engineering هندس...
Lec01 Design of RC Structures under lateral load (Earthquake Engineering هندس...
 

Viewers also liked

Viewers also liked (13)

Roth, Mauro Gonzalo
Roth, Mauro GonzaloRoth, Mauro Gonzalo
Roth, Mauro Gonzalo
 
Audience Expectations
Audience ExpectationsAudience Expectations
Audience Expectations
 
FINALHealthy Habits 101
FINALHealthy Habits 101FINALHealthy Habits 101
FINALHealthy Habits 101
 
Earths motions 2016_website
Earths motions 2016_websiteEarths motions 2016_website
Earths motions 2016_website
 
五个来索契的理由
五个来索契的理由五个来索契的理由
五个来索契的理由
 
Redacción de textos
Redacción de textosRedacción de textos
Redacción de textos
 
Magnitudes Físicas en la vida cotidiana
Magnitudes  Físicas en la vida cotidianaMagnitudes  Físicas en la vida cotidiana
Magnitudes Físicas en la vida cotidiana
 
INEE Curso UIMP 2016 - Evaluación educativa: Luka Boeskens
INEE Curso UIMP 2016 - Evaluación educativa: Luka BoeskensINEE Curso UIMP 2016 - Evaluación educativa: Luka Boeskens
INEE Curso UIMP 2016 - Evaluación educativa: Luka Boeskens
 
History of film
History of filmHistory of film
History of film
 
Jane Austen Paper 1
Jane Austen Paper 1Jane Austen Paper 1
Jane Austen Paper 1
 
Nutrição mineral de plantas. O metabolismo do nitrogênio. Parte 2.1 O Enxof...
Nutrição mineral de plantas. O metabolismo do nitrogênio. Parte 2.1   O Enxof...Nutrição mineral de plantas. O metabolismo do nitrogênio. Parte 2.1   O Enxof...
Nutrição mineral de plantas. O metabolismo do nitrogênio. Parte 2.1 O Enxof...
 
Primeros filosofos
Primeros filosofosPrimeros filosofos
Primeros filosofos
 
Tamylily
TamylilyTamylily
Tamylily
 

Similar to report-on-emmar.docx13

Construction Of A Viaduct/Bridge: An Overview
Construction Of A Viaduct/Bridge: An OverviewConstruction Of A Viaduct/Bridge: An Overview
Construction Of A Viaduct/Bridge: An OverviewSourav Goswami
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxVinayak247538
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxLokeswarSaha1
 
Building construction 02
Building construction 02Building construction 02
Building construction 02Sarah Esa
 
Building Construction 02 (Project1)
Building Construction 02 (Project1)Building Construction 02 (Project1)
Building Construction 02 (Project1)Lek Yuen
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxtoddr4
 
Advad.Ind.Const.Tech. Batch -3
Advad.Ind.Const.Tech. Batch -3Advad.Ind.Const.Tech. Batch -3
Advad.Ind.Const.Tech. Batch -3Prasanth Dasu
 
Ishfaq Rashid.pptx
Ishfaq Rashid.pptxIshfaq Rashid.pptx
Ishfaq Rashid.pptxlovish34
 
REINFORCED CEMENT CONCRETE
REINFORCED CEMENT CONCRETEREINFORCED CEMENT CONCRETE
REINFORCED CEMENT CONCRETEBrijesh Alig
 
Bcon bus shelter skeletal construction P1
Bcon bus shelter skeletal construction P1Bcon bus shelter skeletal construction P1
Bcon bus shelter skeletal construction P1Ow Cong
 
Building construction 2 project 1 report
Building construction 2 project 1 reportBuilding construction 2 project 1 report
Building construction 2 project 1 reportOng Seng Peng Jeff
 

Similar to report-on-emmar.docx13 (20)

Construction Of A Viaduct/Bridge: An Overview
Construction Of A Viaduct/Bridge: An OverviewConstruction Of A Viaduct/Bridge: An Overview
Construction Of A Viaduct/Bridge: An Overview
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
 
