SlideShare a Scribd company logo
1 of 30
Implementation of SMED (Single Minute Exchange
of Dies) in Heavy Machine Shop
Register Number Students Name
511316114053 NAVEEN K
511316114058 PAVITHRA M M
511316114066 RUDHRA RAJ V
511316114073 SIDDHARTH M
Under the Guidance of
Mr. S. Mahendiran, M.E.,
Head of the department,
Department of Mechanical Engineering,
Kingston Engineering College.
 Abstract
 Introduction
 Problem Identification
 Literature Review
 Objective
 Methodology
 Working
 Design overview
 Prototype
 Benefits
 Conclusion
 References
Single Minute Exchange of Dies is a process of minimizing
the changeover time (or setup time) from hours to minutes (i.e.
less than 10 minutes). SMED is one of the lean production
methods, having several steps for implementation, is also used to
focus for reducing waste in a manufacturing process and to
increase the overall equipment effectiveness (OEE) in the shop
floor.
In this project, the availability is found and analyzed, the
time study plan of changeover time was taken, pallet design was
created, and applied all the steps of SMED. As a result, the
production rate can be achieved more and non-value added
activities can be eliminated as much as possible.
• Setup time: The time taken to
prepare the manufacturing processes
and system for production.
• Changeover time: The time taken
to modify the production line for
different products or new batches of
the same product.
• SMED helps reduce time in both
setup and changeover.
• Both setup and changeover are Non-
Value Added (NVA) operations and
so should be minimized as much as
possible.
• CNC boring machines does not have in-built pallets.
• Batch production & its size is min 1 to max 3.
• Machine schedules are dynamic in nature due to
varying customer demands.
• Parts varieties are more. Each parts having 23
variants.
• Parts are heavy weight in nature with weight 2 tons to
25 tons with more time for positioning (10-30min).
Title Author /
Publication
Key findings
Reduction in Setup Time
by SMED
Methodology
Prof. Nagaraj A Raikar
Assistant Professor Dept
of Mechanical
Engineering AITD,
Assagao GOA
International Journal of
Latest Trends in
Engineering and
Technology (IJLTET)
This Study is carried
out in one of the
automotive industry. This
document demonstrates
the need to overcome
most of bottleneck of
equipment’s
unavailability for
resources utilization.
Single Minute Exchange
of Die. A Case Study
Implementation
António Carrizo Moreira 1
, Gil Campos Silva Pais 2.
Journal of Technology
Management &
Innovation
Main finding is that by
implementing SMED
techniques the firm
managed to
eliminate wastefulness
and non-added value
activities
Title Author /
Publication / Year
Key findings
An Industrial Application
Of The Smed
Methodology
And Other Lean
Production Tools
Eric Costa1, Rui Sousa,
Sara Bragança, Anabela
Alves
Centre for Industrial and
Technology Management,
Department of
Production and Systems
(DPS), University of
Minho, Guimarães,
Portugal
This paper describes the
improvement of the
setup process of a
mechanical press
machine in
the metal-mechanic area
of a company.
The Implementation of
Single Minute Exchange
of Die with 5’S in
Machining Processes for
reduction of Setup Time
Vipan Kumar, Amit Bajaj
International Journal on
Recent Technologies in
Mechanical and Electrical
Engineering (IJRMEE)
In this paper we describe
that how the SMED
technique is used and
how it helps to reduce
the time and increasing
the productivity
The main objective of a project:
• To Improve OEE to Global benchmark 85%.
• Overall Equipment Effectiveness = Availability X
Performance X Quality
AVAILABILITY PERFORMANCE QUALITY
74% 92% 99%
OEE
68%
Lowest of OEE Parameter is Availability
What is Availability?
Availability = Machine cutting time / Machine available time
How to improve Availability?
Availability can be improved by reducing the non cutting time
Non cutting time
This 3 Non cutting
times are 70 %
Affect to OEE.
Cutting Time
Unloading fixture
Time = 16 min 38 sec
Machine table cleaning
Time = 19 min 42 sec
Fixture loading & clamping
Time = 15 min 53 sec
Job loading & aligning
Time = 12 min 43 sec
Job aligning
Time = 16 min 33 sec
Job clamping
Time = 9 min 7 sec
Origin loading
Time = 17 min 46 sec
Set up (Change over) time:
Elapsed time from completion of Part 1 to Start machining of Part 2
= 108 min 22 sec +
crane waiting time
approx. 60 min.
Totally 2 hrs 48
min in old
method.
Time study of Change over time
Average Change over time matrix
Four side machining parts Single side machining parts
Press Sizes Base Top – Links Side plate Side Link
65” TCP 180 min 22 sec 180 min 34 sec 120 min 28 sec 90 min 36 sec
91” TCP 220 min 46 sec 180 min 24 sec 180 min 42 sec 120 min 21 sec
104” TCP 240 min 15 sec 180 min 41 sec 180 min 33 sec 150 min 49 sec
To Reduce The Setup Losses , Change Over Time Needs To Be Reduced
Traditional effort taken to reduce Setup time:
