Schedule Margin Management –
                              The Missing Link



                             PM Challenge 2010

                                 Rick Price



                             9-10 February 2010
                                                      1
Used with Permission
Agenda



•   Why Schedule Margin/Reserve Management is Important
•   Current Margin/Reserve Processes & Standards
•   Definitions
•   Purpose
•   Keys to Successful Schedule Margin Management
•   Process & Recommended Approach
•   Summary




                                                          2
Why Managing Schedule Margin/Reserve is Important



• The definition of Program Success (& Failure) has changed
  − “Technical success at all costs” is no longer acceptable
  − Increased scrutiny and consequences for missing cost/schedule objectives
• The least expensive path (schedule) is usually the one you start
  with
• Risks (technical, cost & schedule) & uncertainty (estimating error)
  exist in every development program
• Schedule “Margin” that is hidden in padded task durations is not
  managed tasks end up taking longer (Parkinson’s Law)
• The other 2 legs of program success, technical performance, and
  cost performance use formally managed margins/reserves…why
  not schedule?



                                                                               3
Current Margin/Reserve Processes & Standards


• Program Success today is defined as meeting technical, cost and
  schedule commitments
  − We have well defined approaches and processes for managing technical
    requirements including disciplined use and management of design margins
  − Management Reserve (MR) is formally defined and managed within cost
    reporting systems to account for unknown (but real) cost changes within
    contract scope
  − Schedule Margin/Reserve (SR) generally does not have a similar disciplined
    approach for defining, allocating, and managing appropriate time reserves
     • Not included in DOD EVM Implementation Guide
     • Not included in PMI standard on Scheduling
     • Vaguely included in PMBOK
     • Is included in NASA’s NPR 7120.5D & Schedule Management Handbook
     • Is included in DOD Risk Management Guide for DOD Acquisition
• Development of standards and processes for defining and
  managing schedule margin is lacking or at best lagging
                                                                                 4
Why Is This The Case?


• Why do some balk at the idea of having schedule margin
  discretely identified in critical path (CP) networks/schedules?
  − Sins of the past
     • Not well defined by customers nor contractors/subcontractors
     • Lack of consistency
     • Lack of rigorous process and control
     • Misused
        − To offset schedule performance issues (bad performance)
        − As a “pool” to draw from
  − Fear that including it will prevent achieving the earliest possible schedule
  − Confusing margin (reserve) with slack (float)


• If Management Reserve was ill-defined and misused we’d balk at
  having it as part of our management processes as well


                                                                                   5
Schedule Margin Management Definitions
 − Schedule Margin/Reserve (SR):
    • Defined in DID DI-MGMT-81650 as: “A management method for
      accommodating schedule contingencies. It is a designated buffer and shall
      be identified separately and considered part of the baseline.”
    • Defined in NPR 7120.5D NASA Space Flight Program and Project
      Management Requirements as: “allowances carried in…project
      schedules…to account for uncertainties and risks…baselined in the
      formulation process, based on assessments of risks, and are typically
      consumed as the program/project proceeds through the life cycle.”
    • Defined/visible critical path activity (a defined node included in the CPM
      network) planned during normal work hours with no “defined” scope
    • Defined/allocated/managed in direct correlation to known schedule risk
    • If consumed, it is done so to retire risk; not used to fix schedule performance
      degradation
    • Cannot be negative
 − Management Reserve (MR):
    • An amount of the total allocated budget withheld for management control
      purposes rather than designated for the accomplishment of a specific task or
      set of tasks. It is not a part of the Performance Measurement Baseline.
    • NDIA PMSC Intent Guideline (ANSI/EIA-748-A): “The management reserve
      budget should be commensurate with the level of risks identified by the
      project and/or withheld for management control purposes.”
    • Cannot be negative
                                                                                        6
Schedule Margin Management Definitions (cont.)

 − Schedule Float/Slack:
   • The amount of time a schedule can fluctuate without impacting the end
     date(s)/deliverables
   • Can change on a regular basis driven by current status
   • Can be positive or negative
   • Negative float/slack requires implementation of contingency actions
   • Positive float is like an underrun; negative float is like and overrun
   • Managing schedule float/slack keeps things off of the critical path
 − Schedule Contingency Actions:
   • Out of the ordinary & temporary actions taken to handle “bumps in the
     road” and recover schedule performance (negative float or negative
     performance trends)
   • Includes unplanned overtime, temporary additional shifts/resources, and
     out-of-position (re-sequenced) installations
   • Define early and assess often
 − Management:
   • “Applying and refining good process”
   • Dealing with complexity to achieve results