Building construction 02
Building construction 02Building construction 02
Building construction 02
 
Building Construction 02 (Project1)
Building Construction 02 (Project1)Building Construction 02 (Project1)
Building Construction 02 (Project1)
 
IPT Training
IPT TrainingIPT Training
IPT Training
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
 
STRESS RIBBON BRIDGE
STRESS RIBBON BRIDGESTRESS RIBBON BRIDGE
STRESS RIBBON BRIDGE
 
Advad.Ind.Const.Tech. Batch -3
Advad.Ind.Const.Tech. Batch -3Advad.Ind.Const.Tech. Batch -3
Advad.Ind.Const.Tech. Batch -3
 
INDL PPT 1.pptx
INDL PPT 1.pptxINDL PPT 1.pptx
INDL PPT 1.pptx
 
Acm Unit 1
Acm Unit 1Acm Unit 1
Acm Unit 1
 
vacation work report 2
vacation work report 2vacation work report 2
vacation work report 2
 
Ishfaq Rashid.pptx
Ishfaq Rashid.pptxIshfaq Rashid.pptx
Ishfaq Rashid.pptx
 
Post lintel structre
Post lintel structrePost lintel structre
Post lintel structre
 
Ayush
AyushAyush
Ayush
 
training report LMRC
training report LMRCtraining report LMRC
training report LMRC
 
REINFORCED CEMENT CONCRETE
REINFORCED CEMENT CONCRETEREINFORCED CEMENT CONCRETE
REINFORCED CEMENT CONCRETE
 
Bcon
BconBcon
Bcon
 
Bcon bus shelter skeletal construction P1
Bcon bus shelter skeletal construction P1Bcon bus shelter skeletal construction P1
Bcon bus shelter skeletal construction P1
 
Building construction 2 project 1 report
Building construction 2 project 1 reportBuilding construction 2 project 1 report
Building construction 2 project 1 report
 