• Additional manpower introduced for Set up in
machine.
• Modular fixtures and hydraulic clamping
systems.
Solution:
SMED (Single Minute Exchange of Dies) approach
for reducing setup time.
SMED (Changeover Reduction) is a tool supporting
Lean Manufacturing. It is used to control and decrease
downtime due to changeovers.
Took time
study plan of
change over
time
Analyze each
step of the
change over
process
Separate
internal &
external
activities
Convert
external to
internal
activities
Streamline
internal &
external
activities
Continuous
improvement
Steps in implementing SMED
TIME PROCESS TIME
TAKEN
(IN MINS)
2:15 pm Previous job completed
(1st shift over)
2:30 pm Labour called for
unclamping and
cleaning
15:22
2:31 pm Unclamping started 3:52
2:33 pm Crane arrived 2:15
2:34 pm Burr cleaning started 1:24
2:35 pm Belt fitted (to lift the
job)
1:14
2:37 pm Crane movement
started
3:18
2:40 pm Burr cleaning finished 9:75
2:50 pm Idle time 17:30
3:08 pm Crane departure 2:57
3:11 pm Side angle plate fixing 3:02
3.15 pm De clamping 1:40
3:16 pm Crane arrival 3:59
3:20 pm Stud removal 6:30
3:26 pm Full cleaning of job
including floor
8:47
3:35 pm Jig setting 6:46
3:42 pm Clamping new job 9:07
3:51 pm Jig origin (adjustment) 3:36
3:54 pm Tool setting 2:53
3:56 pm Machine idle 1:05
3:57 pm Tool origin 7:40
4:05 pm Workpiece origin 6.30
TIME PROCESS TIME
TAKEN
(IN MINS)
Existing Job &
Fixture
unloading
Machine
Cleaning
Top Link
Fixture
Loading
Fixture
Clamping
Job Tilting
And Loading
Crane
Waiting
Job Aligning
Job
Clamping
Origin
loading
Part 1
completed
Part 2
started
Internal External
TIME PROCESS TIME
TAKEN
(IN MINS)
2:15 pm Previous job completed
(1st shift over)
2:30 pm Labour called for
unclamping and
cleaning
15:22
2:31 pm Unclamping started 3:52
2:33 pm Crane arrived 2:15
2:34 pm Burr cleaning started 1:24
2:35 pm Belt fitted (to lift the
job)
1:14
2:37 pm Crane movement
started
3:18
2.40 pm Burr cleaning finished 9:75
2:50 pm Idle time 17:30
3:08 pm Crane departure 2:57
3:11 pm Side angle plate
removing
3:02
3.15 pm De clamping 1:40
3:16 pm Crane arrival 3:59
3:20 pm Stud removal 6:30
3:26 pm Full cleaning of job
including floor
8:47
3:35 pm Jig setting 6:46
3:42 pm Clamping new job 9:07
3:51 pm Jig origin (adjustment) 3:36
3:54 pm Tool setting 2:53
3:56 pm Machine idle 1:05
3:57 pm Tool origin 7:40
4:05 pm Workpiece origin 6:30
TIME PROCESS TIME
TAKEN
(IN MINS)
TIME PROCESS TIME
TAKEN
(IN MINS)
2:15 pm Previous job completed
(1st shift over)
2:30 pm Labour called for
unclamping and
cleaning
15:22
2:31 pm Unclamping started 3:52
2:33 pm Crane arrived 2:15
2:34 pm Burr cleaning started 1:24
2:35 pm Belt fitted (to lift the
job)
1:14
2:37 pm Crane movement
started
3:18
2.40 pm Burr cleaning finished 9:75
2:50 pm Idle time 17:30
3:08 pm Crane departure 2:57
3:11 pm Side angle plate
removing
3:02
3.15 pm De clamping 1:40
3:16 pm Crane arrival 3:59
3:20 pm Stud removal 6:30
3:26 pm Full cleaning of job
including floor
8:47
3:35 pm Jig setting 6:46
3:42 pm Clamping new job 9:07
3:51 pm Jig origin (adjustment) 3:36
3:54 pm Tool setting 2:53
3:56 pm Machine idle 1:05
3:57 pm Tool origin 7:40
4:05 pm Workpiece origin 6:30
TIME PROCESS TIME
TAKEN
(IN MINS)
• We designed a Pallet to reduce the setup time
of the machinery and improve the productivity.
• With the help of this Pallet, we can externally
clamp the fixtures and workpiece in it.
• Because of this Pallet, the internal works are
partially converted into external works.
• Now we can easily load the entire arrangement
in the worktable with the help of crane.
Before SMED
SMED design with pallet
Before SMED – without
pallet
After SMED – with
pallet
• Productivity increases or reduced production
time.
• Improved Machine Utilization.
• Economically beneficial to the organization.
• Improved Responsiveness to the Customer
Demand.
• Reduction in WIP and lot size reduction.
The development of this project enabled a
thorough setup diagnosis, which underpinned the
identification of critical points and their solutions.
In this project the importance of setup time
reduction was presented using SMED methodologies.
After implementing the SMED methodology, it is possible
to defend that simple process based innovations, the
separation of internal from external operations and the
conversion of internal to external operations, are the key
drivers to productivity improvement.
•BLAU, J.R. (1994). European carmakers turn lean to mean.
Machine Design, 66(10), 26–32.
•DAFT, R.L. (1992). Organizational Theory and Design. West, St.
Paul, MN.
•DAMANPOUR, F. (1991). Organizational innovation: A meta-
analysis of effects of determinants and moderators. Academy of
Management Journal, 34 (3), 555-590.
•DYER, J.H. (1996). Specialized supplier networks as a source of
competitive advantage: evidence from the auto industry. Strategic
Management Journal, 15, 271-291.
Single Minute Exchange of Dies (SMED)