                                                                               7
The Difference Between Margin and Float Using Cost Terms

• Scenario:
  − Your favorite meal has cost you $10 at the same restaurant every Sunday for
    the past year (historical data)
  − Someone told you they have a new menu (risk the prices went up)
  − You decide to take $12 in your wallet just in case ($2 margin)…preplanned &
    risk-based
  − Walking to the restaurant you find $1 on the sidewalk (float)…change en-route
  − You can spend the $1 on your way (additional scope), lose it through the hole
    in your pocket (lost performance), or put it in your wallet (additional
    margin)…management decision
• Likelihood of Success:
  − With $10; odds are you will have to settle for something less than planned
  − With $12 (margin) chances are good you will get what you wanted
  − With $13 (margin & float) you have an even better chance of getting what you
    wanted and possibly more
• Recognize the differences and manage both for the best chance of
  success

                                                                                    8
Keys to Successful Schedule Margin Management

• Schedule Margin Purpose
  − Designed to protect primarily against critical path “known unknowns”
     • Defined risks
     • Cannot afford (time or $) to protect against all the “unknown unknowns” or
       against catastrophic failure
  − Should also be used to protect use of key shared resources (test facilities,
    etc) as well as deliverables
  − Can be used to accommodate “in-scope” changes to the baseline (like MR)
• Margin burn-down tied to successful completion of key
  events/milestones and retirement of associated schedule risk
• When initially allocated across the period of performance, provides
  reasonable schedule dates for all scheduled activities
• Must be managed to provide a reasonable probability of schedule
  success
• Do NOT use it to “fix” schedule performance issues or allow to
  erode with the passage of time
  − Doing so creates the illusion that things are still on track
  − This “fix” with no action creates potential downstream schedule problems
    since the future risks still exist

                                                                                    9
Schedule Margin Management Hurdles-Changing
    the Culture

• Misunderstanding of the purpose of schedule margin
     − What it is and is not
     − Used to fix poor schedule performance
     − Belief that future schedule margin means “minor” CP schedule delays are “OK”
•    Fear of defining/showing margin in a schedule
•    Often buried within tasks to “protect” individual performance
•    If identified, often based on what’s available vs. what’s needed
•    Margin is often created by squeezing task durations resulting in
     unachievable schedules
•    Schedule risks created in proposing aggressive schedules forgotten
     at ATP
•    Schedule risks and opportunities not actively identified nor tracked
     (all risks should be continuously assessed for schedule risk)
•    Schedule contingency actions not developed in advance and
     implementation is not timely to address schedule delays
•    Not managed through the entire supply chain creating unreasonably
     early dates at the front end due to unintentional “margin stacking”
•    No defined process for schedule margin management
                                                                                  10
Common Approaches to Managing Margin That Can
Create Problems

• Holding all schedule margin at the end of the schedule
  − Forces everything as early as possible and SPI will likely degrade from the
    start with “poor” performance compounding each month.
  − Not used to retire schedule risk
  − Umbrella affect (“No problem, we have margin at the end.”)
  − Unclear on what it can be used for or when contingency actions should be
    taken
  − The desired affect of accomplishing all work ASAP can be accomplished
    with margin allocated across the POP & conserving unused margin
• Establishing and managing margin as a percentage
  − Ignores schedule risk
  − More time-based than task-based
  − Allows margin “erosion” without retiring schedule risk (“As long as we stay
    above X% we can eat into the margin.”)
  − Leads to unwise compromise (“if we started at 10%, 9 % is OK…8% isn’t too
    bad…1% is still margin…”)

                                                                                  11
Schedule Margin Management Process


• The Schedule Margin Management process should define:
  − How the total amount of schedule margin will be determined and allocated
    (according to schedule risk & schedule performance objectives)
  − Conditions for determining red/yellow/green schedule margin ratings and/or
    need for associated recovery actions
  − Conditions for allowable margin use (and who owns it)
  − How unused margin will be conserved, reallocated or spent as risk is retired
  − What, when, how, and by whom contingency actions will be implemented to
    immediately address schedule performance issues


• Implementation of a schedule margin management process will
  help reduce chaos, variability & unpredictability, and dependence
  on individual heroism, ultimately resulting in better schedule
  performance.


