Saba Power PlantSaba Power Plant
134 MW Steam Turbine Unit134 MW Steam Turbine Unit
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
IntroductionIntroduction
Location
Saba Power Plant is situated at 9 km Sargodha road near Jhamke village.
Shaikhupura
Total Area
Total area is around 290779 m2
(72 acres).
Power block of the Plant occupies 20% of total site (200 x 300 = 60000 m2
).
Main Occupied Areas
132 KV Switch Yard, Transformers, Natural Gas Generators, RFO Unloading
Station, RFO Storage Tanks, RFO Day Tank, Demin Plant, Raw Water &
Demin Water Storage Tanks, Auxiliary Boiler, Chemical Laboratory, Control
Building, Main Boiler, ESP & Stack, Steam Turbine, Generator, Cooling
Tower, Retention Ponds, Mechanical Workshop, Rest House and
Administration Block.
Around 14 acres consists of garden that has plants of Lemon, Orange, Kino,
Grapefruit and Guava. Almost 60% of the area is not in use.
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
Arial ViewArial View
IntroductionIntroduction
 Total Generation CapacityTotal Generation Capacity
• 1X134 MW Steam Turbine Generator1X134 MW Steam Turbine Generator
• 4X0.9 MW Natural Gas Engine Generator4X0.9 MW Natural Gas Engine Generator
(Installed in year 2009).(Installed in year 2009).
 Controlling SystemControlling System
• Main Plant Control on DCS Bailey Infi 90 & Rovisys ExperionMain Plant Control on DCS Bailey Infi 90 & Rovisys Experion
• PLC (ABB, Allen Bradley, PanelMate)PLC (ABB, Allen Bradley, PanelMate)
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
Guaranteed Heat Rate
(Thermal Efficiency) as per ppa
8842 Btu's per kWh, based on the higher
heating value (HHV) of fuel and the net
output of the Complex.
 COD Commercial Operation Date = 31 December 1999COD Commercial Operation Date = 31 December 1999
 PPA (Power Purchase Agreement) established in 26 DecemberPPA (Power Purchase Agreement) established in 26 December
1994 and finally signed on 18 August 1997.1994 and finally signed on 18 August 1997.
 Thermal Efficiency = 42.99 %Thermal Efficiency = 42.99 %
Major ComponentsMajor Components
 413 Tons, Main Boiler (B&W)413 Tons, Main Boiler (B&W)
 134 MW, Steam Turbine (Toshiba)134 MW, Steam Turbine (Toshiba)
 170 MVA, Generator (Toshiba)170 MVA, Generator (Toshiba)
 Surface Condenser (Ecolaire Corp.)Surface Condenser (Ecolaire Corp.)
 Cooling Tower (GEA)Cooling Tower (GEA)
 Demineralization Plant (Ecodyne)Demineralization Plant (Ecodyne)
 23 Tons, Auxiliary Boiler (B&W GAMA)23 Tons, Auxiliary Boiler (B&W GAMA)
 132 KV Switchyard (Siemens)132 KV Switchyard (Siemens)
 Generator Switchgear (ABB)Generator Switchgear (ABB)
 6.6 KV/0.415 KV MVSG (Cutler Hammer)6.6 KV/0.415 KV MVSG (Cutler Hammer)
 160 MVA Generator Transformer (Hyundai)160 MVA Generator Transformer (Hyundai)
 12.5 MVA Auxiliary Transformer12.5 MVA Auxiliary Transformer (Pennsylvania)(Pennsylvania)
 UPS (Cyberex Incorporated)UPS (Cyberex Incorporated)
 125 V DC System, Battery Charger (C&D Tech.)125 V DC System, Battery Charger (C&D Tech.)
 Storage TanksStorage Tanks (RFO, HSD, Raw & Demin Water, Acid & Caustic, Chemical Feed)(RFO, HSD, Raw & Demin Water, Acid & Caustic, Chemical Feed)
Major ComponentsMajor Components
 6.6 KV Motors (Westinghouse, )6.6 KV Motors (Westinghouse, )
 Boiler Feed Pumps (KSB)Boiler Feed Pumps (KSB)
 CEP & CW pumps (Johnston)CEP & CW pumps (Johnston)
 0.4 KV Pumps (Goulds)0.4 KV Pumps (Goulds)
 0.4 KV Motor (Reliance)0.4 KV Motor (Reliance)
 500 KW Emergency Diesel Generator500 KW Emergency Diesel Generator (Caterpillar)(Caterpillar)
 200 HP Diesel Fire Engine (Caterpillar)200 HP Diesel Fire Engine (Caterpillar)
 Fire Water System (Viking)Fire Water System (Viking)
 Fire Water Pumps (ITT)Fire Water Pumps (ITT)
 Regenerative Air Heater (ABB Ljungstrom)Regenerative Air Heater (ABB Ljungstrom)
 Steam Coil Air Heater (LAPCO)Steam Coil Air Heater (LAPCO)
 Soot Blowers (Diamond)Soot Blowers (Diamond)
 Safety Valves (Dresser)Safety Valves (Dresser)
 Transmitters (Fisher – Rosemount)Transmitters (Fisher – Rosemount)
 ESP & Ash Handling SystemESP & Ash Handling System
 Feed Water Heaters (Struthers Well Corp.)Feed Water Heaters (Struthers Well Corp.)
 Deaerator (Sterling)Deaerator (Sterling)
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
Main BoilerMain Boiler
Specification:
Manufacturer Babcock & Wilcox (USA)
Model Out Door Type, Series 2, Elpaso Radiant
Year Manufactured 1997
Services Base Load
Type Pressurized Furness, natural circulation with reheat.
Boiler Fuels #6 Residual Fuel Oil (RFO/HSFO)/ Diesel Light of
fuel (HSD)
Number Of Burner and Igniters 6 x 6 Low NOx, Steam automised burners/Igniters,
in 3 floors, 2 burners/Igniters on each floor.
GRF Gas recirculation for RH protection and NOX
controls.
Fuel Consumption 29 tons/hr (On Maximum load)
Heat Rate 7939 btu/kwh (On Ideal Conditions)
Boiler Heating Surface: 8929 sq.foot
Economizer Heating Surface 13.465 sq.foot
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
HP Steam Flow 413 tons/hr
HP Steam Pressure 171.9 kg/cm2
HP Steam Temperature 540.5 o
C
Reheat Steam Flow 354.7
Reheat Steam Pressure 37.2 kg/cm2
Reheat Steam Temperature 538.3 o
C
Burner interlocks and control BMS (Burner management System)
Soot Blowers 09 soot blowers, 06 for super heater, 02
reheater, 01 Economizer & 1 Soot Blower for
Air Heater
Boiler Major Auxiliaries 3x50% BFP 2600 HP, FDF 2250 HP, GRF 585
HP, Seal Air Blower, Air Heater drive Motor,
Flame Scanner Blower
Ash System ESP, Ash Hoppers, Ash, Transport Blower,
Ash Soot Silo, Stack
Boiler Efficiency 88 %
Main Boiler
Prepared by:Prepared by:
Mohammad ShoebMohammad Shoeb
SiddiquiSiddiqui
Senior ShiftSenior Shift
SupervisorSupervisor
Steam TurbineSteam Turbine
Specification:
Manufacturer Toshiba (Japan)
Type
SCSF – 36", Single Cylinder, Single
Flow Reheat Condensing Turbine.
Rating Capacity 134 MW
Speed RPM 3000 rpm
No. Of Stages 21 stages (9 HP, 7 IP, 5LP)
No. Of Extractions 06
Steam Flow 408233 kg/hr
Rating Pressure 169.8 kg/cm2
Turbine Efficiency 49.84 %
Turbine Control System (Governing
System)
D-EHC
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
Steam TurbineSteam Turbine
Steam Condition
HP STEAM
Flow 413 T/hr
Pressure 168 kg/cm2
Temperature 538 °C
LP STEAM (Reheat Steam)
Flow 378 T/hr
Pressure 37.2 kg/cm2
Temperature 538 °C
Exhaust Pressure 6.77 kpaa
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
GeneratorGenerator
Specification
Manufacturer Toshiba
Year Manufactured 1998
Model # TAKL-RCH , 2 pole
Rated voltage 15.5 kv
Rated Capacity 170 MVA
Frequency 50 Hz
Rated Current 6333 Amps
Power Factor 0.8 Lagging
Speed 3000 rpm
Pole 2
Rotor cooling Air (Air Cooling From CCW)
Stator cooling Air (Air Cooling From CCW)
Generator Efficiency 98 %
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
Emergency Diesel GeneratorEmergency Diesel Generator
Emergency Diesel Generator (EDG)Emergency Diesel Generator (EDG)
A 500 KW diesel generator is provided at site for black plant situationA 500 KW diesel generator is provided at site for black plant situation