report-on-emmar.docx13

  • 1. AKNOWLEDGEMENT: WE EXPRESS OUR DEEP SENSE OF GRATITUDETO MR. SHAKIR SIDDIQUE (DIRECTOR DEVELOPMENTHUMAN RESOURECE) FORENCOURAGING US TO DO INTERNSHIP ATTHIS ORGANIZATION, PARAGONCONSTRUCTORS (PVT) LTD. WE ARE VERY MUCH THANKFUL TO MR. SYED HASHIM (GENERAL MANAGER) FORHIS VALUABLEGUIDANCE, KEENINTERESTAND ENCOURAGEMENTAT VARIOUS STAGES OF OURINTERNSHIPPERIOD. WE EXPRESS DEEP GRATITUDETO MR. HARIS (PLANNING ENGINEER), MR. UMAID (SITE ENGINEER), MR. FARHAN(SITESUPERVISOR) AND MR. IRSHAD- UL-HAQ (NESPAK) FORTHEIRGUIDANCE, ENCOURAGEMENT, SUGGESTIONS AND VERY CONSTRUCTIVECRITICISMWHICHHAVECONTRIBUTED IMMENSLY TO OURLEARNING EXPERIENCE. MINHAL HAIDER ARSALAN ASHRAF MOHAMMAD BILAL ABDUL BASIT STAKESHOLDER:  Project Client : Emaar Giga karachi ltd.  Project Contractor : Paragon constructors (pvt) ltd.  Project Consultant : Nespak (pvt) ltd. PARAGON:
  • 2. Paragon Constructors is the leading company of PAKISTAN in the construction field as all the mega projects going on in Pakistan, such as Lucky one shopping mall, Bahria town icon hotel tower, Bahria opal tower, Emaar giga Coral towers, UBL head office building,Creek view & terrace and others are heading under their expertise. Since the company has a long history of completing their projects within in the specified timeline, now they are heading to achieve another historical landmark of completing the “EMMAR CORAL TOWER” project in the upcoming year. Such a progressive attitude of the company reflects their determination and dedication towards their profession.
  • 3. EMAAR : Emaar is a well known construction company with its origin in Dubai. Irrespective of whether a development project is residential or commercial, it has a vast history of creating something out of the box and jaw dropping. Burj kalifa of Dubai. It is an apparent evidence of their determination, innovation and construction skills. Recently, Emaar has its greatest stake in 48 towers named as Coral Towers in Pakistan which are located at sea shore. Project is quite unique as the new construction methods are introduced for the first time in the industry. In order to complete the project in time, Emmar has facilitated the contractor to maximum. NESPAK Nespak is a prominent consultant company of Pakistan assisting and facilitating millions by providing their services in water management, high rise construction, transportation etc. Since its formation, NESPAK has made sure that all necessary requirements are fulfilled regarding safety and durability. In order to prevent any mishandlings and disorganization expert engineers are hired for the inspection purposes. PROJECT DETAIL: The project comprises of 48 towers out of which two are named as CORAL TOWERS which are in under progress. According to the direction of each tower they are
  • 4. designated accordingly as North tower and South tower. Podium connects both the towers and gives an elegant look from the distance. Both the towers are symmetrical in shape and dimensions. Each tower consists of two basements, one mezzanine floor and 26 ordinary floors. There are 9 columns, 9 shear walls and two cores (lift core and stair case core). The projection is provided after every 3rd floor which works as a shade against the scorching sunlight. A single floor is completed in 18days as per the policy of the contractor but it may vary due the delay in the arrival of shipments, environmental hazards or loss of material. FORMWOR K OF SLAB REINFORCM ENT OF SLAB CONCRETEIN G OF SLAB REINFORCM ENT OF COLUMNS AND SHEARWALL POST TENSIONING OF SLAB FORMWORK OF COLUMN AND SHEAR WALL CONCRETING OF COLUMNS AND SHEARWALL S REINFORCE MENT OF COREWALL CONCRETING OF COREWALLS 18 DAYS CYCLE OF A SINGLE FLOOR
  • 5. FORMWORK OF SLAB: The cycle begins with the placement of the scaffolding components such as horizontal props, vertical props and main beams over which the plywood deck is placed so that the slab reinforcements can be placed as per the drawing. REINFORCEMENT OF SLAB: A mesh of the slab reinforcement comprises of different types of bars. U-bars are used to hold the reinforcement wherever the beams lie. Punching shear reinforcement is used to provide strength against the negative moment develop at the support. Chairs are used to provide the designed height to the tendons so that it can balance the moments develop in the slab. A small U-shaped reinforcement is used to hold the trumpet enclosing the strands during stressing. CONCRETING OF SLAB: Concreting of slab is the most critical and important part of the cycle. It takes almost 7 to 8 hours for the complete concreting of the slab, which is done through the Reinforcement used for holding strands on dead end Chairs under the re-bars Slab reinforcement mesh Formwork of slab