                                                                                   12
Recommended Approach

• Develop 3 time estimates (optimistic, most likely, pessimistic) &
  perform Monte Carlo analysis
• Determine required confidence level needed for the schedule (i.e.
  75%)
• Decide on using either “most likely” or “expected value” durations
• Determine difference between most likely (or expected value)
  schedule and XX% confidence level schedule (this = amount of
  total schedule margin needed)
• Allocate incremental discrete schedule margin according to
  known risks to CP(s) & protect usage of critical shared resources
  − Check MR availability to cover identified schedule risks/margin
• Baseline program schedule to early dates with margin included;
  this is the schedule you believe will happen
• Manage resources to achieve the current schedule
• Allow non-critical path activities to use resources efficiently
• When total float erodes/goes negative, Implement fixes
  immediately; do not let risk defined margin to be used for
  schedule performance issues
                                                                       13
Establish the Baseline with Risk Based Margin




Risk based schedule margin included in logic to establish baseline event
dates (contractual commitments and most likely plan)                       14
Manage Critical Path to Earliest Possible Plan
  (Achieving the earliest possible schedule without holding all margin at the end)




Risk based schedule margin bypassed in logic to establish best case event
dates (contractor’s current plan); if margin is not used, reallocate it and begin
subsequent tasks earlier                                                            15
Spacecraft Test Schedule Margin Management Plan
                                               SPT #2
                        **             * *
        20
                                   *         *                                    Green-No Action Rqd
                                                                                  Yellow-Implement Contingency

                                                 *                                Red-Implement All Contingencies
Margin (Work Days)




                                                             Acoustic Test
                                                             Compl
                                                            *
                                                        *        * *EMC/EMI*Compl
                                                                      *
                                                                              * *
                                                                                        *TVAC Compl
                                                                                           *
        10
                                                                                               *
                                                                                                  SPT #3
                                                                                                  Compl
                                                                                                        *
                                                                                                             *
                                                                                                            Spin
                                                                                                            Balance


                                                                                                                    *Ship
                     6/16                                                                                              *
                                                                                                                            11/11
                              20                  15                         10               5
                            * = Actual Performance          Weeks Until Ship
                                                                                                                               16
Summary

• Formalize your process and definitions
• Elevate the understanding and importance of “SR” to that of “MR”
• Plan and manage schedule margin in direct correlation to
  schedule risk
• Validate management reserve will cover schedule margin
• Communicate with your team (including your customer and key
  suppliers) on the reasons for margin (both quantity & placement)
  and the need to take immediate action for critical path delays
• With margin assigned to retire specific schedule risk, do not allow
  margin to dwindle without retiring the associated schedule risk
• Continually assess schedule risk and conserve/reallocate unused
  margin
• Define realistic contingency actions early and assess
  continuously. Take action immediately when float erodes/goes
  negative
• Managing & conserving float, in addition to managing defined
  margin, increases the likelihood of schedule success
                                                                        17

Contenu connexe

Tendances

Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationChris Carson
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2Chris Carson
 
Schedule Design AACE
Schedule Design AACESchedule Design AACE
Schedule Design AACEChris Carson
 
Sally.godfrey
Sally.godfrey Sally.godfrey
Sally.godfrey NASAPMC
 
Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop ConferenceChris Carson
 
Harvey.tony
Harvey.tonyHarvey.tony
Harvey.tonyNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.Chris Carson
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery SchedulingChris Carson
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.garyNASAPMC
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule DevelopmentChris Carson
 
Gary.humphreys
Gary.humphreysGary.humphreys
Gary.humphreysNASAPMC
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion SchedulesChris Carson
 
Thomas.coonce
Thomas.coonceThomas.coonce
Thomas.coonceNASAPMC
 
Law.richard
Law.richardLaw.richard
Law.richardNASAPMC
 
Simon.dekker.vance kotrla
Simon.dekker.vance kotrlaSimon.dekker.vance kotrla
Simon.dekker.vance kotrlaNASAPMC
 
Claunch.cathy
Claunch.cathyClaunch.cathy
Claunch.cathyNASAPMC
 
Amer.tahani
Amer.tahaniAmer.tahani
Amer.tahaniNASAPMC
 
Schedule levels-as-presented 02-may11
Schedule levels-as-presented  02-may11Schedule levels-as-presented  02-may11
Schedule levels-as-presented 02-may11PMA Consultants
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - AirportChris Carson
 

Tendances (20)

Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan Presentation
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2
 
Schedule Design AACE
Schedule Design AACESchedule Design AACE
Schedule Design AACE
 