to run the plant necessary auxiliaries like:to run the plant necessary auxiliaries like:
• Rotary air heaterRotary air heater
• Turbine lube oil systemTurbine lube oil system
• Turbine turning gearTurbine turning gear
• GRF turning gearGRF turning gear
• Necessary plant lighteningNecessary plant lightening
• Turbine drain MOVsTurbine drain MOVs
• Battery charging.Battery charging.
• BFP Lube oil PumpsBFP Lube oil Pumps
EDG starts automatically in case of any power failure. An ATS isEDG starts automatically in case of any power failure. An ATS is
provided at EMCC for transferring load from PCC-2 to EDGprovided at EMCC for transferring load from PCC-2 to EDG
source. 300 gals of HSD tank is also provided for EDGsource. 300 gals of HSD tank is also provided for EDG
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
DSC SYSTEM (REDUNDANT PROCESS CONTROL UNIT INTERFACE)DSC SYSTEM (REDUNDANT PROCESS CONTROL UNIT INTERFACE)
INFI-NET LOOP
NIS NPM NPM NIS
CONTROLWAY
MFP MFP MFP MFP MFP MFP
I/O
Module
I/O
Module
I/O
Module
I/O
Module
I/O
Module
I/O
Module
I/O EXPONDER BUS I/O EXPONDER BUS
PCU
5XOIS
7 X PCU
EWS
3 X
PRINTERS250 NODES
UPTO 32 MODULES
UPTO 64 MODULES UPTO 64 MODULES
HISTORION
Prepared by:Prepared by:
Mohammad ShoebMohammad Shoeb
SiddiquiSiddiqui
Senior Shift SupervisorSenior Shift Supervisor
DCS SYSTEM
DCS SYSTEM
Process Cycles & SystemsProcess Cycles & Systems
Raw & Service Water SystemRaw & Service Water System
Demineralization PlantDemineralization Plant
Close Cooling Water SystemClose Cooling Water System
Circulating Water SystemCirculating Water System
HSD SystemHSD System
RFO SystemRFO System
Aux. Steam SystemAux. Steam System
Feed Water CycleFeed Water Cycle
Condensate CycleCondensate Cycle
Steam CycleSteam Cycle
Extraction Steam SystemExtraction Steam System
Heaters Vents & DrainsHeaters Vents & Drains
132 KV System132 KV System
132 / 6.6 / 0.415 KV System132 / 6.6 / 0.415 KV System
Air & Flue Gas SystemAir & Flue Gas System
Service & Instrument Air SystemService & Instrument Air System
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
Service & Instrument Air SystemService & Instrument Air System
SAC1
SAC2
Air Receiver
SAC3
Air
Compressors
Aspirating Air
Compressor
Air Purification &
Drying System
Instrument Air
Service Air
Main Boiler
Aspirating Air
Instrument Air Pressure
7.2 kg/cm2
Service Air Pressure
7.4 kg/cm2
SAC1
SAC3
SAC2
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
Potable
Water
Tank
Raw & Fire
Water Tank
Capacity
2155 m3
Bore
Well # 1
Bore
Well # 2
Bore
Well # 3
Bore
Well # 4
Bore
Well # 5
Electric
Fire Pump
Diesel
Engine
Fire Pump
Jockey
Fire Pump
To Fire
water
system
To CT
Basin
Makeup
To Air
Heater
Washing
To All Plant Service
Water Supply
Service
Water
Pump 1
Service
Water
Pump 2
Service
Water
Pump 3
To Fire
water
system
Raw / Service & Fire Water SystemRaw / Service & Fire Water System
Service
Water
Pressure
7.2
kg/cm2
Fire water
Pressure
9.5 kg/cm2
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
Demineralization PlantDemineralization Plant
Service CycleService Cycle
Service Water
Inlet Flow 29
m3
/hr
CAT Ion
Exchanger
collect +
ions
De-Gasifier Blowers De-Gasifier
Removes Un dissolve
gases
De-Gasifier Pumps
An Ion
Exchanger
collects -ions
Mixed Bed
Polisher
Demin
water out
to Tank
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
Conductivity = 1000 uS/cm
pH = 7.8 to 8.0, Silica = 27 ppm
Conductivity = < 0.2 uS/cm
pH = 6.8 to 7.2, Silica = < 20 ppb
CCW SystemCCW System
CCW Makeup Tank
Heat
Exchangers
Lube Oil
Cooler
Generator
Coolers
EHC
Cooler
BFP
Cooler
SAC
Cooler
RAH
Cooler
Ash
Handling
System
SWAS
CCW
Pumps
From DM
Tank
Pot
Feeder
Pressure 4.5
kg/cm2
CCW Makeup TankCCW Makeup Tank
Inlet
Temp.
33 o
C
Outlet Temp. 33 o
C
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
Circulating Water SystemCirculating Water System
Raw Water
Tank
Cooling
Tower
Condenser
2x100 %
CW Pump
CTF
From Bore Wells
CT Makeup
Ambient Condition
Temp. 27.5 o
C
Humidity 88.5 %
CW I/L
Temp.
30 o
C
CW O/L
Temp. 45 o
C
CCW Heat
Exchanger
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
Saba Power PlantSaba Power Plant
Water Balance Diagram (Water Balance Diagram (Average Flow)Average Flow)
Mohammad Shoeb Siddiqui
Sr. Shift Supervisor
Cooling Tower
CT
Sump
Drift Loss
Evaporation
Loss
Condenser
CT Basin
Power
System
Makeup
CST
Makeup to CCW
Head Tank
2x100%
CWP
2x100%
SWP
2x100%
FFWP &
Jockey PP
1x100% AH
Washing PP
5x RW Well PP
RW Tank
2x100%
Chlorine Booster PP
CCW Heat
Exchanger
2x100%
CCW PP
CW Blow down
TLO Cooler
Gen. Air Cooler
EHC Cooler
BFP Cooler
Sample Cooler
Boiler Area. Cooler
SAC Cooler
Soot Blower
Fuel oil Atom.
Fuel oil Heating
Blow down Makeup.
Condenser Emerg Makeup
Condenser Initial Filling
Boiler Initial Filling
Main Boiler Chem. Feed
Aux. Boiler Chem. Feed
CCW Makeup
Aux.
Boiler
Makeup
Blow down
Wagon Heating
Potable Water Tank
Potable Water Distribution
DM Regen
2x100%
DM Regen PP
DM Tank
2x100% DM
Transfer PP
2x100%
DM Neut PP
Distribution
Plant Bldg
CW
Treatment
Blow down
Tank
Neut Pit
3.0 m3
/h
212 m3
/h
13000 m3
/h
12400 m3
/h
13085 m3
/h
15.0 m3
/h **
600 m3
/h
58 m3
/h
275 m3
/h
313 m3
/h
200 m3
/h **
340 m3
/h **
407 m3
/h
126 m3
/h
240 m3
/h
6 m3
/h
18 m3
/h
3.0 m3
/h
3.0 m3
/h
11 m3
/h
253 m3
/h
660 m3
/h
1.3 m3
/h
3.8 m3
/h
1.8 m3
/h
7.0 m3
/h
13.1 m3
/h
40 m3
/h **
40m3
/h **
2.4m3
/h
0.05 m3
/h
0.5 m3
/h
0.05 m3
/h
0.01 m3
/h
2.3 m3
/h
17.0 m3
/h
DM Plant
1.0 m3
/h **
1.0 m3
/h **
10 m3
/h **5.8m3
/h **22 m3
/h
1.0 m3
/h
13.1 m3
/h **
** Indicate intermittent or emergency flow. This flow has not been considered in water balance calculation.
Ambient Conditions: Dry bulb 42.8 o
C, Wet bulb 28.3 o
C
Bypass
HSD SystemHSD System
HSD
unloading
Pumps
Suction
Strainers
HSD
Unlading
Pumps
HSD
Pressurizing
Pumps Suction
Strainers Y type HSD
Pressurizing
Pumps
HSD Strainers
HSD Day Tank
HSD
Igniters
Aux. BoilerHSD
Pressurizing
Pumps For
Aux boiler
HSD Suction
strainers for
Aux. boiler
HSD Road
Tanker
HSD SystemHSD System
HSD Day Tank Aux. Boiler
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
RFO SystemRFO System
Road Tankers Bay
Rail Wagons Bay
RFO
Transfer
Pumps
Suction
Strainers
RFO
Unloading
Pumps
RFO
Unloading
Pumps
Suction
Strainers
RFO
Transfer
Pumps
RFO
Pressurizing
Pumps Suction
Strainers
RFO
Pressurizing
Pumps
RFO Burner
Deck Suction
Strainers
RFO
Discharge
Heaters
RFO Day Tank
RFO
Burners
RFO Storage Tank-2
RFO Storage Tank-1
RFO Unloading
direct to day tank
& Recirculation
Line
RFO
Return
RFO SystemRFO System
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
Auxiliary Steam SystemAuxiliary Steam System
SCAPH
Gland
Steam
Air Ejector
APH Soot
blower
Igniter
Atomizing
Steam Burner Atomizing
Steam DA
From
CRH
Aux. Boiler
To RFO Storage Tank Area
Heating & Tracing Steam
To RFO
Unloading
Area
SLDS
Aux. header steam pressure
12.5 kg/cm2
Aux. steam pressure 12.5 kg/cm2
From
EXT # 4
PCV-0470
To day
tank oil
heaters
To RFO UL PP, TRF PP, St. TK & UL
heaters