More Related Content

What's hot

SMED - Single Minute Exchange of Dies
SMED - Single Minute Exchange of DiesSMED - Single Minute Exchange of Dies
SMED - Single Minute Exchange of Dies5S BALAMURUGAN
 
Lean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation SampleLean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation SampleAndrew Schwartz
 
Single Minute Exchange of Dies (SMED)
Single Minute Exchange of Dies (SMED)Single Minute Exchange of Dies (SMED)
Single Minute Exchange of Dies (SMED)Pramod A
 
Lean manufacturing basics
Lean manufacturing basicsLean manufacturing basics
Lean manufacturing basicssarah bridge
 
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSLEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSJulian Kalac P.Eng
 
Tps and lean manufacturing
Tps and lean manufacturingTps and lean manufacturing
Tps and lean manufacturingAdeel Javaid
 
Lean Quick Changeover (SMED) Training Module
Lean Quick Changeover (SMED) Training ModuleLean Quick Changeover (SMED) Training Module
Lean Quick Changeover (SMED) Training ModuleFrank-G. Adler
 
Line balancing and its formulation
Line balancing and its formulationLine balancing and its formulation
Line balancing and its formulationavijit biswas
 
How to implement Single minute exchange of die
How to implement Single minute exchange of die How to implement Single minute exchange of die
How to implement Single minute exchange of die Nikunj Rana
 
Principle 4 heijunka
Principle 4 heijunkaPrinciple 4 heijunka
Principle 4 heijunkaNeha Jagare
 

What's hot (20)

SMED - Single Minute Exchange of Dies
SMED - Single Minute Exchange of DiesSMED - Single Minute Exchange of Dies
SMED - Single Minute Exchange of Dies
 
Lean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation SampleLean Manufacturing PowerPoint Presentation Sample
Lean Manufacturing PowerPoint Presentation Sample
 
Single Minute Exchange of Dies (SMED)
Single Minute Exchange of Dies (SMED)Single Minute Exchange of Dies (SMED)
Single Minute Exchange of Dies (SMED)
 
smed
smedsmed
smed
 
Lean manufacturing basics
Lean manufacturing basicsLean manufacturing basics
Lean manufacturing basics
 