Sally.godfrey
Sally.godfrey Sally.godfrey
Sally.godfrey
 
Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop Conference
 
Harvey.tony
Harvey.tonyHarvey.tony
Harvey.tony
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.DB Medical Pgm Mgmnt.
DB Medical Pgm Mgmnt.
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery Scheduling
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
Gary.humphreys
Gary.humphreysGary.humphreys
Gary.humphreys
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion Schedules
 
Thomas.coonce
Thomas.coonceThomas.coonce
Thomas.coonce
 
Law.richard
Law.richardLaw.richard
Law.richard
 
Simon.dekker.vance kotrla
Simon.dekker.vance kotrlaSimon.dekker.vance kotrla
Simon.dekker.vance kotrla
 
Claunch.cathy
Claunch.cathyClaunch.cathy
Claunch.cathy
 
Amer.tahani
Amer.tahaniAmer.tahani
Amer.tahani
 
Schedule levels-as-presented 02-may11
Schedule levels-as-presented  02-may11Schedule levels-as-presented  02-may11
Schedule levels-as-presented 02-may11
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - Airport
 

En vedette

Stacy.cusack
Stacy.cusackStacy.cusack
Stacy.cusackNASAPMC
 
Wienkoop.glenn
Wienkoop.glennWienkoop.glenn
Wienkoop.glennNASAPMC
 
John.emond
John.emondJohn.emond
John.emondNASAPMC
 
Patrick.guske.update
Patrick.guske.updatePatrick.guske.update
Patrick.guske.updateNASAPMC
 
Michael.aucoin
Michael.aucoinMichael.aucoin
Michael.aucoinNASAPMC
 
Diffoot fayful
Diffoot fayfulDiffoot fayful
Diffoot fayfulNASAPMC
 
Patrick.guske.update
Patrick.guske.updatePatrick.guske.update
Patrick.guske.updateNASAPMC
 
Neiberding
NeiberdingNeiberding
NeiberdingNASAPMC
 
B ackroyd
B ackroydB ackroyd
B ackroydNASAPMC
 
Dillon.r.tinsley.c.rogers.e
Dillon.r.tinsley.c.rogers.eDillon.r.tinsley.c.rogers.e
Dillon.r.tinsley.c.rogers.eNASAPMC
 
Kirsch.mike
Kirsch.mikeKirsch.mike
Kirsch.mikeNASAPMC
 
Harrison.g.poole.k
Harrison.g.poole.kHarrison.g.poole.k
Harrison.g.poole.kNASAPMC
 
Mc nally
Mc nallyMc nally
Mc nallyNASAPMC
 
Brockhurst.lane
Brockhurst.laneBrockhurst.lane
Brockhurst.laneNASAPMC
 
Grubbs teams and digital collaboration pmc2012
Grubbs teams and digital collaboration pmc2012Grubbs teams and digital collaboration pmc2012
Grubbs teams and digital collaboration pmc2012NASAPMC
 
Barth simpkins
Barth simpkinsBarth simpkins
Barth simpkinsNASAPMC
 
C null 01-17-2011
C null 01-17-2011C null 01-17-2011
C null 01-17-2011NASAPMC
 
K.pagel.beene
K.pagel.beeneK.pagel.beene
K.pagel.beeneNASAPMC
 
Debbie.dusterwald
Debbie.dusterwaldDebbie.dusterwald
Debbie.dusterwaldNASAPMC
 
M washington
M washingtonM washington
M washingtonNASAPMC
 

En vedette (20)

Stacy.cusack
Stacy.cusackStacy.cusack
Stacy.cusack
 
Wienkoop.glenn
Wienkoop.glennWienkoop.glenn
Wienkoop.glenn
 
John.emond
John.emondJohn.emond
John.emond
 
Patrick.guske.update
Patrick.guske.updatePatrick.guske.update
Patrick.guske.update
 
Michael.aucoin
Michael.aucoinMichael.aucoin
Michael.aucoin
 
Diffoot fayful
Diffoot fayfulDiffoot fayful
Diffoot fayful
 
Patrick.guske.update
Patrick.guske.updatePatrick.guske.update
Patrick.guske.update
 
Neiberding
NeiberdingNeiberding
Neiberding
 
B ackroyd
B ackroydB ackroyd
B ackroyd
 
Dillon.r.tinsley.c.rogers.e
Dillon.r.tinsley.c.rogers.eDillon.r.tinsley.c.rogers.e
Dillon.r.tinsley.c.rogers.e
 