DS
DS
Attemperator
From CEP
Discharge
From CEP
Discharge
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
FI
PI
PI
Inter Condenser
After Condenser
PI
PI
MC-CON.1
CEP Discharge
Aux Steam
Main Ejector
Startup Ejector
(Hogger)
Initial loop Filling
MC-GL-02
Silencer
Condenser
Reducer
200x100
Reducer
200x150
TI
Reducer
50x65
Saba Power Plant
Vacuum System
Mohammad Shoeb Siddiqui
Sr. Shift Supervisor
Aux Steam
Loop Seal
Air evacuation
Condensate CycleCondensate Cycle
Condenser
HW
CEP
Air Ejector GSC Drain Cooler LPH 1
LPH 2LPH 3
Feed Water Tank
DA
2 X 100 %
Capacity
Condenser
HW
Feed Water Tank
DA
Steam from
Ext # 3
251
o
C
Steam from
Ext # 2
151 o
C
Steam from
Ext # 1
87 o
C
92 o
C
112 o
C
136 o
C
48 o
C
Suction
Pressure 1.4
kg/cm2
CEP
Discharge
Pressure
19.3 kg/cm2
DA Pressure
7.8 kg/cm2
&
Temp. 173 o
C
CEP
Air Ejector Drain Cooler LPH 1
LPH 2LPH 3
Condenser
Pressure
-0.92 kg/cm2
Condensate
Flow 365 t/hr
St. Turbine
CSTCST
From Demin
Tank
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
From Demin
Tank
GSC
To Spray
To SLDS Spray
BFP
HPH 5 HPH 6
Feed Water Tank
DA
Boiler Drum
Economizer
Feed Water CycleFeed Water Cycle
BFP
HPH 5 HPH 6
Feed Water Tank
DA
Boiler Drum
Economizer
Steam from CRHSteam from Ext # 5
To HPH # 5To DA
3 X 50 %
Capacity
425 o
C 343 o
C
242 o
C
204 o
C
174 o
C 198 o
C
182 o
C
Suction
Pressure
10.4 kg/cm2
Discharge
Pressure
196 kg/cm2
HPH 5
BFP
HPH 6
Feed water
flow 430 t/hr
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
From LPH # 3
Aux. Steam
TO RH Spray
TO SH Spray
Steam CycleSteam Cycle
Steam Drum
HP Turbine IP & LP Turbine
Condenser
4 X Primary
Super heaters
Reheater
HP bypass
LP bypass
SH
Attemperator
Steam CycleSteam Cycle
HP Turbine IP & LP Turbine
Condenser
Secondary
Super heater
RH
Spray LP bypass Spray
HP
bypass
Spray
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
HP Turbine IP & LP Turbine
Extraction Steam SystemExtraction Steam System
ToDA
TOHPH#6
ToAuxHeader
To Condenser
From Boiler Main Steam
From Main Boiler RH
Hot Reheat
Extraction Steam SystemExtraction Steam System
ToDA
TOHPH#6
ToAuxHeader
TO RH
Cold Reheat
TO LPH # 1
TO LPH # 2
TO LPH # 3
To DA
HPH # 5
To Condenser
To DA
To Aux. Steam Header
To HPH # 6
HP Turbine IP & LP Turbine
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
Saba Power PlantSaba Power Plant
Heat Balance DiagramHeat Balance Diagram
Furnace
Super heater
Re-Heater
Economizer
HPH6
HPH 5
Feed Water Tank
DA
LPH 3 LPH 2
HP Turbine IP & LP Turbine
LPH 1
Condenser
Drain
Cooler
GSC
SJAE
CEP
RFO TRF
PP
BFP
RFO TK-02RFO TK-01
RFO Day TK
HSD
TK
HSD
PP
RFO
PP
GRF
Y
Y
MVSG
UAT 12.5 MVA,
6.6 KV UAT
160 MVA, 132 KV
GT Traffo
Exciter
170 MVA, 134 MW,
15.5 KV Generator
Cooling
Tower
Stack
ESP
CWP
CTF
RAH
SCAPH
FDF
WAPDA
Mohammad Shoeb Siddiqui
Sr. Shift Supervisor
SH Steam Temp. 538 o
C
Press. 168 kg/cm2
413 t/h, 1460.4 BTU/lb
0.335 t/h,
1.058 t/h,
401 t/h,
Aux. Steam header,
fuel atom. 2.7 t/h
43.15 t/h,
19.7 t/h,
15.82 t/h,
19.94 t/h,
12.04 t/h,
LPH1
15.06 t/h,
275.2 t/h,
413.3 t/h,
To DA
179.8 o
C
To HPH #5
204.55 o
C
To LPH#2
107.9 o
C
To LPH#1
86.5 o
C
LPH 1 to
Condenser
56.8 o
C Condenser
Makeup 2.95 t/h
Heat rejection
952.3 BTU/lb
40.0 o
C
45.0 o
C
50.0 o
C
100.0 o
C
33.0 o
C
21.9 o
C
Stack out
150.0 o
C
70.0 o
C
290.0 o
C
365 o
C
Air Gas
174.0 o
C
198.0 o
C
245.0 o
C
428.0 o
C
337 o
C 42 o
C
138.0 o
C
1.38 t/h,
18.95 t/h,
2.17 t/h,
Fuel Heating Area
0.075 t/h,
8.8 t/h,
0.97 t/h,
Aux. Steam
header, fuel
atom. 2.9 t/h
354.8 t/h,
RH Steam Temp. 538 o
C
Press. 38 kg/cm2
354.8 t/h, 1519.2 BTU/lb
Return
From Fuel
Heating
1.45 t/h,
Return
From
Steam Coil
0.25 t/h,
RH Spray
0.27 t/h,
Spray
333.4 t/h,
334.8 t/h,
413.5 t/h,
0.34 t/h,
GS
GS
GS
0.524 t/h,
0.42 t/h,
0.36 t/h,
1.45 t/h,
LOAD CAPABILITY
GEN. OUTPUT 134000 KW
CONDITION 3.5 HG, 0.7% MU
POWER FACTOR 0.9 PF
HEAT RATE 7939 BTU/KWH
THERMAL EFF. 42.99 %
SH Spray
27.06 t/h,
SCAPH
7.13 t/h,
Heaters Drains & VentsHeaters Drains & Vents
Feed Water Tank
HPH # 5
HPH # 6
Condenser
HP Flash Tank
LPH # 3
LPH # 1
LPH # 2
Drain Cooler
GS Condenser
GS Cond. Drain
CEP Discharge
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
Saba Power Plant
Steam Drain System
Mohammad Shoeb Siddiqui
Sr. Shift Supervisor
Condenser
HP Drain
Flash Tank
DR-FT-01
LP Drain
Flash Tank
DR-FT-012
TE
TI
TE
TI
TE
TI
MS Header Drain
HP bypass Seat Drain
MSV before Seat Drain
MSV after Seat Drain
HPT Casing Drain
UV-0685 Spray
From CEP Discharge
LP bypass Seat Drain
UV-0684
From CEP Discharge
Spray
HRH Seat Drain
CRSV (A) After Seat Drain
CRSV (B) After Seat Drain
HPH # 5 Emergency Drain
HPH # 6 Emergency Drain
CRH Header Drain Upstream NRV
CRH Header Drain DW stream NRV
Ext 6 Line Drain Upstream NRV
Ext 6 Line Drain Dw stream NRV
Ext 5 Line Drain Upstream NRV
Ext 5 Line Drain Dw stream NRV
Ext 4 Line Drain Upstream NRV
Ext 4 Line Drain Dw stream NRV
Ext 3 Line Drain Upstream NRV
Ext 3 Line Drain Dw stream NRV
Ext 2 Line Drain Upstream NRV
Ext 2 Line Drain Dw stream NRV
From CEP Discharge
UV-0693
Spray
TE-0690
TE-0691
TE-0692
Hot Well
Air & Flue Gas SystemAir & Flue Gas System
FDF
SCAPH
RAH
GRF
ESP
Stack
Boiler
Flue Gases Flow
Air Flow
FDF
GRF
RAH
FDF outlet air
Pressure 635
mmH2O
Temp. 29.0 o
C
Flue Gas outlet gas
Pressure 56 mmH2O
Temp. 147 o
C
GRF outlet
Pressure 339
mmH2O
Flue gas Pressure 166
mmH2O
Temp. 344 o
C
SCAPH
RAH ESP
Burners
Wind Box
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
Steam
Drum
Ash Hoppers
SH
SH SH
RH SH
SH
ECO
132 / 6.6 / 0.415 KV System132 / 6.6 / 0.415 KV System
G
160 MVA,
132/15.5 KV
Generator
Transformer
(Traffo)
GCB
Generator
Isolator
Earth
Switch
170 MVA
134 MW
Earth
Switch
132 KV
6.6 KV
CWP1CWP2CEP1CEP2
BFP1BFP2BFP3FDFGRF
TR-1TR-2TR-3
415 Volts
PCC-1
415 Volts
PCC-2
415 Volts
PCC-3
PFI Unit
Spare
Enginator
Transf.
Solar
Energy
Elect. Fire
Pump
MCC-4
MCC-5 MCC-6
MCC-7
MCC-8
MCC-3
ACDB
MCC-9
BDB
MCC-2
EMCC
Admen
Bldg.
CWP2CEP2
BFP1BFP3
CWP1CEP1
FDFGRF BFP2
G
Prepared by:Prepared by:
Mohammad ShoebMohammad Shoeb
SiddiquiSiddiqui
132 KV Electrical System132 KV Electrical System
G
FRQ-3 (Line bay # 2)
FRQ-4 (Line bay # 1)
ES-1
ES-2
101
E1Q1
E1Q11
102
E2Q1
E2Q11
E3Q11
E3Q1
E3Q10
160 MVA,
132/15.5 KV
Generator
Transformer
(Traffo)
GCB
Generator
Isolator
Earth
Switch
132 KV Bus bar
170 MVA
134 MW
Earth
Switch
From & to Wapda
Farooqabad Grid
G
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor
Saba Power PlantSaba Power Plant
Automatic Water Supply Preaction SystemAutomatic Water Supply Preaction System
Mohammad Shoeb Siddiqui
Sr. Shift Supervisor
Hazard To Be Protected
Dry Pilot
Actuator D
PSL
PI
Pressure
Regulator
PI
PSH
From Instrument Air Supply
PAL PAH
Fire
Alarm
Water Motor
Gang
PIV
Lo
Lo
TBST Point
Main Fire Water Header
Saba Power PlantSaba Power Plant
Wet Pipe Sprinkler SystemWet Pipe Sprinkler System
Mohammad Shoeb Siddiqui
Sr. Shift Supervisor
PSH
PAH
Fire
Alarm
Water Motor
Gang
PIV
Main Fire Water Header
Fire
Alarm
Lo
NRV
A
PI
Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui
Senior Shift SupervisorSenior Shift Supervisor