  • 6. placing boom being adjusted as the floor level proceeds. Mostly this activity takes place at night to avoid the rapid setting time. REINFORCEMENT OF COLUMNS AND SHEARWALLS: Once the concrete is set the labors start the work on the reinforcement of columns and shear walls. Proper lap distances between bars, placement of stirrups and placement of vertical bars are laid as per the drawing so that the consultants gives the positive IR and work may proceed further. o SHEAR WALL: The primary purpose of the shear wall is to resist the lateral forces being developed below or above the ground surface. These lateral forces include seismic force, which is maximum at the ground surface and wind pressure, which is maximum at the higher altitude. Shear wall distributes the load developed by these forces and saves the structure from any significant failure. POST TENSION SLAB: The important thing about this project is post tensioning slab which is introduced for the first time in the Pakistan. The function of post tension slab is to reduce the thickness of slab, reduction in self weight of the building, reduction in steel uses in Reinforcement of column Reinforcement of shear wall
  • 7. slab, since all of the tensile forces develop in the structure is taken by the tendons. It reduces or eliminates shrinkage cracking-therefore no joints, or fewer joints, are needed. Post tensioning wires has two ends:  Live end wires  Dead end wires Live end wires are those which are free on both sides of the slab therefore stressing can be done from both ends. Dead end wires are those which are free from one end and discontinued at mid span of slab near the supports where onion of the wires is made to prevent the slippage of the stands during stressing. The procedure of post tensioning begins with the replacement of temporary blocks with the shear blocks in the trumpet. Shear blocks are designed according to the number of strands in the tendon. Threaded wedges are provided in the holes of the block so that during the stressing, strands do not move back and stay elongated. The stressing of tendon is done through the hydraulic jack attached with the hydraulic pump. In the beginning the 50% of the designed pressure is applied then in the second round of stressing the pressure is increased up to 100%. During the stressing procedure if the wire breaks then the threaded coupler is used. The strands are threaded and fixed on both ends of the coupler for the continuity. Shear block with wedges
  • 8. FORMWORK OF COLUMNS AND SHEAR WALLS: Although the formwork of the slab and shear wall is carried out side by side with the post tensioning of the slab but special attention is laid on the alignment of the formwork for which heavy objects are tied and hanged. The measurement is taken from the face of the form work to the string to check the alignment. CONCRETING OF COLUMNS AND SHEARWALLS: Columns and shear walls are concreted through the buckets lifted up by the cranes. Special attention is paid during the concreting in order to avoid the danger of breaking of formwork due to the weight of the concrete. Formworkof column Live end of tendon Dead end of tendon
  • 9. REINFORCEMNT OF COREWALLS: Since the reinforcement of the core is quite heavy and complicated therefore special attention is paid during the placement and the alignment of steel. Here on site there are two core pits, one is for the stairs and other one is for the elevators. CONCRETING OF CORE: In a high rise building majority of the load is taken by the core therefore, its strength and durability for the entire structure is very crucial. Once the consultant give the positive IR to the core reinforcement and formwork alignment then it starts the concreting of the core which is done through the placing boom. OTHER ACTIVITIES DURING CONSTRUCTION: Reinforcement of core walls Concreting through bucket
  • 10. GROUTING: It is a mixture of cement, water and FOSPAK 337 chemical, used as a bonding agent between the tendon wires and corrugated sheet. It prevents the danger of corrosion in the strands and develops the homogeneity between the tendon and the concrete. BLOCK MASONARY Here in this project hollow blocks are used instead of solid concrete blocks. The reasons for selecting hollow blocks over solid concrete blocks are:  It reduces the building cost  Economically friendly and cheap rates  The acoustic system of the rooms becomes good  It maintains the thermal balance  It reduces the labor cost The blocks are prepared on site. The materials used to make the blocks are:  ½ cement bag  3 trolleys of aggregates and sand  Water The material is mixed in a mixing machine and transported through the wheelbarrow to the block making machine. Once the block is put into its size curing is done. These blocks are later on supplied to the site where they were used in making partition walls. During the placements of the blocks alignments is checked through the bob to maintain the uniformity of the blocks. PLASTERING Plastering is done over the block masonry for the uniform and plain surface. The thickness of plaster varies at some walls and ceilings due to uneven surface level. The Block masonry Block masonry