Kirsch.mike
Kirsch.mikeKirsch.mike
Kirsch.mike
 
Harrison.g.poole.k
Harrison.g.poole.kHarrison.g.poole.k
Harrison.g.poole.k
 
Mc nally
Mc nallyMc nally
Mc nally
 
Brockhurst.lane
Brockhurst.laneBrockhurst.lane
Brockhurst.lane
 
Grubbs teams and digital collaboration pmc2012
Grubbs teams and digital collaboration pmc2012Grubbs teams and digital collaboration pmc2012
Grubbs teams and digital collaboration pmc2012
 
Barth simpkins
Barth simpkinsBarth simpkins
Barth simpkins
 
C null 01-17-2011
C null 01-17-2011C null 01-17-2011
C null 01-17-2011
 
K.pagel.beene
K.pagel.beeneK.pagel.beene
K.pagel.beene
 
Debbie.dusterwald
Debbie.dusterwaldDebbie.dusterwald
Debbie.dusterwald
 
M washington
M washingtonM washington
M washington
 

Similaire à Price.rick

Managing projects with shared resources
Managing projects with shared resourcesManaging projects with shared resources
Managing projects with shared resourcesStephen Hightower
 
Dynamic Scheduling for Shutdowns and Turnarounds
Dynamic Scheduling for Shutdowns and TurnaroundsDynamic Scheduling for Shutdowns and Turnarounds
Dynamic Scheduling for Shutdowns and TurnaroundsEJ (Ted) Lister
 
APM QSRA webinar; introduction for risk and planning professionals and decisi...
APM QSRA webinar; introduction for risk and planning professionals and decisi...APM QSRA webinar; introduction for risk and planning professionals and decisi...
APM QSRA webinar; introduction for risk and planning professionals and decisi...Association for Project Management
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueChris Carson
 
DCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdfDCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdfKarim Ragab
 
PMI-ACP Domain V: Adaptive Planning v1.0
PMI-ACP Domain V: Adaptive Planning v1.0PMI-ACP Domain V: Adaptive Planning v1.0
PMI-ACP Domain V: Adaptive Planning v1.0PhuocNT (Fresher.VN)
 
Project Planning and Control
Project Planning and Control Project Planning and Control
Project Planning and Control drpvkhatrissn
 
Getting the basics right
Getting the basics rightGetting the basics right
Getting the basics rightThomas Cream
 
Projects2016_Franks_Top10ReasonsProjectsFail
Projects2016_Franks_Top10ReasonsProjectsFailProjects2016_Franks_Top10ReasonsProjectsFail
Projects2016_Franks_Top10ReasonsProjectsFailBarbara Franks
 
APM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsAPM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsJacobs Engineering
 
The Agility Continuum
The Agility ContinuumThe Agility Continuum
The Agility ContinuumThene Sheehy
 
Project management pocket skills
Project management   pocket skillsProject management   pocket skills
Project management pocket skillsrdlteam
 
@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology OverviewDaniel Brody
 
Erp Implementation Project Planning
Erp Implementation Project PlanningErp Implementation Project Planning
Erp Implementation Project PlanningDarshan Ambhaikar
 
Maintenance Planning and Scheduling Workshop - Greenvile, SC November 12-14,...
Maintenance Planning and Scheduling Workshop  - Greenvile, SC November 12-14,...Maintenance Planning and Scheduling Workshop  - Greenvile, SC November 12-14,...
Maintenance Planning and Scheduling Workshop - Greenvile, SC November 12-14,...Ricky Smith CMRP, CMRT
 

Similaire à Price.rick (20)

Managing projects with shared resources
Managing projects with shared resourcesManaging projects with shared resources
Managing projects with shared resources
 
Dynamic Scheduling for Shutdowns and Turnarounds
Dynamic Scheduling for Shutdowns and TurnaroundsDynamic Scheduling for Shutdowns and Turnarounds
Dynamic Scheduling for Shutdowns and Turnarounds
 
APM QSRA webinar; introduction for risk and planning professionals and decisi...
APM QSRA webinar; introduction for risk and planning professionals and decisi...APM QSRA webinar; introduction for risk and planning professionals and decisi...
APM QSRA webinar; introduction for risk and planning professionals and decisi...
 