Contenu connexe

Tendances

Gas turbine 2 - regeneration and intercooling
Gas turbine   2 - regeneration and intercoolingGas turbine   2 - regeneration and intercooling
Gas turbine 2 - regeneration and intercoolingNihal Senanayake
 
210 mw turbine cycle heat rate
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rateManohar Tatwawadi
 
660 mw turbo generator &amp; its auxiliaries
660 mw turbo generator &amp; its auxiliaries660 mw turbo generator &amp; its auxiliaries
660 mw turbo generator &amp; its auxiliariesAshvani Shukla
 
ASH HANDLING PLANT
ASH HANDLING PLANTASH HANDLING PLANT
ASH HANDLING PLANTAditya Anand
 
Thermal Power Plant - Emergency situations
Thermal Power Plant   -   Emergency situations Thermal Power Plant   -   Emergency situations
Thermal Power Plant - Emergency situations Ashish Kumar Jain
 
Steam Turbine Performance in TPS
Steam Turbine Performance in TPSSteam Turbine Performance in TPS
Steam Turbine Performance in TPSManohar Tatwawadi
 
METHODS OF IMPROVING STEAM TURBINE PERFORMANCE
METHODS OF IMPROVING STEAM TURBINE PERFORMANCEMETHODS OF IMPROVING STEAM TURBINE PERFORMANCE
METHODS OF IMPROVING STEAM TURBINE PERFORMANCEVanita Thakkar
 
Steam Turbines
Steam Turbines Steam Turbines
Steam Turbines Amir Ayad
 
[PPT] on Steam Turbine
[PPT] on Steam Turbine[PPT] on Steam Turbine
[PPT] on Steam TurbineSumit Sharma
 
Hp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesHp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesBoben Anto Chemmannoor
 
Boiler Drum And Its Internals
Boiler Drum And Its InternalsBoiler Drum And Its Internals
Boiler Drum And Its InternalsAshrant Dass
 
Heat rate audit in thermal power plant
Heat rate audit in thermal power plantHeat rate audit in thermal power plant
Heat rate audit in thermal power plantSHIVAJI CHOUDHURY
 
Bhel steam turbine manufacturing
Bhel steam turbine manufacturingBhel steam turbine manufacturing
Bhel steam turbine manufacturingHome
 
Fans in thermal power plants
Fans in thermal power plantsFans in thermal power plants
Fans in thermal power plantsSHIVAJI CHOUDHURY
 
Relief and safety valves for thermal power plants
Relief and safety valves for thermal power plantsRelief and safety valves for thermal power plants
Relief and safety valves for thermal power plantsSHIVAJI CHOUDHURY
 
Mejia Thermal Power Station
Mejia Thermal Power StationMejia Thermal Power Station
Mejia Thermal Power Stationsagnikchoudhury
 
EXPERIMENTAL ANALYSIS OF A MINI STEAM POWER PLANT
EXPERIMENTAL ANALYSIS OF A MINI STEAM  POWER PLANTEXPERIMENTAL ANALYSIS OF A MINI STEAM  POWER PLANT
EXPERIMENTAL ANALYSIS OF A MINI STEAM POWER PLANTMOHAMMED SHAROOQ
 

Tendances (20)

Gas turbine 2 - regeneration and intercooling
Gas turbine   2 - regeneration and intercoolingGas turbine   2 - regeneration and intercooling
Gas turbine 2 - regeneration and intercooling
 
Gas turbines
Gas turbinesGas turbines
Gas turbines
 
210 mw turbine cycle heat rate
210 mw turbine cycle heat rate210 mw turbine cycle heat rate
210 mw turbine cycle heat rate
 
660 mw turbo generator &amp; its auxiliaries
660 mw turbo generator &amp; its auxiliaries660 mw turbo generator &amp; its auxiliaries
660 mw turbo generator &amp; its auxiliaries
 
ASH HANDLING PLANT
ASH HANDLING PLANTASH HANDLING PLANT
ASH HANDLING PLANT
 
Thermal Power Plant - Emergency situations
Thermal Power Plant   -   Emergency situations Thermal Power Plant   -   Emergency situations
Thermal Power Plant - Emergency situations
 
Steam Turbine Performance in TPS
Steam Turbine Performance in TPSSteam Turbine Performance in TPS
Steam Turbine Performance in TPS
 
METHODS OF IMPROVING STEAM TURBINE PERFORMANCE
METHODS OF IMPROVING STEAM TURBINE PERFORMANCEMETHODS OF IMPROVING STEAM TURBINE PERFORMANCE
METHODS OF IMPROVING STEAM TURBINE PERFORMANCE
 
Steam Turbines
Steam Turbines Steam Turbines
Steam Turbines
 
[PPT] on Steam Turbine
[PPT] on Steam Turbine[PPT] on Steam Turbine
[PPT] on Steam Turbine
 
Hp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesHp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbines
 
Boiler Drum And Its Internals
Boiler Drum And Its InternalsBoiler Drum And Its Internals
Boiler Drum And Its Internals
 
Steam generator part 1
Steam generator part 1Steam generator part 1
Steam generator part 1
 
Heat rate audit in thermal power plant
Heat rate audit in thermal power plantHeat rate audit in thermal power plant
Heat rate audit in thermal power plant
 
Bhel steam turbine manufacturing
Bhel steam turbine manufacturingBhel steam turbine manufacturing
Bhel steam turbine manufacturing
 
Power Plant Boiler feed pump
Power Plant Boiler feed pump Power Plant Boiler feed pump
Power Plant Boiler feed pump
 
Fans in thermal power plants
Fans in thermal power plantsFans in thermal power plants
Fans in thermal power plants
 
Relief and safety valves for thermal power plants
Relief and safety valves for thermal power plantsRelief and safety valves for thermal power plants
Relief and safety valves for thermal power plants
 
Mejia Thermal Power Station
Mejia Thermal Power StationMejia Thermal Power Station
Mejia Thermal Power Station
 
EXPERIMENTAL ANALYSIS OF A MINI STEAM POWER PLANT
EXPERIMENTAL ANALYSIS OF A MINI STEAM  POWER PLANTEXPERIMENTAL ANALYSIS OF A MINI STEAM  POWER PLANT
EXPERIMENTAL ANALYSIS OF A MINI STEAM POWER PLANT
 

En vedette

Presentation By N.A. Zuberi
Presentation By N.A. ZuberiPresentation By N.A. Zuberi
Presentation By N.A. ZuberiIEEEP Karachi
 
Migrating Bailey Consoles R1
Migrating Bailey Consoles R1Migrating Bailey Consoles R1
Migrating Bailey Consoles R1Alvaro Rendon
 
Presentation experiance & achievements 2010-16
Presentation experiance & achievements 2010-16Presentation experiance & achievements 2010-16
Presentation experiance & achievements 2010-16waqar ahmed
 
Burness NHS Procurement Seminar - 30 March 2010
Burness NHS Procurement Seminar - 30 March 2010Burness NHS Procurement Seminar - 30 March 2010
Burness NHS Procurement Seminar - 30 March 2010Elaine Creamer
 
An introduction to the hub Initiative for Contacts Fair Conference 2.10.15
An introduction to the hub Initiative for Contacts Fair Conference 2.10.15An introduction to the hub Initiative for Contacts Fair Conference 2.10.15
An introduction to the hub Initiative for Contacts Fair Conference 2.10.15Euan Pirie
 
Circular Debt in Energy Sector of Pakistan
Circular Debt in Energy Sector of PakistanCircular Debt in Energy Sector of Pakistan
Circular Debt in Energy Sector of PakistanAshar Ahmed
 
Credit & Risk analysis of Hubco power company Pakistan
Credit & Risk analysis of Hubco power company PakistanCredit & Risk analysis of Hubco power company Pakistan
Credit & Risk analysis of Hubco power company PakistanIrfan Tanwari
 
combine cycle diesel power plant
combine cycle diesel power plantcombine cycle diesel power plant
combine cycle diesel power plantJawad Ali
 
Lecture 06: Advanced Project Management Project Organization and Integration
Lecture 06: Advanced Project Management  Project Organization and IntegrationLecture 06: Advanced Project Management  Project Organization and Integration
Lecture 06: Advanced Project Management Project Organization and IntegrationFida Karim 🇵🇰
 
Exxon Mobil B2B Project
Exxon Mobil  B2B ProjectExxon Mobil  B2B Project
Exxon Mobil B2B ProjectAli Raza Anjum
 

En vedette (20)

STEAM GENERATOR Part 3
STEAM GENERATOR Part 3STEAM GENERATOR Part 3
STEAM GENERATOR Part 3
 
Cooling water (CW) system
Cooling water (CW) system Cooling water (CW) system
Cooling water (CW) system
 
Presentation By N.A. Zuberi
Presentation By N.A. ZuberiPresentation By N.A. Zuberi
Presentation By N.A. Zuberi
 
Introduction of Electricity
Introduction of ElectricityIntroduction of Electricity
Introduction of Electricity
 
Steam generator part 2
Steam generator part 2Steam generator part 2
Steam generator part 2
 
Steam generator part 3
Steam generator part 3Steam generator part 3
Steam generator part 3
 
High Pressure Boilers
High Pressure BoilersHigh Pressure Boilers
High Pressure Boilers
 
Shaft seals
Shaft sealsShaft seals
Shaft seals
 
Nadeem Naseem CV
Nadeem Naseem CVNadeem Naseem CV
Nadeem Naseem CV
 
Migrating Bailey Consoles R1
Migrating Bailey Consoles R1Migrating Bailey Consoles R1
Migrating Bailey Consoles R1
 
Brain Force Biz
Brain Force BizBrain Force Biz
Brain Force Biz
 
Presentation experiance & achievements 2010-16
Presentation experiance & achievements 2010-16Presentation experiance & achievements 2010-16
Presentation experiance & achievements 2010-16
 