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSLEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
 
SMED Final
SMED FinalSMED Final
SMED Final
 
Single Minute Exchange of Dies
Single Minute Exchange of DiesSingle Minute Exchange of Dies
Single Minute Exchange of Dies
 
16 major losses tng
16 major losses tng16 major losses tng
16 major losses tng
 
TPM Loss Analysis
TPM  Loss AnalysisTPM  Loss Analysis
TPM Loss Analysis
 
OFFICE TPM PPT
OFFICE TPM PPTOFFICE TPM PPT
OFFICE TPM PPT
 
Tps and lean manufacturing
Tps and lean manufacturingTps and lean manufacturing
Tps and lean manufacturing
 
Lean Quick Changeover (SMED) Training Module
Lean Quick Changeover (SMED) Training ModuleLean Quick Changeover (SMED) Training Module
Lean Quick Changeover (SMED) Training Module
 
Line balancing and its formulation
Line balancing and its formulationLine balancing and its formulation
Line balancing and its formulation
 
How to implement Single minute exchange of die
How to implement Single minute exchange of die How to implement Single minute exchange of die
How to implement Single minute exchange of die
 
Principle 4 heijunka
Principle 4 heijunkaPrinciple 4 heijunka
Principle 4 heijunka
 
Lean Manufacturing
Lean ManufacturingLean Manufacturing
Lean Manufacturing
 
7 waste in the production
7 waste in the production7 waste in the production
7 waste in the production
 
Kaizen
KaizenKaizen
Kaizen
 
13 smed methodology_v2
13 smed methodology_v213 smed methodology_v2
13 smed methodology_v2
 

Similar to Single Minute Exchange of Dies (SMED)

SMED implementation on Automated Stamping Line
SMED implementation on Automated Stamping LineSMED implementation on Automated Stamping Line
SMED implementation on Automated Stamping LineParth Patel
 
Smed implementation on manufacturing stamping line
Smed implementation on manufacturing stamping lineSmed implementation on manufacturing stamping line
Smed implementation on manufacturing stamping lineDhruvShah202
 
PRODUCTIVITY IMPROVEMENT THROUGH LEAN TOOLS ON ENGINE COOLING ASSEMBLY
PRODUCTIVITY IMPROVEMENT THROUGH LEAN TOOLS ON  ENGINE COOLING ASSEMBLYPRODUCTIVITY IMPROVEMENT THROUGH LEAN TOOLS ON  ENGINE COOLING ASSEMBLY
PRODUCTIVITY IMPROVEMENT THROUGH LEAN TOOLS ON ENGINE COOLING ASSEMBLYDIPRANJAN GUPTA
 
Study on Improving Throughput Time through Value Stream Mapping
Study on Improving Throughput Time through Value Stream MappingStudy on Improving Throughput Time through Value Stream Mapping
Study on Improving Throughput Time through Value Stream MappingAlwin Thomas
 
Lean NMR Laboratory Layout
  Lean NMR Laboratory Layout    Lean NMR Laboratory Layout
Lean NMR Laboratory Layout Javier Siles
 
Application Of Workstudy
Application Of WorkstudyApplication Of Workstudy
Application Of Workstudybejayrocks
 
4AD15ME042.pptx
4AD15ME042.pptx4AD15ME042.pptx
4AD15ME042.pptxMrHAD
 
Reducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casingReducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casingeSAT Publishing House
 
Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)MohammedLahssaini1
 
Machining time and costs
Machining time and costsMachining time and costs
Machining time and costsendika55
 
Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryijmech
 
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...IRJET Journal
 
Optimization of PVC Pipes Production Process
Optimization of PVC Pipes Production ProcessOptimization of PVC Pipes Production Process
Optimization of PVC Pipes Production ProcessIRJET Journal
 
PMTF INTERNSHIP (9 june tp 25 june-2015)
PMTF INTERNSHIP (9 june tp 25 june-2015)PMTF INTERNSHIP (9 june tp 25 june-2015)
PMTF INTERNSHIP (9 june tp 25 june-2015)Asim Aslam
 
Dore%2520dore%5 B1%5 D[1]
Dore%2520dore%5 B1%5 D[1]Dore%2520dore%5 B1%5 D[1]
Dore%2520dore%5 B1%5 D[1]Gagan306
 