Mpug 111208 generic
Mpug 111208 genericMpug 111208 generic
Mpug 111208 generic
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Planning management process
Planning   management processPlanning   management process
Planning management process
 
DCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdfDCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdf
 
PMI-ACP Domain V: Adaptive Planning v1.0
PMI-ACP Domain V: Adaptive Planning v1.0PMI-ACP Domain V: Adaptive Planning v1.0
PMI-ACP Domain V: Adaptive Planning v1.0
 
Project Planning and Control
Project Planning and Control Project Planning and Control
Project Planning and Control
 
Getting the basics right
Getting the basics rightGetting the basics right
Getting the basics right
 
Projects2016_Franks_Top10ReasonsProjectsFail
Projects2016_Franks_Top10ReasonsProjectsFailProjects2016_Franks_Top10ReasonsProjectsFail
Projects2016_Franks_Top10ReasonsProjectsFail
 
APM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsAPM Practitioner Qualification revision cards
APM Practitioner Qualification revision cards
 
The Agility Continuum
The Agility ContinuumThe Agility Continuum
The Agility Continuum
 
Sadchap03
Sadchap03Sadchap03
Sadchap03
 
Lean Management System Assessment
Lean Management System AssessmentLean Management System Assessment
Lean Management System Assessment
 
Project management pocket skills
Project management   pocket skillsProject management   pocket skills
Project management pocket skills
 
@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview
 
Erp Implementation Project Planning
Erp Implementation Project PlanningErp Implementation Project Planning
Erp Implementation Project Planning
 
Project management
Project managementProject management
Project management
 
Maintenance Planning and Scheduling Workshop - Greenvile, SC November 12-14,...
Maintenance Planning and Scheduling Workshop  - Greenvile, SC November 12-14,...Maintenance Planning and Scheduling Workshop  - Greenvile, SC November 12-14,...
Maintenance Planning and Scheduling Workshop - Greenvile, SC November 12-14,...
 

Plus de NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerryNASAPMC
 

Plus de NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerry
 

Dernier

8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
IoT Insurance Observatory: summary 2024
IoT Insurance Observatory:  summary 2024IoT Insurance Observatory:  summary 2024
IoT Insurance Observatory: summary 2024Matteo Carbone
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menzaictsugar
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxMarkAnthonyAurellano
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCRashishs7044
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesKeppelCorporation
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607dollysharma2066
 

Dernier (20)

No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
No-1 Call Girls In Goa 93193 VIP 73153 Escort service In North Goa Panaji, Ca...
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCREnjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
Enjoy ➥8448380779▻ Call Girls In Sector 18 Noida Escorts Delhi NCR
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
IoT Insurance Observatory: summary 2024
IoT Insurance Observatory:  summary 2024IoT Insurance Observatory:  summary 2024
IoT Insurance Observatory: summary 2024
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu MenzaYouth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
Youth Involvement in an Innovative Coconut Value Chain by Mwalimu Menza
 
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptxContemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
Contemporary Economic Issues Facing the Filipino Entrepreneur (1).pptx
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
Corporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information TechnologyCorporate Profile 47Billion Information Technology
Corporate Profile 47Billion Information Technology
 
8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR8447779800, Low rate Call girls in Rohini Delhi NCR
8447779800, Low rate Call girls in Rohini Delhi NCR
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
Annual General Meeting Presentation Slides
Annual General Meeting Presentation SlidesAnnual General Meeting Presentation Slides
Annual General Meeting Presentation Slides
 
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
(Best) ENJOY Call Girls in Faridabad Ex | 8377087607
 