Burness NHS Procurement Seminar - 30 March 2010
Burness NHS Procurement Seminar - 30 March 2010Burness NHS Procurement Seminar - 30 March 2010
Burness NHS Procurement Seminar - 30 March 2010
 
An introduction to the hub Initiative for Contacts Fair Conference 2.10.15
An introduction to the hub Initiative for Contacts Fair Conference 2.10.15An introduction to the hub Initiative for Contacts Fair Conference 2.10.15
An introduction to the hub Initiative for Contacts Fair Conference 2.10.15
 
Circular Debt in Energy Sector of Pakistan
Circular Debt in Energy Sector of PakistanCircular Debt in Energy Sector of Pakistan
Circular Debt in Energy Sector of Pakistan
 
Credit & Risk analysis of Hubco power company Pakistan
Credit & Risk analysis of Hubco power company PakistanCredit & Risk analysis of Hubco power company Pakistan
Credit & Risk analysis of Hubco power company Pakistan
 
combine cycle diesel power plant
combine cycle diesel power plantcombine cycle diesel power plant
combine cycle diesel power plant
 
Lecture 06: Advanced Project Management Project Organization and Integration
Lecture 06: Advanced Project Management  Project Organization and IntegrationLecture 06: Advanced Project Management  Project Organization and Integration
Lecture 06: Advanced Project Management Project Organization and Integration
 
EAF PDF
EAF PDFEAF PDF
EAF PDF
 
Exxon Mobil B2B Project
Exxon Mobil  B2B ProjectExxon Mobil  B2B Project
Exxon Mobil B2B Project
 

Similaire à Saba Power Plant

St module1 1 jan2008
St module1  1 jan2008St module1  1 jan2008
St module1 1 jan2008kjmughal
 
Rooppur NPP Turbine shop beginners course.pptx
Rooppur NPP Turbine shop beginners course.pptxRooppur NPP Turbine shop beginners course.pptx
Rooppur NPP Turbine shop beginners course.pptxNusrat Karim
 
Hydrogen & Bio Gas Engines Generator sets150 kw to 1 mw 1000kw
Hydrogen & Bio Gas Engines Generator sets150 kw to 1 mw 1000kwHydrogen & Bio Gas Engines Generator sets150 kw to 1 mw 1000kw
Hydrogen & Bio Gas Engines Generator sets150 kw to 1 mw 1000kwDaniel Donatelli
 
CESC SGS project report
CESC SGS project reportCESC SGS project report
CESC SGS project reportSayanSarkar55
 
Congres F-gassen 2015. Workshop 8: Scroll CO2, bied veel meer dan alleen een ...
Congres F-gassen 2015. Workshop 8: Scroll CO2, bied veel meer dan alleen een ...Congres F-gassen 2015. Workshop 8: Scroll CO2, bied veel meer dan alleen een ...
Congres F-gassen 2015. Workshop 8: Scroll CO2, bied veel meer dan alleen een ...RCCKL
 
Amardeep jadeja copy.ppt [autosaved]
Amardeep jadeja   copy.ppt [autosaved]Amardeep jadeja   copy.ppt [autosaved]
Amardeep jadeja copy.ppt [autosaved]Amardeep Jadeja
 
THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)Baibhav Saha
 
Urja thermal solutions
Urja thermal solutionsUrja thermal solutions
Urja thermal solutionsHemant Sharma
 
ENERGY SAVING BY AIR WASHER PUMPS #5 ASH PLANT AT GTPS
ENERGY SAVING BY AIR WASHER PUMPS #5 ASH PLANT AT GTPSENERGY SAVING BY AIR WASHER PUMPS #5 ASH PLANT AT GTPS
ENERGY SAVING BY AIR WASHER PUMPS #5 ASH PLANT AT GTPSDilipkumar Pandya
 
Guru Nanak Dev thermal plant bathinda industrial training by hardeep
Guru Nanak Dev thermal  plant bathinda industrial training by hardeepGuru Nanak Dev thermal  plant bathinda industrial training by hardeep
Guru Nanak Dev thermal plant bathinda industrial training by hardeepHardeep Singh
 
Presentation of thermal_power_plant
Presentation of thermal_power_plantPresentation of thermal_power_plant
Presentation of thermal_power_plantprakash2704
 
EMERSON Power plant applications
EMERSON Power plant applicationsEMERSON Power plant applications
EMERSON Power plant applicationsmirfanm
 
Emerson Power plant applications
Emerson Power plant applicationsEmerson Power plant applications
Emerson Power plant applicationsmirfanm
 
C2 - BINARY POWER PLANTS FOR HIGH-ENTHALPY WELL-HEAD GENERATION
C2 - BINARY POWER PLANTS FOR HIGH-ENTHALPY WELL-HEAD GENERATIONC2 - BINARY POWER PLANTS FOR HIGH-ENTHALPY WELL-HEAD GENERATION
C2 - BINARY POWER PLANTS FOR HIGH-ENTHALPY WELL-HEAD GENERATIONIceland Geothermal
 

Similaire à Saba Power Plant (20)

St module1 1 jan2008
St module1  1 jan2008St module1  1 jan2008
St module1 1 jan2008
 
Rooppur NPP Turbine shop beginners course.pptx
Rooppur NPP Turbine shop beginners course.pptxRooppur NPP Turbine shop beginners course.pptx
Rooppur NPP Turbine shop beginners course.pptx
 
V.T ppt
V.T pptV.T ppt
V.T ppt
 
Engine Brochure.pdf
Engine Brochure.pdfEngine Brochure.pdf
Engine Brochure.pdf
 
Hydrogen & Bio Gas Engines Generator sets150 kw to 1 mw 1000kw
Hydrogen & Bio Gas Engines Generator sets150 kw to 1 mw 1000kwHydrogen & Bio Gas Engines Generator sets150 kw to 1 mw 1000kw
Hydrogen & Bio Gas Engines Generator sets150 kw to 1 mw 1000kw
 
ppt on kstps 2016
ppt on kstps 2016ppt on kstps 2016
ppt on kstps 2016
 
CESC SGS project report
CESC SGS project reportCESC SGS project report
CESC SGS project report
 
Congres F-gassen 2015. Workshop 8: Scroll CO2, bied veel meer dan alleen een ...
Congres F-gassen 2015. Workshop 8: Scroll CO2, bied veel meer dan alleen een ...Congres F-gassen 2015. Workshop 8: Scroll CO2, bied veel meer dan alleen een ...
Congres F-gassen 2015. Workshop 8: Scroll CO2, bied veel meer dan alleen een ...
 
Amardeep jadeja copy.ppt [autosaved]
Amardeep jadeja   copy.ppt [autosaved]Amardeep jadeja   copy.ppt [autosaved]
Amardeep jadeja copy.ppt [autosaved]
 
THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)THERMAL POWER PLANT (COAL TO POWER)
THERMAL POWER PLANT (COAL TO POWER)
 
Urja thermal solutions
Urja thermal solutionsUrja thermal solutions
Urja thermal solutions
 
DCU overview.pdf
DCU overview.pdfDCU overview.pdf
DCU overview.pdf
 
ENERGY SAVING BY AIR WASHER PUMPS #5 ASH PLANT AT GTPS
ENERGY SAVING BY AIR WASHER PUMPS #5 ASH PLANT AT GTPSENERGY SAVING BY AIR WASHER PUMPS #5 ASH PLANT AT GTPS
ENERGY SAVING BY AIR WASHER PUMPS #5 ASH PLANT AT GTPS
 
Guru Nanak Dev thermal plant bathinda industrial training by hardeep
Guru Nanak Dev thermal  plant bathinda industrial training by hardeepGuru Nanak Dev thermal  plant bathinda industrial training by hardeep
Guru Nanak Dev thermal plant bathinda industrial training by hardeep
 
foram
foramforam
foram
 
Pintu raj
Pintu rajPintu raj
Pintu raj
 
Presentation of thermal_power_plant
Presentation of thermal_power_plantPresentation of thermal_power_plant
Presentation of thermal_power_plant
 
EMERSON Power plant applications
EMERSON Power plant applicationsEMERSON Power plant applications
EMERSON Power plant applications
 
Emerson Power plant applications
Emerson Power plant applicationsEmerson Power plant applications
Emerson Power plant applications
 
C2 - BINARY POWER PLANTS FOR HIGH-ENTHALPY WELL-HEAD GENERATION
C2 - BINARY POWER PLANTS FOR HIGH-ENTHALPY WELL-HEAD GENERATIONC2 - BINARY POWER PLANTS FOR HIGH-ENTHALPY WELL-HEAD GENERATION
C2 - BINARY POWER PLANTS FOR HIGH-ENTHALPY WELL-HEAD GENERATION
 

Dernier

How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .Alan Dix
 
Potential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsPotential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsRavi Sanghani
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsPixlogix Infotech
 
So einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdfSo einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdfpanagenda
 
Time Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsTime Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsNathaniel Shimoni
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxLoriGlavin3
 
(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...
(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...
(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...AliaaTarek5
 
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyesHow to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyesThousandEyes
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxLoriGlavin3
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfLoriGlavin3
 
Data governance with Unity Catalog Presentation
Data governance with Unity Catalog PresentationData governance with Unity Catalog Presentation
Data governance with Unity Catalog PresentationKnoldus Inc.
 
A Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersA Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersNicole Novielli
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc
 
A Framework for Development in the AI Age
A Framework for Development in the AI AgeA Framework for Development in the AI Age
A Framework for Development in the AI AgeCprime
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...Wes McKinney
 
[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality Assurance[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality AssuranceInflectra
 
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better StrongerModern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better Strongerpanagenda
 
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Alkin Tezuysal
 

Dernier (20)

How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .From Family Reminiscence to Scholarly Archive .
From Family Reminiscence to Scholarly Archive .
 