  • 11. minimum thickness of plaster is 0.75in and maximum is 2in. The material used in making a durable plaster is cement and sand mixed in the ratio of 1:4. A layout for the plaster is made on the wall and on the ceiling so that the uniformity in the thickness is maintained. Plastering at the joints is discontinued so that the cracks develop on the ceiling do not transfer at the plastering layer of the wall. CURING OF CONCRETE: Curing is done so that the temperature and the moisture content of the newly placed concrete remain stable. Generally curing is done for 7 days but here early strength concrete is used therefore the curing period is reduced up to 3 days. chippingisdone forplastering Layout of plastering Discontinuityatthe topand bottomplastering
  • 12. BATCHING OF CONCRETE: Batching of concrete is a process whereby cement is mixed with the coarse aggregate and fine aggregate as well as with the water. Concrete batch plants are devices used to mix the various ingredients to form concrete. Here on site the plant used for batching is Central Mixed Plant. The concrete batch plant can be categorizes into 4 parts: 1- Aggregate feeding 2- Cement feeding 3- Water and admixture for mixing the material 4- Conveyance and storage The process begins with the mixture of aggregate of size 10mm and 20mm along with the sand which is pushed forward by the operator into the bucket having a capacity of 1m3. The bucket is lifted up by the conveyor belt and drop the mixture into mixing machine where it get mixed with the water supplied through the pipe and cement supplied through the silos of capacity 100, 110 and 130 tons. The TM underneath the mixing machine hopper receives the mixture into the rotating drum mounted on a transit mixture. It takes just 17 seconds in this entire process. The concrete prepared in the plant is of the following strength: Lean concrete 2000psi Pile 5000psi Curing of slab
  • 13. Columns 5000psi Shear walls 5000psi PT slab 5000psi The admixture used for the slab concrete is R-850 which works as an accelerator i.e. increases the setting time of concrete. PILE LOAD TEST: Piles are used where the bearing capacity of the soil is too weak to carry the structural load. Generally piles are of two types, the one is friction pile which is used where hard strata is not available at sufficient depth so the pile uses the friction of the surrounding soil and get stuck within it. The other is end bearing pile which is used when the hard strata is available at required depth. The pile rests on that hard strata and transfers the structural load. Since the strata of the soil under the pile sometimes varies which results in the differential settlement. In order to avoid the danger of differential settlement some tests are conducted to ensure the safety of the future structure. REACTION PILE METHOD: In this method design load of 590 tons and maximum working load of 890 tons is applied on the index pile. The load is applied through the hydraulic pump attached with the heavy girders supported by the two supporting piles. Criteria can be carried out by loading and unloading process. If the rate of settlement is greater than 0.25mm/hr then test will go for 24 hours. Load is applied in a cyclic manner i.e. 25%, 50%, 75% and 100% of design load which is 590 tons; this cycle is reversed on an unloading condition. A same criterion is applied at max load which is 890 tons. Pile load test Gauges measuring the settlement
  • 14. EQUIPMENTS USED IN CONSTRUCTION: SELF ERECTING TOWER CRANE: Self erecting tower crane is used for transferring of materials such as steel, plywood deck, hydraulic pump at high floors. The bucket used for concreting the shear wall and columns is also carried by such crane. Its maximum load carrying capacity is 4 to 5 tons and has a jib length of 40 m. TRANSIT MIXTURE: Transit mixture is used for transferring concrete from the batching plant to the construction site. Its carrying capacity varies according to the demand on site. Here the TM. Of 9m3 is used. PLACING BOOM Placing boom is used for concreting the slabs and the corewalls. It is a combination of large pipes operated hydraulically. The main pipe goes down to the last floor Tower crane Transit mixture
  • 15. where it is attached with the static pump. When the TM pours the concrete it is pushed forward by the static pump. STATIC PUMP A static pump is a machine used for transferring concrete at higher floors by applying a high pressure on it. This pump is used in large construction projects where high volume of concrete is required constantly. It applies the hydraulic pressure of 10 to 20 MPA while pushing forward the concrete through the pipe line. The maximum voltage of the pump is 380volts and current is 100 ampere. HYDRAULIC JACK AND HYDRAULIC PUMP: Placing boom Static pump
  • 16. It is a device used for stressing the wires. It consists of the meter which shows the applied pressure value on application. The meter is filled with fluid so that needles do not get disturbed due the air pressure. Hydraulic jack