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET Journal
 

Similar to Single Minute Exchange of Dies (SMED) (20)

SMED implementation on Automated Stamping Line
SMED implementation on Automated Stamping LineSMED implementation on Automated Stamping Line
SMED implementation on Automated Stamping Line
 
Smed implementation on manufacturing stamping line
Smed implementation on manufacturing stamping lineSmed implementation on manufacturing stamping line
Smed implementation on manufacturing stamping line
 
PRODUCTIVITY IMPROVEMENT THROUGH LEAN TOOLS ON ENGINE COOLING ASSEMBLY
PRODUCTIVITY IMPROVEMENT THROUGH LEAN TOOLS ON  ENGINE COOLING ASSEMBLYPRODUCTIVITY IMPROVEMENT THROUGH LEAN TOOLS ON  ENGINE COOLING ASSEMBLY
PRODUCTIVITY IMPROVEMENT THROUGH LEAN TOOLS ON ENGINE COOLING ASSEMBLY
 
Study on Improving Throughput Time through Value Stream Mapping
Study on Improving Throughput Time through Value Stream MappingStudy on Improving Throughput Time through Value Stream Mapping
Study on Improving Throughput Time through Value Stream Mapping
 
Sip
SipSip
Sip
 
Lean NMR Laboratory Layout
  Lean NMR Laboratory Layout    Lean NMR Laboratory Layout
Lean NMR Laboratory Layout
 
Term Project
Term ProjectTerm Project
Term Project
 
Application Of Workstudy
Application Of WorkstudyApplication Of Workstudy
Application Of Workstudy
 
4AD15ME042.pptx
4AD15ME042.pptx4AD15ME042.pptx
4AD15ME042.pptx
 
Reducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casingReducing manufacturing lead time of steam turbine casing
Reducing manufacturing lead time of steam turbine casing
 
Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)
 
Ijmet 10 02_042
Ijmet 10 02_042Ijmet 10 02_042
Ijmet 10 02_042
 
Machining time and costs
Machining time and costsMachining time and costs
Machining time and costs
 
Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industry
 
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
 
Optimization of PVC Pipes Production Process
Optimization of PVC Pipes Production ProcessOptimization of PVC Pipes Production Process
Optimization of PVC Pipes Production Process
 
PMTF INTERNSHIP (9 june tp 25 june-2015)
PMTF INTERNSHIP (9 june tp 25 june-2015)PMTF INTERNSHIP (9 june tp 25 june-2015)
PMTF INTERNSHIP (9 june tp 25 june-2015)
 
PG thesis
PG thesisPG thesis
PG thesis
 
Dore%2520dore%5 B1%5 D[1]
Dore%2520dore%5 B1%5 D[1]Dore%2520dore%5 B1%5 D[1]
Dore%2520dore%5 B1%5 D[1]
 
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
 

Recently uploaded

Cost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based questionCost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based questionSneha Padhiar
 
Turn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxTurn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxStephen Sitton
 
Novel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsNovel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsResearcher Researcher
 
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSHigh Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSsandhya757531
 
List of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfList of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfisabel213075
 
A brief look at visionOS - How to develop app on Apple's Vision Pro
A brief look at visionOS - How to develop app on Apple's Vision ProA brief look at visionOS - How to develop app on Apple's Vision Pro
A brief look at visionOS - How to develop app on Apple's Vision ProRay Yuan Liu
 
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptJohnWilliam111370
 
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithmComputer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithmDeepika Walanjkar
 
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.elesangwon
 
Forming section troubleshooting checklist for improving wire life (1).ppt
Forming section troubleshooting checklist for improving wire life (1).pptForming section troubleshooting checklist for improving wire life (1).ppt
Forming section troubleshooting checklist for improving wire life (1).pptNoman khan
 
Levelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodLevelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodManicka Mamallan Andavar
 
TEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACHTEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACHSneha Padhiar
 
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTFUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTSneha Padhiar
 
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfComprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfalene1
 
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESCME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESkarthi keyan
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communicationpanditadesh123
 
Theory of Machine Notes / Lecture Material .pdf
Theory of Machine Notes / Lecture Material .pdfTheory of Machine Notes / Lecture Material .pdf
Theory of Machine Notes / Lecture Material .pdfShreyas Pandit
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating SystemRashmi Bhat
 