Price.rick

  • 1. Schedule Margin Management – The Missing Link PM Challenge 2010 Rick Price 9-10 February 2010 1 Used with Permission
  • 2. Agenda • Why Schedule Margin/Reserve Management is Important • Current Margin/Reserve Processes & Standards • Definitions • Purpose • Keys to Successful Schedule Margin Management • Process & Recommended Approach • Summary 2
  • 3. Why Managing Schedule Margin/Reserve is Important • The definition of Program Success (& Failure) has changed − “Technical success at all costs” is no longer acceptable − Increased scrutiny and consequences for missing cost/schedule objectives • The least expensive path (schedule) is usually the one you start with • Risks (technical, cost & schedule) & uncertainty (estimating error) exist in every development program • Schedule “Margin” that is hidden in padded task durations is not managed tasks end up taking longer (Parkinson’s Law) • The other 2 legs of program success, technical performance, and cost performance use formally managed margins/reserves…why not schedule? 3
  • 4. Current Margin/Reserve Processes & Standards • Program Success today is defined as meeting technical, cost and schedule commitments − We have well defined approaches and processes for managing technical requirements including disciplined use and management of design margins − Management Reserve (MR) is formally defined and managed within cost reporting systems to account for unknown (but real) cost changes within contract scope − Schedule Margin/Reserve (SR) generally does not have a similar disciplined approach for defining, allocating, and managing appropriate time reserves • Not included in DOD EVM Implementation Guide • Not included in PMI standard on Scheduling • Vaguely included in PMBOK • Is included in NASA’s NPR 7120.5D & Schedule Management Handbook • Is included in DOD Risk Management Guide for DOD Acquisition • Development of standards and processes for defining and managing schedule margin is lacking or at best lagging 4
  • 5. Why Is This The Case? • Why do some balk at the idea of having schedule margin discretely identified in critical path (CP) networks/schedules? − Sins of the past • Not well defined by customers nor contractors/subcontractors • Lack of consistency • Lack of rigorous process and control • Misused − To offset schedule performance issues (bad performance) − As a “pool” to draw from − Fear that including it will prevent achieving the earliest possible schedule − Confusing margin (reserve) with slack (float) • If Management Reserve was ill-defined and misused we’d balk at having it as part of our management processes as well 5
  • 6. Schedule Margin Management Definitions − Schedule Margin/Reserve (SR): • Defined in DID DI-MGMT-81650 as: “A management method for accommodating schedule contingencies. It is a designated buffer and shall be identified separately and considered part of the baseline.” • Defined in NPR 7120.5D NASA Space Flight Program and Project Management Requirements as: “allowances carried in…project schedules…to account for uncertainties and risks…baselined in the formulation process, based on assessments of risks, and are typically consumed as the program/project proceeds through the life cycle.” • Defined/visible critical path activity (a defined node included in the CPM network) planned during normal work hours with no “defined” scope • Defined/allocated/managed in direct correlation to known schedule risk • If consumed, it is done so to retire risk; not used to fix schedule performance degradation • Cannot be negative − Management Reserve (MR): • An amount of the total allocated budget withheld for management control purposes rather than designated for the accomplishment of a specific task or set of tasks. It is not a part of the Performance Measurement Baseline. • NDIA PMSC Intent Guideline (ANSI/EIA-748-A): “The management reserve budget should be commensurate with the level of risks identified by the project and/or withheld for management control purposes.” • Cannot be negative 6
  • 7. Schedule Margin Management Definitions (cont.) − Schedule Float/Slack: • The amount of time a schedule can fluctuate without impacting the end date(s)/deliverables • Can change on a regular basis driven by current status • Can be positive or negative • Negative float/slack requires implementation of contingency actions • Positive float is like an underrun; negative float is like and overrun • Managing schedule float/slack keeps things off of the critical path − Schedule Contingency Actions: • Out of the ordinary & temporary actions taken to handle “bumps in the road” and recover schedule performance (negative float or negative performance trends) • Includes unplanned overtime, temporary additional shifts/resources, and out-of-position (re-sequenced) installations • Define early and assess often − Management: • “Applying and refining good process” • Dealing with complexity to achieve results 7
  • 8. The Difference Between Margin and Float Using Cost Terms • Scenario: − Your favorite meal has cost you $10 at the same restaurant every Sunday for the past year (historical data) − Someone told you they have a new menu (risk the prices went up) − You decide to take $12 in your wallet just in case ($2 margin)…preplanned & risk-based − Walking to the restaurant you find $1 on the sidewalk (float)…change en-route − You can spend the $1 on your way (additional scope), lose it through the hole in your pocket (lost performance), or put it in your wallet (additional margin)…management decision • Likelihood of Success: − With $10; odds are you will have to settle for something less than planned − With $12 (margin) chances are good you will get what you wanted − With $13 (margin & float) you have an even better chance of getting what you wanted and possibly more • Recognize the differences and manage both for the best chance of success 8