Potential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsPotential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and Insights
 
The Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and ConsThe Ultimate Guide to Choosing WordPress Pros and Cons
The Ultimate Guide to Choosing WordPress Pros and Cons
 
So einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdfSo einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdf
 
Time Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsTime Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directions
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
 
(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...
(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...
(How to Program) Paul Deitel, Harvey Deitel-Java How to Program, Early Object...
 
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyesHow to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
How to Effectively Monitor SD-WAN and SASE Environments with ThousandEyes
 
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptxPasskey Providers and Enabling Portability: FIDO Paris Seminar.pptx
Passkey Providers and Enabling Portability: FIDO Paris Seminar.pptx
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdf
 
Data governance with Unity Catalog Presentation
Data governance with Unity Catalog PresentationData governance with Unity Catalog Presentation
Data governance with Unity Catalog Presentation
 
A Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software DevelopersA Journey Into the Emotions of Software Developers
A Journey Into the Emotions of Software Developers
 
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data PrivacyTrustArc Webinar - How to Build Consumer Trust Through Data Privacy
TrustArc Webinar - How to Build Consumer Trust Through Data Privacy
 
A Framework for Development in the AI Age
A Framework for Development in the AI AgeA Framework for Development in the AI Age
A Framework for Development in the AI Age
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
The Future Roadmap for the Composable Data Stack - Wes McKinney - Data Counci...
 
[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality Assurance[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality Assurance
 
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better StrongerModern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
 
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
Unleashing Real-time Insights with ClickHouse_ Navigating the Landscape in 20...
 