Triangulation survey (Basic Mine Surveying)_MI10412MI.pptx
Triangulation survey (Basic Mine Surveying)_MI10412MI.pptxTriangulation survey (Basic Mine Surveying)_MI10412MI.pptx
Triangulation survey (Basic Mine Surveying)_MI10412MI.pptxRomil Mishra
 

Recently uploaded (20)

Cost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based questionCost estimation approach: FP to COCOMO scenario based question
Cost estimation approach: FP to COCOMO scenario based question
 
Turn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxTurn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptx
 
Novel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsNovel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending Actuators
 
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSHigh Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
 
List of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdfList of Accredited Concrete Batching Plant.pdf
List of Accredited Concrete Batching Plant.pdf
 
A brief look at visionOS - How to develop app on Apple's Vision Pro
A brief look at visionOS - How to develop app on Apple's Vision ProA brief look at visionOS - How to develop app on Apple's Vision Pro
A brief look at visionOS - How to develop app on Apple's Vision Pro
 
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
 
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithmComputer Graphics Introduction, Open GL, Line and Circle drawing algorithm
Computer Graphics Introduction, Open GL, Line and Circle drawing algorithm
 
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
 
Forming section troubleshooting checklist for improving wire life (1).ppt
Forming section troubleshooting checklist for improving wire life (1).pptForming section troubleshooting checklist for improving wire life (1).ppt
Forming section troubleshooting checklist for improving wire life (1).ppt
 
Levelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument methodLevelling - Rise and fall - Height of instrument method
Levelling - Rise and fall - Height of instrument method
 
TEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACHTEST CASE GENERATION GENERATION BLOCK BOX APPROACH
TEST CASE GENERATION GENERATION BLOCK BOX APPROACH
 
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTFUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
 
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfComprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
 
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTESCME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
CME 397 - SURFACE ENGINEERING - UNIT 1 FULL NOTES
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communication
 
Theory of Machine Notes / Lecture Material .pdf
Theory of Machine Notes / Lecture Material .pdfTheory of Machine Notes / Lecture Material .pdf
Theory of Machine Notes / Lecture Material .pdf
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating System
 
Triangulation survey (Basic Mine Surveying)_MI10412MI.pptx
Triangulation survey (Basic Mine Surveying)_MI10412MI.pptxTriangulation survey (Basic Mine Surveying)_MI10412MI.pptx
Triangulation survey (Basic Mine Surveying)_MI10412MI.pptx
 

Single Minute Exchange of Dies (SMED)