  • 9. Keys to Successful Schedule Margin Management • Schedule Margin Purpose − Designed to protect primarily against critical path “known unknowns” • Defined risks • Cannot afford (time or $) to protect against all the “unknown unknowns” or against catastrophic failure − Should also be used to protect use of key shared resources (test facilities, etc) as well as deliverables − Can be used to accommodate “in-scope” changes to the baseline (like MR) • Margin burn-down tied to successful completion of key events/milestones and retirement of associated schedule risk • When initially allocated across the period of performance, provides reasonable schedule dates for all scheduled activities • Must be managed to provide a reasonable probability of schedule success • Do NOT use it to “fix” schedule performance issues or allow to erode with the passage of time − Doing so creates the illusion that things are still on track − This “fix” with no action creates potential downstream schedule problems since the future risks still exist 9
  • 10. Schedule Margin Management Hurdles-Changing the Culture • Misunderstanding of the purpose of schedule margin − What it is and is not − Used to fix poor schedule performance − Belief that future schedule margin means “minor” CP schedule delays are “OK” • Fear of defining/showing margin in a schedule • Often buried within tasks to “protect” individual performance • If identified, often based on what’s available vs. what’s needed • Margin is often created by squeezing task durations resulting in unachievable schedules • Schedule risks created in proposing aggressive schedules forgotten at ATP • Schedule risks and opportunities not actively identified nor tracked (all risks should be continuously assessed for schedule risk) • Schedule contingency actions not developed in advance and implementation is not timely to address schedule delays • Not managed through the entire supply chain creating unreasonably early dates at the front end due to unintentional “margin stacking” • No defined process for schedule margin management 10
  • 11. Common Approaches to Managing Margin That Can Create Problems • Holding all schedule margin at the end of the schedule − Forces everything as early as possible and SPI will likely degrade from the start with “poor” performance compounding each month. − Not used to retire schedule risk − Umbrella affect (“No problem, we have margin at the end.”) − Unclear on what it can be used for or when contingency actions should be taken − The desired affect of accomplishing all work ASAP can be accomplished with margin allocated across the POP & conserving unused margin • Establishing and managing margin as a percentage − Ignores schedule risk − More time-based than task-based − Allows margin “erosion” without retiring schedule risk (“As long as we stay above X% we can eat into the margin.”) − Leads to unwise compromise (“if we started at 10%, 9 % is OK…8% isn’t too bad…1% is still margin…”) 11
  • 12. Schedule Margin Management Process • The Schedule Margin Management process should define: − How the total amount of schedule margin will be determined and allocated (according to schedule risk & schedule performance objectives) − Conditions for determining red/yellow/green schedule margin ratings and/or need for associated recovery actions − Conditions for allowable margin use (and who owns it) − How unused margin will be conserved, reallocated or spent as risk is retired − What, when, how, and by whom contingency actions will be implemented to immediately address schedule performance issues • Implementation of a schedule margin management process will help reduce chaos, variability & unpredictability, and dependence on individual heroism, ultimately resulting in better schedule performance. 12
  • 13. Recommended Approach • Develop 3 time estimates (optimistic, most likely, pessimistic) & perform Monte Carlo analysis • Determine required confidence level needed for the schedule (i.e. 75%) • Decide on using either “most likely” or “expected value” durations • Determine difference between most likely (or expected value) schedule and XX% confidence level schedule (this = amount of total schedule margin needed) • Allocate incremental discrete schedule margin according to known risks to CP(s) & protect usage of critical shared resources − Check MR availability to cover identified schedule risks/margin • Baseline program schedule to early dates with margin included; this is the schedule you believe will happen • Manage resources to achieve the current schedule • Allow non-critical path activities to use resources efficiently • When total float erodes/goes negative, Implement fixes immediately; do not let risk defined margin to be used for schedule performance issues 13
  • 14. Establish the Baseline with Risk Based Margin Risk based schedule margin included in logic to establish baseline event dates (contractual commitments and most likely plan) 14
  • 15. Manage Critical Path to Earliest Possible Plan (Achieving the earliest possible schedule without holding all margin at the end) Risk based schedule margin bypassed in logic to establish best case event dates (contractor’s current plan); if margin is not used, reallocate it and begin subsequent tasks earlier 15
  • 16. Spacecraft Test Schedule Margin Management Plan SPT #2 ** * * 20 * * Green-No Action Rqd Yellow-Implement Contingency * Red-Implement All Contingencies Margin (Work Days) Acoustic Test Compl * * * *EMC/EMI*Compl * * * *TVAC Compl * 10 * SPT #3 Compl * * Spin Balance *Ship 6/16 * 11/11 20 15 10 5 * = Actual Performance Weeks Until Ship 16
  • 17. Summary • Formalize your process and definitions • Elevate the understanding and importance of “SR” to that of “MR” • Plan and manage schedule margin in direct correlation to schedule risk • Validate management reserve will cover schedule margin • Communicate with your team (including your customer and key suppliers) on the reasons for margin (both quantity & placement) and the need to take immediate action for critical path delays • With margin assigned to retire specific schedule risk, do not allow margin to dwindle without retiring the associated schedule risk • Continually assess schedule risk and conserve/reallocate unused margin • Define realistic contingency actions early and assess continuously. Take action immediately when float erodes/goes negative • Managing & conserving float, in addition to managing defined margin, increases the likelihood of schedule success 17