Saba Power Plant

  • 1.
  • 2. Saba Power PlantSaba Power Plant 134 MW Steam Turbine Unit134 MW Steam Turbine Unit Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor
  • 3. IntroductionIntroduction Location Saba Power Plant is situated at 9 km Sargodha road near Jhamke village. Shaikhupura Total Area Total area is around 290779 m2 (72 acres). Power block of the Plant occupies 20% of total site (200 x 300 = 60000 m2 ). Main Occupied Areas 132 KV Switch Yard, Transformers, Natural Gas Generators, RFO Unloading Station, RFO Storage Tanks, RFO Day Tank, Demin Plant, Raw Water & Demin Water Storage Tanks, Auxiliary Boiler, Chemical Laboratory, Control Building, Main Boiler, ESP & Stack, Steam Turbine, Generator, Cooling Tower, Retention Ponds, Mechanical Workshop, Rest House and Administration Block. Around 14 acres consists of garden that has plants of Lemon, Orange, Kino, Grapefruit and Guava. Almost 60% of the area is not in use. Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor
  • 5. IntroductionIntroduction  Total Generation CapacityTotal Generation Capacity • 1X134 MW Steam Turbine Generator1X134 MW Steam Turbine Generator • 4X0.9 MW Natural Gas Engine Generator4X0.9 MW Natural Gas Engine Generator (Installed in year 2009).(Installed in year 2009).  Controlling SystemControlling System • Main Plant Control on DCS Bailey Infi 90 & Rovisys ExperionMain Plant Control on DCS Bailey Infi 90 & Rovisys Experion • PLC (ABB, Allen Bradley, PanelMate)PLC (ABB, Allen Bradley, PanelMate) Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor Guaranteed Heat Rate (Thermal Efficiency) as per ppa 8842 Btu's per kWh, based on the higher heating value (HHV) of fuel and the net output of the Complex.  COD Commercial Operation Date = 31 December 1999COD Commercial Operation Date = 31 December 1999  PPA (Power Purchase Agreement) established in 26 DecemberPPA (Power Purchase Agreement) established in 26 December 1994 and finally signed on 18 August 1997.1994 and finally signed on 18 August 1997.  Thermal Efficiency = 42.99 %Thermal Efficiency = 42.99 %
  • 6. Major ComponentsMajor Components  413 Tons, Main Boiler (B&W)413 Tons, Main Boiler (B&W)  134 MW, Steam Turbine (Toshiba)134 MW, Steam Turbine (Toshiba)  170 MVA, Generator (Toshiba)170 MVA, Generator (Toshiba)  Surface Condenser (Ecolaire Corp.)Surface Condenser (Ecolaire Corp.)  Cooling Tower (GEA)Cooling Tower (GEA)  Demineralization Plant (Ecodyne)Demineralization Plant (Ecodyne)  23 Tons, Auxiliary Boiler (B&W GAMA)23 Tons, Auxiliary Boiler (B&W GAMA)  132 KV Switchyard (Siemens)132 KV Switchyard (Siemens)  Generator Switchgear (ABB)Generator Switchgear (ABB)  6.6 KV/0.415 KV MVSG (Cutler Hammer)6.6 KV/0.415 KV MVSG (Cutler Hammer)  160 MVA Generator Transformer (Hyundai)160 MVA Generator Transformer (Hyundai)  12.5 MVA Auxiliary Transformer12.5 MVA Auxiliary Transformer (Pennsylvania)(Pennsylvania)  UPS (Cyberex Incorporated)UPS (Cyberex Incorporated)  125 V DC System, Battery Charger (C&D Tech.)125 V DC System, Battery Charger (C&D Tech.)  Storage TanksStorage Tanks (RFO, HSD, Raw & Demin Water, Acid & Caustic, Chemical Feed)(RFO, HSD, Raw & Demin Water, Acid & Caustic, Chemical Feed)
  • 7. Major ComponentsMajor Components  6.6 KV Motors (Westinghouse, )6.6 KV Motors (Westinghouse, )  Boiler Feed Pumps (KSB)Boiler Feed Pumps (KSB)  CEP & CW pumps (Johnston)CEP & CW pumps (Johnston)  0.4 KV Pumps (Goulds)0.4 KV Pumps (Goulds)  0.4 KV Motor (Reliance)0.4 KV Motor (Reliance)  500 KW Emergency Diesel Generator500 KW Emergency Diesel Generator (Caterpillar)(Caterpillar)  200 HP Diesel Fire Engine (Caterpillar)200 HP Diesel Fire Engine (Caterpillar)  Fire Water System (Viking)Fire Water System (Viking)  Fire Water Pumps (ITT)Fire Water Pumps (ITT)  Regenerative Air Heater (ABB Ljungstrom)Regenerative Air Heater (ABB Ljungstrom)  Steam Coil Air Heater (LAPCO)Steam Coil Air Heater (LAPCO)  Soot Blowers (Diamond)Soot Blowers (Diamond)  Safety Valves (Dresser)Safety Valves (Dresser)  Transmitters (Fisher – Rosemount)Transmitters (Fisher – Rosemount)  ESP & Ash Handling SystemESP & Ash Handling System  Feed Water Heaters (Struthers Well Corp.)Feed Water Heaters (Struthers Well Corp.)  Deaerator (Sterling)Deaerator (Sterling) Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor
  • 8. Main BoilerMain Boiler Specification: Manufacturer Babcock & Wilcox (USA) Model Out Door Type, Series 2, Elpaso Radiant Year Manufactured 1997 Services Base Load Type Pressurized Furness, natural circulation with reheat. Boiler Fuels #6 Residual Fuel Oil (RFO/HSFO)/ Diesel Light of fuel (HSD) Number Of Burner and Igniters 6 x 6 Low NOx, Steam automised burners/Igniters, in 3 floors, 2 burners/Igniters on each floor. GRF Gas recirculation for RH protection and NOX controls. Fuel Consumption 29 tons/hr (On Maximum load) Heat Rate 7939 btu/kwh (On Ideal Conditions) Boiler Heating Surface: 8929 sq.foot Economizer Heating Surface 13.465 sq.foot Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor
  • 9. HP Steam Flow 413 tons/hr HP Steam Pressure 171.9 kg/cm2 HP Steam Temperature 540.5 o C Reheat Steam Flow 354.7 Reheat Steam Pressure 37.2 kg/cm2 Reheat Steam Temperature 538.3 o C Burner interlocks and control BMS (Burner management System) Soot Blowers 09 soot blowers, 06 for super heater, 02 reheater, 01 Economizer & 1 Soot Blower for Air Heater Boiler Major Auxiliaries 3x50% BFP 2600 HP, FDF 2250 HP, GRF 585 HP, Seal Air Blower, Air Heater drive Motor, Flame Scanner Blower Ash System ESP, Ash Hoppers, Ash, Transport Blower, Ash Soot Silo, Stack Boiler Efficiency 88 % Main Boiler Prepared by:Prepared by: Mohammad ShoebMohammad Shoeb SiddiquiSiddiqui Senior ShiftSenior Shift SupervisorSupervisor
  • 10. Steam TurbineSteam Turbine Specification: Manufacturer Toshiba (Japan) Type SCSF – 36", Single Cylinder, Single Flow Reheat Condensing Turbine. Rating Capacity 134 MW Speed RPM 3000 rpm No. Of Stages 21 stages (9 HP, 7 IP, 5LP) No. Of Extractions 06 Steam Flow 408233 kg/hr Rating Pressure 169.8 kg/cm2 Turbine Efficiency 49.84 % Turbine Control System (Governing System) D-EHC Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor
  • 11. Steam TurbineSteam Turbine Steam Condition HP STEAM Flow 413 T/hr Pressure 168 kg/cm2 Temperature 538 °C LP STEAM (Reheat Steam) Flow 378 T/hr Pressure 37.2 kg/cm2 Temperature 538 °C Exhaust Pressure 6.77 kpaa Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor
  • 12. GeneratorGenerator Specification Manufacturer Toshiba Year Manufactured 1998 Model # TAKL-RCH , 2 pole Rated voltage 15.5 kv Rated Capacity 170 MVA Frequency 50 Hz Rated Current 6333 Amps Power Factor 0.8 Lagging Speed 3000 rpm Pole 2 Rotor cooling Air (Air Cooling From CCW) Stator cooling Air (Air Cooling From CCW) Generator Efficiency 98 % Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor
  • 13. Emergency Diesel GeneratorEmergency Diesel Generator Emergency Diesel Generator (EDG)Emergency Diesel Generator (EDG) A 500 KW diesel generator is provided at site for black plant situationA 500 KW diesel generator is provided at site for black plant situation to run the plant necessary auxiliaries like:to run the plant necessary auxiliaries like: • Rotary air heaterRotary air heater • Turbine lube oil systemTurbine lube oil system • Turbine turning gearTurbine turning gear • GRF turning gearGRF turning gear • Necessary plant lighteningNecessary plant lightening • Turbine drain MOVsTurbine drain MOVs • Battery charging.Battery charging. • BFP Lube oil PumpsBFP Lube oil Pumps EDG starts automatically in case of any power failure. An ATS isEDG starts automatically in case of any power failure. An ATS is provided at EMCC for transferring load from PCC-2 to EDGprovided at EMCC for transferring load from PCC-2 to EDG source. 300 gals of HSD tank is also provided for EDGsource. 300 gals of HSD tank is also provided for EDG Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor
  • 14. DSC SYSTEM (REDUNDANT PROCESS CONTROL UNIT INTERFACE)DSC SYSTEM (REDUNDANT PROCESS CONTROL UNIT INTERFACE) INFI-NET LOOP NIS NPM NPM NIS CONTROLWAY MFP MFP MFP MFP MFP MFP I/O Module I/O Module I/O Module I/O Module I/O Module I/O Module I/O EXPONDER BUS I/O EXPONDER BUS PCU 5XOIS 7 X PCU EWS 3 X PRINTERS250 NODES UPTO 32 MODULES UPTO 64 MODULES UPTO 64 MODULES HISTORION Prepared by:Prepared by: Mohammad ShoebMohammad Shoeb SiddiquiSiddiqui Senior Shift SupervisorSenior Shift Supervisor
  • 17. Process Cycles & SystemsProcess Cycles & Systems Raw & Service Water SystemRaw & Service Water System Demineralization PlantDemineralization Plant Close Cooling Water SystemClose Cooling Water System Circulating Water SystemCirculating Water System HSD SystemHSD System RFO SystemRFO System Aux. Steam SystemAux. Steam System Feed Water CycleFeed Water Cycle Condensate CycleCondensate Cycle Steam CycleSteam Cycle Extraction Steam SystemExtraction Steam System Heaters Vents & DrainsHeaters Vents & Drains 132 KV System132 KV System 132 / 6.6 / 0.415 KV System132 / 6.6 / 0.415 KV System Air & Flue Gas SystemAir & Flue Gas System Service & Instrument Air SystemService & Instrument Air System Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor
  • 18. Service & Instrument Air SystemService & Instrument Air System SAC1 SAC2 Air Receiver SAC3 Air Compressors Aspirating Air Compressor Air Purification & Drying System Instrument Air Service Air Main Boiler Aspirating Air Instrument Air Pressure 7.2 kg/cm2 Service Air Pressure 7.4 kg/cm2 SAC1 SAC3 SAC2 Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor
  • 19. Potable Water Tank Raw & Fire Water Tank Capacity 2155 m3 Bore Well # 1 Bore Well # 2 Bore Well # 3 Bore Well # 4 Bore Well # 5 Electric Fire Pump Diesel Engine Fire Pump Jockey Fire Pump To Fire water system To CT Basin Makeup To Air Heater Washing To All Plant Service Water Supply Service Water Pump 1 Service Water Pump 2 Service Water Pump 3 To Fire water system Raw / Service & Fire Water SystemRaw / Service & Fire Water System Service Water Pressure 7.2 kg/cm2 Fire water Pressure 9.5 kg/cm2 Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor
  • 20. Demineralization PlantDemineralization Plant Service CycleService Cycle Service Water Inlet Flow 29 m3 /hr CAT Ion Exchanger collect + ions De-Gasifier Blowers De-Gasifier Removes Un dissolve gases De-Gasifier Pumps An Ion Exchanger collects -ions Mixed Bed Polisher Demin water out to Tank Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor Conductivity = 1000 uS/cm pH = 7.8 to 8.0, Silica = 27 ppm Conductivity = < 0.2 uS/cm pH = 6.8 to 7.2, Silica = < 20 ppb