  • 1. Implementation of SMED (Single Minute Exchange of Dies) in Heavy Machine Shop Register Number Students Name 511316114053 NAVEEN K 511316114058 PAVITHRA M M 511316114066 RUDHRA RAJ V 511316114073 SIDDHARTH M Under the Guidance of Mr. S. Mahendiran, M.E., Head of the department, Department of Mechanical Engineering, Kingston Engineering College.
  • 2.  Abstract  Introduction  Problem Identification  Literature Review  Objective  Methodology  Working  Design overview  Prototype  Benefits  Conclusion  References
  • 3. Single Minute Exchange of Dies is a process of minimizing the changeover time (or setup time) from hours to minutes (i.e. less than 10 minutes). SMED is one of the lean production methods, having several steps for implementation, is also used to focus for reducing waste in a manufacturing process and to increase the overall equipment effectiveness (OEE) in the shop floor. In this project, the availability is found and analyzed, the time study plan of changeover time was taken, pallet design was created, and applied all the steps of SMED. As a result, the production rate can be achieved more and non-value added activities can be eliminated as much as possible.
  • 4. • Setup time: The time taken to prepare the manufacturing processes and system for production. • Changeover time: The time taken to modify the production line for different products or new batches of the same product. • SMED helps reduce time in both setup and changeover. • Both setup and changeover are Non- Value Added (NVA) operations and so should be minimized as much as possible.
  • 5. • CNC boring machines does not have in-built pallets. • Batch production & its size is min 1 to max 3.
  • 6. • Machine schedules are dynamic in nature due to varying customer demands. • Parts varieties are more. Each parts having 23 variants.
  • 7. • Parts are heavy weight in nature with weight 2 tons to 25 tons with more time for positioning (10-30min).
  • 8. Title Author / Publication Key findings Reduction in Setup Time by SMED Methodology Prof. Nagaraj A Raikar Assistant Professor Dept of Mechanical Engineering AITD, Assagao GOA International Journal of Latest Trends in Engineering and Technology (IJLTET) This Study is carried out in one of the automotive industry. This document demonstrates the need to overcome most of bottleneck of equipment’s unavailability for resources utilization. Single Minute Exchange of Die. A Case Study Implementation António Carrizo Moreira 1 , Gil Campos Silva Pais 2. Journal of Technology Management & Innovation Main finding is that by implementing SMED techniques the firm managed to eliminate wastefulness and non-added value activities
  • 9. Title Author / Publication / Year Key findings An Industrial Application Of The Smed Methodology And Other Lean Production Tools Eric Costa1, Rui Sousa, Sara Bragança, Anabela Alves Centre for Industrial and Technology Management, Department of Production and Systems (DPS), University of Minho, Guimarães, Portugal This paper describes the improvement of the setup process of a mechanical press machine in the metal-mechanic area of a company. The Implementation of Single Minute Exchange of Die with 5’S in Machining Processes for reduction of Setup Time Vipan Kumar, Amit Bajaj International Journal on Recent Technologies in Mechanical and Electrical Engineering (IJRMEE) In this paper we describe that how the SMED technique is used and how it helps to reduce the time and increasing the productivity
  • 10. The main objective of a project: • To Improve OEE to Global benchmark 85%. • Overall Equipment Effectiveness = Availability X Performance X Quality
  • 11. AVAILABILITY PERFORMANCE QUALITY 74% 92% 99% OEE 68% Lowest of OEE Parameter is Availability What is Availability? Availability = Machine cutting time / Machine available time How to improve Availability? Availability can be improved by reducing the non cutting time
  • 12. Non cutting time This 3 Non cutting times are 70 % Affect to OEE. Cutting Time
  • 13. Unloading fixture Time = 16 min 38 sec Machine table cleaning Time = 19 min 42 sec Fixture loading & clamping Time = 15 min 53 sec Job loading & aligning Time = 12 min 43 sec Job aligning Time = 16 min 33 sec Job clamping Time = 9 min 7 sec Origin loading Time = 17 min 46 sec Set up (Change over) time: Elapsed time from completion of Part 1 to Start machining of Part 2 = 108 min 22 sec + crane waiting time approx. 60 min. Totally 2 hrs 48 min in old method.
  • 14. Time study of Change over time Average Change over time matrix Four side machining parts Single side machining parts Press Sizes Base Top – Links Side plate Side Link 65” TCP 180 min 22 sec 180 min 34 sec 120 min 28 sec 90 min 36 sec 91” TCP 220 min 46 sec 180 min 24 sec 180 min 42 sec 120 min 21 sec 104” TCP 240 min 15 sec 180 min 41 sec 180 min 33 sec 150 min 49 sec To Reduce The Setup Losses , Change Over Time Needs To Be Reduced