  • 21. CCW SystemCCW System CCW Makeup Tank Heat Exchangers Lube Oil Cooler Generator Coolers EHC Cooler BFP Cooler SAC Cooler RAH Cooler Ash Handling System SWAS CCW Pumps From DM Tank Pot Feeder Pressure 4.5 kg/cm2 CCW Makeup TankCCW Makeup Tank Inlet Temp. 33 o C Outlet Temp. 33 o C Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor
  • 22. Circulating Water SystemCirculating Water System Raw Water Tank Cooling Tower Condenser 2x100 % CW Pump CTF From Bore Wells CT Makeup Ambient Condition Temp. 27.5 o C Humidity 88.5 % CW I/L Temp. 30 o C CW O/L Temp. 45 o C CCW Heat Exchanger Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor
  • 23. Saba Power PlantSaba Power Plant Water Balance Diagram (Water Balance Diagram (Average Flow)Average Flow) Mohammad Shoeb Siddiqui Sr. Shift Supervisor Cooling Tower CT Sump Drift Loss Evaporation Loss Condenser CT Basin Power System Makeup CST Makeup to CCW Head Tank 2x100% CWP 2x100% SWP 2x100% FFWP & Jockey PP 1x100% AH Washing PP 5x RW Well PP RW Tank 2x100% Chlorine Booster PP CCW Heat Exchanger 2x100% CCW PP CW Blow down TLO Cooler Gen. Air Cooler EHC Cooler BFP Cooler Sample Cooler Boiler Area. Cooler SAC Cooler Soot Blower Fuel oil Atom. Fuel oil Heating Blow down Makeup. Condenser Emerg Makeup Condenser Initial Filling Boiler Initial Filling Main Boiler Chem. Feed Aux. Boiler Chem. Feed CCW Makeup Aux. Boiler Makeup Blow down Wagon Heating Potable Water Tank Potable Water Distribution DM Regen 2x100% DM Regen PP DM Tank 2x100% DM Transfer PP 2x100% DM Neut PP Distribution Plant Bldg CW Treatment Blow down Tank Neut Pit 3.0 m3 /h 212 m3 /h 13000 m3 /h 12400 m3 /h 13085 m3 /h 15.0 m3 /h ** 600 m3 /h 58 m3 /h 275 m3 /h 313 m3 /h 200 m3 /h ** 340 m3 /h ** 407 m3 /h 126 m3 /h 240 m3 /h 6 m3 /h 18 m3 /h 3.0 m3 /h 3.0 m3 /h 11 m3 /h 253 m3 /h 660 m3 /h 1.3 m3 /h 3.8 m3 /h 1.8 m3 /h 7.0 m3 /h 13.1 m3 /h 40 m3 /h ** 40m3 /h ** 2.4m3 /h 0.05 m3 /h 0.5 m3 /h 0.05 m3 /h 0.01 m3 /h 2.3 m3 /h 17.0 m3 /h DM Plant 1.0 m3 /h ** 1.0 m3 /h ** 10 m3 /h **5.8m3 /h **22 m3 /h 1.0 m3 /h 13.1 m3 /h ** ** Indicate intermittent or emergency flow. This flow has not been considered in water balance calculation. Ambient Conditions: Dry bulb 42.8 o C, Wet bulb 28.3 o C Bypass
  • 24. HSD SystemHSD System HSD unloading Pumps Suction Strainers HSD Unlading Pumps HSD Pressurizing Pumps Suction Strainers Y type HSD Pressurizing Pumps HSD Strainers HSD Day Tank HSD Igniters Aux. BoilerHSD Pressurizing Pumps For Aux boiler HSD Suction strainers for Aux. boiler HSD Road Tanker HSD SystemHSD System HSD Day Tank Aux. Boiler Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor
  • 25. RFO SystemRFO System Road Tankers Bay Rail Wagons Bay RFO Transfer Pumps Suction Strainers RFO Unloading Pumps RFO Unloading Pumps Suction Strainers RFO Transfer Pumps RFO Pressurizing Pumps Suction Strainers RFO Pressurizing Pumps RFO Burner Deck Suction Strainers RFO Discharge Heaters RFO Day Tank RFO Burners RFO Storage Tank-2 RFO Storage Tank-1 RFO Unloading direct to day tank & Recirculation Line RFO Return RFO SystemRFO System Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor
  • 26. Auxiliary Steam SystemAuxiliary Steam System SCAPH Gland Steam Air Ejector APH Soot blower Igniter Atomizing Steam Burner Atomizing Steam DA From CRH Aux. Boiler To RFO Storage Tank Area Heating & Tracing Steam To RFO Unloading Area SLDS Aux. header steam pressure 12.5 kg/cm2 Aux. steam pressure 12.5 kg/cm2 From EXT # 4 PCV-0470 To day tank oil heaters To RFO UL PP, TRF PP, St. TK & UL heaters DS DS Attemperator From CEP Discharge From CEP Discharge Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor
  • 27. FI PI PI Inter Condenser After Condenser PI PI MC-CON.1 CEP Discharge Aux Steam Main Ejector Startup Ejector (Hogger) Initial loop Filling MC-GL-02 Silencer Condenser Reducer 200x100 Reducer 200x150 TI Reducer 50x65 Saba Power Plant Vacuum System Mohammad Shoeb Siddiqui Sr. Shift Supervisor Aux Steam Loop Seal Air evacuation
  • 28. Condensate CycleCondensate Cycle Condenser HW CEP Air Ejector GSC Drain Cooler LPH 1 LPH 2LPH 3 Feed Water Tank DA 2 X 100 % Capacity Condenser HW Feed Water Tank DA Steam from Ext # 3 251 o C Steam from Ext # 2 151 o C Steam from Ext # 1 87 o C 92 o C 112 o C 136 o C 48 o C Suction Pressure 1.4 kg/cm2 CEP Discharge Pressure 19.3 kg/cm2 DA Pressure 7.8 kg/cm2 & Temp. 173 o C CEP Air Ejector Drain Cooler LPH 1 LPH 2LPH 3 Condenser Pressure -0.92 kg/cm2 Condensate Flow 365 t/hr St. Turbine CSTCST From Demin Tank Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor From Demin Tank GSC To Spray To SLDS Spray
  • 29. BFP HPH 5 HPH 6 Feed Water Tank DA Boiler Drum Economizer Feed Water CycleFeed Water Cycle BFP HPH 5 HPH 6 Feed Water Tank DA Boiler Drum Economizer Steam from CRHSteam from Ext # 5 To HPH # 5To DA 3 X 50 % Capacity 425 o C 343 o C 242 o C 204 o C 174 o C 198 o C 182 o C Suction Pressure 10.4 kg/cm2 Discharge Pressure 196 kg/cm2 HPH 5 BFP HPH 6 Feed water flow 430 t/hr Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor From LPH # 3 Aux. Steam TO RH Spray TO SH Spray
  • 30. Steam CycleSteam Cycle Steam Drum HP Turbine IP & LP Turbine Condenser 4 X Primary Super heaters Reheater HP bypass LP bypass SH Attemperator Steam CycleSteam Cycle HP Turbine IP & LP Turbine Condenser Secondary Super heater RH Spray LP bypass Spray HP bypass Spray Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor
  • 31. HP Turbine IP & LP Turbine Extraction Steam SystemExtraction Steam System ToDA TOHPH#6 ToAuxHeader To Condenser From Boiler Main Steam From Main Boiler RH Hot Reheat Extraction Steam SystemExtraction Steam System ToDA TOHPH#6 ToAuxHeader TO RH Cold Reheat TO LPH # 1 TO LPH # 2 TO LPH # 3 To DA HPH # 5 To Condenser To DA To Aux. Steam Header To HPH # 6 HP Turbine IP & LP Turbine Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor
  • 32. Saba Power PlantSaba Power Plant Heat Balance DiagramHeat Balance Diagram Furnace Super heater Re-Heater Economizer HPH6 HPH 5 Feed Water Tank DA LPH 3 LPH 2 HP Turbine IP & LP Turbine LPH 1 Condenser Drain Cooler GSC SJAE CEP RFO TRF PP BFP RFO TK-02RFO TK-01 RFO Day TK HSD TK HSD PP RFO PP GRF Y Y MVSG UAT 12.5 MVA, 6.6 KV UAT 160 MVA, 132 KV GT Traffo Exciter 170 MVA, 134 MW, 15.5 KV Generator Cooling Tower Stack ESP CWP CTF RAH SCAPH FDF WAPDA Mohammad Shoeb Siddiqui Sr. Shift Supervisor SH Steam Temp. 538 o C Press. 168 kg/cm2 413 t/h, 1460.4 BTU/lb 0.335 t/h, 1.058 t/h, 401 t/h, Aux. Steam header, fuel atom. 2.7 t/h 43.15 t/h, 19.7 t/h, 15.82 t/h, 19.94 t/h, 12.04 t/h, LPH1 15.06 t/h, 275.2 t/h, 413.3 t/h, To DA 179.8 o C To HPH #5 204.55 o C To LPH#2 107.9 o C To LPH#1 86.5 o C LPH 1 to Condenser 56.8 o C Condenser Makeup 2.95 t/h Heat rejection 952.3 BTU/lb 40.0 o C 45.0 o C 50.0 o C 100.0 o C 33.0 o C 21.9 o C Stack out 150.0 o C 70.0 o C 290.0 o C 365 o C Air Gas 174.0 o C 198.0 o C 245.0 o C 428.0 o C 337 o C 42 o C 138.0 o C 1.38 t/h, 18.95 t/h, 2.17 t/h, Fuel Heating Area 0.075 t/h, 8.8 t/h, 0.97 t/h, Aux. Steam header, fuel atom. 2.9 t/h 354.8 t/h, RH Steam Temp. 538 o C Press. 38 kg/cm2 354.8 t/h, 1519.2 BTU/lb Return From Fuel Heating 1.45 t/h, Return From Steam Coil 0.25 t/h, RH Spray 0.27 t/h, Spray 333.4 t/h, 334.8 t/h, 413.5 t/h, 0.34 t/h, GS GS GS 0.524 t/h, 0.42 t/h, 0.36 t/h, 1.45 t/h, LOAD CAPABILITY GEN. OUTPUT 134000 KW CONDITION 3.5 HG, 0.7% MU POWER FACTOR 0.9 PF HEAT RATE 7939 BTU/KWH THERMAL EFF. 42.99 % SH Spray 27.06 t/h, SCAPH 7.13 t/h,
  • 33. Heaters Drains & VentsHeaters Drains & Vents Feed Water Tank HPH # 5 HPH # 6 Condenser HP Flash Tank LPH # 3 LPH # 1 LPH # 2 Drain Cooler GS Condenser GS Cond. Drain CEP Discharge Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor
  • 34. Saba Power Plant Steam Drain System Mohammad Shoeb Siddiqui Sr. Shift Supervisor Condenser HP Drain Flash Tank DR-FT-01 LP Drain Flash Tank DR-FT-012 TE TI TE TI TE TI MS Header Drain HP bypass Seat Drain MSV before Seat Drain MSV after Seat Drain HPT Casing Drain UV-0685 Spray From CEP Discharge LP bypass Seat Drain UV-0684 From CEP Discharge Spray HRH Seat Drain CRSV (A) After Seat Drain CRSV (B) After Seat Drain HPH # 5 Emergency Drain HPH # 6 Emergency Drain CRH Header Drain Upstream NRV CRH Header Drain DW stream NRV Ext 6 Line Drain Upstream NRV Ext 6 Line Drain Dw stream NRV Ext 5 Line Drain Upstream NRV Ext 5 Line Drain Dw stream NRV Ext 4 Line Drain Upstream NRV Ext 4 Line Drain Dw stream NRV Ext 3 Line Drain Upstream NRV Ext 3 Line Drain Dw stream NRV Ext 2 Line Drain Upstream NRV Ext 2 Line Drain Dw stream NRV From CEP Discharge UV-0693 Spray TE-0690 TE-0691 TE-0692 Hot Well
  • 35. Air & Flue Gas SystemAir & Flue Gas System FDF SCAPH RAH GRF ESP Stack Boiler Flue Gases Flow Air Flow FDF GRF RAH FDF outlet air Pressure 635 mmH2O Temp. 29.0 o C Flue Gas outlet gas Pressure 56 mmH2O Temp. 147 o C GRF outlet Pressure 339 mmH2O Flue gas Pressure 166 mmH2O Temp. 344 o C SCAPH RAH ESP Burners Wind Box Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor Steam Drum Ash Hoppers SH SH SH RH SH SH ECO
  • 36. 132 / 6.6 / 0.415 KV System132 / 6.6 / 0.415 KV System G 160 MVA, 132/15.5 KV Generator Transformer (Traffo) GCB Generator Isolator Earth Switch 170 MVA 134 MW Earth Switch 132 KV 6.6 KV CWP1CWP2CEP1CEP2 BFP1BFP2BFP3FDFGRF TR-1TR-2TR-3 415 Volts PCC-1 415 Volts PCC-2 415 Volts PCC-3 PFI Unit Spare Enginator Transf. Solar Energy Elect. Fire Pump MCC-4 MCC-5 MCC-6 MCC-7 MCC-8 MCC-3 ACDB MCC-9 BDB MCC-2 EMCC Admen Bldg. CWP2CEP2 BFP1BFP3 CWP1CEP1 FDFGRF BFP2 G Prepared by:Prepared by: Mohammad ShoebMohammad Shoeb SiddiquiSiddiqui
  • 37. 132 KV Electrical System132 KV Electrical System G FRQ-3 (Line bay # 2) FRQ-4 (Line bay # 1) ES-1 ES-2 101 E1Q1 E1Q11 102 E2Q1 E2Q11 E3Q11 E3Q1 E3Q10 160 MVA, 132/15.5 KV Generator Transformer (Traffo) GCB Generator Isolator Earth Switch 132 KV Bus bar 170 MVA 134 MW Earth Switch From & to Wapda Farooqabad Grid G Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor
  • 38. Saba Power PlantSaba Power Plant Automatic Water Supply Preaction SystemAutomatic Water Supply Preaction System Mohammad Shoeb Siddiqui Sr. Shift Supervisor Hazard To Be Protected Dry Pilot Actuator D PSL PI Pressure Regulator PI PSH From Instrument Air Supply PAL PAH Fire Alarm Water Motor Gang PIV Lo Lo TBST Point Main Fire Water Header
  • 39. Saba Power PlantSaba Power Plant Wet Pipe Sprinkler SystemWet Pipe Sprinkler System Mohammad Shoeb Siddiqui Sr. Shift Supervisor PSH PAH Fire Alarm Water Motor Gang PIV Main Fire Water Header Fire Alarm Lo NRV A PI
  • 40. Prepared by: Mohammad Shoeb SiddiquiPrepared by: Mohammad Shoeb Siddiqui Senior Shift SupervisorSenior Shift Supervisor