  • 15. Traditional effort taken to reduce Setup time: • Additional manpower introduced for Set up in machine. • Modular fixtures and hydraulic clamping systems. Solution: SMED (Single Minute Exchange of Dies) approach for reducing setup time.
  • 16. SMED (Changeover Reduction) is a tool supporting Lean Manufacturing. It is used to control and decrease downtime due to changeovers.
  • 17. Took time study plan of change over time Analyze each step of the change over process Separate internal & external activities Convert external to internal activities Streamline internal & external activities Continuous improvement Steps in implementing SMED
  • 18. TIME PROCESS TIME TAKEN (IN MINS) 2:15 pm Previous job completed (1st shift over) 2:30 pm Labour called for unclamping and cleaning 15:22 2:31 pm Unclamping started 3:52 2:33 pm Crane arrived 2:15 2:34 pm Burr cleaning started 1:24 2:35 pm Belt fitted (to lift the job) 1:14 2:37 pm Crane movement started 3:18 2:40 pm Burr cleaning finished 9:75 2:50 pm Idle time 17:30 3:08 pm Crane departure 2:57 3:11 pm Side angle plate fixing 3:02 3.15 pm De clamping 1:40 3:16 pm Crane arrival 3:59 3:20 pm Stud removal 6:30 3:26 pm Full cleaning of job including floor 8:47 3:35 pm Jig setting 6:46 3:42 pm Clamping new job 9:07 3:51 pm Jig origin (adjustment) 3:36 3:54 pm Tool setting 2:53 3:56 pm Machine idle 1:05 3:57 pm Tool origin 7:40 4:05 pm Workpiece origin 6.30 TIME PROCESS TIME TAKEN (IN MINS)
  • 19. Existing Job & Fixture unloading Machine Cleaning Top Link Fixture Loading Fixture Clamping Job Tilting And Loading Crane Waiting Job Aligning Job Clamping Origin loading Part 1 completed Part 2 started Internal External
  • 20. TIME PROCESS TIME TAKEN (IN MINS) 2:15 pm Previous job completed (1st shift over) 2:30 pm Labour called for unclamping and cleaning 15:22 2:31 pm Unclamping started 3:52 2:33 pm Crane arrived 2:15 2:34 pm Burr cleaning started 1:24 2:35 pm Belt fitted (to lift the job) 1:14 2:37 pm Crane movement started 3:18 2.40 pm Burr cleaning finished 9:75 2:50 pm Idle time 17:30 3:08 pm Crane departure 2:57 3:11 pm Side angle plate removing 3:02 3.15 pm De clamping 1:40 3:16 pm Crane arrival 3:59 3:20 pm Stud removal 6:30 3:26 pm Full cleaning of job including floor 8:47 3:35 pm Jig setting 6:46 3:42 pm Clamping new job 9:07 3:51 pm Jig origin (adjustment) 3:36 3:54 pm Tool setting 2:53 3:56 pm Machine idle 1:05 3:57 pm Tool origin 7:40 4:05 pm Workpiece origin 6:30 TIME PROCESS TIME TAKEN (IN MINS)
  • 21.
  • 22. TIME PROCESS TIME TAKEN (IN MINS) 2:15 pm Previous job completed (1st shift over) 2:30 pm Labour called for unclamping and cleaning 15:22 2:31 pm Unclamping started 3:52 2:33 pm Crane arrived 2:15 2:34 pm Burr cleaning started 1:24 2:35 pm Belt fitted (to lift the job) 1:14 2:37 pm Crane movement started 3:18 2.40 pm Burr cleaning finished 9:75 2:50 pm Idle time 17:30 3:08 pm Crane departure 2:57 3:11 pm Side angle plate removing 3:02 3.15 pm De clamping 1:40 3:16 pm Crane arrival 3:59 3:20 pm Stud removal 6:30 3:26 pm Full cleaning of job including floor 8:47 3:35 pm Jig setting 6:46 3:42 pm Clamping new job 9:07 3:51 pm Jig origin (adjustment) 3:36 3:54 pm Tool setting 2:53 3:56 pm Machine idle 1:05 3:57 pm Tool origin 7:40 4:05 pm Workpiece origin 6:30 TIME PROCESS TIME TAKEN (IN MINS)
  • 23. • We designed a Pallet to reduce the setup time of the machinery and improve the productivity. • With the help of this Pallet, we can externally clamp the fixtures and workpiece in it. • Because of this Pallet, the internal works are partially converted into external works. • Now we can easily load the entire arrangement in the worktable with the help of crane.
  • 26. Before SMED – without pallet After SMED – with pallet
  • 27. • Productivity increases or reduced production time. • Improved Machine Utilization. • Economically beneficial to the organization. • Improved Responsiveness to the Customer Demand. • Reduction in WIP and lot size reduction.
  • 28. The development of this project enabled a thorough setup diagnosis, which underpinned the identification of critical points and their solutions. In this project the importance of setup time reduction was presented using SMED methodologies. After implementing the SMED methodology, it is possible to defend that simple process based innovations, the separation of internal from external operations and the conversion of internal to external operations, are the key drivers to productivity improvement.
  • 29. •BLAU, J.R. (1994). European carmakers turn lean to mean. Machine Design, 66(10), 26–32. •DAFT, R.L. (1992). Organizational Theory and Design. West, St. Paul, MN. •DAMANPOUR, F. (1991). Organizational innovation: A meta- analysis of effects of determinants and moderators. Academy of Management Journal, 34 (3), 555-590. •DYER, J.H. (1996). Specialized supplier networks as a source of competitive advantage: evidence from the auto industry. Strategic Management Journal, 15, 271-291.